Operator, Operator
Thank you for your patience. This is the conference operator. Welcome to the Eldorado Gold Second Quarter 2024 Results Conference Call. As a reminder, all participants are in listen-only mode and the conference is being recorded. After the presentation, there will be an opportunity to ask questions. I would now like to turn the conference over to Lynette Gould, Vice President, Investor Relations, Communications and External Affairs. Please proceed, Ms. Gould.
Lynette Gould, Vice President, Investor Relations
Thank you, operator, and good morning, everyone. I'm excited to welcome you to our second quarter 2024 results conference call. Before we begin, I would like to remind you that we will be making forward-looking statements and referring to non-IFRS measures during the call. Please refer to the cautionary statements included in the presentation and the disclosure on non-IFRS measures and risk factors in our management's discussion and analysis. Joining me on the call today, we have George Burns, President and Chief Executive Officer; Paul Ferneyhough, Executive Vice President and Chief Financial Officer; Louw Smith, Executive Vice President, Development, Greece; and Simon Hille, Executive Vice President, Operations and Technical Services. Our news release yesterday details our second quarter 2024 financial and operating results. This should be read in conjunction with our second quarter 2024 financial statements and management's discussion and analysis, both of which are available on our website. They have also both been filed on SEDAR+ and EDGAR. All dollar figures discussed today are in U.S. dollars unless otherwise stated. We will be speaking to the slides that accompany this webcast and you can download a copy of those slides from our website. After the prepared remarks, we will open the call for Q&A. At this time, we will invite analysts to queue for questions. I will now turn the call over to George.
George Burns, President and CEO
Thanks, Lynette, and good morning, everyone. Here is the outline for today's call. I will provide a brief overview of Q2 results and highlights. I will then pass the call over to Paul to go through our financial results and then to Louw and Simon to review our operational performance. We will then open the call to questions from our analysts. Turning to Slide 4, the second quarter delivered safe gold production of 122,319 ounces in line with our progress towards full production guidance. Production was in line with expectations as grades increased at Lamaque, Efemcukuru, and Kisladag. During the quarter, we did have a small impact on production as a result of labor-initiated work stoppages at Olympias totaling 17 days in the quarter during negotiations on a new collective bargaining agreement. Currently, we are in the final stages of negotiating a mutually acceptable collective bargaining agreement with our union. Looking ahead, we continue to expect increased production in the second half of the year, remaining on track with our guidance to produce between 505,000 and 555,000 ounces of gold in 2024. Total cash costs and all-in sustaining costs were in line with our expectations at $940 per ounce sold and $1,331 per ounce sold, respectively. Costs increased primarily as a result of higher royalties driven by higher gold prices in addition to higher labor and contractor costs and higher fuel prices during the quarter. As noted in Q1 and subsequently in the second quarter, continued higher gold prices during the quarter have led to increased royalty expenses in Greece and Türkiye as the royalty structures are calculated on a sliding scale linked to gold price. While we did see higher costs this quarter, they are in line with our 2024 guidance ranges. Paul will touch on our costs in more detail later in the call. Turning to Slide 5 in the second quarter, our lost time frequency rate decreased to 0.40 recorded incidents per million person hours worked compared to 1.32 in Q2 2023. Our commitment to create and maintain a safe and healthy workplace is unchanged, and we recognize this is a continuous journey of improvement. Our health and safety focus in 2024 is based on preventing high potential incidents and further empowering our employees to promote a positive health and safety culture. In sustainability, I'd like to start by congratulating our teams in Türkiye on the outstanding scores they received following their external verification against the Mining Association of Canada's Towards Sustainable Mining protocols. TSM scoring is arranged from C through AAA, with A indicating good practice and AAA indicating excellence and leadership. At Efemcukuru, the site received AAA scores in tailings, health and safety, biodiversity, and indigenous and community relations. The site received A, AA, and AAA scores across all other indicators. At Kisladag, the site received AAA scores in all safety and health protocol indicators and A, AA, and AAA scores across all other indicators. Notably, with the completion of the first round of TSM verifications, we now have AAA score tailings facilities across all of our operations. I would also like to extend my congratulations to a number of our global teams that received awards during the quarter, including a silver award from the Hellenic Institute for Occupational Health and Safety, the Best Natural Resources deal at the 2023 EMEA Project Finance Awards. This was in recognition of our Skouries project financing facility, and a Bronze Award in the Gender & Inclusion category at the 2024 EBRD Sustainability Awards. These awards recognize the outstanding achievements of EBRD's clients in promoting green economies and better environmental and social performance. We take great pride in our team's commendable success, and this is reflected in the awards received across health and safety, sustainability, and finance. I'll stop there and turn the call over to Paul for a review of our financial results.
Paul Ferneyhough, CFO
Thank you, George. Slide 6 provides a summary of our second quarter results. Our operations delivered a steady second quarter in line with expectations and guidance, with continued high gold prices driving overall financial results. Looking to the full year, our annual guidance remains unchanged across all operational and financial metrics with some upside possible in cash flow generation if gold prices remain at their current levels. Eldorado reported net earnings attributable to shareholders from continuing operations of approximately $56 million or $0.28 per share in the second quarter, positively impacted by higher revenue due to higher volumes sold and higher prices realized when compared to the second quarter in 2023. After adjusting for one-time non-recurring items, adjusted net earnings were $66.6 million or $0.33 per share for the quarter. Adjusted net earnings in Q2 2024 accounted for the reversal of two principal items: firstly, a $1.9 million gain on foreign exchange due to the translation of Turkish deferred tax balances, net of inflation accounting impacts; and secondly, a $12 million unrealized loss on derivative instruments, including our gold zero-cost collars. Our free cash flow in the quarter was negative $32 million and positive $33.9 million excluding the capital investment in the Skouries project. Cash flow generated by operating activities before changes in working capital in the quarter was around $132 million compared to $82 million in the same quarter last year. As previously noted, the increase is principally relating to higher sales volumes and realized gold prices. Second quarter total cash costs were $940 per ounce sold, and all-in sustaining costs were $1,331 per ounce sold. Our costs increased compared to Q2 2023 as a result of higher labor costs and consumables such as fuel, driven by production volumes as well as higher royalty expenses primarily due to higher realized gold prices. The higher royalty expense in Q2 impacted AISC by approximately $40 per ounce. In addition, increased sustaining capital investment contributed to higher AISC for the quarter compared to the same period in the prior year. Capital expenditures on a cash basis were $133 million in the second quarter, including investment in growth projects at Kisladag, where we focused on plant waste stripping, the North Heap Leach Pad, and related infrastructure. At Skouries, we continue to advance major earthworks and infrastructure construction for the project and as expected, invested approximately $92 million in the period. We anticipate that we will restart investing our own equity in the project as early as the fourth quarter this year. Current tax expense of just over $20 million for the second quarter decreased from approximately $22 million compared to the same period in 2023, primarily due to reduced Turkish taxes after accounting for increased investment tax credits and inflation accounting adjustments. Deferred tax - sorry, deferred income tax decreased to a $1 million expense in Q2 2024 from an expense of $17 million in the comparable quarter in the prior year. In Q2 2024, deferred tax included a $4.4 million expense for use of tax attributes in Canada, a $5.8 million expense related to the weakening of the Turkish lira and the euro against the U.S. dollar, partially offset by a $7.6 million recovery from the application of Turkish inflation accounting. Turning to Slide 7. Stability and status quo are the key themes. Our balance sheet continues to be well funded and able to support our growth strategy. We ended the quarter with total liquidity of $810 million, including $595 million of cash and cash equivalents and $215 million of available credit capacity. During the quarter, we extended and increased our senior secured credit facility by $100 million. This was done proactively, taking advantage of favorable market conditions and allowing us to update and renew our previous facility that was due to expire in 2025. Cash increased over the quarter as a result of positive cash flow from our mining operations combined with drawdowns of the project finance facility for the Skouries development. We expect to build cash during the remainder of 2024 from cash flow at our operations as we benefit from strong gold prices. Additionally, we continue to focus on maintaining a solid financial position that provides flexibility to respond to opportunities and fund our growth strategy to unlock value across our global business. With that, I'll now turn the call over to Louw to go through the Greek asset highlights.
Louw Smith, Executive Vice President, Development, Greece
Thanks, Paul, and good morning. Starting on Slide 8 at our Skouries Copper Gold Project. While tier 1 was primarily focused on earthworks, Q2 saw construction work commence in multiple areas. Going forward in Q3 and Q4, underground mining, mechanical piping, and instrumentation in the main plant will continue to ramp up in addition to the construction of the filter plant building. Overall progress is 76% when including the first phase of the construction, and we remain on track for first production in Q3 2025, with commercial production expected at the end of 2025. Detailed engineering has advanced and is now at 72% complete, and procurement is substantially completed. Work rigorously continues to ramp up on the construction of major earthworks structures, including the haul roads, water management ponds, low-grade stockpile, primary crusher, process facilities, filter plant facility, and the integrated extractive waste management facility (IEWMF). Productivity improvement initiatives by the earthworks contractor, including adding a partial second shift, have yielded significant improvements, including optimizing cycle times for the fleet as well as improved sequencing of material placement and quality control activities. On the critical path is the filter plant facility, which continues to advance. We expect to expedite the filter plant construction contract in the next few weeks. The filter press plates continue to be preassembled with 225 now completed out of a total of 588, and during Q2, the fabricated frames for those plates arrived on-site. Work in the mill/flotation building is progressing well. Commissioning of all overhead claims was completed during the second quarter. Construction, lighting, scaffolding steel, and concrete work are all on track. In addition, off-site pipe spooling fabrication and contractor mobilization continue on plan. Work is also progressing on the underground development to support test stope mining in 2025. We awarded the second contract in Q2 which includes the test stope work as well as additional development and services work to support the development of the underground mine. The contractor mobilized to site, and the first blast occurred on June 17. We have also completed the earthworks to allow access to the coffer dam site during the second quarter, and construction has now commenced. In addition, the low-grade ore stockpile full placement has also started. Moving on to Slide 9. During the second quarter, capital investment at Skouries was $92 million, almost double the first quarter spend. This brings our year-to-date spend at Skouries to $144 million which is in line with our expectations as the spend is expected to ramp up significantly as mobilization and the site labor increases over the second half of the year. We remain on track to meet our guidance for investment in Skouries in 2024 of between $375 million and $425 million. At the end of Q2 2024, we had 841 personnel on site and are still on track to ramp up to 1,300 by the end of the year. The next few slides will show the advancement of the work underway. Turning to Slide 10. On the left-hand side is the primary crusher. As planned, the upward obtaining walls are now completed, and it is expected that the first part for the concrete slab for the base of the crusher building will be built in August. On the right-hand side is the filter plant area where you can see two drills are actively working, with the third one having recently arrived in July. The contract productivity has increased significantly and 270 piles are now completed, effectively finishing the piles required for the filter plant building. There are a total of 871 piles with the remainder to be completed for the ancillary buildings. In July 2024, preparation work for the concrete foundations on the filter plant have commenced, with assembly of the building structure to commence in Q3 2024, following the award of the filter plant construction contract. The inside photo shows a closer view of what will become the floor of the filter plant building once the concrete slab is poured. On the next two slides, you will see workers commenced on support infrastructure, including the process control room building, process plant substation, water pump station, lime plant, air blowers building, and flotation reagents plant areas. On Slide 11, these pictures are all on the west side of the main process plant building. On the left-hand side, you can see the secondary substation. On the picture on the right-hand side at the top is the pump house and the bottom is the process plant control room which, when completed, will be four levels high. On Slide 12, the photo shows the east side of the main process plant building. You can see where the reagents mixing building, compressors, air blowers, and lime building will be. We will continue to provide progress updates as we advance towards the first production in the third quarter of 2025. Moving to Olympias on Slide 13. Second quarter gold production was 13,541 ounces and total cash costs were $1,231 per ounce sold. Production was impacted by 17 days of labor-initiated work stoppages, primarily in June as we negotiated the new collective bargaining agreement. Total cash costs were positively impacted by the productivity efficiencies from the region transformation initiatives as well as slightly lower unit costs of certain consumables, including electricity. We also benefited from lower transport costs as a result of improved shipment logistics. For 2024, production guidance at Olympias is between 75,000 to 85,000 ounces of gold. Production in the second half of the year is expected to increase over the first half of the year as a result of expected increase in ore mined and processed. As George mentioned at the beginning of the call, we are in the final stages of the collective bargaining agreement negotiations. I'll stop there and hand over to Simon to discuss the Turkish and Canadian operations.
Simon Hille, Executive Vice President, Operations and Technical Services
Thanks, Louw. Starting on Turkey in Slide 14. At Kisladag, second quarter production was 38,990 ounces with total cash costs of $941 per ounce sold. Production was in line with our expectations as grades increased during the quarter as we saw higher tons placed on the pad. Total cash costs were impacted by increased royalties. To further advance our understanding and unlock opportunities within our ore body, we currently have a geometallurgical test work program underway. This program is evaluating the effects of ore type variability on the life of mine resource in order to refine the crushing, agglomeration, and heap leach circuits with an expectation of completing a study in 2025. The study will focus on optimal moisture, reagent addition, particle size, and incremental debottlenecking of processing plants to maximize value at Kisladag. Optimization of drum and belt agglomeration continues within the circuit to ensure product consistency and operability. For 2024, production guidance at Kisladag is between 180,000 and 195,000 ounces of gold. Production is expected to increase in the second half as compared to the first half of the year as we expect to achieve higher stacking rates. At Efemçukuru, on Slide 15, second quarter gold production was 22,397 ounces at a total cash cost of $1,087 per ounce sold. Gold production throughput and average gold grade at Efemçukuru were in line with the plan for the quarter. For 2024, production guidance at Efemçukuru is between 75,000 and 85,000 ounces of gold. Production in the second half of the year is expected to be relatively consistent with the first half of the year. And now moving to the Lamaque complex on Slide 16. Lamaque delivered a strong second quarter of 47,391 ounces and total cash costs of $759 per ounce sold. Production was positively impacted by higher grades during the third quarter, which were in line with expectations. The total cash cost increases were affected by higher sales volumes and the remaining increases were due to additional costs incurred in labor, contractors, and equipment rentals. The team is focused on increasing productivity with an aim to ramp up development and mucking rates in the Triangle and Ormaque deposits during the second half of the year. The Ormaque deposit remains on track to take a bulk sample, complete a prefeasibility study, and announce inaugural reserves by the end of 2024. We have advanced development to 190 meters at the end of June and plan monthly advancement ramping to 120 meters moving forward. For 2024, production guidance at Lamaque is between 175,000 and 190,000 ounces of gold. Production in the remainder of the year is expected to be stronger than the first half of the year as grades are expected to increase. I'll stop there and hand back to George for his closing remarks.
George Burns, President and CEO
Thanks, team. It's an exciting time at Eldorado. We are now just over a year away from bringing Skouries, our transformational copper gold project online, and it is rewarding to see the continued progress as we advance towards first gold. We expect Skouries to be a powerful catalyst to drive shareholder returns as we continue to deliver construction progress over the next year and production in Q3 2025. In addition, across our global operations, our teams continue to focus on continuous improvement projects with the objective to deliver safe, profitable ounces. I couldn't be more proud of this team. We also delivered another consistent quarter, which positions us well to achieve our production and cost guidance for 2024. In addition, the record high gold prices have benefited us significantly from margin expansion. Additionally, the jurisdictions in which we operate have also benefited from higher royalties and increased tax payments as a result of the higher gold price. By maintaining a disciplined focus on cost and capital allocation, coupled with higher gold prices, we continue to realize margin expansions resulting in continued growth in our free cash flow from operations. This positions us well to further build on our already strong cash balance and continue to create value for our stakeholders. Thank you for your time. I will now turn it over to the operator for questions from our analysts.
Operator, Operator
The first question comes from Mike Parkin with National Bank.
Michael Parkin, Analyst
Congrats on the good quarter. Starting with Kisladag. The CapEx trend that we're seeing, I guess, we could - is it still fair to assume that growth capital will be in and around how you're kind of trending in the last 12 months on a go-forward basis? Or are you still running at modestly elevated capital? Like when I look back a year or two ago, it was generally growth around $20-ish million. It's been more kind of mid- to high 20s, $32 million in Q2. How should we think about that kind of going forward?
George Burns, President and CEO
Well, I mean, at a high level, Mike, I would say we've gone through most of the growth capital involved with the HPGR or heap leach pad and agglomeration. This year, we're completing construction on the ADR plant. So you remember, we put the absorption part of the plant in last year. That's where we pulled the solution, the gold out of solution on the carbon. During the past year, we've been using the south lead pad to strip the gold out that carbon and the poured gold. So anyway, we're advancing now to add the absorption and recovery plant to the north leach plant pad. So it's not a lot of capital for that piece, but it's the last piece of that expansion for leaching. I mean the rest of our growth capital primarily is around stripping, and that will continue for the next six years or so, at which point, there will be a big drop off in stripping requirements for the remaining life of mine and an inflection point in free cash flow.
Michael Parkin, Analyst
And on production, are you getting all the production from the new pad now? Or is it still a blend? And if it is, do you have like - can you give us an idea of like what percentage is coming from the new pad versus the old pad?
Simon Hille, Executive Vice President, Operations and Technical Services
It's Simon. We through the course of 2024 and 2025, are still utilizing both the south and the north heap leach pad. As you know, we have a long lead cycle at Kisladag, so we need to ensure we have sufficient leach space to allow for that leach cycle to run to its full cycle. The percentage, we have to get back to you on the exact numbers, but we would see product north heap leach heap being more dominant moving forward in '25 and beyond that.
Michael Parkin, Analyst
Obviously, it's a heap leach. So like analysis of recovery rates is a little tricky. And then your long leach curve, as you pointed out, adds to that complexity. But if I look at like a trailing 12 months and I look back to like you added in the HPGRs, the agglomeration tie-in about a year ago. On the numbers you've been kind of posting, it does kind of bounce around based off grade and ounces stacked and everything. But it did seem like you were kind of in the mid- to high 50s, some quarters, even 60, but now you're kind of shifting down kind of sub-50. Is that what's kind of spurring this review in optimization? You talked about exceeding your budget on the sites over last fall. I'm just kind of wondering what's your thoughts there? Like I know the technical report had yet 56%, are you still seeing that as ultimately achievable? Or do you feel like there's maybe a need for additional tweaks beyond what that technical report called for?
George Burns, President and CEO
Maybe I'll frame into the high level, and Simon can add some color. So when you go back to the original studies, we have six different rock types that we looked at recoveries and the impact of the HPGR investment and then later the agglomeration, and those recoveries are variable. They run from low 50s to low 60s. And so part of the recoveries is just a matter of which ore types we are processing. And then beyond that, how fine we crush it, how well we agglomerate it also has implications on recovery for every one of those rock types. So it's a pretty complex geometallurgical situation. We've got quite a bit of data now since we started up the circuit. And so we're just leveraging off that information to say, all right. What can we do to further improve the circuit? So we'll be looking at debottlenecking the plant. We'll be looking at additional agglomeration impacts on recovery and maybe even debottlenecking the entire plant. So we're taking now that the circuit's up and running, we've got lots of data. We're going to take a wholesome full look at how the circuit is performing and what the opportunities are to make further improvement to NET asset value for ore at Kisladag. So I mean, high level, we're comfortable with that 56% but we're going to do study work and we're going to look to see where we have opportunities to improve.
Michael Parkin, Analyst
Regarding Olympias, you mentioned earlier that the labor agreement is still being worked on. Have there been any operational disruptions in July? Is there a possibility of experiencing daily disruptions while finalizing this? Also, do you have an estimate on when a signed agreement might be achieved? What is the duration of the contract—three years, two years, or five years?
Louw Smith, Executive Vice President, Development, Greece
Yes, Mike, it's Louw here. There have been no further interruptions in July. We expect to conclude the discussions over the next two weeks, and we are indeed nearing the end of these discussions.
Michael Parkin, Analyst
And just the term of the contract?
Louw Smith, Executive Vice President, Development, Greece
It will be a three-year contract.
Simon Hille, Executive Vice President, Operations and Technical Services
Mike, just before you go, those percentages stacked or planned for 2024, roughly around 66% on the south heap leach pad for this year and obviously, 33% for the north heap leach pad. That will probably migrate to higher numbers on the north in 2025.
Operator, Operator
Next question comes from Tanya Jakusconek with Scotiabank.
Tanya Jakusconek, Analyst
Maybe just a follow-up on the Olympias contract. Just for ourselves without getting into the nitty-gritty, but can we just assume in terms of wage increases to be in line with what has been sort of the inflation rate in the global mining sector, about 5% for labor? We're just trying to benchmark ourselves here.
George Burns, President and CEO
Yes, I don't want to go into details, but I can assure you that there will be no surprises regarding costs. We have negotiated a contract that benefits both the workforce and the company. We are concentrating on productivity initiatives, and the union is aiming for wage increases. Therefore, we do not anticipate any surprises, and we expect this to be positive for both parties.
Tanya Jakusconek, Analyst
Regarding the Skouries, there is only the filter plant contract that needs to be finalized, which is expected in the next couple of weeks. Is that the only outstanding contract? We have all the other contracts in place, including the underground work and, hopefully, the filter tailings contracts. We have everything necessary, and now it's just a matter of managing labor and training. Should I view it that way? It seems quite general, but I am trying to grasp from a broader perspective that we have all the essential components in place.
George Burns, President and CEO
Yes, I'd love to tell you every contract's been signed other than the filter plant. But really, it's all the material contracts. There are smaller contracts for ancillary buildings and so forth like a G&A building, or fine administrative building. Some of those aren't finalized, but they're not on the critical path and not going to impact production and we're on track with those types of contracts. But in terms of the material contracts required to get us into startup in Q3, it is just this last filter plant facility. And as Louw said, we're a couple of weeks from having that finalized. And we're not late in finalizing that contract and that we're still working on the piling, the concrete foundation and at which point then we can put up the building, so on track.
Tanya Jakusconek, Analyst
Going back to the labor agreement, George, I remember when we were on site, we discussed the need to get the labor force at Skouries established, possibly even increasing it. We also talked about the idea of potentially transferring some workers from your Olympias operation. Is there anything in this new contract that would prevent that from happening, or are there provisions being implemented to facilitate it? I'm just trying to gain clarity on the labor situation.
George Burns, President and CEO
Yes. Well, I mean, first of all, on the management side, we have moved some of our leadership team from Olympias over Skouries. And as a result, we have been able to promote and move people around within the Olympias workforce. In terms of mining, we're in the contract phase of both open pit or underground pit that are being driven by contractors. On the plant facility, we've got the operational leadership team in place. We're working now on the second level doing recruiting in Greece. And we're preparing the training facility or not the facility, but the training program for the hourly workforce. So that will ramp up in the second half of the year and accelerate in the first half of next year. So we're on track with all of that. There's no implications coming out of the negotiations on the Skouries build and looking uncomfortable on the labor side for operations.
Tanya Jakusconek, Analyst
And then just my final question and just more of a modeling question, so maybe someone can just help me out on here. Just on the depreciation. It looks like you're running well below, I annualize that you're well below the guidance level you've given us. So maybe someone can just help me understand why this depreciation, i.e., not being an accountant here. But should we be thinking of lowering are you thinking of it coming in lower than what your guidance is? Or is depreciation really going to ramp up in the second half of the year?
Paul Ferneyhough, CFO
Tanya, it's Paul. There are three important points to consider. First, in Q1, we had a small one-off adjustment that reduced first half depreciation. Second, we booked some additional reserves at the start of the year that were not included in the rates we used for our guidance, which slightly lowered the unit rates. Lastly, keep in mind that our production is back half weighted, with a split of 45% to 55%. As a result, we expect depreciation to increase by about 20% due to production in the second half, combined with the unit rates. While we are lower now, I would suggest anticipating the low end of our guidance at this time.
Tanya Jakusconek, Analyst
I wanted to clarify because the numbers seemed quite low. Regarding the 45% and 55%, as mentioned, while forecasting quarterly, I'm trying to determine if we should expect an improvement from one quarter to the next, or if Q3 will be similar to Q4. A significant factor is the grades, and there's also the leach time at Kisladag. I want to know if Kisladag is expected to perform better in Q4, and whether Lamaque and Olympias will also see great performance in both Q3 and Q4. I'm trying to understand how the 55% will be divided between Q3 and Q4.
Paul Ferneyhough, CFO
I mean just talking on the consolidated guidance, a stronger second half, we expect Q3 and Q4 both to be strong. And I think my seven years at Eldorado, the fourth quarter has been the strongest quarter every year and expect that to be the case again this year. So a ramp up quarter-over-quarter and 10% higher production in the second half, a bit higher in Q4.
Tanya Jakusconek, Analyst
If I could ask about the Kisladag study, we discussed the potential improvements at the mill, including agglomeration. Is the main goal to boost the NPV through increased throughput and recovery? I'm trying to grasp your end objectives and whether you're focusing on one area or multiple areas to enhance the NPV.
Simon Hille, Executive Vice President, Operations and Technical Services
Yes, I think you hit on the major topics there being that we're evaluating. As you know, we still have a long mine life at Kisladag. We are moving into Phase 5 and Phase 6. So we're just reassessing the geometallurgical performance as it relates to the plant and assessing the full plant capabilities to maximize capital invested, so that we can set the circuit up for that, and that's the purpose of the study so that we can evaluate those aspects that you mentioned.
Operator, Operator
Since there are no more questions in the queue, this concludes the question-and-answer session and today's conference call. You may disconnect your lines. Thank you for participating, and have a pleasant day.