Lion Copper and Gold Corp.: Form 8-K - Filed by newsfilecorp.com

false 2025-08-05 0001339688 Lion Copper and Gold Corp. 0001339688 2025-08-05 2025-08-05

UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
___________________________

FORM 8-K

CURRENT REPORT
Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934

Date of Report (Date of earliest event reported): August 5, 2025

LION COPPER AND GOLD CORP.
(Exact name of registrant as specified in its charter)

British Columbia 000-55139 98-1664106
(State or other jurisdiction (Commission (IRS Employer
of incorporation) File Number) Identification No.)

143 S Nevada St.
Yerington, Nevada, United States 89447
(Address of principal executive offices) (ZIP Code)

Registrant’s telephone number, including area code: (775) 463-9600

Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions:

Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)

Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)

Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))

Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))

Securities registered pursuant to Section 12(b) of the Act:

Title of each class   Trading Symbols   Name of each exchange on which registered
N/A   N/A   N/A

Indicate by check mark whether the registrant is an emerging growth company as defined in Rule 405 of the Securities Act of 1933 (§ 230.405 of this chapter) or Rule 12b-2 of the Securities Exchange Act of 1934 (§ 240.12b -2 of this chapter).

Emerging growth company

If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.


Item 7.01. Regulation FD.

On August 5 ,2025, Lion Copper and Gold Corp. (the "Registrant") issued a press release announcing the results of the Pre-Feasibility Study for its wholly-owned Yerington Copper Project, located in Lyon County, Nevada. A copy of the press release is attached to this report as Exhibit 99.1.

In accordance with General Instruction B.2 of Form 8-K, the information set forth in Item 7.01 and in the press release is deemed to be "furnished" and shall not be deemed "filed" for purposes of the Securities Exchange Act of 1934, as amended (the "Exchange Act"), and shall not be incorporated by reference into any registration statement or other document filed under the Securities Act of 1933, as amended, or the Exchange Act, except as shall be expressly set forth by specific reference in such filing. The information set forth in Item 7.01 of this report shall not be deemed an admission as to the materiality of any information in this report on Form 8-K that is required to be disclosed solely to satisfy the requirements of Regulation FD.

Item 9.01 Exhibits.
   
99.1 News release dated August 5, 2025
104 Cover Page Interactive Data File (embedded within the Inline XBRL document)

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned hereunto duly authorized.

      Lion Copper and Gold Corp.
Date: August 6, 2025   (Registrant)
       
       
      /s/ Lei Wang
      Lei Wang, Chief Financial Officer



CSE: LEO | OTCQB: LCGMF

LION COPPER AND GOLD ANNOUNCES PRE-FEASIBILITY STUDY RESULTS FOR BROWNFIELD YERINGTON COPPER PROJECT AND MAIDEN MINERAL RESERVE

Base Case $4.30/lb copper, Post-Tax NPV (7%) $694 million and 14.6% IRR with payback at 6.7 years

Advancing Clear Path to Near-Term Production of U.S. Refined Copper Cathode

Yerington, Nevada - August 5, 2025 - Lion Copper and Gold Corp. ("Lion Copper and Gold" or the "Company") (CSE: LEO, OTCQB: LCGMF) is pleased to announce the results of the Pre-Feasibility Study (PFS) for its wholly-owned Yerington Copper Project, located in Lyon County, Nevada. The PFS, completed pursuant to the provisions of National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101"), demonstrates and confirms the Project's potential as a significant refined copper cathode producer in the United States in the heart of the Yerington Copper District. The PFS was prepared by Samuel Engineering Inc., with input from independent Qualified Persons (QPs), and was fully funded by the Company's strategic partner, Nuton LLC, a Rio Tinto venture.

In this news release, all dollar amounts are in United States dollars ("$") and imperial units are utilized.

Highlights

Sizeable and scalable open pit heap leach project


John Banning, CEO of the Company, states, "With growing domestic demand for refined copper, we are pleased to announce the completion of the Pre-Feasibility Study for our Yerington Copper Project, a brownfield asset in Nevada, planned to produce 120 million pounds of refined copper cathode annually over a 12-year mine life. This PFS showcases Lion Copper and Gold's strategic advantage in the Yerington Copper District, bolstered by secured water rights, the Bear Deposit's significant potential, strategic land control, and proximity to major neighboring copper projects, positioning us to deliver significant shareholder value and strengthen North America's critical minerals supply chain."

Economics

* Initial capital expenditures divided by average annual copper production for mine life

Copper Price Sensitivity

Sensitivity Copper Price Pre-Tax Post-Tax
(%) /item Cu/lb NPV(7%) IRR Payback NPV(7%) IRR Payback
    $M % Years $M % Years
-25% $3.23 $111 8% 8.9 ($21) 7% N/A
-20% $3.44 $284 10% 8.2 $122 8% 8.6
-15% $3.66 $457 12% 7.6 $266 10% 7.9
-10% $3.87 $629 14% 7.1 $410 12% 7.4
-5% $4.09 $802 15% 6.7 $553 13% 7.0
Base Case $4.30 $975 17% 6.4 $694 15% 6.7
5% $4.52 $1,148 19% 6.1 $836 16% 6.4
10% $4.73 $1,321 20% 5.8 $976 18% 6.1
15% $4.95 $1,494 22% 5.5 $1,116 19% 5.9
20% $5.16 $1,667 23% 5.3 $1,254 20% 5.6
25% $5.38 $1,840 25% 5.0 $1,390 22% 5.4


Figure 1. Copper Price Sensitivity After Tax

Significantly Derisked Project at PFS level with Resource Upside Potential

Strategically Important U.S. Copper Production


Project Overview

The Yerington Copper Project integrates the Yerington and MacArthur deposits, located in Nevada's Yerington Copper District, a historic mining region with excellent infrastructure (rail, power, U.S. Highway 95A). The Project benefits from 100% Lion Copper and Gold owned water rights of 6,014 acre-feet/year permitted for mining use for the life of the project and de-risked permitting and mine development. The PFS envisions conventional open-pit mines feeding a heap leach operation, producing LME Grade A copper cathode via SX/EW, with Nuton's technology enhancing sulfide recoveries. The Project plans to create approximately 400 direct jobs during construction and up to 250 permanent jobs during operations, contributing significantly to the local and state economies.

The Project offers significant environmental benefits compared to traditional copper production. Benefits of the Project include utilizing previously disturbed project facilities area suitable for new mine infrastructure, using pit water for multiple beneficial uses in Mason Valley, zero discharge of water from copper processing operations, lower carbon intensity, and efficiently delivering refined copper cathode directly into U.S. supply chains. These environmental benefits are an important part of the Project being a partner in the Mason Valley to foster growth and diversity in the local economy together with the local stakeholders.

The Project is approximately 70 miles by road from Reno, Nevada, 50 miles south of Tahoe-Reno Industrial Center, and 10 miles from the nearest rail spur of Wabuska. The Project includes both the historic Yerington and MacArthur open pit mines with shared mineral processing infrastructure for operational efficiency. The Project is bordered on the east by the town of Yerington, Nevada, which provides access via a network of paved and gravel roads that were used during previous mining operations. 


Figure 2. Yerington Copper Project Overview


Base Case Economics - Based on $4.30/lb Copper Price

Parameter Unit Pre-tax Post-tax
Net Revenue $USM 2,914 2,315
NPV (7%) (LOM) $USM $975 $694
IRR (LOM) % 16.9% 14.6%
Payback Years 6.4 6.7
Cash Costs1 $US/lb payable $1.92
AISC1 $US/lb payable $2.67
Copper - Payable Mlbs 1,443
Mine Life Years 12
Average Annual Production LOM Mlbs 120
LOM Production tons 721,352

1 Total cash cost and AISC are non-GAAP measures and include royalties payable. See reference below regarding non-IFRS measures.

NPV Sensitivities

The sensitivity analysis provides a range of results for the Project when key parameters are varied from their base-case values. The NPV estimate is most sensitive to the copper price.

The PFS uses a base case copper price of $4.30/lb, using the COMEX two-year trailing average copper prices. Project sensitivities were completed on the copper price with a range of $3.25/lb through $5.38/lb:

Capital and Operating Costs

The initial capital, expensed over the first 3 years of the Project, amounts to $724 million. The sustaining capital over the remainder of LOM amounts to $1,008 million. A breakdown of capital is presented in the tables below.

Operating Costs   $USM     $/t Feed     $/lb payable  
Open Pit Mining   1,698     3.35     1.18  
Processing   947     1.87     0.66  
G&A   124     0.24     0.09  
Total   2,769     5.47     1.92  



Capital Costs  
Initial Capital $USM   724  
Sustaining Capital $USM   1,008  
Total Capital $USM   1,732  
$/lb payable   1.20  

Reserves and Resources

The PFS includes the first Mineral Reserve estimate for the Yerington Copper Project. The PFS is based on the Mineral Reserves only and the reserve estimate is based on pit designs using a copper price of $3.90/lb, with cut-off grades ranging from 0.03 to 0.07% CuT for oxide material and 0.09% CuT for sulfide material.

Mineral Reserves

Pit Area Proven Probable Total
Ore Type Tons (kt) Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Tons (kt) Grade
(Cu%)
Copper
Mlbs
Yerington Pit/VLT
Oxide 34,295 0.22 148.3 73,681 0.13 193.1 107,976 0.16 341.5
Sulfide 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
MacArthur Area
Oxide 110,224 0.19 411.7 54,553 0.16 173.5 164,777 0.18 585.2
Sulfide - - - - -        
Total  Oxide 144,519 0.19 560.0 128,234 0.14 366.7 272,753 0.17 926.7
Total Sulfide 81,037 0.30 481.1 152,761 0.24 732.3 233,798 0.26 1,213.3
Total
Reserve
225,556 0.23 1,041.1 280,995 0.20 1,099.0 506,551 0.21 2,140.0

Note: This Mineral Reserve estimate has an effective date of May 31, 2025, and is based on the mineral resource estimates for Yerington and VLT dated March 17, 2025 by AGP Mining Consultants Inc. and MacArthur Area Pits dated March 17, 2025 by Independent Mining Consultants Inc. The Mineral Reserve estimate was completed under the supervision of Gordon Zurowski, P.Eng. of AGP, who is a Qualified Person as defined under NI 43-101. Mineral Reserves are stated within the final pit designs based on a $3.90/lb copper price.

1. The copper cutoff grades used were:

Yerington Pit - 0.05% copper (oxide ROM), 0.09% copper (sulfide)
Vat Leach Tailings (VLT) Pit - 0.03% copper (oxide ROM)
MacArthur - 0.05% copper (oxide ROM)
Gallagher Pit - 0.07% copper (oxide ROM)
North Ridge Pit - 0.06% copper (oxide ROM)

2. Open pit mining costs varied by area and elevation with waste of $2.53/t, oxide material at $2.49/t and sulfide at $2.22/t.  Incremental costs of $0.027/25ft bench were applied below the 4225 foot elevation for waste and oxide and 0.024/t for sulfide material below the 4225 foot elevation.

3. Processing costs were based on the use of an acid plant at site with crushing for sulfide material.  The processing costs by pit area were:

Yerington Pit - $2.00/t ore (oxide ROM), $4.44/t (sulfide)
VLT Pit - $1.34/t ore (oxide ROM)
MacArthur - $1.67/t ore (oxide ROM)
Gallagher Pit - $2.14/t ore (oxide ROM)
North Ridge Pit - $1.73/t ore (oxide ROM)
G&A costs were $0.49/t ore.

4. Process copper recoveries varied by material and area and were as follows:


Yerington Pit - 70% (oxide ROM), 74% (sulfide)
VLT Pit - 75% (oxide ROM)
MacArthur - 55% (oxide ROM)
Gallagher Pit - 54% (oxide ROM)
North Ridge Pit - 55% (oxide ROM)

Mineral Resources (Inclusive of Mineral Reserves)

Pit Area   Measured     Indicated     Measured + Indicated  
Resource
Type
  Tons
(kt)
    Grade
(Cu%)
    Copper
Mlbs
    Tons
(kt)
    Grade
(Cu%)
    Copper
Mlbs
    Tons
(kt)
    Grade
(Cu%)
    Copper
Mlbs
 
Yerington Pit/VLT  
Oxide   37,531     0.21     157.6     96,556     0.13     257.9     134,087     0.16     417.0  
Sulfide   84,163     0.30     505.0     263,230     0.22     1,158.2     347,393     0.24     1,663.2  
MacArthur Area  
Oxide   163,333     0.18     577.8     155,086     0.15     471.6     318,419     0.17     1,049.4  
Sulfide   -     -     -     -     -     -     -     -     -  
Total  
Oxide Total   200,864     0.19     735.4     251,642     0.15     729.4     452,506     0.16     1,464.9  
Sulfide Total   84,163     0.30     505.0     263,230     0.22     1,158.2     347,393     0.24     1,663.2  
Total   285,027     0.22     1,240.4     514,872     0.18     1,887.6     799,899     0.20     3,129.0  

Pit Area Inferred
Resource Type Tons (kt) Grade (Cu %) Copper Mlbs
Yerington Pit/VLT
Oxide 67,338 0.11 145.8
Sulfide 67,576 0.17 229.8
MacArthur Area
Oxide 23,169 0.15 67.9
Sulfide - - -
Total
Oxide Total 90,507 0.12 213.6
Sulfide Total 67,576 0.17 229.8
Total 158,083 0.14 443.4

Notes:

1. Mineral Resources are reported in situ for the Yerington Pit and MacArthur Pit area and the effective date is March 17, 2025. Mineral Resources for the VLT are surficial and the effective date is March 17, 2025. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resource estimate will be converted into Mineral Reserves.  The Mineral Resource Estimate of Yerington and the VLT was performed by Mr. Tim Maunula, P. Geo of T. Maunula & Associates Consulting and the MacArthur Area Pits by Mr. Herb Welhener, MMSA-QPM, Vice President of Independent Mining Consultants Inc. Both responsible parties are both Qualified Persons under 43-101 standards. All figures are rounded to reflect the relative accuracy of the estimates and totals may not add correctly.


2. Mineral Resources of the Yerington pit area are reported within a conceptual pit shell that used the following input parameters: a variable break-even economic cut-off grade of 0.04 % TCu and 0.08% TCu, for oxide and sulfide material respectively, based on assumptions of a net copper price of US$4.22 per pound (after smelting, refining, transportation, and royalty charges), 70% recovery in oxide material, 74% recovery in sulfide material, base mining costs of $2.49/st for oxide and $2.22/st for sulfide, and processing plus G&A costs of $2.00/st for oxide and $4.44/st for sulfide.

3. Mineral Resources of the VLT are reported within a conceptual pit shell that used the following input parameters: a break-even cut-off grade of 0.03 % TCu based on assumptions of a net copper price of US$4.22 per pound (after smelting, refining, transportation and royalty charges) and 75% recovery in oxide material.

4. Mineral Resources of the MacArthur Pit area are reported within a conceptual pit shell that used the following input parameters: a break-even cut-off grade of 0.05 % for the MacArthur pit, 0.07 % TCu for the Gallagher pit, and 0.06 % TCu for the North Ridge pit. Metal price of $4.22 per pound (after smelting, refining, transportation, and royalty charges); process costs between $1.67 and $2.14/st; and base mining costs for heap tonnage of $2.49/st and $2.53/st for waste,

5. Recovery of Total Copper in redox zones of leach cap, overburden, oxide and mixed: MacArthur domain 55%, North Ridge domain 53%, Gallagher domain 54%.


Figure 3. Yerington Pit Long Section


Figure 4. Yerington Pit Mine Phases

 


Figure 5. MacArthur Pit North-South Section


Figure 6. MacArthur Pit Mine Phases

Metallurgy

Nuton™ Technology will be utilized for copper recovery in the form of bioleaching for the Yerington Sulfide Ore. Nuton technology will utilize microorganism assisted acid leach system to extract the copper from the Yerington Sulfide Ore that has been crushed and stacked onto a heap leach pad. Pyrite and Nuton additives will be added to the process at the agglomeration stage to enhance the extraction process. This innovative approach has been demonstrated via extensive column testing, lab testing and modelling to enhance the overall copper recovery for the sulfide ore, offering a lower cost and more water efficient sulfide copper recovery process compared to conventional milling and floatation.

Lion Copper and Gold in partnership with Nuton™ completed extensive column and laboratory testing on the Yerington sulfide material to optimize recoveries from deploying the Nuton sulfide leaching technology.  Over 40 test columns were leached by Nuton at their own laboratory to develop both recovery models and fine tune process design criteria. The forthcoming PFS Technical Report will provide additional testwork details and associated results.

Process Description Summary

Copper will be extracted through a heap leach process, followed by SX/EW. Ore will originate from multiple sources which will be stacked and processed on three separate leach pads with two SX circuits. The sulfide and oxide ore from the Yerington open pit will be distributed onto separate heap leach pads but will share an SX circuit. The MacArthur open pits will have one heap leach pad and one SX circuit. There will be a single EW facility for the project co-located with the Yerington SX system.


The Yerington Oxide Heap Leach Facility (HLF) will be ROM truck dumped with a peak placement rate of 83,000 short tons per day (tpd) of new oxide ore and residual stockpiled ore. The crushing, conveying, agglomeration and ore stacking at the Yerington Sulfide HLF is designed for 114,000 tpd to process the peak sulfide ore placement rate of 94,000 tpd.  The MacArthur HLF will also be ROM truck dump with a peak placement rate of 142,000 tpd.

The Yerington solvent extraction (SX) systems will handle up to 30,000 gallons per minute (gpm) of pregnant leach solution (PLS). MacArthur's SX system will be designed to process up to 22,000 gpm of PLS. The shared electrowinning (EW) circuit will process electrolyte from both Yerington and MacArthur with the ability to produce up to 90,000 tons per year of refined copper cathode.

The planned mine life is 12 years, with SX/EW to be in operation for 14 years with the acid plants to be in operation for their life cycle of 19 years. Sulfuric acid production that exceeds project requirements will be sold into the domestic market. The combined copper recovery is expected to be 67.4%.


Figure 7. Yerington Copper Project Copper Cathode Production Simplified Flowsheet


Project Development

Lion Copper and Gold anticipates securing all required permits and authorizations needed to construct and operate the Project within reasonable and normal timeframes. Preliminary permitting schedule estimates that the completion of baseline studies, acquisition of requisite state permits, and the National Environmental Policy Act (NEPA) process necessary for project authorization could be completed in as little as 2.5 years.  Furthermore, the Project's permitting schedule may benefit from the Executive Order (EO) 14241 titled Immediate Measures to Increase American Mineral Production issued in March 2025 to streamline permitting processes for mining projects, particularly those focused on critical minerals.

Figure 8: Development Timeline

Future Opportunities

The Yerington Copper Project covers an extensive strategic land package, including the Bear Deposit and numerous other underexplored targets. While Lion Copper and Gold's Project is compelling on its own, it creates the potential to act as a catalyst to consolidate with adjacent copper projects.


Figure 9. Yerington Area, Including Bear Deposit, Pumpkin Hollow Mine, and Ann Mason Deposit


Qualified Persons

For the purposes of Canadian National Instrument 43-101, the independent Qualified Persons responsible for preparing the scientific and technical information disclosed in this news release announcing the Study are Michael McGlynn (Samuel Engineering Inc.), Gordon Zurowski (AGP Mining Consultants) Steve Pozder (Samuel Engineering Inc.), John Rupp (Piteau Associates), Tim Maunula (T.  Maunula & Associates Consulting), Herb Welhener (Independent Mining Consultants), Marie-Hélène Paré (GSI Environmental) and Adrien Butler (NewFields). The Qualified Persons named herein have reviewed and approved the information in this news release relevant to the portion of the scientific and technical information for which they are responsible.

Other disclosures of a technical or scientific nature included in this news release have been reviewed, verified, and approved by Todd Bonsall, Douglas Stiles, Steven Dischler and John Banning who are Qualified Persons as defined by Canadian National Instrument 43-101 and are employees of Lion Copper and Gold.

A Technical Report in the form required under Canadian National Instrument 43-101 will be filed within 45 days of this news release and will be available on Lion Copper and Gold's website and on its SEDAR profile.

About Lion

Lion Copper and Gold Corp. is advancing its flagship copper project in Yerington, Nevada through an Option to Earn-in Agreement with Nuton LLC, a Rio Tinto Venture.

Further information can be found at www.lioncg.com

About Nuton

Nuton is an innovative venture that aims to help grow Rio Tinto's copper business. At the core of Nuton is a portfolio of proprietary copper leaching technologies and capability. Nuton has the potential to economically unlock copper from hard-to-leach ores, including primary sulfides and, in doing so, increase domestic production of critical minerals to support the energy transition. Nuton technologies can achieve market-leading recovery rates and boost copper production in new, ongoing and historical operations, increasing resource utilization and maximizing value.

With significantly lower energy and water needs than conventional concentrating and smelting, and the ability to produce copper cathode at the mine site, Nuton offers a reliable source of domestically produced copper, with a short mine-to-metal supply chain and the ambition to set industry-leading ESG credentials.

One of the key differentiators of Nuton is the ambition to produce the world's lightest environmental footprint copper while having at least one Positive Impact at each of its deployment sites, across its five pillars: water, energy, land, materials and society. 

To learn more about Nuton, visit https://nuton.tech/


On behalf of the Board of Directors,

John Banning
Chief Executive Officer
Lion Copper and Gold Corp.

Pre-Feasibility Study Webinar

Please join John Banning on August 12, 2025, at 10:30 AM PDT via the Livestorm webinar link below for an overview of the Yerington Copper Project Pre-Feasibility Study results, which evaluates the Project's technical and economic viability and its potential role in the U.S. copper supply chain amid rising domestic demand and supply limitations.

Join the webinar at the link.

Contact Information

Lion Copper and Gold Corp.
(775) 463 9600
[email protected]

Non-IFRS Measures

Alternative performance measures in this news release such as "C1 cash cost", "AISC" "free cash flow" are furnished to provide additional information. These non-GAAP performance measures are included in this news release because these statistics are used as key performance measures that management uses to monitor and assess performance of the Project, and to plan and assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a standard meaning within International Financial Reporting Standards ("IFRS") and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with IFRS.

Non-IFRS financial measures used in this news release and common to the copper mining industry are defined below.

Total Cash Costs and Total Cash Costs per Pound: Total Cash Costs are reflective of the cost of production. Total Cash Costs reported in the PFS include mining costs, processing & water treatment costs, general and administrative costs of the mine, offsite costs, refining costs, transportation costs and royalties. Total Cash Costs per Pound is calculated as Total Cash Costs divided by payable copper pounds.

Total Operating Costs and Total Operating Costs per Pound: Total Operating Costs are reflective of the cost of mine operations. Total Operating Costs reported in the PFS include mining costs, processing & water treatment costs, and general and administrative costs of the mine. Total Operating Cost per Pound is calculated as Total Operating Costs divided by payable copper pounds.

All-in Sustaining Costs ("AISC") and AISC per Pound: AISC is reflective of all of the expenditures that are required to produce a pound of copper from operations. AISC reported in the PFS includes total cash costs, sustaining capital, expansion capital and closure costs, but excludes corporate general and administrative costs and salvage. AISC per Pound is calculated as AISC divided by payable copper pounds.

Forward Looking Statements

Neither Canadian Stock Exchange (CSE) nor its Regulation Services Provider (as that term is defined in the policies of the CSE Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

The technical information in this news release has been reviewed and approved by John Banning, QP MMSA, CEO of Lion Copper and Gold Corp., and a qualified person as defined in NI 43-101.

Certain information in this news release constitutes forward-looking statements under applicable securities laws. Any statements that are contained in this news release that are not statements of historical fact may be deemed to be forward-looking statements. Forward-Looking statements are often identified by terms such as "may", "expect", or the negative of these terms and similar expressions. Forward-Looking statements in this news release include, but are not limited to, statements with respect to the future exploration activities and anticipated results. Forward-Looking statements necessarily involve known and unknown risks, including, without limitation, risks associated with exploration activity; general economic conditions; adverse industry events; marketing costs; loss of markets; future legislative and regulatory developments; inability to access sufficient capital from internal and external sources, and/or inability to access sufficient capital on favorable terms; the ability of Lion Copper and Gold to implement its business strategies; competition; currency and interest rate fluctuations and other risks.


Cautionary Note for U.S. Investors Concerning Mineral Resources and Reserves

National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") is a rule of the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards differ from the requirements of the U.S. Securities and Exchange Commission ("SEC") and resource information contained in this press release may not be comparable to similar information disclosed by domestic United States companies subject to the SEC's reporting and disclosure requirements.