0001326160 false 0000030371 false 8-K 2023-08-22 false false false false false 0001326160 2023-08-22 2023-08-22 0001326160 duk:DukeEnergyProgressMember 2023-08-22 2023-08-22 0001326160 us-gaap:CommonStockMember 2023-08-22 2023-08-22 0001326160 duk:JuniorSubordinatedDebentures5.625CouponDueSeptember2078Member 2023-08-22 2023-08-22 0001326160 duk:DepositoryShareMember 2023-08-22 2023-08-22 0001326160 duk:Percentage310seniornotesdue2028Member 2023-08-22 2023-08-22 0001326160 duk:Percentage385seniornotesdue2034Member 2023-08-22 2023-08-22 iso4217:USD xbrli:shares iso4217:USD xbrli:shares

 

 

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

FORM 8-K

 

CURRENT REPORT

Pursuant to Section 13 or 15(d) of the

Securities Exchange Act of 1934

 

Date of Report (Date of earliest event reported): August 22, 2023

 

Commission file number Registrant, State of Incorporation or Organization,
Address of Principal Executive Offices and Telephone Number
IRS Employer
Identification Number
     
1-32853

DUKE ENERGY CORPORATION

(a Delaware corporation)

550 South Tryon Street

Charlotte, North Carolina 28202-1803

704-382-3853

 

20-2777218

1-4928

DUKE ENERGY CAROLINAS, LLC

(a North Carolina limited liability company)

526 South Church Street

Charlotte, North Carolina 28202-1803

704-382-3853

56-0205520

     

 

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

 

¨            Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

 

¨            Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

 

¨            Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

 

¨            Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

 

SECURITIES REGISTERED PURSUANT TO SECTION 12(b) OF THE ACT:

 

Registrant Title of each class Trading Symbol(s) Name of each exchange on
which registered
Duke Energy Common Stock, $0.001 par value DUK New York Stock Exchange LLC
Duke Energy 5.625% Junior Subordinated Debentures due September 15, 2078 DUKB New York Stock Exchange LLC
Duke Energy Depositary Shares each representing a 1/1,000th interest in a share of 5.75% Series A Cumulative Redeemable Perpetual Preferred Stock, par value $0.001 per share DUK PR A New York Stock Exchange LLC
Duke Energy 3.10% Senior Notes due 2028 DUK 28A New York Stock Exchange LLC
Duke Energy 3.85% Senior Notes due 2034 DUK34 New York Stock Exchange LLC

 

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§240.12b-2 of this chapter).

 

Emerging growth company ¨

 

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act. ¨

 

 

 

 

 

 

Item 7.01. Regulation FD Disclosure.

 

On August 22, 2023, Duke Energy Carolinas, LLC (“DEC”) reached a partial settlement (the “Stipulation”) with the Public Staff – North Carolina Utilities Commission (the “Public Staff”) in connection with DEC’s Performance Based Regulation (“PBR”) application filed with the North Carolina Utilities Commission (the “NCUC”) on January 19, 2023. Testimony consistent with the Stipulation will be filed later this week. The Stipulation includes, among other things, (i) agreement on prudence of plant-related investments as of June 30, 2023, subject to Public Staff audit of final supplemental updates, (ii) agreement on capital projects and related costs to be included in the 3-year multi-year rate plan, (iii) the acceptance of depreciation rates proposed by DEC, with certain adjustments, and (iv) support for full recovery of Grid Improvement Plan deferred costs over 18 years with a debt return during the deferral period and a full weighted-average cost of capital return during the amortization period.

 

The Stipulation does not include an agreement on return on equity, capitalization structure, or recovery of deferred costs resulting from the COVID-19 pandemic, among other items. The Stipulation is subject to the review and approval of the NCUC. An evidentiary hearing to review the Stipulation and remaining issues in the case is scheduled to commence on August 28, 2023.

 

The Stipulation will result in a one-time pre-tax accounting charge of approximately $30 - 40 million, to be recognized in 3rd quarter 2023.

 

An overview providing additional detail on the Stipulation is attached to this Form 8-K as Exhibit 99.1. The information in Exhibit 99.1 is being furnished pursuant to this Item 7.01 and shall not be deemed “filed” for purposes of Section 18 of the Securities and Exchange Act of 1934, as amended, or otherwise subject to the liabilities of that section.

 

Item 9.01. Financial Statements and Exhibits.

 

(d)       Exhibits.

 

99.1  Duke Energy Carolinas Summary of Partial Settlement in North Carolina Rate Case
104  Cover Page Interactive Data File (the cover page XBRL tags are embedded in the Inline XBRL document).

 

 

 

 

SIGNATURE

 

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

 

  DUKE ENERGY CORPORATION
   
Date: August 22, 2023 By: /s/ David S. Maltz            
  Name: David S. Maltz
 

Title:   

Vice President, Legal, Chief Governance Officer and Assistant Corporate Secretary

   
  DUKE ENERGY CAROLINAS, LLC
   
Date: August 22, 2023 By: /s/ David S. Maltz            
  Name: David S. Maltz
 

Title:

Vice President, Legal, Chief Governance Officer and Assistant Secretary

 

 

 

Co-Registrant CIK 0000030371
Co-Registrant Amendment Flag false
Co-Registrant Form Type 8-K
Co-Registrant DocumentPeriodEndDate 2023-08-22
Co-Registrant Written Communications false
Co-Registrant Solicitating Materials false
Co-Registrant PreCommencement Tender Offer false
Co-Registrant PreCommencement Issuer Tender Offer false
Co-Registrant Emerging Growth Company false

 

Exhibit 99.1

 

Duke Energy Carolinas, LLC

Updates Regarding the North Carolina Rate Case (Docket E-2 Sub 1276)

 

Background:

 

·On January 19, 2023, Duke Energy Carolinas, LLC (“DEC” or “the Company”) filed a rate case with the North Carolina Utilities Commission (“NCUC”) to request an increase in base rate retail revenues. DEP’s rate request before the NCUC includes a Performance Based Regulation (“PBR”) Application which includes a Multi-Year Rate Plan (“MYRP”) that proposes rates for the 3 year MYRP period (January 1, 2024 to December 31, 2026).

 

oThe initial rate case filing requested an approximate overall 15.7% increase in retail revenues over the three-year period, or approximately $823 million.

 

oThe rate case filing requested an overall rate of return of 7.53% based on approval of a 10.4% return on equity (“ROE”) and a 53% equity component of the capital structure.1

 

oThe historic base case in the initial filing is based on a North Carolina retail rate base of $19.1 billion as of December 31, 2021, adjusted for known and measurable changes projected through July 31, 2023.

 

oThe initial filing included impacts of approximately $4.7 billion (NC retail allocation) of capital projects that are projected to go in service over the 3-year MYRP period.

 

·On August 22, 2023, DEC and the Public Staff - North Carolina Utilities Commission (“Public Staff”) filed an Agreement and Stipulation of Partial Settlement (the “Stipulation”) with the NCUC resolving certain issues in the base rate and MYRP proceeding.

 

Major components of the Stipulation:

 

·Rate base: Agreement on prudence of plant-related investments as of June 30, 2023 (with minor exceptions), subject to Public Staff audit of the final two supplemental updates. Taking into consideration the Stipulation and supplemental updates since the initial filing, the agreed-upon NC retail rate base for the historic base case is approximately $19.5 billion.

 

·MYRP Capital: Agreement on capital projects and related costs to be included in the 3-year MYRP, including approximately $4.6 billion (NC retail allocation) projected to go in service over the MYRP period. This amount reflects reduced contingency for MYRP project cost estimates and certain other adjustments agreed to in the Stipulation.

 

·Depreciation rates: Acceptance of depreciation rates proposed by DEC, including coal plant retirement dates, as adjusted for revised retirement dates for Cliffside Unit 5 to align with the Company’s Carolinas Resource Plan filed with the NCUC on August 17, 2023, and other Public Staff adjustments.

 

 

1 This overall rate of return includes the provisions of the CCR settlement which includes a 150 basis point reduction in the ROE with a 52% equity component for the capital structure allowed for coal ash deferrals during the amortization period.

 

1

 

 

o75% of impact of updated subcritical coal plant retirement dates to be deferred to a regulatory asset (as compared to 50% originally proposed by DEC) and agreement on deferral treatment for any remaining net book value upon retirement not eligible for securitization.

 

·Grid Improvement Plan (“GIP”): Support for full recovery of GIP deferred costs over 18 years (rather than 3 years proposed by the Company) with a debt return during the deferral period and a full weighted-average cost of capital (“WACC”) return during the amortization period.

 

·Duke Energy Plaza: Support for recovery of the cost of the Duke Energy Plaza (new headquarters building in downtown Charlotte, NC) with an agreed upon reduction of $50 million of system-level capital costs (rate case request will be reduced by NC retail allocation).

 

·Other Adjustments: Agreement on various other adjustments impacting the revenue requirement, including employee incentives, executive compensation, and coal fleet O&M spend.

 

Key issues on which the parties have not reached a compromise include the following – these issues will be litigated at hearing:

 

·Return on equity and capital structure.

 

·Recovery of deferred costs resulting from the COVID-19 pandemic, including the appropriate amortization period.

 

·Storm balancing account proposed by DEC to reduce volatility of future major storm costs.

 

·Appropriate treatment for DEC’s proposal to net over amortizations (regulatory liabilities) against similar regulatory assets.

 

Additional Information:

 

·The Stipulation is subject to the review and approval of the NCUC.

 

·An evidentiary hearing to review the Stipulation and remaining issues in the case is scheduled to commence August 28, 2023.

 

·DEC will implement temporary rates subject to refund for the historic base case in September 2023.

 

·Subject to NCUC approval, DEC has requested permanent total Year 1 rates to be in effect no later than January 1, 2024.

 

·The Stipulation will result in a one-time pre-tax accounting charge of approximately $30 - 40 million, to be recognized in 3rd quarter 2023.

 

2

 

 

Reconciliation of Company Request to Reflect Stipulation

 

($ in millions)  Historic Base
Case
   Year 1 - MYRP   Total Year 1 
Original requested revenue requirement increase  $361   $140   $501 
Post-filing, pre-Stipulation adjustments   95    23    117 
Revised company requested revenue requirement increase  $456   $163   $618 
Agreed upon adjustments:               
Reduction in depreciation expense   (40)        (40)
Extended amortization period for GIP deferral   (31)        (31)
Reduced contingency in MYRP projects        (5)   (5)
Other revenue reductions   (23)   (20)   (43)
Total agreed upon adjustments   (94)   (25)   (119)
Company requested revenue requirement increase considering agreed upon items  $362   $138   $500 
Net annualized customer rate increase   6.9%   2.6%   9.5%

 

($ in millions)  Year 2 - MYRP   Year 3 - MYRP   Combined Total 
Original requested revenue requirement increase  $172   $150   $823 
Post-filing, pre-Stipulation adjustments   8    33    158 
Revised company requested revenue requirement increase  $180   $183   $981 
Agreed upon adjustments:               
Reduction in depreciation expense             (40)
Extended amortization period for GIP deferral             (31)
Reduced contingency in MYRP projects   (9)   (9)   (24)
Other revenue reductions   (8)   (13)   (63)
Total agreed upon adjustments   (17)   (22)   (158)
Company requested revenue requirement increase considering agreed upon items  $163   $161   $824 
Net annualized customer rate increase   3.1%   3.1%   15.7%

 

·Totals may not add due to rounding.

 

·Historic Base Case includes DEC requested change of $10M to EDIT decrement rider.

 

3