6-K

Equinox Gold Corp. (EQX)

6-K 2024-05-09 For: 2024-03-31
View Original
Added on April 07, 2026

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

FORM 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO

RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of May, 2024.

Commission File Number: 001-39038

EQUINOX GOLD CORP.
(Translation of registrant’s name into English)
700 West Pender Street, Suite 1501, Vancouver, British Columbia, V6C 1G8
(Address of principal executive offices)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F ☐    Form 40-F

INCORPORATION BY REFERENCE

Exhibits 99.1, 99.2, 99.3 and 99.4 of this Form 6-K are incorporated by reference as additional exhibits to the registrant’s Registration Statement on Form F-10 (File No. 333-268499).

EXHIBIT INDEX

Exhibit Number Description
99.1 Condensed Consolidated Interim Financial Statements for the three months ended March 31, 2024 and 2023
99.2 Management’s Discussion and Analysis for the three months ended March 31, 2024
99.3 Consent of Scott Heffernan, M.Sc., P.Geo, dated May8, 2024scottheffernanconsent1.htm
99.4 Consent of Doug Reddy, M.Sc., P.Geo, dated May 8, 2024

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

EQUINOX GOLD CORP.
(Registrant)
Date: May 8, 2024 By: /s/ Susan Toews
Name: Susan Toews
Title: General Counsel

Document

Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Unaudited, expressed in thousands of United States dollars, unless otherwise stated)

eqxlogoonelinenoringsrgba.jpg

Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

CONTENTS
Condensed Consolidated Interim Statements of Financial Position 3
Condensed Consolidated Interim Statements of(Loss)Income 4
Condensed Consolidated Interim Statements of Comprehensive(Loss)Income 5
Condensed Consolidated Interim Statements of Cash Flows 6
Condensed Consolidated Interim Statements of Changes in Equity 7
Notes to the Consolidated Financial Statements
Note 1 – Nature of operations 8
Note 2 – Basis of preparation andmaterial accounting policies 8
Consolidated Statements of Financial Position
Note 3 – Marketable securities 9
Note 4 – Inventories 10
Note 5 – Mineral properties, plant and equipment 10
Note 6 – Investment in associate 11
Note 7 – Loans and borrowings 12
Note 8 – Deferred revenue 14
Note 9 – Derivative financial instruments 14
Note 10 – Share capital and share-based payments 16
Consolidated Statements of (Loss) Income
Note 11 – Operating expense 17
Note 12 – General and administration expense 18
Note 13 – Other(expense)income 18
Note 14 – Net(loss)income per share 18
Other Disclosures
Note 15 – Segment information 19
Note 16 – Supplemental cash flow information 20
Note 17 – Fair value measurements 20
Note 18 – Subsequent events 22

eqxlogoonelinenoringsrgba.jpg

Condensed Consolidated Interim Statements of Financial Position

At March 31, 2024 and December 31, 2023

(Expressed in thousands of United States dollars)

(Unaudited)

Note March 31,<br>2024 December 31,<br>2023
Assets
Current assets
Cash and cash equivalents $ 125,266 $ 191,995
Marketable securities 3 71,306 92,666
Trade and other receivables 65,487 82,307
Inventories 4 414,554 412,005
Derivative assets 9(a) 53 17,700
Prepaid expenses and other current assets 35,802 37,285
712,468 833,958
Non-current assets
Restricted cash 13,419 15,322
Inventories 4 214,807 200,368
Mineral properties, plant and equipment 5 3,274,269 3,225,213
Investment in associate 6 28,098 29,263
Deferred income tax assets 1,859
Other non-current assets 48,011 46,253
Total assets $ 4,292,931 $ 4,350,377
Liabilities and Equity
Current liabilities
Accounts payable and accrued liabilities $ 223,433 $ 246,522
Current portion of loans and borrowings 7 275,630 138,604
Current portion of deferred revenue 8 65,514 39,598
Current portion of derivative liabilities 9(b) 16,463 8,829
Other current liabilities 30,137 46,048
611,177 479,601
Non-current liabilities
Loans and borrowings 7 653,498 786,376
Deferred revenue 8 171,893 194,535
Reclamation and closure cost provisions 116,361 120,083
Derivative liabilities 9(b) 13,322 11,082
Deferred income tax liabilities 247,674 244,704
Other non-current liabilities 71,976 71,535
Total liabilities 1,885,901 1,907,916
Shareholders’ equity
Common shares 10(a) 2,140,217 2,085,565
Reserves 77,780 79,077
Accumulated other comprehensive loss (116,761) (70,730)
Retained earnings 305,794 348,549
Total equity 2,407,030 2,442,461
Total liabilities and equity $ 4,292,931 $ 4,350,377

Contingencies (notes 5(c) and 9(b)(iv))

Subsequent events (notes 7(a), 7(b), 10(a) and 18)

The accompanying notes form an integral part of these condensed consolidated interim financial statements.

eqxlogoonelinenoringsrgba.jpg

Condensed Consolidated Interim Statements of (Loss) Income

For the three months ended March 31, 2024 and 2023

(Expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

Note 2024 2023
Revenue $ 241,318 $ 234,090
Cost of sales
Operating expense 11 (183,768) (172,191)
Depreciation and depletion (46,188) (47,438)
(229,956) (219,629)
Income from mine operations 11,362 14,461
Care and maintenance expense (1,107)
Exploration and evaluation expense (2,474) (1,776)
General and administration expense 12 (14,141) (9,943)
(Loss) income from operations (5,253) 1,635
Finance expense (17,443) (12,692)
Finance income 1,972 2,959
Share of net income (loss) of associates 6 423 (15,982)
Other (expense) income 13 (13,906) 31,861
(Loss) income before taxes (34,207) 7,781
Income tax (expense) recovery (8,548) 9,622
Net (loss) income $ (42,755) $ 17,403
Net (loss) income per share
Basic 14 $ (0.13) $ 0.06
Diluted 14 $ (0.13) $ 0.05
Weighted average shares outstanding
Basic 14 323,989,015 311,563,097
Diluted 14 323,989,015 341,615,126

The accompanying notes form an integral part of these condensed consolidated interim financial statements.

eqxlogoonelinenoringsrgba.jpg

Condensed Consolidated Interim Statements of Comprehensive (Loss) Income

For the three months ended March 31, 2024 and 2023

(Expressed in thousands of United States dollars)

(Unaudited)

Note 2024 2023
Net (loss) income $ (42,755) $ 17,403
Other comprehensive (loss) income
Items that may be reclassified subsequently to net income or loss:
Foreign currency translation (24,479) (1,327)
Items that will not be reclassified subsequently to net income or loss:
Net decrease in fair value of marketable securities and other investments in equity instruments 3(a) (21,552) (1,093)
Income tax recovery relating to change in fair value of marketable securities and other investments in equity instruments 75
(46,031) (2,345)
Total comprehensive (loss) income $ (88,786) $ 15,058

The accompanying notes form an integral part of these condensed consolidated interim financial statements.

eqxlogoonelinenoringsrgba.jpg

Condensed Consolidated Interim Statements of Cash Flows

For the three months ended March 31, 2024 and 2023

(Expressed in thousands of United States dollars)

(Unaudited)

Note 2024 2023
Cash provided by (used in):
Operating activities
Net (loss) income for the period $ (42,755) $ 17,403
Adjustments for:
Depreciation and depletion 46,424 47,523
Finance expense 17,443 12,692
Share of net (income) loss of associates 6 (423) 15,982
Change in fair value of derivatives 13 14,585 (8,843)
Settlements of derivatives 9(b)(i), 9(b)(ii) 13,333 5,903
Unrealized foreign exchange loss 293 2,843
Net gain on sale of partial interest and reclassification of investment in i-80 Gold Corp. (“i-80 Gold”) (34,467)
Income tax expense (recovery) 8,548 (9,622)
Income taxes paid (7,250) (1,462)
Prepayments from gold sale contracts 139,524
Other (2,476) 7,889
Operating cash flow before changes in non-cash working capital 47,722 195,365
Changes in non-cash working capital 16 (29,817) (51,969)
17,905 143,396
Investing activities
Expenditures on mineral properties, plant and equipment (104,769) (127,904)
Purchases of marketable securities (6,697)
Proceeds from dispositions of marketable securities 53,359
Net proceeds from sale of partial interest in i-80 Gold 22,916
Other (3,995) 1,553
(108,764) (56,773)
Financing activities
Draw down on revolving credit facility 7 126,667
Repayment of loans and borrowings 7 (127,000)
Interest paid 7 (15,753) (14,257)
Lease payments (8,808) (8,526)
Net proceeds from issuance of shares 10(a) 49,203 16,593
Proceeds from exercise of warrants and stock options 10(a) 1,456 1,154
Proceeds from other financing activities 3,830
Transaction costs and other (1,191) (1,936)
24,907 (3,475)
Effect of foreign exchange on cash and cash equivalents (777) 990
(Decrease) increase in cash and cash equivalents (66,729) 84,138
Cash and cash equivalents – beginning of period 191,995 200,769
Cash and cash equivalents – end of period $ 125,266 $ 284,907

The accompanying notes form an integral part of these condensed consolidated interim financial statements.

eqxlogoonelinenoringsrgba.jpg

Condensed Consolidated Interim Statements of Changes in Equity

For the three months ended March 31, 2024 and 2023

(Expressed in thousands of United States dollars, except for share amounts)

(Unaudited)

Common Shares
Note Number Amount Reserves Accumulated other comprehensive loss Retained earnings Total
Balance –<br><br>December 31, 2023 318,013,861 $ 2,085,565 $ 79,077 $ (70,730) $ 348,549 $ 2,442,461
Shares issued in public offerings 10(a) 10,892,076 50,207 50,207
Shares issued on exercise of stock options and settlement of restricted share units 10(a) 897,208 5,449 (3,993) 1,456
Share-based compensation 2,696 2,696
Share issue costs (1,004) (1,004)
Net loss and total comprehensive loss (46,031) (42,755) (88,786)
Balance – March 31, 2024 329,803,145 $ 2,140,217 $ 77,780 $ (116,761) $ 305,794 $ 2,407,030
Balance –<br><br>December 31, 2022 307,365,588 2,035,974 41,620 (52,076) 326,262 2,351,780
Shares issued in public offerings 10(a) 4,369,615 16,936 16,936
Shares issued on exercise of warrants and stock options, and settlement of restricted share units 10(a) 584,396 4,179 (3,026) 1,153
Share-based compensation 1,843 1,843
Share issue costs (343) (343)
Dispositions of marketable securities 6,597 (6,597)
Net income and total comprehensive income (2,345) 17,403 15,058
Balance – March 31, 2023 312,319,599 $ 2,056,746 $ 40,437 $ (47,824) $ 337,068 $ 2,386,427

The accompanying notes form an integral part of these condensed consolidated interim financial statements.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

1.    NATURE OF OPERATIONS

Equinox Gold Corp. (the “Company” or “Equinox Gold”) was incorporated under the Business Corporations Act of British Columbia on March 23, 2007. Equinox Gold’s primary listing is on the Toronto Stock Exchange in Canada where its common shares trade under the symbol “EQX”. The Company’s shares also trade on the NYSE American Stock Exchange in the United States under the symbol “EQX”. The Company’s corporate office is at Suite 1501, 700 West Pender Street, Vancouver, British Columbia, Canada, V6C 1G8.

Equinox Gold is a mining company engaged in the operation, acquisition, exploration and development of mineral properties, with a focus on gold.

All of the Company’s principal properties are located in the Americas. The Company’s principal properties and material subsidiaries are wholly owned except for Greenstone Gold Mines LP, which is a joint operation that owns the Greenstone development project in which the Company has a 60% interest (note 18). Details of the Company’s principal properties, material subsidiaries and joint operation are as follows:

Location Principal property Principal activity Ownership interest
Subsidiary
Western Mesquite Mines, Inc. USA Mesquite Mine (“Mesquite”) Production 100 %
Castle Mountain Venture USA Castle Mountain Mine (“Castle Mountain”) Production 100 %
Desarrollos Mineros San Luis S.A. de C.V. Mexico Los Filos Mine Complex (“Los Filos”) Production 100 %
Mineração Aurizona S.A. Brazil Aurizona Mine (“Aurizona”) Production 100 %
Fazenda Brasileiro Desenvolvimento Mineral Ltda Brazil Fazenda Mine (“Fazenda”) Production 100 %
Mineração Riacho Dos Machados Ltda Brazil RDM Mine (“RDM”) Production 100 %
Santa Luz Desenvolvimento Mineral Ltda Brazil Santa Luz Mine <br>(“Santa Luz”) Production 100 %
Joint operation
Greenstone Gold Mines LP Canada Greenstone Project<br>(“Greenstone”) Development 60 %

2.    BASIS OF PREPARATION AND MATERIAL ACCOUNTING POLICIES

(a)Statement of compliance

These unaudited condensed consolidated interim financial statements have been prepared in accordance with International Accounting Standard (“IAS”) 34, Interim Financial Reporting as issued by the International Accounting Standards Board (“IASB”). These unaudited condensed consolidated interim financial statements do not include all of the information required for annual financial statements prepared using International Financial Reporting Standards (“IFRS”) and should be read in conjunction with the Company’s audited consolidated financial statements for the year ended December 31, 2023.

These unaudited condensed consolidated interim financial statements were approved and authorized for issuance by the Board of Directors on May 8, 2024.

(b)Presentation currency

Except as otherwise noted, these unaudited condensed consolidated interim financial statements are presented in United States dollars (“$”, “US dollars” or “USD”). All references to C$ are to Canadian dollars (“CAD”).

(c)Material accounting policies

Except as described in note 2(d), the material accounting policies applied in the preparation of these unaudited condensed consolidated interim financial statements are consistent with those applied and disclosed in the Company’s audited consolidated financial statements for the year ended December 31, 2023.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

2.    BASIS OF PREPARATION AND MATERIAL ACCOUNTING POLICIES (CONTINUED)

(d)Amended IFRS standards effective January 1, 2024

In January 2020, the IASB issued Classification of Liabilities as Current or Non-current (Amendments to IAS 1), which amended IAS 1, Presentation of Financial Statements (“IAS 1”) to clarify the requirements for presenting liabilities in the statement of financial position as current or non-current. In October 2022, the IASB issued Non-current Liabilities with Covenants, which amended IAS 1 to improve the information an entity provides when its right to defer settlement of a liability for at least 12 months after the reporting period is subject to compliance with covenants and to clarify how such compliance affects the classification of the liability as current or non-current.

For a liability to be classified as non-current, the amendments removed the requirement for the Company’s right to defer settlement of a liability for at least 12 months after the reporting period to be ‘unconditional’ and instead require that the Company’s right must exist at the end of the reporting period. In addition, the amendments clarify that: (a) classification is unaffected by management’s intentions or expectations about whether the Company will exercise its right to defer settlement; (b) for loan arrangements that are subject to covenants, only covenants that the Company must comply with on or before the reporting date affect the classification of a liability as current or non-current at such date; (c) if the Company’s right to defer settlement is subject to the Company complying with covenants on or before the reporting date, such covenants affect whether the Company’s right exists at the end of the reporting period even if compliance with the covenant is assessed only after the reporting period; and (d) the term settlement includes the transfer of the Company’s own equity instruments to the counterparty that results in the extinguishment of the liability, except when the settlement of the liability with the Company transferring its own equity instruments is at the option of the counterparty and such option has been classified as an equity instrument, separate from the host liability.

The amendments also require new disclosures for non-current liabilities that are subject to future covenants to help users understand the risk that those liabilities could become repayable within 12 months after the reporting date. The required disclosures include (i) the nature of the covenants; (ii) when the Company is required to comply with the covenants; (iii) the carrying amounts of the related liabilities; and (iv) facts and circumstances, if any, that indicate the Company may have difficulty complying with the covenants.

The Company applied the above amendments effective January 1, 2024. The amendments did not have any impact on the classification of the Company’s liabilities as at December 31, 2023. The Company has disclosed, in note 7(a), the required information relating to covenants to which it must comply in respect of its revolving credit facility, which is classified as non-current at March 31, 2024.

3.    MARKETABLE SECURITIES

Note March 31,<br>2024
Balance – beginning of period $ 92,666
Additions 213
Change in fair value 3(a) (21,573)
Balance – end of period 3(b) $ 71,306

(a)Change in fair value

During the three months ended March 31, 2024, the Company recognized a net loss of $21.6 million (2023 – $1.1 million) on remeasurement of the fair value of its investments in marketable securities, of which a total loss of $21.6 million (2023 – $1.1 million) was recognized in other comprehensive loss (“OCI”).

(b)i-80 Gold common shares held in escrow

On May 15, 2023, pursuant to an escrow agreement in respect of the i-80 Gold share purchase warrants issued by the Company on March 31, 2023, 5.8 million of the i-80 Gold common shares owned by the Company were deposited into an escrow account. The shares were released from escrow on March 31, 2024 upon expiry of the warrants.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

4.    INVENTORIES

March 31,<br>2024 December 31,<br>2023
Heap leach ore $ 496,230 $ 470,894
Stockpiled ore 38,232 52,890
Work-in-process 24,483 16,406
Finished goods 7,989 14,139
Supplies 62,427 58,044
Total inventories $ 629,361 $ 612,373
Classified and presented as:
Current $ 414,554 $ 412,005
Non-current(1) 214,807 200,368
$ 629,361 $ 612,373

(1)    Non-current inventories at March 31, 2024 and December 31, 2023 relate to heap leach ore at Mesquite and Castle Mountain.

At March 31, 2024, the Company’s total provision for obsolete and slow-moving supplies inventories was $13.8 million (December 31, 2023 – $14.8 million).

During the three months ended March 31, 2024, the Company recognized within cost of sales $5.5 million (2023 – $0.6 million) in write-downs of inventories to net realizable value, mainly relating to heap leach ore at Castle Mountain and Los Filos (2023 – RDM).

5.    MINERAL PROPERTIES, PLANT AND EQUIPMENT

Mineral properties<br><br>(note 5(a)) Plant and<br>equipment Construction-<br><br>in-progress<br><br>(note 5(b)) Exploration and evaluation assets Total
Cost
Balance – December 31, 2023 $ 2,217,943 $ 971,885 $ 746,138 $ 51,003 $ 3,986,969
Additions(1) 40,541 5,487 88,386 134,414
Transfers 77 7,817 (7,894)
Disposals and write-downs (16,553) (16,553)
Change in reclamation and closure cost asset (2,782) (2,782)
Foreign currency translation (10,027) (2,969) (16,990) (211) (30,197)
Balance – March 31, 2024 $ 2,245,752 $ 965,667 $ 809,640 $ 50,792 $ 4,071,851
Accumulated depreciation and depletion
Balance – December 31, 2023 $ 457,780 $ 303,976 $ $ $ 761,756
Depreciation and depletion 18,203 27,370 45,573
Disposals (9,437) (9,437)
Foreign currency translation (310) (310)
Balance – March 31, 2024 $ 475,983 $ 321,599 $ $ $ 797,582
Net book value
At December 31, 2023 $ 1,760,163 $ 667,909 $ 746,138 $ 51,003 $ 3,225,213
At March 31, 2024 $ 1,769,769 $ 644,068 $ 809,640 $ 50,792 $ 3,274,269

(1)Additions for the three months ended March 31, 2024 include the following non-cash additions: $7.2 million in additions to right-of-use assets included in plant and equipment, and $3.9 million and $2.7 million of depreciation and depletion capitalized to mineral properties and construction-in-progress, respectively. In addition, $15.6 million of borrowing costs incurred were capitalized to construction-in-progress.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

5.    MINERAL PROPERTIES, PLANT AND EQUIPMENT (CONTINUED)

(a)Non-depletable mineral properties

Mineral properties at March 31, 2024 that are currently not subject to depletion amount to $393.3 million and $44.1 million relating to Greenstone and Los Filos, respectively (December 31, 2023 – $403.4 million and $63.4 million, respectively).

(b)Construction-in-progress

During the three months ended March 31, 2024, the Company capitalized $74.1 million of costs, including capitalized borrowing costs of $15.6 million, to construction-in-progress at Greenstone.

(c)Geotechnical event at Aurizona

On March 27, 2024, due to persistent heavy rains in Maranhão, Brazil there was a displacement of material in two locations in the south wall of the Piaba pit at the Company’s Aurizona mine. As a result of this geotechnical event, access to the Piaba pit has been restricted and mining has been paused while the Company establishes a remediation plan. Milling and gold production continues from the ore stockpile, as is typical during the rainy season.

The Company will perform an updated geotechnical assessment of the Piaba pit and nearby infrastructure to determine what remediation is required for long-term stability. Once the outcome of the updated assessment is known the Company will assess whether there is an indicator of impairment and a requirement to perform an impairment test for the Aurizona mine.

Of the $3.3 billion of mineral properties, plant and equipment at March 31, 2024, $299.7 million relates to Aurizona.

6.    INVESTMENT IN ASSOCIATE

The Company’s investment in associate at March 31, 2024 represents its 20.3% (December 31, 2023 – 20.3%) interest in Sandbox Royalties Corp. (“Sandbox”).

The following table summarizes the changes in the carrying amount of the Company’s investment in Sandbox during the three months ended March 31, 2024:

March 31,<br>2024
Balance – beginning of period $ 29,263
Dilution loss (1,588)
Share of net income 423
Balance – end of period $ 28,098

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

6.    INVESTMENT IN ASSOCIATE (CONTINUED)

Summarized financial information in respect of Sandbox as at March 31, 2024 and December 31, 2023 is set out below. The summarized financial information is based on amounts included in Sandbox’s most recently available consolidated financial statements prepared in accordance with IFRS as at December 31, 2023 and September 30, 2023, respectively, and adjustments made by the Company in applying the equity method, including fair value adjustments on acquisition of its interest in the associate.

March 31,<br>2024 December 31,<br>2023
Cash and cash equivalents $ 6,720 $ 6,034
Other current assets 6,107 315
Non-current assets 144,911 69,756
Total assets 157,738 76,105
Current liabilities 226 414
Non-current liabilities 43,742 16,039
Total liabilities 43,968 16,453
Net assets (100%) $ 113,770 $ 59,652
Equinox Gold’s share of net assets(1) $ 23,071 $ 20,531
Adjustments to Equinox Gold’s share of net assets 5,027 8,732
Carrying amount $ 28,098 $ 29,263

(1)The Company’s share of net assets of Sandbox at March 31, 2024 is based on its 20.3% equity interest in Sandbox as of December 31, 2023 (December 31, 2023 – 34.4% equity interest as of September 30, 2023).

7.    LOANS AND BORROWINGS

Note March 31,<br>2024 December 31,<br>2023
Revolving credit facility 7(a) $ 527,897 $ 527,368
2023 convertible notes 125,601 123,720
2020 convertible notes 7(b) 136,094 135,288
2019 convertible notes 7(b) 139,536 138,604
Total loans and borrowings $ 929,128 $ 924,980
Classified and presented as:
Current(1) $ 275,630 $ 138,604
Non-current 653,498 786,376
$ 929,128 $ 924,980

(1)    The current portion of loans and borrowings at March 31, 2024 represents the outstanding principal under the 2020 convertible notes and 2019 convertible notes (December 31, 2023 – 2019 convertible notes).

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

7.    LOANS AND BORROWINGS (CONTINUED)

The following is a reconciliation of the changes in the Company’s loans and borrowings balance during the three months ended March 31, 2024 and 2023 to cash flows arising from financing activities:

2024 2023
Balance – beginning of period(1) $ 927,551 $ 828,024
Financing cash flows:
Draw down on revolving credit facility 126,667
Repayment of loans and borrowings (127,000)
Interest paid (15,753) (14,257)
Transaction costs (1,525)
Other changes:
Interest and accretion expense 22,393 16,424
Loss on modification of revolving credit facility 4,348
Balance – end of period(1) 934,191 832,681
Less: accrued interest(2) (5,063)
Balance – end of period, excluding accrued interest $ 929,128 $ 832,681

(1)    Includes accrued interest.

(2)    Included in accounts payable and accrued liabilities.

(a)Revolving credit facility

At March 31, 2024, there was $164.6 million undrawn on the Company’s revolving credit facility (the “Revolving Facility”).

The Revolving Facility is secured by a first-ranking security interest over all present and future property and assets of the Company and its material subsidiaries, and the Company’s present and future equity interests in Greenstone.

The Revolving Facility is subject to standard conditions and covenants. During the quarter, the Company amended certain of the financial covenants under the Revolving Facility. At March 31, 2024, the Company was in compliance with the applicable covenants. To maintain the classification of the liability as non-current, the Company is required to comply with future covenants which include: (a) a maximum senior net debt to earnings before interest, income taxes, depreciation and depletion, and certain other adjustments for the preceding 12 months (“Rolling EBITDA”) ratio; (b) a maximum total net debt to Rolling EBITDA ratio; (c) a minimum Rolling EBITDA to interest expense for the preceding 12 months ratio; (d) a minimum tangible net worth; and (e) minimum liquidity.

On April 9, 2024, the Company drew down $60 million on the Revolving Facility.

(b)2019 and 2020 convertible notes

The convertible notes issued in 2019 and 2020 that were set to mature on April 12, 2024 and March 10, 2025, respectively (the “2019 Convertible Notes” and “2020 Convertible Notes”, respectively), are secured by a second ranking security interest over all present and future assets of the Company and its material subsidiaries, and the Company’s present and future equity interests in Greenstone, and are subordinate to the Revolving Facility.

Subsequent to March 31, 2024, the maturity date of the 2019 Convertible Notes was extended to October 12, 2024 and the maturity date of the 2020 Convertible Notes was extended to September 10, 2025. In addition, the conversion price of the 2020 Convertible Notes was amended from $7.80 per share to $6.50 per share.

The 2019 Convertible Notes and 2020 Convertible Notes are subject to standard conditions and covenants. During the quarter, the Company amended certain of the financial covenants under the 2019 Convertible Notes and 2020 Convertible Notes. At March 31, 2024, the Company was in compliance with the applicable covenants.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

8.    DEFERRED REVENUE

Pursuant to the Sandbox arrangement, the Company delivered 1,500 ounces at an average price of $2,304 per ounce during the three months ended March 31, 2024. No ounces were delivered for the Gold prepay transactions as the delivery obligations commence on October 1, 2024.

The following table summarizes the changes in the carrying amounts of deferred revenue during the three months ended March 31, 2024:

Sandbox arrangement Gold prepay transactions Total
Balance – December 31, 2023 $ 75,061 $ 159,072 $ 234,133
Gold delivered (2,835) (2,835)
Accretion expense 2,915 3,194 6,109
Balance – March 31, 2024 $ 75,141 $ 162,266 $ 237,407
Classified and presented as:
Current(1) $ 15,242 $ 50,272 $ 65,514
Non-current 59,899 111,994 171,893
$ 75,141 $ 162,266 $ 237,407

(1)    The current portion of deferred revenue represents the amounts of gold expected to be delivered within 12 months of the reporting date.

9.    DERIVATIVE FINANCIAL INSTRUMENTS

(a)Derivative assets

The following is a summary of the Company’s derivative assets measured at fair value through profit or loss (“FVTPL”) at March 31, 2024 and December 31, 2023:

Note March 31,<br>2024 December 31,<br>2023
Foreign exchange contracts 9(b)(i) $ 56 $ 18,107
Other 87 89
$ 143 $ 18,196
Classified and presented as:
Current $ 53 $ 17,700
Non-current(1) 90 496
$ 143 $ 18,196

(1) Included in other non-current assets.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

9.    DERIVATIVE FINANCIAL INSTRUMENTS (CONTINUED)

(b) Derivative liabilities

The following is a summary of the Company’s derivative liabilities at March 31, 2024 and December 31, 2023:

Note March 31,<br>2024 December 31,<br>2023
Foreign exchange contracts 9(b)(i) $ 343 $ 35
Gold contracts 9(b)(ii) 14,580 4,009
Power purchase agreement 9(b)(iii) 2,502 4,420
Contingent consideration – Greenstone 9(b)(iv) 12,360 11,279
i-80 Gold warrant liability 168
$ 29,785 $ 19,911
Classified and presented as:
Current $ 16,463 $ 8,829
Non-current 13,322 11,082
$ 29,785 $ 19,911

(i)Foreign exchange contracts

In accordance with its foreign currency exchange risk management program, the Company uses foreign exchange contracts to manage its exposure to currency risk on expenditures in Brazilian Réal (“BRL”), Mexican Pesos (“MXN”) and Canadian dollars (“CAD”). At March 31, 2024, the Company had in place USD:BRL and USD:CAD put and call options with the following notional amounts, weighted average rates and maturity dates:

notional amount Call options’ weighted average strike price Put options’ weighted average strike price
Currency Within 1 year 1-2 years
BRL $ 16,000 4.98 5.34
CAD(1) 49,315 19,954 1.30 1.39

All values are in US Dollars.

(1)    USD notional amount calculated as the CAD notional amount translated using the USD:CAD spot exchange rate at March 31, 2024.

The following table summarizes the changes in the carrying amounts of the Company’s outstanding foreign exchange contracts during the three months ended March 31, 2024 and 2023:

2024 2023
Net asset – beginning of period $ (18,072) $ (4,702)
Settlements 14,323 5,419
Change in fair value 4,036 (18,493)
Net liability (asset) – end of period $ 287 $ (17,776)

The fair value of the outstanding foreign exchange contracts is presented as follows:

March 31,<br>2024 December 31,<br>2023
Net liability (asset) presented as:
Current derivative assets $ (53) $ (17,700)
Non-current derivative assets (3) (407)
Current derivative liabilities 112 35
Non-current derivative liabilities 231
$ 287 $ (18,072)

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

9.    DERIVATIVE FINANCIAL INSTRUMENTS (CONTINUED)

(ii)Gold contracts

During the three months ended March 31, 2024, the Company entered into gold collar contracts with a weighted average put and call strike price of $2,021 and $2,232, respectively, per ounce for a total notional quantity of 88,000 ounces over the period from February 2024 to December 2024. At March 31, 2024, the Company had 111,996 ounces remaining under its outstanding gold collar contracts which will be settled within one year of the reporting date with a weighted average put and call strike price of $2,008 and $2,221, respectively, per ounce.

At March 31, 2024, the Company also had financial swap agreements for gold bullion outstanding that were entered into in March 2023 and June 2023 in connection with the Company’s gold prepay transactions (note 8). Under the agreements, the Company will receive $2,170 and $2,109 per ounce in exchange for paying the spot price for 1,290 and 264 ounces per month, respectively, from October 2024 to July 2026.

The following table summarizes the changes in the carrying amounts of the Company’s outstanding gold contracts during the three months ended March 31, 2024 and 2023:

2024 2023
Balance – beginning of period $ 4,009 $
Change in fair value 11,561 4,962
Settlements (990) 484
Balance – end of period $ 14,580 $ 5,446

Of the total derivative liability relating to the gold contracts, $9.5 million (December 31, 2023 – $2.3 million) is included in current derivative liabilities and $5.1 million (December 31, 2023 – $1.7 million) is included in non-current derivative liabilities.

(iii)Power purchase agreement

At March 31, 2024, the fair value of the Company’s derivative liability relating to the power purchase agreement at Santa Luz for the delivery of 14.6 megawatts of power per hour at fixed prices over a period of 10 years to December 2032, was $2.5 million (December 31, 2023 – $4.4 million), of which $2.4 million (December 31, 2023 – $2.3 million) is included in current derivative liabilities and $0.1 million (December 31, 2023 – $2.1 million) is included in non-current derivative liabilities. During the three months ended March 31, 2024, the Company recognized a gain of $1.9 million (2023 – nil) on revaluation of the derivative liability within other (expense) income.

(iv)Contingent consideration - Greenstone

As part of the consideration for the Company’s acquisition of an additional 10% interest in Greenstone in April 2021, the Company assumed a contingent payment obligation to deliver approximately 2,200 ounces of refined gold, the cash equivalent value of such refined gold, or a combination thereof, after each production milestone of 250,000 ounces, 500,000 ounces and 700,000 ounces from Greenstone.

The fair value of the contingent consideration derivative liability at March 31, 2024 was $12.4 million (December 31, 2023 – $11.3 million), of which $4.4 million (December 31, 2023 – $4.0 million) is included in current derivative liabilities and $8.0 million (December 31, 2023 – $7.3 million) is included in non-current derivative liabilities. During the three months ended March 31, 2024, the Company recognized a loss of $1.1 million (2023 – $1.1 million) on revaluation of the derivative liability within other (expense) income.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

10.    SHARE CAPITAL AND SHARE-BASED PAYMENTS

(a)Share issuances

During the three months ended March 31, 2024, the Company issued 10.9 million (2023 – 4.4 million) common shares under its at-the-market equity offering program (the “ATM Program”) provided by the equity distribution agreement it entered into in November 21, 2022. Under the ATM Program, the Company may sell up to $100 million of its common shares through or to the agents at the prevailing market price at the time of sale until December 21, 2024. The common shares were issued at a weighted average share price of $4.61 (2023 – $3.88) per common share for total gross proceeds of $50.2 million (2023 – $16.9 million). At March 31, 2024, the Company had issued a cumulative total of 22.5 million (December 31, 2023 – 11.6 million) common shares under the ATM Program for total gross proceeds of $100.0 million (December 31, 2023 – $49.8 million).

The Company also issued 0.9 million common shares on exercise of stock options and settlement of restricted share units (“RSUs”) and restricted share units with performance-based vesting conditions (“pRSUs”) during the three months ended March 31, 2024 (2023 – 0.6 million on exercise of warrants and stock options, and settlement of RSUs and pRSUs). The weighted average exercise price of stock options exercised during the three months ended March 31, 2024 was C$5.20 per common share (2023 – C$5.30 and C$7.82 per common share for warrants and stock options exercised, respectively).

On April 26, 2024, the Company issued 56,419,000 common shares at a price of $5.30 per common share for aggregate gross proceeds of approximately $299 million (note 18).

(b)Share-based compensation plans

Equity-settled RSUs and pRSUs

During the three months ended March 31, 2024, the Company granted 1.1 million equity-settled RSUs to directors, officers and employees and 0.4 million equity-settled pRSUs to officers and employees with a weighted average grant date fair value of $4.46. The RSUs granted vest over a period of three years. The pRSUs granted are subject to a multiplier of 0% to 200% of the number of units granted based on the Company’s total shareholder return as compared to the S&P Global Gold Index over a three-year vesting period.

Cash-settled RSUs

During the three months ended March 31, 2024, the Company granted 0.7 million cash-settled RSUs to certain employees with a weighted average grant date fair value of $4.45. The RSUs granted vest over a period of three years.

11.    OPERATING EXPENSE

Operating expense during the three months ended March 31, 2024 and 2023 consists of the following expenses by nature:

2024 2023
Raw materials and consumables $ 66,462 $ 79,250
Salaries and employee benefits(1) 37,987 34,252
Contractors 45,556 48,653
Repairs and maintenance 15,803 15,796
Site administration 31,422 23,259
Royalties 6,131 5,101
203,361 206,311
Change in inventories (19,593) (34,120)
Total operating expense $ 183,768 $ 172,191

(1)    Total salaries and employee benefits, excluding share-based compensation, for the three months ended March 31, 2024, including amounts recognized within care and maintenance expense, exploration and evaluation expense and general and administration expense, was $44.2 million (2023 – $40.3 million).

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

12.    GENERAL AND ADMINISTRATION EXPENSE

General and administration expense during the three months ended March 31, 2024 and 2023 consists of the following expenses by nature:

2024 2023
Salaries and benefits $ 5,484 $ 5,071
Professional fees 3,134 567
Share-based compensation 3,357 1,924
Office and other expenses 1,936 2,344
Depreciation 230 37
Total general and administration expense $ 14,141 $ 9,943

13.    OTHER (EXPENSE) INCOME

Other (expense) income during the three months ended March 31, 2024 and 2023 consists of the following:

Note 2024 2023
Change in fair value of foreign exchange contracts 9(b)(i) $ (4,036) $ 18,493
Change in fair value of gold contracts 9(b)(ii) (11,561) (4,962)
Change in fair value of power purchase agreement 9(b)(iii) 1,928
Foreign exchange gain (loss) 473 (1,895)
Gain on sale of partial interest and reclassification of investment in i-80 Gold 34,467
Loss on modification of Revolving Facility (4,349)
Other expense (710) (9,893)
Total other (expense) income $ (13,906) $ 31,861

14.    NET (LOSS) INCOME PER SHARE

The calculations of basic and diluted net (loss) income per share (“EPS”) for the three months ended March 31, 2024 and 2023 were as follows:

2024 2023
Weighted<br>average shares<br>outstanding Net loss Net loss per share Weighted<br>average shares<br>outstanding Net income Net income<br>per share
Basic EPS 323,989,015 $ (42,755) $ (0.13) 311,563,097 $ 17,403 $ 0.06
Dilutive RSUs and pRSUs 3,233,961
Dilutive convertible notes 26,603,030 1,283
Dilutive stock options 182,331
Dilutive warrants 32,707 (72)
Diluted EPS 323,989,015 $ (42,755) $ (0.13) 341,615,126 $ 18,614 $ 0.05

The outstanding instruments that were not included in the calculation of diluted EPS as they were anti-dilutive for the three months ended March 31, 2024 were 71.8 million shares issuable for convertible notes, 6.1 million equity-settled RSUs and pRSUs and 0.7 million stock options (2023 – 17.9 million shares issuable for convertible notes, 0.2 million equity-settled pRSUs and 0.2 million stock options).

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

15.    SEGMENT INFORMATION

Operating results of operating segments are regularly reviewed by the Company’s chief operating decision maker to make decisions about resources to be allocated to the segment and to assess performance. The Company considers each of its mine sites as a reportable operating segment. The following table presents significant information about the Company’s reportable operating segments as reported to the Company’s chief operating decision maker:

Three months ended March 31, 2024
Revenue Operating<br>expense Depreciation<br>and depletion Exploration and evaluation<br>expense Other operating<br>expenses Income<br>(loss) from<br>operations
Mesquite $ 48,997 $ (28,038) $ (9,621) $ $ $ 11,338
Castle Mountain 10,001 (10,870) (1,184) (74) (2,127)
Los Filos 54,168 (46,624) (7,358) (121) 65
Aurizona 50,655 (33,368) (10,124) (1,339) 5,824
Fazenda 30,233 (21,909) (9,599) (457) (1,732)
RDM 23,137 (19,176) (3,016) 945
Santa Luz 24,127 (23,783) (5,286) (456) (5,398)
Greenstone
Corporate (27) (14,141) (14,168)
$ 241,318 $ (183,768) $ (46,188) $ (2,474) $ (14,141) $ (5,253)
Three months ended March 31, 2023
Revenue Operating<br>expense Depreciation<br>and depletion Exploration and evaluation<br>expense Other operating<br>expenses Income<br>(loss) from<br>operations
Mesquite $ 31,414 $ (24,488) $ (6,538) $ $ $ 388
Castle Mountain 8,563 (5,551) (903) (233) 1,876
Los Filos 75,049 (59,929) (14,052) (160) 908
Aurizona 50,479 (31,814) (9,756) (338) 8,571
Fazenda 30,097 (18,411) (9,108) (366) 2,212
RDM(1) 11,485 (9,437) (1,781) (1,107) (840)
Santa Luz 27,003 (22,561) (5,300) (447) (1,305)
Greenstone (226) (226)
Corporate (6) (9,943) (9,949)
$ 234,090 $ (172,191) $ (47,438) $ (1,776) $ (11,050) $ 1,635

(1)Other operating expenses for the three months ended March 31, 2023 at RDM relate to care and maintenance costs incurred.

Total assets Total liabilities
March 31,<br>2024 December 31,<br>2023 March 31,<br>2024 December 31,<br>2023
Mesquite $ 307,257 $ 297,252 $ (57,738) $ (65,312)
Castle Mountain 338,999 329,236 (22,055) (24,014)
Los Filos 1,180,253 1,171,265 (220,417) (227,567)
Aurizona 357,370 365,952 (46,107) (55,914)
Fazenda 93,783 94,065 (29,643) (30,746)
RDM 149,733 165,021 (24,119) (39,124)
Santa Luz 311,481 306,076 (28,864) (30,693)
Greenstone 1,336,908 1,300,441 (232,096) (227,533)
Corporate(1) 217,147 321,069 (1,224,862) (1,207,013)
$ 4,292,931 $ 4,350,377 $ (1,885,901) $ (1,907,916)

(1)Corporate assets at March 31, 2024 and December 31, 2023 include the Company’s investment in Sandbox (note 6).

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

15.    SEGMENT INFORMATION (CONTINUED)

Capital expenditures(1)
Three months ended March 31 2024 2023
Mesquite $ 990 $ 11,945
Castle Mountain 1,801 1,479
Los Filos 18,828 6,636
Aurizona 15,060 11,767
Fazenda 5,301 3,002
RDM 6,199 20,732
Santa Luz 5,324 82
Greenstone 80,911 98,717
Corporate 97
$ 134,414 $ 154,457

(1)Capital expenditures in the above table represents capital expenditures on an accrual basis. Expenditures on mineral properties, plant and equipment in the consolidated statement of cash flows for the three months ended March 31, 2024 represent capital expenditures on a cash basis which excludes non-cash additions and capitalized borrowing costs (note 5) and includes a decrease in accrued expenditures of $0.2 million (2023 – capital expenditures on the consolidated statement of cash flows excludes $22.6 million of non-cash additions to right-of-use assets, $3.1 million of capitalized depreciation and depletion, and capitalized borrowing costs of $7.4 million, and includes a decrease in accrued expenditures of $6.2 million).

16.    SUPPLEMENTAL CASH FLOW INFORMATION

The changes in non-cash working capital during the three months ended March 31, 2024 and 2023 were as follows:

2024 2023
Decrease in trade and other receivables $ 11,126 $ 1,916
Increase in inventories (24,501) (39,474)
Decrease in prepaid expenses and other current assets 1,374 7,505
Decrease in accounts payable, accrued liabilities and other current liabilities (17,816) (21,916)
Changes in non-cash working capital $ (29,817) $ (51,969)

17.    FAIR VALUE MEASUREMENTS

Fair value is the price that would be received to sell an asset or paid to transfer a liability in an orderly transaction between market participants at the measurement date. The fair value hierarchy categorizes inputs to valuation techniques used in measuring fair value into the following three levels:

Level 1 – quoted prices (unadjusted) in active markets for identical assets or liabilities.

Level 2 – inputs other than quoted market prices included in Level 1 that are observable for the asset or liability, either directly, such as prices, or indirectly (derived from prices).

Level 3 – unobservable inputs for which market data are not available.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

17.    FAIR VALUE MEASUREMENTS (CONTINUED)

(a)Financial assets and financial liabilities measured at fair value

The fair values of the Company’s financial assets and financial liabilities that are measured at fair value in the statement of financial position and the levels in the fair value hierarchy into which the inputs to the valuation techniques used to measure the fair values are categorized are as follows:

At March 31, 2024 Level 1(3) Level 2(4) Level 3(5) Total
Marketable securities $ 71,306 $ $ $ 71,306
Derivative assets(1) 143 143
Other financial assets(2) 27,109 27,109
Derivative liabilities(1) (14,923) (14,862) (29,785)
Net financial assets (liabilities) $ 71,306 $ 12,329 $ (14,862) $ 68,773
At December 31, 2023
Marketable securities $ 92,666 $ $ $ 92,666
Derivative assets(1) 18,196 18,196
Other financial assets(2) 25,200 25,200
Derivative liabilities(1) (4,212) (15,699) (19,911)
Net financial assets (liabilities) $ 92,666 $ 39,184 $ (15,699) $ 116,151

(1)Includes current and non-current derivatives (note 9).

(2)Other financial assets measured at fair value relate to the Company’s convertible note receivable from Bear Creek Mining Corporation (“Bear Creek”) included in other non-current assets.

(3)The fair values of marketable securities are based on the quoted market price of the underlying securities.

(4)The fair values of derivative assets and certain derivative liabilities are measured using Level 2 inputs. The fair values of the Company’s foreign currency contracts are based on forward foreign exchange rates and the fair values of the Company’s gold contracts are based on forward metal prices.

The fair value of the Bear Creek convertible note is determined using FINCAD’s convertible debt valuation model based on the contractual terms of the convertible note and market-derived inputs including Bear Creek’s share price and share price volatility, and a market interest rate that reflects the risks associated with the financial instrument.

(5)The fair values of the Company’s power purchase and contingent consideration derivative liabilities are measured using Level 3 inputs.

The fair value of the Company’s power purchase derivative liability at Santa Luz is calculated as the net present value of the expected future cash flows based on contractual and projected future energy prices discounted using a market interest rate that reflects the risks associated with the liability.

The fair value of the contingent consideration derivative liability relating to Greenstone is calculated as the present value of projected future cash flows using a market-interest rate that reflects the risk associated with the delivery of the contingent consideration. The projected cash flows are affected by assumptions related to the achievement of production milestones.

There were no amounts transferred between levels of the fair value hierarchy during the three months ended March 31, 2024.

(b)Financial assets and financial liabilities not already measured at fair value

At March 31, 2024 and December 31, 2023, the carrying amounts of the Company’s cash and cash equivalents, trade and other current receivables, restricted cash, and trade payables and accrued liabilities approximate their fair values due to the short-term nature of the instruments.

eqxlogoonelinenoringsrgba.jpg

Notes to Condensed Consolidated Interim Financial Statements

For the three months ended March 31, 2024 and 2023

(Tabular amounts expressed in thousands of United States dollars, except share and per share amounts)

(Unaudited)

17.    FAIR VALUE MEASUREMENTS (CONTINUED)

The fair values of the Company’s other financial assets and financial liabilities, excluding lease liabilities, that are not measured at fair value in the statement of financial position as compared to the carrying amounts were as follows:

March 31, 2024 December 31, 2023
Level Carrying amount Fair value Carrying amount Fair value
Revolving Facility(1) 2 $ 527,897 $ 539,004 $ 527,368 $ 539,454
2023 Convertible Notes(2) 1 125,601 200,747 123,720 181,453
2020 Convertible Notes(2) 2 136,094 144,537 135,288 142,203
2019 Convertible Notes(2) 2 139,536 160,070 138,604 147,033
Equipment financing facility(3) 2 30,379 31,133 31,070 31,710

(1)The fair value of the Revolving Facility (note 7(a)) is calculated as the present value of future cash flows based on the contractual cash flows discounted using a market rate of interest for similar instruments.

(2)The carrying amounts of the convertible notes issued in September 2023 (“2023 Convertible Notes”), 2020 Convertible Notes and 2019 Convertible Notes represent the liability components of the convertible notes (note 7), while the fair values represent the liability and equity components of the convertible notes. The fair value of the 2023 Convertible Notes is based on the quoted market price of the underlying securities. The fair value of the 2020 Convertible Notes at March 31, 2024 represents the fair value of the liability component of $133.8 million (December 31, 2023 – $132.8 million) and the fair value of the equity component of $10.8 million (December 31, 2023 – $9.4 million). The fair value of the 2019 Convertible Notes at March 31, 2024 represents the fair value of the liability component of $138.8 million (December 31, 2023 – $138.1 million) and the fair value of the equity component of $21.3 million (December 31, 2023 – $8.9 million). The fair values of the liability components of the 2020 Convertible Notes and 2019 Convertible Notes are calculated as the present value of future cash flows based on the contractual cash flows discounted using a market rate of interest for similar instruments.

(3)The fair value of the Company’s equipment financing facility at Greenstone (the “Equipment Facility”) is calculated as the present value of future cash flows based on the contractual cash flows discounted using a market rate of interest for similar instruments. At March 31, 2024, $26.3 million (December 31, 2023 – $27.2 million) of the carrying amount of the Equipment Facility is included in other non-current liabilities and the remaining $4.1 million (December 31, 2023 – $3.9 million) is included in other current liabilities.

18.    SUBSEQUENT EVENTS

On April 23, 2024, the Company announced it had entered into a binding share purchase agreement (the ‘SPA”) with certain funds managed by Orion Mine Finance Management LP (“Orion”) to acquire Orion’s 40% interest in Greenstone (the “Transaction”). Upon closing of the Transaction, the Company would own 100% of Greenstone. Under the terms of the SPA, the consideration to be paid by the Company consists of $705 million in cash on closing, $40 million cash payable by December 31, 2024 and 42.0 million common shares of the Company. Closing of the Transaction is subject to customary closing conditions, including the receipt of certain regulatory approvals.

In connection with the Transaction, the Company received commitments from a syndicate of banks for a $500 million three-year term loan (the “Term Loan”) which will be used to partially fund the cash consideration payable pursuant to the SPA. The Term Loan will have a three-year term with no principal payments during the first two years. Commencing two years after the closing date, the Term Loan will be repaid in quarterly installments equal to 10% of the then outstanding principal amount of the Term Loan, with the remaining principal amount to be repaid at maturity.

Concurrent with the announcement of the Transaction, the Company entered into an agreement for a bought deal equity financing of up to 49,060,000 common shares of Equinox Gold at a price of $5.30 per common share, with a 15% over-allotment option (the “Offering”). The Offering closed on April 26, 2024 with the Company issuing 56,419,000 common shares for aggregate gross proceeds of approximately $299 million. The Company intends to use a portion of the proceeds from the Offering to partially fund the cash consideration payable pursuant to the SPA.

22

Document

Management’s Discussion and Analysis

For the three months ended March 31, 2024

(Expressed in United States Dollars, unless otherwise stated)

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

This Management’s Discussion and Analysis (“MD&A”) of the financial position and results of operations for Equinox Gold Corp. (the “Company” or “Equinox Gold”) should be read in conjunction with the audited consolidated financial statements of the Company as at and for the year ended December 31, 2023 and the unaudited condensed consolidated interim financial statements of the Company for the three months ended March 31, 2024 and the related notes thereto, which have been prepared in accordance with International Financial Reporting Standards (“IFRS”) as issued by the International Accounting Standards Board. For further information on the Company, reference should be made to its public filings on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar.

This MD&A is prepared by management and approved by the Board of Directors as of May 8, 2024. This discussion covers the three months ended March 31, 2024 (“Q1 2024” or the “Quarter”) and the subsequent period up to the date of issuance of this MD&A. All dollar amounts are in United States Dollars (“USD”), except where otherwise noted.

This MD&A contains forward-looking statements. Readers are cautioned as to the risks and uncertainties related to the forward-looking statements, the risks and uncertainties associated with investing in the Company’s securities, and the risks and uncertainties associated with technical and scientific information under National Instrument 43-101 (“NI 43-101”) concerning the Company’s material properties, including information about mineral reserves and mineral resources.

Throughout this MD&A, cash costs, cash costs per ounce (“oz”) sold, all-in sustaining costs (“AISC”), AISC per oz sold, AISC contribution margin, adjusted net income, adjusted earnings per share (“EPS”), mine-site free cash flow, EBITDA (earnings before interest, taxes, depreciation and amortization), adjusted EBITDA, net debt, and sustaining capital expenditures are non-IFRS financial measures with no standard meaning under IFRS. Non-IFRS measures are further discussed in the Non-IFRS Measures section of this MD&A.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || CONTENTS | | | --- | --- | | Business Overview | 4 | | Highlights for the Three Months EndedMarch 31, 2024 | 4 | | Recent Developments | 5 | | Consolidated Operational and Financial Highlights | 6 | | Operations | 8 | | Development Projects | 22 | | Health, Safety and Environment | 23 | | Community Development and ESG Reporting | 23 | | Corporate | 24 | | Financial Results | 25 | | Liquidity and Capital Resources | 28 | | Outstanding Share Data | 29 | | Commitments and Contingencies | 29 | | Related Party Transactions | 30 | | Non-IFRS Measures | 30 | | Accounting Matters | 34 | | Internal Controls Over Financial Reporting and Disclosure Controls and Procedures | 35 | | Cautionary Notes and Forward-looking Statements | 35 | | Technical Information | 37 | | eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || BUSINESS OVERVIEW | | --- |

Operations Description

Equinox Gold is a growth-focused mining company delivering on its strategy of creating the premier Americas gold producer. In its first six years the Company has grown from a single-asset developer to a multi-asset gold producer with seven operating gold mines in the Americas, an eighth mine expected to commence operations in 2024, a multi-million-ounce gold reserve base and a strong growth profile from a pipeline of expansion projects. At the date of this MD&A, the Company’s operating gold mines are the Mesquite Mine (“Mesquite”) and Castle Mountain Mine (“Castle Mountain”) in the United States, the Los Filos Mine Complex (“Los Filos”) in Mexico, and the Aurizona Mine (“Aurizona”), Fazenda Mine (“Fazenda”), RDM Mine (“RDM”) and Santa Luz Mine (“Santa Luz”) in Brazil. The Company also has the Greenstone Project (“Greenstone”) in Canada, which had begun commissioning at year-end 2023 and is on track to pour gold in the first half of 2024.

Equinox Gold was created with the strategic vision of building a diversified, Americas-focused gold company that will responsibly and safely produce more than one million ounces of gold annually, bring long-term social and economic benefits to its host communities, create a safe and rewarding workplace for its employees and contractors, and provide above average investment returns to its shareholders. To achieve its growth objectives, Equinox Gold intends to expand production from its current asset base through exploration and development and will also consider opportunities to acquire other companies, producing mines and development projects that fit the Company’s portfolio and strategy.

Equinox Gold’s common shares trade under the symbol “EQX” on the Toronto Stock Exchange (“TSX”) in Canada and on the NYSE American Stock Exchange (“NYSE-A”) in the United States.

HIGHLIGHTS FOR THE THREE MONTHS ENDED MARCH 31, 2024

Operational

•Produced 111,725 ounces of gold

•Sold 116,504 ounces of gold at an average realized gold price of $2,066 per oz

•Total cash costs of $1,567 per oz and AISC of $1,950 per oz(1)

•Two lost-time injuries; total recordable injury frequency rate(2) of 1.55 per million hours worked for the 12-month rolling period (1.61 for the Quarter)

•Significant environmental incident frequency rate(2) per million hours worked of 0.30 per million hours worked for the 12-month rolling period (0.00 for the Quarter)

Earnings

•Income from mine operations of $11.4 million

•Net loss of $42.8 million or $0.13 per share (basic)

•Adjusted net loss of $14.4 million or $0.04 per share(1)

Financial

•Cash flow from operations before changes in non-cash working capital of $47.7 million ($17.9 million after changes in non-cash working capital)

•Adjusted EBITDA of $52.2 million(1)

•Sustaining expenditures of $44.6 million and non-sustaining expenditures of $69.3 million

Corporate

•Provided 2024 production and cost guidance of 660,000 to 750,000 ounces of gold at cash costs of $1,340 to $1,445 per oz and AISC of $1,630 to $1,740 per oz(1)

•Provided 2024 sustaining and non-sustaining expenditure guidance of $424 million

◦$212 million of sustaining expenditures, of which $196 million is sustaining capital expenditures(1)

◦$213 million of non-sustaining expenditures, of which $205 million is non-sustaining capital expenditures

◦Non-sustaining capital expenditures includes $95 million to advance Greenstone to commercial production

•For the three months ended March 31, 2024, the Company issued 10.9 million common shares under its at-the-market equity program (“ATM Program”) at a weighted average share price of $4.61 per common share for total gross proceeds of $50.2 million

(1)Cash costs per oz sold, AISC per oz sold, sustaining capital, sustaining expenditures, adjusted net income, adjusted EBITDA, adjusted EPS, and net debt are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.
(2)Total recordable injury frequency rate (“TRIFR”) and significant environmental incident frequency rate (“SEIFR”) are both reported per million hours worked. TRIFR is the total number of injuries excluding those requiring simple first aid treatment. eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024
--- HIGHLIGHTS FOR THE THREE MONTHS ENDED MARCH 31, 2024 (CONTINUED)
---

Construction, Development and Exploration

•Advanced Greenstone commissioning:

◦Commissioned crushing circuit, ore storage dome, high-pressure grinding rolls (HPGR), ball mill #1, and thickener and leach tanks; loaded flocculant and lime into the system during last week of March

◦More than 1.5 million tonnes of ore stockpiled for startup

◦Spent $54 million (Equinox Gold’s 60% share) during the Quarter

◦On track to achieve production in Q2 2024

◦Completed approximately 6.4 million hours project-to-date with 1 lost-time injury; 12-month rolling average TRIFR of 2.03

RECENT DEVELOPMENTS

•Commenced processing ore at Greenstone

◦Ore introduced into the grinding circuit on April 6, 2024

◦First gold pour expected in May, commercial production targeted by the end of Q3 2024

•On April 23, 2024, the Company announced it had entered into a binding share purchase agreement (“SPA”) with certain funds managed by Orion Mine Finance Management LP (“Orion”) to acquire Orion’s 40% interest in Greenstone Gold Mine GP Inc. (the “Transaction”), giving Equinox Gold 100% ownership of Greenstone

◦Equinox Gold will pay $995 million to acquire Orion’s 40% interest in Greenstone, payable as:

▪42 million common shares of Equinox Gold valued at $250 million;

▪$705 million in cash payable on closing; and

▪$40 million cash payable by December 31, 2024

◦Equinox Gold will fund the cash consideration with net proceeds from a new $500 million three-year term loan and a bought deal equity financing of 49,060,000 common shares of Equinox Gold at a price of $5.30 per common share (the “Offering”) for aggregate gross proceeds of approximately $260 million

◦The $500 million term loan will include a requirement that Equinox Gold hedge 15% of anticipated gold production through mid-2026

◦On April 26, 2024, the Company announced that the Offering, including an over-allotment option, has closed and the Company has issued 56,419,000 common shares for aggregate gross proceeds of $299 million

◦The Transaction is expected to close in Q2 2024, subject to customary closing conditions and receipt of certain regulatory and other approvals

•Subsequent to March 31, 2024, extended existing 2019 and 2020 convertible notes

◦Maturity date of the $139.7 million principal 5.00% convertible notes due April 12, 2024 (the “2019 Convertible Notes”) extended by six months to October 12, 2024

◦Maturity date of the $139.3 million principal 4.75% convertible notes due March 10, 2025 (the “2020 Convertible Notes”) extended by six months to September 10, 2025 and conversion price amended from $7.80 to $6.50

•On April 8, 2024, the Company reported a geotechnical event at Aurizona and a pause of mining activities while the Company establishes a remediation plan; milling and gold production continued from the ore stockpile through April. Subsequently, the Company commenced mining of the Tatajuba open pit at Aurizona and anticipates a ramp-up of mining activities to produce ore for plant feed by June 2024

•On April 9, 2024, the Company drew down $60.0 million on the Company’s revolving credit facility (the “Revolving Facility”)

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || CONSOLIDATED OPERATIONAL AND FINANCIAL HIGHLIGHTS | | --- || | | Three months ended | | | | --- | --- | --- | --- | --- | | Operating data | Unit | March 31,<br>2024 | December 31, 2023 | March 31,<br>2023 | | Gold produced | oz | 111,725 | 154,960 | 122,746 | | Gold sold | oz | 116,504 | 149,861 | 123,295 | | Average realized gold price | $/oz | 2,066 | 1,983 | 1,895 | | Cash costs per oz sold(1)(2) | $/oz | 1,567 | 1,330 | 1,346 | | AISC per oz sold(1)(2) | $/oz | 1,950 | 1,657 | 1,658 | | Financial data | | | | | | Revenue | M$ | 241.3 | 297.8 | 234.1 | | Income from mine operations | M$ | 11.4 | 38.6 | 14.5 | | Net income (loss) | M$ | (42.8) | 3.9 | 17.4 | | Net income (loss) per share (basic) | $/share | (0.13) | 0.01 | 0.06 | | Adjusted EBITDA(1) | M$ | 52.2 | 95.3 | 57.0 | | Adjusted net income (loss)(1) | M$ | (14.4) | 2.4 | (8.2) | | Adjusted EPS(1) | $/share | (0.04) | 0.01 | (0.03) | | Balance sheet and cash flow data | | | | | | Cash and cash equivalents (unrestricted) | M$ | 125.3 | 192.0 | 284.9 | | Net debt(1) | M$ | 803.9 | 733.0 | 547.8 | | Operating cash flow before changes in non-cash working capital | M$ | 47.7 | 168.2 | 195.4 |

(1)Cash costs per oz sold, AISC per oz sold, adjusted EBITDA, adjusted net loss, adjusted EPS and net debt are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Consolidated AISC per oz sold excludes corporate general and administration expenses.

(3)Numbers in tables throughout this MD&A may not sum due to rounding.

Gold ounces sold in Q1 2024 were 6% lower compared to Q1 2023 primarily due to planned lower production at Los Filos, offset partially by higher production at Mesquite and RDM. At Los Filos, the lower production was planned as a result of mine sequencing, with more waste stripping during the Quarter as compared to Q1 2023, as well as the crusher being offline for most of the Quarter due to a planned repositioning of a portion of the conveyor. At Mesquite, the higher production was mainly due to higher ore tonnes stacked on the leach pad as a result of contribution from three pits during the Quarter compared to one pit in Q1 2023. At RDM, production was higher as a result of higher grades mined from in situ mining. RDM’s main ore source for Q1 2023 was from lower grade stockpiles.

Revenue was higher in Q1 2024 compared to Q1 2023 primarily due to a 9% increase in realized gold prices, offset partially by a decrease in gold ounces sold. The Company realized $2,066 per ounce sold in Q1 2024 generating $241.3 million in revenue, compared to $1,895 per ounce sold in Q1 2023 generating $234.1 million in revenue.

Cash cost per oz sold and AISC per oz sold were 16% and 18% higher in Q1 2024 compared to Q1 2023, respectively, primarily driven by lower production at Los Filos and higher costs at Fazenda and Santa Luz, offset partially by the impact of higher production at Mesquite. While input costs were generally lower in 2024, the impact of the strengthening of the Mexican Peso (“MXN”) and Brazilian Réal (“BRL”) compared to the USD more than offset these lower costs in Mexico and Brazil in Q1 2024.

In Q1 2024, income from mine operations was $11.4 million compared to $14.5 million in Q1 2023. The lower income from mine operations in Q1 2024 compared to Q1 2023 was mainly the result of lower income from operations at Castle Mountain, Fazenda and Santa Luz, offset partially by higher income from mine operations at Mesquite. Income from mine operations at Castle Mountain and Fazenda were impacted by higher operating costs, while Santa Luz was impacted by lower production compared to Q1 2023. The increase in Mesquite’s income from mine operations in Q1 2024 compared to Q1 2023 was driven by higher production compared to Q1 2023. Additionally, all sites benefited from higher realized gold prices, offset partially by the impact of the strengthening of the MXN and BRL on the Company’s Los Filos and Brazil operations.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || CONSOLIDATED OPERATIONAL AND FINANCIAL HIGHLIGHTS (CONTINUED) | | --- |

The net loss for Q1 2024 was $42.8 million (Q1 2023 - net income of $17.4 million). The net loss in Q1 2024 compared to net income in Q1 2023 was primarily due to other expense of $13.9 million in Q1 2024 compared to other income of $31.9 million in Q1 2023, in addition to lower income from mine operations and higher general and administrative and finance expense compared to Q1 2023 (refer to Financial Results section). Other expense in Q1 2024 was primarily due to a $11.6 million loss on the change in fair value of gold contracts as a result of an increase in average forward gold prices during the Quarter. Other income in Q1 2023 was primarily due to a $34.5 million gain on sale of the Company’s partial interest and reclassification of investment in i-80 Gold Corp.

In Q1 2024, adjusted EBITDA was $52.2 million (Q1 2023 - $57.0 million). In Q1 2024, adjusted net loss was $14.4 million (Q1 2023 - $8.2 million). The decrease in adjusted EBITDA and increase in adjusted net loss was primarily due to lower income from mine operations, a higher realized loss on foreign exchange and higher general and administrative expense compared to Q1 2023, offset partially by the impact of a $14.3 million realized gain on foreign exchange contracts in Q1 2024 compared to a realized gain of $5.4 million in Q1 2023. The increase in the adjusted net loss between periods was also due to higher finance expense compared to Q1 2023.

Sustaining and Non-sustaining Expenditures(1)

Three months ended March 31, 2024 Three months ended March 31, 2023
$ amounts in millions Sustaining Non-sustaining Sustaining Non-sustaining
Canada
Greenstone(3)(4) $ $ 52.8 $ $ 85.8
USA
Mesquite 0.8 4.1 10.2 4.5
Castle Mountain 1.5 1.3 0.3 1.4
Mexico
Los Filos 17.4 6.6 0.2
Brazil
Aurizona 15.0 2.2 10.9 1.1
Fazenda 3.4 2.7 1.6 1.6
RDM 1.0 5.6 2.8
Santa Luz 5.4 0.8 0.1 0.4
Total sustaining and non-sustaining expenditures(2) $ 44.6 $ 69.3 $ 32.5 $ 95.0

(1)Sustaining and non-sustaining expenditures include exploration expense and capital expenditures. Sustaining and non-sustaining expenditures exclude non-cash additions including right-of-use asset additions, capitalized interest expense and capitalized depreciation expense. Sustaining expenditures is a non-IFRS measure. See Non-IFRS Measures and Cautionary Notes.

(2)Total sustaining and non-sustaining capital expenditures for the three months ended March 31, 2024 were $39.0 million and $59.6 million, respectively (three months ended March 31, 2023 - $32.5 million and $88.4 million, respectively).

(3)For the three months ended March 31, 2024, non-sustaining expenditures at Greenstone exclude capitalized interest of $15.6 million (three months ended March 31, 2023 - $7.4 million).

(4)Non-sustaining expenditures at Greenstone reflect the Company’s 60% ownership of the project.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || OPERATIONS | | --- |

Mesquite Gold Mine, California, USA

Mesquite is an open pit, run-of-mine (“ROM”) heap leach gold mine located in Imperial County, California, approximately 200 miles south of Castle Mountain. Mesquite has been in production since 1986 and was acquired by Equinox Gold in Q4 2018.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined and stacked on leach pad kt 2,786 3,844 1,428
Waste mined kt 11,909 8,067 13,357
Open pit strip ratio w:o 4.27 2.10 9.35
Average gold grade stacked to leach pad g/t 0.35 0.52 0.24
Gold produced oz 22,025 25,923 16,405
Gold sold oz 23,783 24,190 16,406
Financial data
Revenue(2) M$ 49.0 48.6 31.4
Cash costs(1) M$ 27.4 25.9 18.5
Sustaining capital(1) M$ 0.1 10.2
Sustaining lease payments M$
Reclamation expenses M$ 0.8 (0.1) 0.5
Total AISC(1) M$ 28.2 25.9 29.2
AISC contribution margin(1) M$ 20.7 22.7 2.2
Non-sustaining expenditures M$ 4.1 5.9 4.5
Unit analysis
Realized gold price per oz sold $/oz 2,059 2,009 1,914
Cash costs per oz sold(1) $/oz 1,153 1,070 1,129
AISC per oz sold(1) $/oz 1,188 1,068 1,780
Mining cost per tonne mined $/t 1.37 1.91 1.29
Processing cost per tonne processed $/t 4.50 3.85 7.46
G&A cost per tonne processed $/t 2.10 1.39 2.06

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 34% higher at a 33% lower AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 45% higher and the average realized gold price was 8% higher compared to Q1 2023.

Production was higher in Q1 2024 compared to Q1 2023 as Q1 2024 had more than twice the recoverable ounces delivered to the leach pad with three pits contributing ore, whereas in Q1 2023 delivery of ore was predominantly from the Brownie pit.

The total tonnes mined in Q1 2024 was similar to Q1 2023 but ore tonnes mined were twice as much as Q1 2023, which reflects the relative position in the mining sequence, with completion of the current phase of mining from the Don Juan and Vista East pits and pre-stripping commencing for mining of the Ginger deposit. The strip ratio in Q1 2024 was 4.27 compared to 9.35 in Q1 2023.

Mining unit costs in Q1 2024 were in line with Q1 2023 despite a much lower strip ratio, as the waste hauls in Q1 2023 for Vista East 3 were much longer than waste hauls in Q1 2024. Process unit costs were lower in Q1 2024 compared to Q1 2023 due to stacking twice the ore tonnes in Q1 2024. Cyanide and lime prices were lower in Q1 2024, whereas consumption was higher reflecting higher quantities of fresh ore. G&A unit costs in Q1 2024 were in line with Q1 2023 despite an increase in ore tonnes stacked primarily due to the timing of lease payments.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Cash costs per oz sold in Q1 2024 were in line with Q1 2023. AISC per oz sold decreased in Q1 2024 compared to Q1 2023 due to higher ounces sold and minimal sustaining capital spend in Q1 2024 compared to Q1 2023, which had significant capitalized stripping.

Sustaining capital expenditures in Q1 2024 were nil. Non-sustaining expenditures in Q1 2024 were $4.1 million primarily related to lease payments for haul trucks, capitalized stripping in the Ginger pit and capitalized exploration drilling costs.

Exploration and Development

In Q1 2024, exploration work at Mesquite included a 4,970 meter (“m”) step-out reverse circulation (“RC”) drill program designed to test for extensions of the Ginger deposit, primarily to the north and west, and ongoing geological mapping of the main open pits to further enhance the geological model. Exploration expenditures at Mesquite in Q1 2024 were $0.8 million.

Outlook

Mesquite production guidance for 2024 is 75,000 to 85,000 ounces of gold, with approximately 60% of production expected in the first half of 2024 (“H1 2024”). Costs guidance for 2024 is cash costs of $1,345 to $1,445 per oz and AISC of $1,410 to $1,510 per oz. Budgeted sustaining expenditures of $5 million primarily relate to processing equipment. Budgeted non-sustaining expenditures of $82 million primarily relate to capitalized waste stripping of the Ginger pit.

In 2024, mining at Mesquite will be focused on waste stripping the Ginger pit, which is expected to deliver most of the ounces in early 2025. Efforts to establish additional Mineral Reserves through exploration and resource drilling are expected to continue and the Company will also continue the permitting required to enable mine life extensions beyond 2024.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Castle Mountain Gold Mine, California, USA

Castle Mountain is an open-pit heap leach gold mine located in San Bernardino County, California, approximately 200 miles north of Mesquite. Under a previous owner, Castle Mountain produced more than 1.3 million ounces of gold from 1992 to 2004, when production ceased due to low gold prices. Equinox Gold acquired Castle Mountain in December 2017 and commenced Phase 1 operations in Q4 2020. In 2021, Equinox Gold completed a feasibility study for a Phase 2 expansion that is expected to increase average production to more than 200,000 ounces of gold annually. In March 2022, the Company applied to amend existing permits to accommodate the Phase 2 expansion, as described in Development Projects.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined and stacked to leach pad kt 838 1,421 1,077
Waste mined kt 1,154 506 676
Open pit strip ratio w:o 1.38 0.36 0.63
Average gold grade stacked to leach pad g/t 0.32 0.32 0.29
Gold produced oz 4,716 5,977 4,455
Gold sold oz 4,716 5,977 4,455
Financial data
Revenue(2) M$ 10.0 12.1 8.6
Cash costs(1) M$ 10.9 11.9 5.5
Sustaining capital(1) M$ 0.3 2.9 0.3
Sustaining lease payments M$ 1.0 1.0 1.0
Sustaining exploration expenditures M$ 0.1 0.0 0.0
Reclamation expenses M$ 0.1 0.1 0.1
Total AISC(1) M$ 12.4 15.9 6.9
AISC contribution margin(1) M$ (2.4) (3.8) 1.6
Non-sustaining expenditures M$ 1.3 1.3 1.4
Unit analysis
Realized gold price per oz sold $/oz 2,118 2,030 1,920
Cash costs per oz sold(1) $/oz 2,303 1,996 1,244
AISC per oz sold(1) $/oz 2,618 2,658 1,567
Mining cost per tonne mined $/t 3.26 3.44 2.71
Processing cost per tonne processed $/t 9.27 5.77 5.37
G&A cost per tonne processed $/t 2.91 2.08 1.85

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 6% higher at a 67% higher AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 6% higher and the average realized gold price was 10% higher compared to Q1 2023.

Production was slightly higher in Q1 2024 compared to Q1 2023 mainly due to higher feed grades and a higher proportion of material being crushed. Crushing and agglomeration was achieved for 85% of ore processed in Q1 2024 compared to 63% for Q1 2023.

Mining unit costs were higher in Q1 2024 compared to Q1 2023 primarily due to higher mining contractor rates. Processing unit costs were higher in Q1 2024 compared to Q1 2023 as there was a higher proportion of ore tonnes crushed and agglomerated in Q1 2024 which results in higher unit costs compared to stacking run-of-mine (“ROM”) ore, but a lower amount of ore available to place on the leach pad. G&A unit costs were higher in Q1 2024 compared to Q1 2023 primarily due to fewer total ore tonnes processed in spite of higher total tonnes mined.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Cash costs per oz sold were higher in Q1 2024 compared to Q1 2023, driven by an increase in mining, processing and G&A unit costs as work continued to increase production. AISC per oz sold increased in Q1 2024 compared to Q1 2023 mainly due to the higher cash cost per oz sold. Cash costs and AISC per oz sold in Q1 2024 were also affected by a $2.5 million ($532 per oz sold) write-down of inventories to net realizable value (“NRV”), driven by the higher unit operating costs noted above.

Sustaining capital expenditures in Q1 2024 were $0.3 million for capitalized exploration. Non-sustaining expenditures in Q1 2024 were $1.3 million primarily related to Phase 2 permitting and engineering.

Exploration and Development

There was no exploration drilling at Castle Mountain in Q1 2024, nor is any planned for the year. A surface exploration program of geological mapping and channel sampling is expected to commence in Q3 2024, with the primary goal to sample previously identified mineralization exposed on surface so those data can be used in future Mineral Resource estimation. Exploration expenditures at Castle Mountain in Q1 2024 were $0.4 million.

Outlook

Castle Mountain production guidance for 2024 is 30,000 to 35,000 ounces of gold, with cash costs of $2,045 to $2,145 per oz and AISC of $2,125 to $2,200 per oz.

Costs at Castle Mountain are expected to remain elevated as a result of modifications to the crushing and agglomerating circuit to improve ore permeability and gold production. Budgeted sustaining expenditures at Castle Mountain in 2024 include $3 million of sustaining capital for a variety of equipment upgrades. The Company is advancing plans for a Phase 2 expansion at Castle Mountain, as discussed in the Development Projects section. Budgeted non-sustaining expenditures of $4 million include engineering and permitting work for the expansion.

Production and cost guidance for the Castle Mountain Mine is subject to change pending completion of an internal evaluation of the Phase 1 operation. The mine is currently operating as a small “phase 1” project designed to process mineralized material deposited in the open pits during prior mining operations while permitting and engineering for the Phase 2 expansion to more than 200,000 ounces of gold production per year is being advanced. As this permitting process is expected to continue into fiscal 2026, the Company is evaluating the Phase 1 operation to ensure appropriate allocation and preservation of capital, which could result in reduced operations-related activities and gold production from Castle Mountain Phase 1 through the remaining Phase 2 permitting period.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Los Filos Gold Mine, Guerrero, Mexico

Los Filos is located in Guerrero State, Mexico, and commenced production in 2008. Mining operations in 2024 involve three open pits (Los Filos, Bermejal and Guadalupe) and one underground mine (Los Filos). In February 2023, operations at Bermejal underground were suspended to defer development capital while the Company advances plans to improve productivity and reduce costs. Crushed and ROM ore from the various deposits is processed by heap leaching.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined - open pit kt 895 1,307 2,401
Waste mined - open pit kt 10,044 7,411 11,247
Open pit strip ratio w:o 11.22 5.67 4.69
Average open pit gold grade g/t 0.55 1.21 0.93
Ore mined - underground kt 151 125 121
Average underground gold grade g/t 3.13 3.26 3.36
Tonnes processed kt 963 1,488 2,572
Ore re-handled for secondary leaching kt 1,240
Gold produced oz 23,955 42,210 39,574
Gold sold oz 26,315 39,474 39,611
Financial data
Revenue(2) M$ 53.9 78.2 74.8
Cash costs(1) M$ 46.3 65.2 59.7
Sustaining capital(1) M$ 16.5 16.1 6.6
Sustaining lease payments M$ 0.1
Sustaining exploration expenditures M$ 0.1
Reclamation expenses M$ 0.7 0.7 0.8
Total AISC(1) M$ 63.8 82.0 67.2
AISC contribution margin(1) M$ (9.9) (3.8) 7.6
Non-sustaining expenditures M$ 0.2 0.2
Unit analysis
Realized gold price per oz sold $/oz 2,048 1,982 1,889
Cash costs per oz sold(1) $/oz 1,761 1,651 1,507
AISC per oz sold(1) $/oz 2,424 2,078 1,696
Mining cost per tonne mined - open pit $/t 1.96 2.65 1.97
Mining cost per tonne mined - underground $/t 97.42 110.34 129.06
Processing cost per tonne processed $/t 9.58 17.80 8.91
G&A cost per tonne processed $/t 4.52 7.54 2.81

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold, and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 39% lower at a 43% higher AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 34% lower compared to Q1 2023 and the average realized gold price was 8% higher compared to Q1 2023.

Production was better than plan in Q1 2024, but lower compared to Q1 2023 as Q1 2024 was primarily focused on waste stripping and development as planned, with a strip ratio of 11.2 compared to 4.7 in Q1 2023. Additionally, the portion of the conveyor between the crusher and agglomerator on the heap leach pad was relocated, resulting in the crusher being offline for approximately 70% of the Quarter, as planned.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Open pit mining unit costs in Q1 2024 were in line with Q1 2023. Underground mining unit costs in Q1 2024 were lower compared to Q1 2023 as a result of higher costs in Q1 2023 related to Bermejal underground activity. Processing unit costs increased in Q1 2024 compared to Q1 2023 due to fewer ore tonnes being placed in Q1 2024, while total processing costs in Q1 2024 decreased due to the crusher and conveyor being offline for approximately 70% of the Quarter as planned. G&A unit costs were 61% higher in Q1 2024 compared to Q1 2023 due to 63% fewer tonnes processed compared to Q1 2023.

Cash costs per oz sold were higher than Q1 2023 due to mine sequencing, with Q1 2024 having a lower proportion of ore tonnes and ounces placed resulting in higher average cost per oz. Cash costs per oz sold were also impacted by an 8% strengthening of the MXN compared to the USD in Q1 2024 as compared to Q1 2023. The increase in AISC per oz sold compared to Q1 2023 was due to the higher cash costs per oz sold and an increase in sustaining spend compared to Q1 2023 due to increased spend related to stripping in the Bermejal, Guadalupe and Los Filos open pits in Q1 2024.

Sustaining capital expenditures in Q1 2024 were $16.5 million primarily related to Bermejal, Guadalupe and Los Filos open pit capitalized stripping and Los Filos underground development. Non-sustaining expenditures in Q1 2024 were nil.

Exploration and Development

Exploration drilling at Los Filos during Q1 2024 included 1,982 m of infill core drilling in the Los Filos open pit area and 519 m of step-out drilling in the Los Filos underground. In addition to the drill programs, a major core re-logging exercise is ongoing and an additional 1,955 m of previously unsampled historical core was sampled during Q1 2024. Exploration expenditures at Los Filos in Q1 2024 totaled $1.3 million.

Outlook

Los Filos production guidance for 2024 is 155,000 to 175,000 ounces of gold, with approximately 60% of production expected in the second half of 2024, and with cash costs of $1,785 to $1,885 per oz and AISC of $2,090 to $2,190 per oz.

Budgeted sustaining expenditures at Los Filos of $50 million in 2024 include $15 million for Bermejal open pit development, $8 million for Los Filos open pit development, $5 million for Guadalupe open pit development, $3 million for Los Filos North underground development, $7 million for processing equipment and $5 million for exploration. There were no non-sustaining expenditures budgeted for Los Filos in 2024.

Currently, Los Filos operates as an open pit and underground mining operation with all ore being processed on a heap leach facility. To ensure the long-term viability of the mine and maximize the value of the gold endowment at Los Filos, a carbon-in-leach (“CIL”) plant is needed to increase gold recovery from higher-grade ore from both underground and open pit deposits.

Cost and production guidance for Los Filos is subject to the successful execution of new social and land access agreements with local community stakeholders and landowners. The Los Filos team is in a dialogue process with the three communities where the mine is located, with the goal of reaching new land access agreements with each of them in a collaborative and transparent way. These new agreements are necessary to help ensure the long-term economic and investment viability of the mine, including the addition of a new 10,000 tpd CIL processing plant. If the Company is unable to satisfactorily complete these agreements, the Company will re-evaluate the current operation and may elect to cease operations. Accordingly, Los Filos production and cost guidance for 2024 is subject to change.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Aurizona Gold Mine, Maranhão, Brazil

Aurizona is an open pit gold mine located in northeastern Brazil. Aurizona commenced production in July 2019 and mining is currently from the Piaba and Piaba East open pits with ore being processed in a CIL process plant. The Company is advancing permitting, exploration and studies related to an expansion that is expected to extend the mine life and increase annual gold production with development of an underground mine and satellite open pit deposits that would operate concurrently with the existing open pit mine.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined kt 86 1,453 438
Waste mined kt 3,641 5,347 3,513
Open pit strip ratio w:o 42.26 3.68 8.02
Tonnes processed kt 803 812 868
Average gold grade processed g/t 1.04 1.44 1.00
Recovery % 90.2 90.1 91.0
Gold produced oz 23,857 34,104 25,800
Gold sold oz 24,506 33,638 26,539
Financial data
Revenue(2) M$ 50.6 65.9 50.4
Cash costs(1) M$ 33.3 30.7 31.8
Sustaining capital(1) M$ 14.0 11.6 10.9
Sustaining lease payments M$ 0.4 0.5 0.3
Reclamation expenses M$ 0.5 0.4 0.3
Total AISC(1) M$ 48.2 43.2 43.3
AISC contribution margin(1) M$ 2.3 22.8 7.1
Non-sustaining expenditures M$ 2.2 3.5 1.1
Unit analysis
Realized gold price per oz sold $/oz 2,065 1,960 1,901
Cash costs per oz sold(1) $/oz 1,360 913 1,197
AISC per oz sold(1) $/oz 1,973 1,283 1,634
Mining cost per tonne mined $/t 4.04 3.32 3.27
Processing cost per tonne processed $/t 11.72 12.68 12.22
G&A cost per tonne processed $/t 5.58 5.30 5.02

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 8% lower at a 21% higher AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 8% lower and the average realized gold price was 9% higher compared to Q1 2023.

Production was lower in Q1 2024 compared to Q1 2023 due to the mining sequence, with longer hauls in the Piaba open pit, and heavy rainfall and increased geotechnical activity reducing access to ore in lower sections of the Piaba pit. Consequently, in Q1 2024 the strip ratio was 42.3 compared to 8.0 in Q1 2023 and the operation relied on processing stockpiled ore.

Mining unit costs were higher in Q1 2024 compared to Q1 2023 primarily due to the impact of a contract renewal at higher rates with the current mining contractor. Processing unit costs were lower in Q1 2024 compared to Q1 2023 mainly due to lower pricing for cyanide and other reagents.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Cash costs per oz sold were higher in Q1 2024 compared to Q1 2023 due to the impact of mining deeper with longer hauls in the Piaba pit, as well as a 3% strengthening of the BRL compared to the USD compared to Q1 2023. AISC per oz sold was higher in Q1 2024 compared to Q1 2023, reflecting lower gold production, higher sustaining capital expenditures and higher cash costs per oz sold.

Sustaining capital expenditures in Q1 2024 of $14.0 million primarily related to capitalized stripping and completion of construction of a new tailings storage facility (“TSF”) which is now in use. Non-sustaining expenditures in Q1 2024 were $2.2 million primarily related to engineering studies for the planned underground portal and decline for underground development and drilling.

Exploration and Development

Exploration drilling activities continued in Q1 2024, with the primary focus being resource delineation of the western extension of the Tatajuba deposit, as well as continued testing of high potential regional targets. A total of 1,832 m of core drilling was completed during the Quarter on the Tatajuba deposit and 3,391 m of core drilling was carried out on regional exploration targets. Exploration expenditures at Aurizona in Q1 2024 were $1.3 million.

Outlook

Aurizona production guidance for 2024 is 110,000 to 120,000 ounces of gold, with cash costs of $1,070 to $1,170 per oz and AISC of $1,575 to $1,675 per oz. Budgeted sustaining expenditures at Aurizona of $58 million in 2024 include $35 million in capitalized stripping and $16 million for TSF expansion. Budgeted non-sustaining expenditures at Aurizona of $11 million in 2024 primarily relate to underground infrastructure and development.

On March 27, 2024, due to persistent heavy rains in Maranhão, Brazil, there was a displacement of material in two locations in the south wall of the Piaba pit at the Aurizona mine. As a result of this geotechnical event, access to the Piaba pit has been restricted and mining has been paused while the Company establishes an initial remediation plan and confirms the safety of the pit.

Milling and gold production continued from the existing ore stockpile until the end of April 2024. During Q2 2024, the Company expects the plant to be idle for 4 to 6 weeks while mining transitions to the Tatajuba deposit, from which mining was originally planned for Q4 2024. In April 2024, mining commenced at the Tatajuba open pit. Ore production for plant feed is anticipated to be in June 2024. The Company will provide an update for 2024 production guidance when more information becomes available.

The Company will perform an updated geotechnical assessment of the Piaba pit and nearby infrastructure to determine if further remediation is required for long-term stability. Once the outcome of the updated assessment is known, the Company will assess whether there is an indicator of impairment and a requirement to perform an impairment test for the Aurizona mine.

The Company is advancing plans for an expansion at Aurizona, as discussed in the Development Projects section.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Fazenda Gold Mine, Bahia, Brazil

Fazenda is located in Bahia State, Brazil and has been in operation since 1984. Fazenda is primarily an underground operation complemented with production from several small open pits.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined - open pit kt 127 118 121
Waste mined - open pit kt 1,429 989 1,556
Open pit strip ratio w:o 11.22 8.36 12.83
Average open pit gold grade g/t 1.10 1.18 1.51
Ore mined - underground kt 158 262 193
Average underground gold grade g/t 1.78 1.88 1.69
Ore mined - total kt 285 380 314
Tonnes processed kt 364 369 337
Average gold grade processed g/t 1.36 1.68 1.58
Recovery % 89.8 89.7 91.0
Gold produced oz 14,402 17,708 15,685
Gold sold oz 14,483 17,273 16,012
Financial data
Revenue(2) M$ 30.2 34.1 30.1
Cash costs(1) M$ 21.9 21.3 18.5
Sustaining capital(1) M$ 2.8 5.5 1.6
Sustaining lease payments M$ 0.4 0.4 0.4
Reclamation expenses M$ 0.2 0.2 0.1
Total AISC(1) M$ 25.3 27.4 20.6
AISC contribution margin(1) M$ 4.9 6.7 9.7
Non-sustaining expenditures M$ 2.7 2.8 1.6
Unit analysis
Realized gold price per oz sold $/oz 2,085 1,977 1,877
Cash costs per oz sold(1) $/oz 1,510 1,234 1,153
AISC per oz sold(1) $/oz 1,745 1,588 1,279
Mining cost per tonne mined - open pit $/t 2.30 2.39 2.25
Mining cost per tonne mined - underground $/t 39.65 33.58 31.24
Processing cost per tonne processed $/t 12.97 14.06 14.20
G&A cost per tonne processed $/t 7.11 7.69 6.77

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold, and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 8% lower at a 36% higher AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 10% lower and the average realized gold price was 11% higher compared to Q1 2023.

Production was lower in Q1 2024 compared to Q1 2023 mainly due to lower grades from open pit mining driven by mine sequencing, and lower underground tonnes mined as a result of slow development rates. These issues resulted in 14% lower grade processed, offset partially by 8% higher volume tonnes processed through the mill.

Open pit mining unit costs in Q1 2024 were in line with Q1 2023. Underground mining unit costs were higher in Q1 2024 compared to Q1 2023 due to increased labour costs as the result of renegotiated contracts, in addition to fewer underground ore tonnes mined. Processing unit costs were lower in Q1 2024 compared to Q1 2023 primarily due to higher ore tonne volumes processed.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Cash costs per oz sold were higher in Q1 2024 compared to Q1 2023 primarily due to lower production as a result of delays in accessing higher grade ore tonnes in the open pit and underground, as well as a 3% strengthening of the BRL compared to the USD compared to Q1 2023. AISC per oz sold was higher in Q1 2024 compared to Q1 2023 due to higher cash costs per oz sold, as well as higher sustaining capital spend compared to Q1 2023.

Sustaining capital expenditures in Q1 2024 were $2.8 million primarily related to underground development and construction of a TSF raise. Non-sustaining expenditures in Q1 2024 were $2.7 million primarily related to underground development and exploration.

Exploration and Development

In Q1 2024, the Company drilled 15,525 m of core focused on mineral reserve replacement in the immediate underground mine area. Surface exploration started late in the Quarter and 676 m of core was drilled on several brownfield and regional targets. Exploration expenditures at Fazenda in Q1 2024 were $1.9 million.

Outlook

Fazenda’s production guidance for 2024 is 65,000 to 70,000 ounces of gold, with cash costs of $1,195 to $1,295 per oz and AISC of $1,560 to $1,660 per oz.

Budgeted sustaining expenditures at Fazenda of $25 million in 2024 primarily relate to $6 million for underground development, $7 million for equipment acquisition and $5 million for exploration.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

RDM Gold Mine, Minas Gerais, Brazil

RDM is located in Minas Gerais State, Brazil and commenced production in early 2014 as a conventional open-pit operation.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined kt 85 849 202
Waste mined kt 2,205 1,891 2,343
Open pit strip ratio w:o 25.97 2.23 11.58
Ore rehandled kt 179 57 186
Tonnes processed kt 597 684 397
Average gold grade processed g/t 0.62 0.90 0.51
Recovery % 88.5 88.1 89.8
Gold produced oz 10,932 16,994 6,342
Gold sold oz 11,125 17,177 6,024
Financial data
Revenue(2) M$ 23.0 34.0 11.4
Cash costs(1) M$ 19.0 18.8 9.4
Sustaining capital(1) M$ 0.4 3.3 2.8
Sustaining lease payments M$ 0.5 2.5 1.9
Reclamation expenses M$ 0.2 0.3 0.2
Total AISC(1) M$ 20.1 24.9 14.3
AISC contribution margin(1) M$ 2.9 9.1 (2.8)
Care and maintenance M$ 1.0
Non-sustaining expenditures M$ 5.6
Unit analysis
Realized gold price per oz sold $/oz 2,065 1,980 1,897
Cash costs per oz sold(1) $/oz 1,709 1,097 1,557
AISC per oz sold(1) $/oz 1,801 1,453 2,368
Mining cost per tonne mined $/t 3.11 2.88 1.83
Processing cost per tonne processed $/t 12.51 12.18 14.16
G&A cost per tonne processed $/t 3.80 3.62 5.39

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold, and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 72% higher at a 24% lower AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 85% higher and the average realized gold price was 9% higher compared to Q1 2023.

Production increased in Q1 2024 compared to Q1 2023 due to higher grades mined from in-situ mining, as well as a delay in Q1 2023 in receiving a license which meant the Company was not able to process ore until the third week of January 2023 and then processed primarily low-grade stockpiles.

Mining unit costs were higher in Q1 2024 compared to Q1 2023 due to lower availability of the rental fleet, lower productivity of the mining contractor, and maintenance on the owner-operated fleet. Productivity is expected to improve in future quarters with the replacement of the rental fleet being operated by RDM personnel. Processing and G&A unit costs were lower for Q1 2024 compared to Q1 2023 due to higher ore tonnes processed.

Cash costs per oz sold were higher in Q1 2024 compared to Q1 2023 primarily due to higher mining unit costs in addition to a 3% strengthening of the BRL compared to the USD compared to Q1 2023, offset partially by higher gold production due to higher grades mined. AISC per oz sold was lower in Q1 2024 compared to Q1 2023 mainly due to lower sustaining capital spend, offset partially by higher cash costs per oz sold.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Sustaining capital expenditures in Q1 2024 of $0.4 million were primarily related to mining equipment. Non-sustaining expenditures in Q1 2024 were $5.6 million related to capitalized stripping.

Exploration and Development

No exploration drilling occurred at RDM in Q1 2024.

Outlook

RDM production guidance for 2024 is 50,000 to 60,000 ounces of gold, with cash costs of $1,260 to $1,360 per oz and AISC of $1,800 to $1,900 per oz.

Budgeted sustaining expenditures at RDM of $29 million in 2024 include $5 million for a dry tailings storage facility and $22 million of equipment expenditures and rentals. In April 2024, RDM received the permit for the dry tailings storage facility. Budgeted non-sustaining expenditures of $14 million in 2024 relate primarily to capitalized stripping.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Santa Luz Gold Mine, Bahia, Brazil

Santa Luz is an open pit gold mine located in Bahia State, Brazil. Santa Luz poured first gold on March 30, 2022 and achieved commercial production effective October 1, 2022.

Operating and financial results for the three months ended March 31, 2024

Three months ended
Operating data Unit March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Ore mined kt 391 678 762
Waste mined kt 2,832 1,323 3,069
Open pit strip ratio w:o 7.25 1.95 4.03
Tonnes processed kt 526 536 534
Average gold grade processed g/t 1.19 1.17 1.26
Recovery % 53.9 61.7 62.6
Gold produced oz 11,836 12,044 14,485
Gold sold oz 11,575 12,132 14,249
Financial data
Revenue(2) M$ 24.1 24.2 27.0
Cash costs(1) M$ 23.8 25.4 22.5
Sustaining capital(1) M$ 5.0 3.3 0.1
Sustaining lease payments M$ 0.1 0.1 0.1
Reclamation expenses M$ 0.3 0.2 0.3
Total AISC(1) M$ 29.2 29.0 23.0
AISC contribution margin(1) M$ (5.0) (4.8) 4.0
Non-sustaining expenditures M$ 0.8 0.6 0.4
Unit analysis
Realized gold price per oz sold $/oz 2,083 1,993 1,892
Cash costs per oz sold(1) $/oz 2,053 2,092 1,581
AISC per oz sold(1) $/oz 2,519 2,392 1,610
Mining cost per tonne mined $/t 3.14 3.45 3.14
Processing cost per tonne processed $/t 23.83 25.84 26.12
G&A cost per tonne processed $/t 4.44 5.66 5.90

(1)Cash costs, sustaining capital, AISC, AISC contribution margin, mine-site free cash flow, cash costs per oz sold and AISC per oz sold are non-IFRS measures. See Non-IFRS Measures and Cautionary Notes.

(2)Revenue is reported net of silver revenue.

Q1 2024 Analysis

Production

In Q1 2024, ounces produced were 18% lower at a 56% higher AISC per oz sold compared to Q1 2023. In Q1 2024, ounces sold were 19% lower and the average realized gold price was 10% higher compared to Q1 2023.

Production in Q1 2024 was lower than Q1 2023 due to 14% lower recoveries, 2% lower ore processed and 6% lower feed grades. Processing challenges were encountered in Q1 2024 and the plant had increased down time for modifications to the detox, adsorption/desorption/recovery (“ADR”) and electrowinning circuits. The team continues to work through planned optimization initiatives. In April 2024, recoveries progressively increased and averaged approximately 69%, which is in line with expectations for H1 2024.

Mining unit costs in Q1 2024 were in line with Q1 2023 unit costs. Processing unit costs in Q1 2024 were lower than Q1 2023 driven by lower cyanide costs. G&A unit costs in Q1 2024 were lower than Q1 2023 driven by a decrease in shared regional costs, which are allocated based on revenue.

Cash costs per oz sold were higher in Q1 2024 compared to Q1 2023 mainly due to lower production during the Quarter, in addition to a 3% strengthening of the BRL compared to the USD compared to Q1 2023. AISC per oz sold for Q1 2024 was higher compared to Q1 2023 due to higher cash costs per oz sold, in addition to higher sustaining capital spend driven by higher capitalized stripping.

eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024

Sustaining capital expenditures in Q1 2024 were $5.0 million primarily related to capitalized waste stripping and a TSF raise. Non-sustaining expenditures in Q1 2024 were $0.8 million primarily related to exploration.

Exploration and Development

The 2024 surface exploration program at Santa Luz is underway and included 626 m of core drilling and an 18.6 line-kilometer program of soil sampling on regional targets. Exploration expenditures at Santa Luz in Q1 2024 were $0.8 million.

Outlook

The focus at Santa Luz in 2024 is on improving steady state plant throughput to achieve design capacity of 2.5 million tonnes per year and increasing recoveries, with the objective of achieving recoveries of 73% or more for the second half of 2024. In addition to modifications to the detox, ADR and electrowinning circuits, Santa Luz plans to add a new trunnion and desliming circuit in late Q2 2024. The new trunnion is expected to increase throughput by up to 10%. The addition of a desliming circuit is intended to remove the highest total organic carbon from ore feed and is expected to result in an overall improvement in recovery of up to 6%.

Santa Luz production guidance for 2024 is 70,000 to 80,000 ounces of gold, with cash costs of $1,495 to $1,595 per oz and AISC of $1,720 to $1,820 per oz.

Budgeted sustaining expenditures at Santa Luz of $17 million in 2024 relate primarily to a $7 million TSF raise, as well as the new trunnion and desliming circuit. Budgeted non-sustaining expenditures of $4 million in 2024 relate primarily to exploration.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || DEVELOPMENT PROJECTS | | --- |

Greenstone Project, Ontario, Canada

On April 23, 2024, the Company announced it will fully consolidate its ownership of Greenstone by acquiring Orion Mine Finance Group’s (“Orion”) 40% ownership interest in the project. The acquisition is expected to close in May 2024. The Company acquired an initial 50% interest in Greenstone in April 2021, and subsequently purchased an additional 10% interest from Orion to bring its total interest in the project to 60%. Greenstone will be an open-pit mine with the expectation of producing more than 5 million ounces of gold over an initial 14-year mine life. Gold production for the first five years of operations is estimated at more than 400,000 ounces annually with life-of-mine production expected to average 360,000 ounces annually.

2024 Update and Outlook

During Q1 2024, commissioning activities focused on the high-pressure grinding rolls (HPGR), ball mill #1, and thickener and leach tanks. Flocculant and lime were loaded into the system during the last week of March 2024. Wet commissioning activities for the gravity circuit, reagents, carbon stripping, refining and gold room advanced during the Quarter and are near completion. At March 31, 2024, the mine had moved more than 24.1 million tonnes of material and had more than 1.5 million tonnes of ore was stockpiled for commissioning. The operations team completed the assembly and commissioning of one additional Komatsu PC5500 shovel and one Komatsu L1850 wheel loader during Q1 2024. Fourteen CAT 793F trucks, two Epiroc D65 drills, two Epiroc Pit Viper 235 drills, three Komatsu PC5500 shovels and four Komatsu D375A-8 bulldozers were in service at March 31, 2024. Plant operational readiness activities were essentially complete at Quarter end and ready for plant operations and ramp-up, all senior plant operators were on board, and hiring was on track with more than 400 positions filled.

At the end of Q1 2024, $1,300 million had been spent on construction and commissioning (100% basis). The Company’s share was $54 million during the Quarter and $780 million project to date, which excludes capitalized interest and other non-cash amounts capitalized. The Company capitalized interest of $16 million during the Quarter and $76 million project to date.

Commissioning activities are expected to continue during Q2 2024. Ore was introduced into the system on April 6, 2024, the first gold pour is expected in May 2024, and commercial production is targeted by the end of Q3 2024. Process plant facilities will be turned over to the operations team in Q2 2024 and construction team demobilization activities are expected to be substantially complete by the end of Q2 2024. Mining activities will continue to ramp-up, with two additional Pit Viper 235 drills, one additional Komatsu PC5500 shovel, and eleven CAT 793F trucks planned to be delivered in Q2 and Q3 2024.

Los Filos Expansion, Guerrero, Mexico

On October 19, 2022, the Company released the results of an updated feasibility study for a potential expansion that would increase production and extend the mine life of Los Filos by developing the Bermejal underground deposit and constructing a CIL processing plant that would process higher-grade ore and operate concurrent with the existing heap leach facilities.

2024 Update and Outlook

While the economic and production estimates outlined in the feasibility study were predicated on construction of the CIL plant commencing in 2023, Equinox Gold has not made a construction decision at this time. Any decision to proceed with the Los Filos expansion will be made considering the operating stability in the region, the ability to successfully renegotiate existing land access agreements, an amended environmental permit, market conditions, and availability and cost of capital. Currently the Los Filos team is focused on implementation of operational improvements, advancing community dialogue, and social investment projects.

Castle Mountain Expansion, California, USA

In March 2021, the Company announced the results of the feasibility study for a Phase 2 expansion at Castle Mountain. The current operation consists of mining mineralized material that was deposited in the open pits during prior mining operations and processing the material on a heap leach facility. Phase 2 is expected to increase production to an average of 218,000 ounces per year for 14 years followed by leach pad rinsing to recover residual gold. On a standalone basis, Phase 2 is expected to produce 3.2 million ounces of gold with AISC in the lower industry quartile.

2024 Update and Outlook

During Q1 2024 the Company continued to advance optimization work on the processing circuit and continued work on Front End Engineering Design (“FEED”). While Phase 2 is expected to operate within the existing approved mine boundary, the changes to previously analyzed impacts, such as increased land disturbance within the mine boundary and increased water use, require modification to the Company’s approved Mine and Reclamation Plan (“Plan”) for the project. The Plan amendment application was submitted to the lead agencies (San Bernardino County and U.S. Bureau of Land Management (BLM)) in March 2022. The lead agencies reviewed Plan completeness in early 2023 and the BLM requested minor Plan changes, which were resubmitted for final BLM review in Q3 2023.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || DEVELOPMENT PROJECTS (CONTINUED) | | --- |

The Company received the BLM determination that the Plan is complete in Q1 2024. The next step is to enter into a Memorandum of Understanding between the BLM, San Bernardino County and Castle Mountain to conduct an Environmental Impact Statement (“EIS”) / Environmental Impact Report to analyze the potential environmental impact of the Phase 2 expansion. The Company anticipates the draft EIS stage of formal environmental analysis to occur throughout 2024 and 2025.

Aurizona Expansion, Brazil

The Company sees potential to extend the Aurizona mine life to more than 10 years and increase annual production through development of a new underground mine and satellite open pit deposits. The underground mine would operate concurrently with the existing open pit until the Piaba pit is fully mined out; afterwards, the satellite open pits would be mined concurrently with the underground mine.

2024 Update and Outlook

In Q1 2024, the Company continued to advance engineering studies for an underground mine at Piaba pit. The Company is focused on improving accuracy for underground work areas of ventilation, access from the portals and mining, as well as planning that is required prior to construction of a portal and underground decline that is planned to commence in late 2024. The underground decline would allow for bulk sampling and underground drilling. The portal and underground development would be sized to ultimately be useable as a production decline for underground operations.

HEALTH, SAFETY AND ENVIRONMENT

Health & Safety

While Equinox Gold had two lost-time injuries during the Quarter, six of the Company’s mine sites had no lost-time injuries during Q1 2024. The Company’s Lost-time Injury Frequency Rate was 0.35 per million hours worked for the 12-month rolling period (0.46 for the Quarter), compared to the target of 0.61 per million hours worked for calendar year 2024. The Company’s TRIFR, which is a measure of all injuries that require the attention of medically trained personnel, was 1.55 per million hours worked for the 12-month rolling period (1.61 for the Quarter), compared to the target of 3.00 per million hours worked for calendar year 2024.

Environment

The Company’s SEIFR was 0.30 per million hours worked for the 12-month rolling period (0.00 for the Quarter) compared to the target of 1.26 per million hours worked for calendar year 2024. During the Quarter, there were no significant environmental incidents as defined by the Company’s environmental standards.

COMMUNITY DEVELOPMENT AND ESG REPORTING

Community Engagement and Development

Equinox Gold seeks to engage in early, frequent and transparent dialogue with stakeholders as a means to build trust and provide a space for collaboration and long-term commitment. At all operations, dedicated community engagement teams seek feedback from local communities and stakeholders so that collaborative solutions to concerns can be implemented.

During the Quarter, the Company undertook a number of Indigenous and community engagement activities.

In Canada, Greenstone sponsored curling and hockey tournaments in Geraldton and Longlac. Greenstone also started delivering Indigenous Cross-Cultural Awareness Training to its workforce, and members of the Greenstone team participated in the Lakehead University Powwow.

In Brazil, all sites continued the implementation of community programs that support education, sports, cultural development and skills training. Aurizona supported community health by providing opportunities for physical activity such as establishing a gym facility, investing in the Street Soccer program, and sponsoring the Female Soccer Tournament. Fazenda worked with one of its contractors to support their community hire program and successfully hired 14 individuals from Barrocas and Teofilândia in March.

Fazenda also organized an Easter egg manufacturing course for 40 women from Canto, Barreiras, and Fazenda Brasileiro, providing them with valuable skills and alternative income generating activities. Santa Luz assisted the local government with road maintenance and also organized an environmental education lecture in the Nova Esperança community. RDM supported the local government in their campaign to prevent and fight the spread of dengue fever.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || COMMUNITY DEVELOPMENT AND ESG REPORTING (CONTINUED) | | --- |

In Mexico, Los Filos continued the community dialogue process to agree on revisions to land use and social agreements that would improve the long-term economic viability of the mine. The site continues its commitment to supporting education through its Scholarship Programs. Additionally, Los Filos has started a reforestation campaign in Mezcala, with the collaboration and oversight of the Autonomous University of Guerrero, continued with construction of the Carrizalillo healthcare center, and supported local economy projects, such as mezcal production in Xochipala.

In the USA, Castle Mountain maintained an ongoing partnership with the Desert Research Institute, focusing on ecology research. To support conservation efforts, the team donated a dozen salvaged cactus to the Mojave Desert Heritage & Cultural Association and donated salvaged Joshua tree, yucca and other cacti to the Las Vegas Valley Water District.

ESG Reporting

During Q1 2024, the Company continued working on the 2023 ESG reporting cycle, which includes increasing the automation of site-level data collection. By the end of the Quarter, all data had been collected and consolidated. Following the publishing of the 2023 ESG report, the Company will conduct an internal audit of selected indicators that will help identify opportunities to improve the Company’s ESG data systems.

In March 2024, the Company received its Morningstar Sustainalytics ESG Risk Rating, achieving a score of 31 out of 100 (a lower number is better) a 14% improvement compared to the 2023 score.

CORPORATE

Acquisition of Orion’s 40% Interest in Greenstone

On April 23, 2024, the Company announced it had entered into a binding SPA with certain funds managed by Orion to acquire Orion’s 40% interest in Greenstone. Upon closing of the Transaction, the Company would own 100% of Greenstone. Under the terms of the SPA, the consideration to be paid by the Company consists of $705 million in cash on closing, $40 million cash payable by December 31, 2024 and 42,000,000 common shares of the Company. Closing of the Transaction is subject to customary closing conditions, including the receipt of certain regulatory approvals.

In connection with the Transaction, the Company received commitments from a syndicate of banks for a $500 million three-year term loan (the “Term Loan”) which will be used to partially fund the cash consideration payable pursuant to the SPA. The Term Loan will have a three-year term with no principal payments during the first two years. Commencing two years after the closing date, the Term Loan will be repaid in quarterly installments equal to 10% of the then outstanding principal amount of the Term Loan, with the remaining principal amount to be repaid at maturity. The Term Loan will enjoy the same security as the Company’s Revolving Facility, namely, first-ranking security interest over all present and future property and assets of the Company and its material subsidiaries, and the Company’s present and future equity interests in Greenstone, and be subject to the same financial covenants as the Revolving Facility. The Term Loan will include a requirement that Equinox Gold hedge 15% of anticipated gold production through mid-2026.

Concurrent with the announcement of the Transaction, the Company entered into an agreement for a bought deal equity financing of up to 49,060,000 common shares of Equinox Gold at a price of $5.30 per common share, with a 15% over-allotment option (the “Offering”). The Offering closed on April 26, 2024 with the Company issuing 56,419,000 common shares for aggregate gross proceeds of approximately $299 million. The Company intends to use a portion of the proceeds from the Offering to partially fund the cash consideration payable pursuant to the SPA.

At-the-Market Equity Offering Program

For the three months ended March 31, 2024, the Company issued 10.9 million common shares under the ATM Program at a weighted average share price of $4.61 per common share for total gross proceeds of $50.2 million. At March 31, 2024, the Company had issued a cumulative total of 22.5 million (December 31, 2023 - 11.6 million) common shares under the ATM Program for total gross proceeds of $100.0 million (December 31, 2023 - $49.8 million), and the ATM Program had been fully utilized.

Convertible Note Amendment and Debt Covenants

Subsequent to March 31, 2024, the maturity date of the 2019 Convertible Notes was extended from April 12, 2024 to October 12, 2024 and the maturity date of the 2020 Convertible Notes was extended from March 10, 2025 to September 10, 2025. In addition, the conversion price of the 2020 Convertible Notes was amended from $7.80 per share to $6.50 per share.

The 2019 Convertible Notes and 2020 Convertible Notes are subject to standard conditions and covenants. During the Quarter, the Company amended certain of the financial covenants under the Revolving Facility. At March 31, 2024, the Company was in compliance with the applicable covenants.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || FINANCIAL RESULTS | | --- |

Selected financial results for the three months ended March 31, 2024 and 2023

amounts in millions, except per share amounts Three months ended
March 31,<br>2023
Revenue $ 241.3 $ 234.1
Cost of sales
Operating expense (183.8) (172.2)
Depreciation and depletion (46.2) (47.4)
Income from mine operations 11.4 14.5
Care and maintenance expense (1.1)
Exploration and evaluation expense (2.5) (1.8)
General and administration expense (14.1) (9.9)
Income (loss) from operations (5.3) 1.6
Finance expense (17.4) (12.7)
Finance income 2.0 3.0
Share of net income (loss) in associate 0.4 (16.0)
Other income (expense) (13.9) 31.9
Net income (loss) before taxes (34.2) 7.8
Income tax recovery (expense) (8.5) 9.6
Net income (loss) $ (42.8) $ 17.4
Net income (loss) per share attributable to Equinox Gold shareholders
Basic $ (0.13) $ 0.06
Diluted $ (0.13) $ 0.05

All values are in US Dollars.

Income from Mine Operations

Revenue for Q1 2024 was $241.3 million (Q1 2023 - $234.1 million) on sales of 116,504 ounces of gold (Q1 2023 - 123,295 ounces). Revenue increased by 3% in Q1 2024 compared to Q1 2023 primarily due to a 9% increase in the average realized gold price per ounce sold.

Gold ounces sold in Q1 2024 were 6% lower compared to Q1 2023. The decrease was primarily due to lower production at Los Filos, offset partially by higher production at Mesquite and RDM. At Los Filos, the lower production was a result of mine sequencing with more waste stripping during the Quarter, as well as the crusher being offline for most of the Quarter while a portion of the conveyor was relocated. At Mesquite, the higher production was mainly due to higher ore tonnes stacked on the leach pad as a result of contribution from three pits during the Quarter compared to one pit in Q1 2023. At RDM, production was higher mainly due to higher grades mined from in-situ mining, as well as a delay in Q1 2023 in receiving a license which mean the Company was not able to process ore until the third week of January 2023 and then processed primarily low-grade stockpiles.

Operating expense in Q1 2024 was $183.8 million (Q1 2023 - $172.2 million). The increase was primarily due to higher operating expense at RDM as a result of higher production, and at Castle Mountain, driven by higher operating costs, offset partially by lower operating expense at Los Filos as a result of lower production.

Depreciation and depletion in Q1 2024 was $46.2 million (Q1 2023 - $47.4 million). The decrease was primarily due to lower depreciation and depletion at Los Filos as a result of lower production, offset partially by higher depreciation and depletion at Mesquite due to higher sales volumes.

General and Administration

General and administration expense in Q1 2024 was $14.1 million (Q1 2023 - $9.9 million). The increase was primarily due to an increase in professional fees, driven by the impact of a change in classification of certain costs relating to the Company’s operating sites and costs associated with business development activities, and increases in share-based compensation expense and salaries and benefits, due in part to an increase in the number of employees compared to Q1 2023.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || FINANCIAL RESULTS (CONTINUED) | | --- |

Finance Expense

Finance expense in Q1 2024 was $17.4 million (Q1 2023 - $12.7 million). The increase was primarily due to interest expense related to the gold sale prepay arrangements executed late in Q1 2023 and in Q2 2023 and the gold sale arrangement with Sandbox Royalties Corp. (“Sandbox”), which closed in Q4 2023 (collectively, the “Gold Prepay Transactions”).

Share of Net Income (Loss) in Associate

Share of net income in associate in Q1 2024 was $0.4 million (Q1 2023 - $16.0 million share of net loss). The increase from share of net loss to net income was primarily due to a net loss incurred by i-80 Gold in Q4 2022, which the Company recognized its share of in Q1 2023. The income in Q1 2024 relates only to the Company’s investment in Sandbox as the Company discontinued the use of the equity method to account for its investment in i-80 Gold on March 31, 2023 when the Company sold a portion of its shares in i-80 Gold.

Other Income (Expense)

Other expense for Q1 2024 was $13.9 million (Q1 2023 - other income of $31.9 million).

The following table summarizes the significant components of other income (expense):

Three months ended
$ amounts in millions March 31,<br>2024 March 31,<br>2023
Change in fair value of foreign exchange contracts $ (4.0) $ 18.5
Change in fair value of gold contracts (11.6) (5.0)
Change in fair value of power purchase agreement 1.9
Gain on sale of partial interest and reclassification of investment in i-80 Gold 34.5
Loss on modification of Revolving Facility (4.3)
Foreign exchange (gain) loss $ 0.5 $ (1.9)
Other expense $ (0.7) $ (9.9)
Total other income (expense) $ (13.9) $ 31.9

The change in fair value of foreign exchange contracts for Q1 2024 was a loss of $4.0 million (Q1 2023 - gain of $18.5 million). The loss recognized in Q1 2024 was primarily due to the impact of the weakening of the BRL and CAD relative to the USD compared to Q4 2023. The gain recognized in Q1 2023 was primarily due to the impact of the strengthening of the MXN and BRL relative to the USD compared to Q4 2022.

The change in fair value of gold contracts for Q1 2024 was a loss of $11.6 million (Q1 2023 - loss of $5.0 million). The loss in Q1 2024 related to gold collar contracts entered into during 2023 and Q1 2024. The loss in Q1 2023 related to gold collar contracts that were in place when the Company acquired Leagold Mining Corporation. Both losses were driven by changes in the forward gold price relative to the gold contract strike price.

Income Tax Recovery (Expense)

In Q1 2024, the Company recognized a tax expense of $8.5 million (Q1 2023 - tax recovery of $9.6 million). The tax expense in Q1 2024 was primarily due to the impact of profitable operations in Brazil and Mexico. The tax recovery in Q1 2023 was primarily due to the impact of operating losses in Brazil and Mexico, as well as tax benefits on foreign exchange recoveries in connection with the strengthening of the BRL and MXN relative to the USD compared to Q4 2022 and an inflation adjustment in Mexico, offset partially by profitable operations in the US.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || FINANCIAL RESULTS (CONTINUED) | | --- |

Selected Quarterly Information

The following tables set out selected unaudited consolidated quarterly results for the last eight quarters through March 31, 2024:

$ amounts in millions, except per share amounts March 31,<br>2024 December 31,<br>2023 September 30,<br>2023 June 30,<br>2023
Revenue $ 241.3 $ 297.8 $ 284.7 $ 271.6
Cost of sales
Operating expense (183.8) (198.2) (201.1) (192.7)
Depreciation and depletion (46.2) (61.0) (58.4) (48.2)
Income from mine operations 11.4 38.6 25.2 30.7
Care and maintenance expense (0.3)
Exploration and evaluation expense (2.5) (3.3) (2.6) (4.0)
General and administration expense (14.1) (10.0) (14.0) (12.3)
Income (loss) from operations (5.3) 25.3 8.6 14.1
Finance expense (17.4) (17.9) (15.3) (14.3)
Finance income 2.0 2.4 3.0 3.3
Share of net income (loss) in associate 0.4 (0.4) (1.1)
Other income (expense) (13.9) (1.0) (2.3) 2.6
Net income (loss) before taxes (34.2) 8.3 (5.9) 4.5
Income tax recovery (expense) (8.5) (4.5) 8.1 0.8
Net income (loss) $ (42.8) $ 3.9 $ 2.2 $ 5.4
Net income (loss) per share attributable to Equinox Gold shareholders
Basic $ (0.13) $ 0.01 $ 0.01 $ 0.02
Diluted $ (0.13) $ 0.01 $ 0.01 $ 0.02 March 31,<br>2023 December 31,<br>2022 September 30,<br>2022 June 30,<br>2022
--- --- --- --- --- --- --- --- ---
Revenue $ 234.1 $ 259.3 $ 245.1 $ 224.6
Cost of sales
Operating expense (172.2) (168.2) (188.8) (170.7)
Depreciation and depletion (47.4) (59.0) (48.9) (37.0)
Income from mine operations 14.5 32.0 7.4 17.0
Care and maintenance expense (1.1) (1.4) (2.9) (4.7)
Exploration and evaluation expense (1.8) (4.5) (6.2) (4.5)
General and administration expense (9.9) (12.8) (10.9) (11.1)
Income (loss) from operations 1.6 13.3 (12.6) (3.3)
Finance expense (12.7) (12.4) (10.3) (8.2)
Finance income 3.0 2.6 1.3 0.9
Share of net income (loss) in associate (16.0) (3.6) 4.9 (5.9)
Other income (expense) 31.9 (4.9) (11.3) (32.7)
Net income (loss) before taxes 7.8 (5.0) (28.0) (49.2)
Income tax recovery (expense) 9.6 27.6 (2.1) (29.5)
Net income (loss) $ 17.4 $ 22.6 $ (30.1) $ (78.7)
Net income (loss) per share attributable to Equinox Gold shareholders
Basic $ 0.06 $ 0.07 $ (0.10) $ (0.26)
Diluted $ 0.05 $ 0.07 $ (0.10) $ (0.26)
eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024
--- LIQUIDITY AND CAPITAL RESOURCES
---

At March 31, 2024, the Company had financial, operating, and capital commitments of $720.0 million that require settlement within the next 12 months. In April 2024, the maturity date of the 2020 Convertible Notes was extended from March 2025 to September 2025, resulting in a $145.5 million decrease in commitments that require settlement within the next 12 months (refer to Commitments and Contingencies section).

At March 31, 2024, the Company had cash and cash equivalents of $125.3 million and marketable securities of $71.3 million. The Company has a $700.0 million Revolving Facility available for general corporate purposes, of which $164.6 million remained undrawn as at March 31, 2024. On April 9, 2024, the Company drew down $60 million on the Revolving Facility. The Revolving Facility also provides for an uncommitted accordion feature which permits the Company to request an increase in the principal amount of the facility by up to $100.0 million.

In April 2024, in connection with the Transaction, the Company received commitments from a syndicate of banks for a $500 million Term Loan and received gross proceeds of approximately $299 million on close of the Offering on April 26, 2024.

Management believes that the Company’s operating cash flows expected over the next 12 months, in addition to its liquid assets, available credit from the Revolving Facility, and proceeds received in connection with the Offering which are not expected to be used to partially fund the cash consideration payable pursuant to the SPA, are sufficient to satisfy its financial, operating, and capital commitments that require settlement within the next 12 months, which includes repayment of its 2019 convertible notes in October 2024 and the required funding of Greenstone during commissioning.

Volatility in the gold price contributes to risk that cash flow from operations and other sources of liquidity will be insufficient to meet the Company’s financial obligations as they become due, and fund the Company’s ongoing development and construction projects. If Equinox Gold’s cash flows and capital resources are insufficient to fund its debt service obligations, the Company could face substantial liquidity problems and could be forced to reduce or delay investments and capital expenditures or to dispose of material assets or operations, seek additional debt or equity capital or restructure or refinance indebtedness, including indebtedness under its Revolving Facility. The Company may not be able to implement any such alternative measures on commercially reasonable terms or at all and, even if successful, those alternatives may not allow Equinox Gold to meet its scheduled debt service obligations.

Working Capital

Cash and cash equivalents at March 31, 2024 were $125.3 million (December 31, 2023 - $192.0 million) and net working capital was $101.3 million (December 31, 2023 - $354.4 million). The decrease in working capital compared to December 31, 2023 was primarily due to an increase in the current portion of loans and borrowings and deferred revenue associated with the Gold Prepay Transactions, in addition to decreases in marketable securities, derivative assets, and trade and other receivables. The significant components of working capital are described below.

Current inventories at March 31, 2024 were $414.6 million (December 31, 2023 - $412.0 million). The increase was mainly due to an increase in heap leach inventories at Los Filos, driven by a 19% increase in cost per ounce on the leach pad, offset partially by a 9% draw down of ounces from the leach pad. Offsetting the increase was a decrease in current inventories at Aurizona due to the processing of stockpiled ore as is typical during the rainy season.

Marketable securities at March 31, 2024 were $71.3 million (December 31, 2023 - $92.7 million). The decrease was primarily due to a $22.3 million decrease in the fair value of the Company’s investment in i-80 Gold.

Trade and other receivables at March 31, 2024 were $65.5 million (December 31, 2023 - $82.3 million). The following table summarizes the significant components of trade and other receivables:

$ amounts in millions March 31,<br>2024 December 31,<br>2023
Trade receivables $ 6.4 $ 9.9
Value-added tax receivables 46.7 55.3
Income tax receivables 5.6 7.6
Other receivables 6.8 9.6
Total other income (expense) $ 65.5 $ 82.3

The decrease in value-added tax (“VAT”) receivable primarily relates to decreases at Los Filos and Aurizona.

Current liabilities at March 31, 2024 were $611.2 million (December 31, 2023 - $479.6 million). The increase was primarily due to reclassifying $136.1 million related to the Company’s 2020 Convertible Notes, which mature in March 2025, from non-current liabilities to current liabilities. Subsequent to March 31, 2024, the maturity date of the 2020 Convertible Notes was extended to September 2025.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || LIQUIDITY AND CAPITAL RESOURCES (CONTINUED) | | --- |

Cash Flow

Cash provided by operating activities in Q1 2024 was $17.9 million (Q1 2023 - $143.4 million). The decrease in cash provided by operating activities was primarily due to a net cash payment of $139.5 million received in connection with the gold prepay arrangement entered into in March 2023.

Cash used in investing activities in Q1 2024 was $108.8 million (Q1 2023 - $56.8 million). In Q1 2024, the Company spent $104.8 million on capital expenditures (Q1 2023 - $127.9 million). The decrease in capital expenditures was primarily due to lower capital spending at Greenstone as construction was effectively complete at the end of 2023. Capital expenditures at Greenstone in Q1 2024 were $55.7 million excluding capitalized interest of $15.6 million (Q1 2023 - $83.8 million excluding capitalized interest of $7.4 million). In Q1 2023, the Company received $53.4 million related to the disposition of Solaris shares and $22.9 million related to the sale of a partial interest in i-80 Gold. There were no similar dispositions in Q1 2024.

Financing activities in Q1 2024 provided cash of $24.9 million (Q1 2023 - used cash of $3.5 million). In Q1 2024, the Company received net proceeds on issuance of shares of $49.2 million (Q1 2023 - $16.6 million). In Q1 2024, the Company did not draw on its Revolving Facility (Q1 2023 - $126.7 million), repaid principal and interest of $15.8 million (Q1 2023 - $141.3 million) and made lease payments of $8.8 million (Q1 2023 - $8.5 million).

Corporate Investments

At March 31, 2024, the Company’s corporate investments included the following:

•50.2 million shares of i-80 Gold (TSX: IAU), representing approximately 17.2% of i-80 Gold on a basic basis

•58.1 million shares of Sandbox (not currently listed), representing approximately 20.3% of Sandbox on a basic basis

•25.4 million shares of Bear Creek (TSX: BCM), representing approximately 11.2% of Bear Creek on a basic basis

•10.8 million shares of Inca One (TSX: IO), representing approximately 19.99% of Inca One on a basic basis

OUTSTANDING SHARE DATA

As at the date of this MD&A, the Company has 386,395,908 shares issued and outstanding, 590,515 shares issuable under stock options and 7,816,123 shares issuable under restricted share units. The Company also has 75,410,406 shares potentially issuable on conversion of Convertible Notes. The fully diluted outstanding share count at the date of this MD&A is 470,212,952.

COMMITMENTS AND CONTINGENCIES

The Company enters into contracts in the normal course of business that give rise to commitments for future payments. The following table summarizes the contractual maturities of the Company’s financial liabilities, and operating and capital purchase commitments, at March 31, 2024:

Within 1<br>year 1-2<br>years 2-3<br>years 3-4<br>years 4–5<br>years Thereafter Total
Trade payables and accrued liabilities $ 216,217 $ $ $ $ $ $ 216,217
Loans and borrowings(1)(2) 345,278 59,314 558,417 8,308 180,830 1,152,147
Derivative liabilities 9,612 5,311 14,923
Lease liabilities(2) 16,834 12,507 7,944 5,800 2,281 89 45,455
Other financial liabilities(2) 7,510 13,016 7,510 7,350 6,710 2,333 44,429
Reclamation and closure costs(2) 10,525 16,508 19,263 17,533 15,510 129,049 208,388
Purchase commitments(2) 75,380 8,069 7,394 7,052 6,911 25,286 130,092
Other operating commitments(2) 38,597 21,862 22,737 23,646 24,592 11,668 143,102
Total $ 719,953 $ 136,587 $ 623,265 $ 69,689 $ 236,834 $ 168,425 $ 1,954,753

(1)Amount includes principal and interest payments, except accrued interest which is included in accounts payable and accrued liabilities.

(2)Amounts represent undiscounted future cash flows.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || COMMITMENTS AND CONTINGENCIES (CONTINUED) | | --- |

At March 31, 2024, the Company had the following outstanding matters involving contingencies that, if not resolved favorably, could have an adverse impact on the Company’s financial performance, cash flows and results of operations:

Legal

The Company is a defendant in various lawsuits and legal actions for alleged fines, labour related and other matters in the jurisdictions in which it operates. Management regularly reviews these lawsuits and legal actions with outside counsel to assess the likelihood that the Company will ultimately incur a material cash outflow to settle a claim. To the extent management believes it is probable that a cash outflow will be incurred to settle a claim, a provision for the estimated settlement amount is recognized. At March 31, 2024, the Company recognized a provision of $7.3 million (December 31, 2023 - $7.8 million) for legal matters which is included in other non-current liabilities.

Environmental

A historic rain event caused widespread flooding in the Aurizona region in March 2021 and a freshwater pond on the Aurizona site overflowed. The TSF and other infrastructure at the Aurizona site remained operational. The Company received notices from the local state government of environmental infractions related to turbidity in the local water supply at Aurizona with associated fines at March 31, 2024 totaling $10.2 million (2023 - $10.6 million). In addition to the fines, public civil actions have been filed against the Company in the State and Federal courts claiming various damages as a result of the rain event. The Company and its advisors believe the fines and public civil actions are without merit and it is not probable that a cash outflow will occur. Accordingly, no amount has been recognized in relation to the fines and public civil actions.

RELATED PARTY TRANSACTIONS

The Company’s related parties include its subsidiaries, associates, joint operation and key management personnel. The Company’s key management personnel consists of executive and non-executive directors and members of executive management. There were no significant related party transactions during Q1 2024.

NON-IFRS MEASURES

This MD&A refers to cash costs, cash costs per oz sold, AISC, AISC per oz sold, AISC contribution margin, adjusted net income, adjusted EPS, mine-site free cash flow, adjusted EBITDA, net debt, and sustaining capital expenditures that are measures with no standardized meaning under IFRS, i.e. they are non-IFRS measures, and may not be comparable to similar measures presented by other companies. Their measurement and presentation is consistently prepared and is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Numbers presented in the tables below may not sum due to rounding.

Cash Costs and Cash Costs per oz Sold

Cash costs is a common financial performance measure in the gold mining industry; however, it has no standard meaning under IFRS. The Company reports total cash costs on a per oz sold basis. The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company’s performance and ability to generate operating income and cash flow from mining operations. Cash costs are calculated as mine site operating costs and are net of silver revenue. Cash costs are divided by ounces sold to arrive at cash costs per oz sold. In calculating cash costs, the Company deducts silver revenue as it considers the cost to produce the gold is reduced as a result of the by-product sales incidental to the gold production process, thereby allowing management and other stakeholders to assess the net costs of gold production. The measure is not necessarily indicative of cash flow from operations under IFRS or operating costs presented under IFRS.

AISC per oz Sold

The Company uses AISC per oz of gold sold to measure performance. The methodology for calculating AISC was developed internally and is calculated below. Current IFRS measures used in the gold industry, such as operating expenses, do not capture all of the expenditures incurred to discover, develop and sustain gold production. The Company believes the AISC measure provides further transparency into costs associated with producing gold and will assist analysts, investors and other stakeholders of the Company in assessing its operating performance, its ability to generate free cash flow from current operations and its overall value. AISC includes cash costs (described above) and also includes sustaining capital expenditures (described in following section), sustaining lease payments, reclamation cost accretion and amortization and exploration and evaluation costs.

This measure seeks to reflect the full cost of gold production from current operations, therefore, expansionary capital and non-sustaining expenditures are excluded.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || NON-IFRS MEASURES (CONTINUED) | | --- |

Prior to Q2 2023, the Company’s calculation of cash costs included the principal portion of sustaining lease payments. Commencing in Q2 2023, to improve the comparability of the Company’s financial performance measures with its peers and align to the standards outlined by the World Gold Council, the Company has excluded sustaining lease payments from its calculation of cash costs and has included them as a component of AISC. The calculations of cash costs and AISC for comparative periods have been adjusted to conform with the current methodology and are different from the measures previously reported.

The following table provides a reconciliation of cash costs per oz of gold sold and AISC per oz of gold sold to the most directly comparable IFRS measure on an aggregate basis:

’s in millions, except ounce and per oz figures Three months ended
December 31,<br>2023 March 31,<br>2023
Operating expenses 183.8 198.2 172.2
Silver revenue (0.6) (0.6) (0.3)
Fair value adjustment on acquired inventories (0.6) 1.6 (5.9)
Total cash costs $ 182.6 $ 199.3 $ 165.9
Sustaining capital 39.0 42.7 32.5
Sustaining lease payments 2.6 4.6 3.8
Reclamation expense 2.8 1.7 2.2
Sustaining exploration expense 0.2
Total AISC $ 227.2 $ 248.3 $ 204.4
Gold oz sold 116,504 149,861 123,295
Cash costs per gold oz sold 1,567 $ 1,330 $ 1,346
AISC per oz sold $ 1,950 $ 1,657 $ 1,658

All values are in US Dollars.

Sustaining Capital and Sustaining Expenditures

Sustaining expenditures are defined as those expenditures which do not increase annual gold ounce production at a mine site and excludes all expenditures at the Company’s projects and certain expenditures at the Company’s operating sites which are deemed expansionary. Sustaining capital can include, but are not limited to, capitalized stripping costs at open pit mines, underground mine development, mining and milling equipment, and TSF raises. Sustaining expenditures includes sustaining capital, sustaining lease payments, reclamation expense and sustaining exploration expense.

The following table provides a reconciliation of sustaining expenditures to the Company’s total expenditures for continuing operations:

Three months ended
$’s in millions March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Capital additions to mineral properties, plant and equipment(1) $ 134.4 $ 157.0 $ 154.5
Less: Non-sustaining capital at operating sites (10.0) (8.1) (4.6)
Less: Non-sustaining capital at development projects (64.1) (94.6) (91.1)
Less: Capital expenditures - corporate 0.1 (0.1)
Less: Other non-cash additions(2) (21.4) (11.7) (26.1)
Sustaining capital $ 39.0 $ 42.7 $ 32.5
Add: sustaining lease payments $ 2.6 $ 4.6 $ 3.8
Add: reclamation expense $ 2.8 $ 1.7 $ 2.2
Add: sustaining exploration expense $ 0.2 $ $
Sustaining expenditures $ 44.6 $ 49.1 $ 38.5

(1)Per mineral properties, plant and equipment note of the Company’s financial statements. Capital additions exclude non-cash changes to reclamation assets arising from changes in discount rate and inflation rate assumptions in the reclamation provision.

(2)Non-cash additions include right-of-use assets associated with leases recognized in the period, capitalized depreciation for deferred stripping activities, and capitalized non-cash share-based compensation.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || NON-IFRS MEASURES (CONTINUED) | | --- |

Total Mine-Site Free Cash Flow

Mine-site free cash flow is a non-IFRS financial performance measure. The Company believes this measure is a useful indicator of its ability to operate without reliance on additional borrowing or usage of existing cash. In calculating total mine-site free cash flow, the Company excludes the impact of fair value adjustments on acquired inventories as these adjustments do not impact cash flow from operating mine sites. Mine-site free cash flow is intended to provide additional information only and does not have any standardized meaning under IFRS and may not be comparable to similar measures of performance presented by other mining companies. Mine-site free cash flow should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.

Prior to Q1 2023, mine-site free cash flow was calculated inclusive of fair value adjustments on acquired inventories. The calculation of mine-site free cash flow for comparative periods has been adjusted to conform with the current methodology and is different from the measure previously reported.

In Q4 2023, the Company revised the calculation to include changes in non-cash working capital and present mine-site free cash flow after changes in non-cash working capital. The Company believes it is useful to provide mine-site free cash flow before and after changes in non-cash working capital as working capital can fluctuate significantly between periods due to numerous factors.

The following table provides a reconciliation of mine-site free cash flow to the most directly comparable IFRS measure on an aggregate basis:

Three months ended
$’s in millions March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Operating cash flow before non-cash changes in working capital $ 47.7 $ 168.2 $ 195.4
Less: Fair value adjustments on acquired inventories 0.6 (1.6) 5.9
Less: Operating cash flow (generated) used by non-mine site activity(1) 7.3 (71.1) (138.3)
Cash flow from operating mine sites $ 55.7 $ 95.6 $ 63.0
Mineral property, plant and equipment additions $ 134.4 157.0 154.5
Less: Capital expenditures relating to development projects and corporate and other non-cash additions (85.5) (106.2) (117.3)
Capital expenditure from operating mine sites 49.0 50.8 37.1
Lease payments related to non-sustaining capital items 7.5 7.0 4.8
Non-sustaining exploration expense 2.3 3.1 1.8
Total mine-site free cash flow before changes in non-cash working capital $ (3.0) $ 34.7 $ 19.3
(Increase) decrease in non-cash working capital $ (29.8) $ (42.3) $ (52.0)
Total mine site free cash flow after changes in non-cash working capital $ (32.8) $ (7.6) $ (32.7)

(1)Includes taxes paid and proceeds from gold prepayments that are not factored into mine-site free cash flow and are included in operating cash flow before non-cash changes in working capital in the statement of cash flows.

AISC Contribution Margin, EBITDA and Adjusted EBITDA

The Company believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors and other stakeholders use AISC contribution margin, AISC contribution margin per gold ounce sold, EBITDA and adjusted EBITDA to evaluate the Company’s performance and ability to generate cash flows and service debt.

AISC contribution margin is defined as revenue less AISC. EBITDA is defined as earnings before interest, tax, depreciation and amortization. Adjusted EBITDA is defined as earnings before interest, tax, depreciation, and amortization, adjusted to exclude specific items that are significant but not reflective of the underlying operating performance of the Company, such as the impact of fair value changes of warrants, foreign exchange contracts and gold contracts; unrealized foreign exchange gains and losses, transaction costs, and non-cash share-based compensation expense. It is also adjusted to exclude items whose timing or amount cannot be reasonably estimated in advance or that are not considered representative of core operating performance, such as impairments and gains and losses on disposals of assets.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || NON-IFRS MEASURES (CONTINUED) | | --- |

The following tables provide the calculation of AISC contribution margin, EBITDA and adjusted EBITDA, as calculated by the Company:

AISC Contribution Margin

Three months ended
$’s in millions March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Revenue $ 241.3 $ 297.8 $ 234.1
Less: silver revenue (0.6) (0.6) (0.3)
Less: AISC (227.2) (248.3) (204.4)
AISC contribution margin $ 13.6 $ 48.9 $ 29.3
Gold ounces sold 116,504 149,861 123,295
AISC contribution margin per oz sold $ 116 $ 326 $ 238

EBITDA and Adjusted EBITDA

Three months ended
$’s in millions March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Net income (loss) $ (42.8) 3.9 17.4
Income tax expense (recovery) 8.5 4.5 (9.6)
Depreciation and depletion 46.4 61.3 47.5
Finance expense 17.4 17.9 12.7
Finance income (2.0) (2.4) (3.0)
EBITDA $ 27.7 $ 85.2 $ 65.0
Non-cash share-based compensation expense 2.4 2.6 1.5
Unrealized (gain) loss on gold contracts 10.6 12.7 5.4
Unrealized (gain) loss on foreign exchange contracts 18.4 (4.3) (13.1)
Unrealized (gain) loss on power purchase agreement (1.9) (3.3)
Unrealized foreign exchange (gain) loss (5.7) 1.5 2.3
Share of net (income) loss of investment in associate (0.4) 0.4 16.0
Other (income) expense 1.2 0.6 (20.2)
Adjusted EBITDA $ 52.2 $ 95.3 $ 57.0

Adjusted Net Income and Adjusted EPS

Adjusted net income and adjusted EPS are used by management and investors to measure the underlying operating performance of the Company. Adjusted net income is defined as net income adjusted to exclude specific items that are significant but not reflective of the underlying operating performance of the Company, such as the impact of fair value changes in the value of warrants, foreign exchange contracts and gold contracts, unrealized foreign exchange gains and losses, and non-cash share-based compensation expense. It is also adjusted to exclude items whose timing or amount cannot be reasonably estimated in advance or that are not considered representative of core operating performance, such as impairments and gains and losses on disposals of assets. Adjusted net income per share amounts are calculated using the weighted average number of shares outstanding on a basic and diluted basis as determined by IFRS.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || NON-IFRS MEASURES (CONTINUED) | | --- |

The following table provides the calculation of adjusted net income and adjusted EPS, as adjusted and calculated by the Company:

Three months ended
$’s and shares in millions March 31,2024 December 31,2023 March 31,2023
Net income (loss) attributable to Equinox Gold shareholders
Add (deduct):
Non-cash share-based compensation expense 2.4 2.6 1.5
Unrealized (gain) loss on gold contracts 10.6 12.7 5.4
Unrealized (gain) loss on foreign exchange contracts 18.4 (4.3) (13.1)
Unrealized (gain) loss on power purchase agreement (1.9) (3.3)
Unrealized foreign exchange (gain) loss (5.7) 1.5 2.3
Share of net (income) loss of investment in associate (0.4) 0.4 16.0
Other (income) expense 1.2 0.6 (20.2)
Income tax impact related to above adjustments 1.2 0.6 (0.1)
Unrealized foreign exchange (gain) loss recognized in deferred tax expense 2.7 (12.2) (17.5)
Adjusted net income (loss)
Basic weighted average shares outstanding 324.0 313.7 311.6
Diluted weighted average shares outstanding 324.0 317.3 341.6
Adjusted income (loss) per share - basic ($/share) (0.04) 0.01 (0.03)
Adjusted income (loss) per share - diluted ($/share) (0.04) 0.01 (0.03)

All values are in US Dollars.

Net Debt

The Company believes that in addition to conventional measures prepared in accordance with IFRS, the Company and certain investors and analysts use net debt to evaluate the Company’s performance. Net debt does not have any standardized meaning prescribed under IFRS, and therefore it may not be comparable to similar measures employed by other companies. This measure is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performances prepared in accordance with IFRS. Net debt is calculated as the sum of the current and non-current portions of loans and borrowings, net of the cash and cash equivalent balance as at the balance sheet date. A reconciliation of net debt is provided below.

$’s in millions March 31,<br>2024 December 31,<br>2023 March 31,<br>2023
Current portion of loans and borrowings $ 275.6 $ 138.6 $
Non-current portion of loans and borrowings 653.5 786.4 832.7
Total debt 929.1 925.0 832.7
Less: Cash and cash equivalents (unrestricted) (125.3) (192.0) (284.9)
Net debt $ 803.8 $ 733.0 $ 547.8
ACCOUNTING MATTERS
---

Basis of Preparation and Accounting Policies

The Company’s consolidated financial statements have been prepared in accordance with IFRS as issued by the International Accounting Standards Board (“IASB”). Details of material accounting policies are disclosed in note 3 of the Company’s annual audited consolidated financial statements for the year ended December 31, 2023. Except as disclosed in note 2(d) of the Company’s condensed consolidated interim financial statements, the accounting policies applied in the preparation of the condensed consolidated interim financial statements are consistent with those applied in the Company’s annual audited consolidated financial statements for the year ended December 31, 2023.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || ACCOUNTING MATTERS (CONTINUED) | | --- |

Critical Accounting Estimates and Judgments

In preparing the Company’s condensed consolidated financial statements in conformity with IFRS, management has made judgments, estimates and assumptions that affect the application of the Company’s accounting policies and the reported amounts of assets, liabilities, income and expense. Actual results may differ. Critical accounting estimates represent estimates that are uncertain and for which changes in those estimates could materially impact the consolidated financial statements. All estimated and underlying assumptions are reviewed on an ongoing basis. Revisions are recognized in the period in which the estimates are revised and in any future periods affected. Areas of judgment and key sources of estimation uncertainty that have the most significant effect are disclosed in note 4 of the Company’s annual audited consolidated financial statements for the year ended December 31, 2023.

INTERNAL CONTROLS OVER FINANCIAL REPORTING AND DISCLOSURE CONTROLS AND PROCEDURES

The Company's management, with the participation of the Chief Executive Officer and Chief Financial Officer, are responsible for establishing and maintaining adequate internal control over financial reporting and disclosure controls and procedures. The Company's internal control over financial reporting is a process designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with IFRS. Any system of internal control over financial reporting, no matter how well designed, has inherent limitations. These inherent limitations include the realities that judgements in decision making can be faulty, and that breakdowns can occur because of simple error or mistake. Additionally, controls can be circumvented by the actions of one individual, by collusion of two or more people, or by unauthorized override of the control. Therefore, even those systems determined to be effective can provide only reasonable assurance with respect to financial statement preparation and presentation. During the three months ended March 31, 2024, there were no changes in internal controls over financial reporting that have materially affected, or are reasonably likely to materially affect, the Company's internal controls over financial reporting.

CAUTIONARY NOTES AND FORWARD-LOOKING STATEMENTS

This MD&A contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation and may include future-oriented financial information or financial outlook information. Actual results of operations and the ensuing financial results may vary materially from the amounts set out in any future-oriented financial information or financial outlook information. Forward-looking statements and forward-looking information in this MD&A relate to, among other things: the strategic vision for the Company and expectations regarding exploration potential, production capabilities, growth potential and future financial or operating performance, including investment returns; the Company’s production and cost guidance; the timing for and Company’s ability to successfully advance its growth and development projects, including the commissioning of Greenstone and the expansions at Castle Mountain, Los Filos and Aurizona; the Company’s ability to successfully complete the Transaction and the timing thereof, including receipt of all required regulatory approvals; the completion and closing of the Term Loan; the Company’s ability to pay the deferred payment in connection with the Transaction; the timing of Greenstone achieving first gold pour and commercial production; the Company’s ability to successfully renegotiate existing land access agreements at Los Filos and the anticipated impact on Los Filos if those negotiations are unsuccessful; the ability of the Company to mitigate the impact of the geotechnical event in the Piaba pit on planned 2024 production from Aurizona; the timing and the ability of the Company to complete an updated geotechnical assessment of the Piaba pit and nearby infrastructure and develop a plan to remediate long-term stability and recommence mining of the Piaba pit; the strength of the Company’s balance sheet, and the Company’s liquidity and future cash requirements; the potential future offerings of Securities under the Base Shelf Prospectus or corresponding Registration Statement on Form F-10 and any Prospectus Supplement; the Company’s expectations for reducing its GHG emissions and the impact of its operations on climate change, including reaching its GHG emissions reduction target and implementing its water stewardship strategy; the expectations for the Company’s investments in Sandbox, i-80 Gold, and Bear Creek; and conversion of Mineral Resources to Mineral Reserves.

Forward-looking statements or information generally identified by the use of the words “believe”, “will”, “advance”, “achieve”, “strategy”, “increase”, “plan”, “vision”, “improve”, “maintain”, “potential”, “intend”, “on budget”, “anticipate”, “expect”, “estimate”, “on track”, “target”, “objective”, and similar expressions and phrases or statements that certain actions, events or results “may”, “could”, or “should”, or the negative connotation of such terms, are intended to identify forward-looking statements and information. Although the Company believes that the expectations reflected in such forward-looking statements and information are reasonable, undue reliance should not be placed on forward-looking statements since the Company can give no assurance that such expectations will prove to be correct.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || CAUTIONARY NOTES AND FORWARD-LOOKING STATEMENTS (CONTINUED) | | --- |

The Company has based these forward-looking statements and information on the Company’s current expectations and projections about future events and these assumptions include: Equinox Gold’s ability to achieve the exploration, production, cost and development expectations for its respective operations and projects; existing assets are retained and continue to produce at current rates; expectations regarding the impact of macroeconomic factors on the Company’s operations, share price performance and gold price; prices for gold remaining as estimated; currency exchange rates remaining as estimated; availability of funds for the Company’s projects and future cash requirements; prices for energy inputs, labour, materials, supplies and services remaining as estimated; commissioning of Greenstone being completed and performed in accordance with current expectations; the expansion projects at Los Filos, Castle Mountain and Aurizona being completed and performed in accordance with current expectations; the Company’s ability to identify and implement opportunities to mitigate the impact of the geotechnical event at Aurizona; the mine plans outlined in the technical reports for each project, including estimated development schedules, are unchanged; tonnage of ore to be mined and processed and ore grades and recoveries are consistent with mine plans; capital, decommissioning and reclamation estimates remaining as estimated; Mineral Reserve and Mineral Resource estimates and the assumptions on which they are based; no labour-related disruptions and no unplanned delays or interruptions in scheduled construction, development and production, including by blockade or industrial action; the Company’s working history with the workers, unions and communities at Los Filos; all necessary permits, licenses and regulatory approvals are received in a timely manner; the Company’s ability to comply with environmental, health and safety laws and other regulatory requirements; the Company’s ability to achieve its objective of becoming an industry leader for responsible mining and sustainable development; the strategic visions for Sandbox, i-80 Gold, and Bear Creek and their respective abilities to successfully advance their businesses; the ability of Bear Creek to meet its payment commitments to the Company; and the ability of Equinox Gold to work productively with its Indigenous partners at Greenstone. While the Company considers these assumptions to be reasonable based on information currently available, they may prove to be incorrect. Accordingly, readers are cautioned not to put undue reliance on the forward-looking statements or information contained in this MD&A.

The Company cautions that forward-looking statements and information involve known and unknown risks, uncertainties and other factors that may cause actual results and developments to differ materially from those expressed or implied by such forward-looking statements and information contained in this MD&A and the Company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: fluctuations in gold prices; fluctuations in prices for energy inputs, labour, materials, supplies and services; fluctuations in currency markets; recent market events and conditions; operational risks and hazards inherent with the business of mining (including environmental accidents and hazards, geotechnical failures, industrial accidents, equipment breakdown, unusual or unexpected geological or structural formations, cave-ins, flooding and severe weather); inadequate insurance, or inability to obtain insurance to cover these risks and hazards; employee relations; relationships with, and claims by, local communities and Indigenous populations; the effect of blockades and community issues on the Company’s production and cost estimates; the Company’s ability to obtain all necessary permits, licenses and regulatory approvals in a timely manner or at all; changes in laws, regulations and government practices, including mining, environmental and export and import laws and regulations; legal restrictions relating to mining; risks relating to expropriation; increased competition in the mining industry; a successful relationship between the Company and its joint venture partner; the failure by Bear Creek to meet its commitments to the Company; and those factors identified in the section titled “Risks and Uncertainties” in Equinox Gold’s MD&A dated February 21, 2024 for the year ended December 31, 2023, and in the section titled “Risks Related to the Business” in the Company’s most recently filed Annual Information Form which are both available on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov/edgar.

Forward-looking statements and information are designed to help readers understand management's views as of that time with respect to future events and speak only as of the date they are made. Except as required by applicable law, the Company assumes no obligation to update or to publicly announce the results of any change to any forward-looking statement or information contained or incorporated by reference to reflect actual results, future events or developments, changes in assumptions or changes in other factors affecting the forward-looking statements and information. If the Company updates any one or more forward-looking statements, no inference should be drawn that the Company will make additional updates with respect to those or other forward-looking statements. All forward-looking statements and information contained in this MD&A are expressly qualified in their entirety by this cautionary statement.

Cautionary Note to U.S. Readers Concerning Estimates of Mineral Reserves and Mineral Resources

Disclosure regarding the Company's mineral properties, including with respect to mineral reserve and mineral resource estimates included in this MD&A, was prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”). NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. NI 43-101 differs significantly from the disclosure requirements of the Securities and Exchange Commission (the “SEC”) generally applicable to U.S. companies. Accordingly, information contained in this MD&A is not comparable to similar information made public by U.S. companies reporting pursuant to SEC disclosure requirements.

| eqxlogoonelinenoringsrgb002a.jpg<br><br>Management’s Discussion and Analysis<br><br>For the three months ended March 31, 2024 | | --- || TECHNICAL INFORMATION | | --- |

Doug Reddy, MSc, P.Geo, Chief Operating Officer, and Scott Heffernan, MSc, P.Geo., EVP Exploration, are the Qualified Persons under NI 43-101 for Equinox Gold and have reviewed and approved the technical content of this document.

37

Document

EXHIBIT 99.3

CONSENT OF SCOTT HEFFERNAN, M.Sc., P.GEO.

The undersigned hereby consents to the incorporation by reference in the Registration Statement on Form F-10 of Equinox Gold Corp. (the “Company”) (File No. 333-268499) of their name and the information that has been reviewed and approved by them in the Company’s Management’s Discussion and Analysis for the three months ended March 31, 2024, dated May 8, 2024, included in the Current Report on Form 6-K of the Company, dated May 8, 2024.

Date: May 8, 2024 /s/ Scott Heffernan
By: Scott Heffernan, M.Sc., P.Geo.

Document

EXHIBIT 99.4

CONSENT OF DOUG REDDY, M.Sc., P.GEO.

The undersigned hereby consents to the incorporation by reference in the Registration Statement on Form F-10 of Equinox Gold Corp. (the “Company”) (File No. 333-268499) of their name and the information that has been reviewed and approved by them in the Company’s Management’s Discussion and Analysis for the three months ended March 31, 2024, dated May 8, 2024, included in the Current Report on Form 6-K of the Company, dated May 8, 2024.

Date: May 8, 2024 /s/ Doug Reddy