Earnings Call
Southern Copper Corp/ (SCCO)
Earnings Call Transcript - SCCO Q4 2022
Operator, Operator
Good morning, and welcome to Southern Copper Corporation's Fourth Quarter and 2022 Full Results Conference Call. With us this morning, we have Southern Copper Corporation, Mr. Raul Jacob, Vice President, Finance, Treasurer and CFO, who will discuss the results of the company for the past quarter and year 2022 as well as answer any questions that you might have. The information discussed on today's call may include forward-looking statements regarding the company's results and prospects, which are subject to risks and uncertainties. Actual results may differ materially, and the company cautions to not place undue reliance on these forward-looking statements. Southern Copper Corporation undertakes no obligation to publicly update or revise any forward-looking statement, whether as a result of new information, future events or otherwise. All results are expressed in full U.S. GAAP. Now I will pass the call on to Mr. Raul Jacob.
Raul Jacob, CFO
Thank you very much. Good morning, everyone, and welcome to Southern Copper's Fourth Quarter of 2022 and Full Year Results Conference Call. At today's conference, I am joined by Mr. Oscar Gonzalez Rocha, CEO of Southern Copper and Board member as well as Mr. Javier Garcia de Careo and Leonardo Contreras, both also federal Board members. In today's call, we will begin with an update on our view of the copper market and then review Southern Copper's key results related to production, sales, operating costs, financial results, expansion projects, and ESG. After this, we will open the session for questions. Before we get to the agenda of today's meeting, let me say that 2022 was a very challenging year for us. We faced some difficulties in the economies where we operate, which have tested our strength and ability to operate on competitive terms. On top of lower metal prices and inflation, we had to deal with a 54-day stoppage in the first half of 2022. Nonetheless, we have persevered, bolstered by the resilience of our workforce, SEC's strength, and our strong financial position. Evidence of our quality can be seen when we compare the fourth quarter of 2022 to the third quarter of the same year. Net sales in the fourth quarter were 31% over the same period. Consistent with these positive results, the operating cash cost per pound of copper, including byproduct revenue credits, was $0.45 per pound. This is 57% lower than the $1.03 we reported in the third quarter of 2022. On December 7 of last year, the Peruvian Congress invoked its power under the constitution and removed President Pedro Castillo from office. Mrs. Dina Boluarte, the Vice President, immediately assumed the presidency. These fast-moving events led to considerable upheaval, particularly in the south of Peru, where acts of vandalism have escalated. Road blocks are scattered throughout the country, which has negatively affected the normal course of business in various regions. Fortunately, our operations have not been impacted. SEC hopes that the government will take clear actions to restore order, recover the rights of all citizens, and set the stage for a peaceful resolution to this process, so that Peru can resume growth and achieve the development it deserves. For 2023, we continue to focus on growth, and we expect to deliver the La Caridad concentrator from the Pilares mine in the second quarter of this year. This will contribute 35,000 tons of copper annually. Additionally, the new zinc concentrator at Buenavista is expected to begin operations in the second half of 2023, generating 100,000 tons of zinc and 20,000 tons of copper per year. Now let us focus on the copper market. In the fourth quarter of 2022, the London Metal Exchange copper price decreased 18% from an average of $4.40 per pound in the fourth quarter of 2021 to $3.63 per pound, reflecting concerns about a possible recession in the U.S. and Europe, partially offset by good news on a positive Chinese recovery. Current prices for copper are over $4.10 per pound, reflecting a relatively more positive outlook for this market. We believe this is due to the following factors: a reduction in global inflation, which may slow down or even stop eventually, the interest rate hike cycle led by the Fed and the European Central Bank, the turnaround in China's policies regarding COVID-19 after the government embraced proven practices, and stimulus measures that have been implemented in China to support a weak real estate market. The most relevant market intelligence houses for the copper market are expecting a market balance or a small surplus for 2023. This assumes a growth in demand of about 2% to 3% this year. There is uncertainty regarding future production growth in Chile and Peru, which together represent about 40% of the global supply. Low copper inventories stood at 241,000 tons as of December 2022. These low inventories represent about 3.5 days of consumption, an extremely low level by copper inventories, including the London Metal Exchange, the Comex, the Shanghai, and bonded warehouses in China. It is important to emphasize that copper plays a leading role in the global shift to clean energy, which correlates positively with our assertion that the underlying demand for copper will be strong in the long term. Now let's look at Southern Copper's production for the past quarter and the year 2022. Copper represented 70% of our sales in the fourth quarter of 2022. Copper production registered an increase of 1.6% in the fourth quarter to stand at 241,273 tons. Our quarterly results reflect a 4% increase in production in Peru and flat growth in production in Mexico. On a year-on-year basis, copper production fell 6.6% in 2022 and totaled 894,703 tons. This figure was nonetheless 0.5 percentage points higher than our adjusted year plan of 890,000 tons. With the exception of the Buenavista operation, where production levels were higher than those registered in 2021, a decrease in yearly copper production was reported by our other open-pit operations due to a temporary drop in ore grades and the Cuajone stoppage, which reduced our 2022 production by 22,208 tons. Compared to the third quarter, copper production increased 4.7%, which was mainly attributable to our growth in production at all the open-pit operations. For 2023, we expect to produce 925,800 tons of copper, an increase of about 4% over the 2022 final trend. Molybdenum prices averaged $21.17 per pound in the quarter compared to $18.53 in the fourth quarter of 2021. This represents a 14% increase in prices. Molybdenum production decreased by 16% in the fourth quarter of 2022 when compared to the same period of 2021. This was mainly driven by a drop in production at the Toquepala mine due to lower ore grades. These results were partially offset by higher production at Cuajone and Buenavista. Molybdenum production fell 13% year-on-year in 2022 after production fell at Toquepala, Cuajone, and La Caridad. This was partially offset by an increase at the Buenavista mine. For 2023, we expect to produce 22,200 tons of molybdenum. Current molybdenum prices are over $35 per pound. We believe that prices will be supported by global supply shortages and strong demand in China and the U.S. Silver represented 4% of our sales value in the fourth quarter of last year with an average price of $21.25 per ounce in the quarter, which reflected a decrease of 9%. Silver is currently our second by-product. Mine silver production increased 10% in the fourth quarter versus the same period in 2021, and silver production rose at La Caridad, Buenavista, Cuajone, and Toquepala. This was partially offset by a decrease in production at La Caridad. Refined silver production fell by 1% year-over-year, which was mainly driven by a drop in production at our IMS and Hilo refineries. In 2022, we produced 18.6 million ounces of silver, which represents a 2% decrease compared to the 2021 figure. This was mainly due to a drop in production at Cuajone, Cuajone, and La Caridad, which was partially offset by an increase in production at Buenavista and IMS. In 2023, we expect to produce 20.5 million ounces of silver, which is a 10% increase from 2022 and higher than the 19 million ounces produced in 2021, higher by 8% compared to 2021 as well. Zinc represented 3% of our sales value in the fourth quarter of last year with an average price of $1.36 per pound in the quarter, which represents an 11% decrease compared to the fourth quarter of 2021. Zinc is currently our third by-product. Zinc mine production decreased 7% quarter-on-quarter and totaled 15,263 tons. This was driven primarily by a drop in production at the Charcas and Santa Barbara mines. Refined zinc production increased by 26% in the fourth quarter of 2022 when compared to the same period of 2021. For the year 2022, we produced 6,010 tons of zinc, a decrease of 10% compared to 2021 that was mainly attributable to a drop in production at the Charcas and Santa Barbara operations. This was partially offset by increases in production at the San Martin mine. Refining production increased 8% in year-over-year terms. For 2023, we expect to produce 116,800 tons of zinc, which represents an increase of 95% over our 2022 production level. This growth will be driven by production start-up at the Buenavista zinc operations. The Buenavista zinc concentrator will add 51,600 tons of zinc to our production and also by the recovery of the Insamines that will add 6,200 tons. In the case of the ISA mines, we have identified better ore areas in the different mines. And we are contributing with a much higher production for this year coming from the inside. For the year 2024 and beyond, we expect to produce over 200,000 tons of zinc per year. Financial results. For the fourth quarter of 2022, sales were $2.8 billion, which is similar to the level reported in the fourth quarter of 2021. Copper sales volume increased by 2%, while value decreased after the price drop for this metal. Regarding our main by-products, we reported higher sales of molybdenum which increased by 65% due to better prices. This was partially offset by a drop in molybdenum volume. Zinc sales were up by 26% due to an increase in volume of 38%, which was partially offset by lower prices. Silver sales were down in the fourth quarter by 0.5 percentage points due to lower prices. This evolution was partially offset by an uptick in silver volume. Comparing the fourth quarter of 2022 with the third quarter of last year, sales totaled $2.8 billion and represented an increase of $663 million over the figure reported in the third quarter of the previous year. This is a 31% increase in sales. The copper sales volume saw a 1% increase, while value increased by 23% in a scenario of better prices. Regarding our main by-products, we registered higher sales of molybdenum for 138% due to an increase in the volume and better prices. Molybdenum was also favored by provisional price adjustments of $92.6 million. Silver sales increased by 26% due to an uptick in the volume and in prices. Zinc sales fell 7% due to lower prices. This drop was partially offset by an increase in the volume of 4%. Our total operating cost and expenses increased by $157 million or 12% when compared to the fourth quarter of 2021. The main cost increment has been in higher inventory consumption, workers' participation, repair materials, diesel and fuel, explosives, and sales expenses. These cost increases were partially offset by a decrease in leachable material costs, translation differences, and labor costs. Our total operating cost and expenses in the fourth quarter of 2022 increased by $80 million or 6% in comparison with the third quarter of last year. The main cost increments have been in workers' participation, purchased copper, sales expenses, operational and repair materials, higher inventory consumption, and contractors. These cost increases were partially offset by a drop in energy costs and the effect of translation differences and other factors. The fourth quarter of 2022 adjusted EBITDA was $1,647 million, which represented a decrease of 5% compared to the $1,726 million registered in the fourth quarter of 2021. The adjusted EBITDA margin in the fourth quarter of last year was 58% versus 61% in the fourth quarter of 2021. For the year 2022, adjusted EBITDA was $5,365 million. This is 22% below the figure of 2021. The adjusted EBITDA margin in 2022 was 53% versus 63% in 2021. Operating cash cost per ton of copper before byproduct credits was $2.04 per pound in the fourth quarter of 2022. That is $0.25 lower than the value for the third quarter of last year. This 1% decrease in operating cash cost was driven by a drop in cost per pound from higher production that was partially offset by an increase in treatment and refining charges, administrative expenses, and a decrease in the premiums received by our refined copper. Southern Copper's operating cash cost, including the benefit of by-product credit, was $0.45 per pound in the fourth quarter of 2022. This cash cost was $0.59 lower than the cash cost of $1.03 reported in the third quarter of 2022. This is a 47% reduction. Regarding by-products, we had a total credit of $806 million or $1.59 per pound in the fourth quarter of 2022. These figures represent a 55% increase over the $501 million or $1.03 per pound reported in the third quarter of last year. Total credits have increased for molybdenum, silver, and decreased for zinc and sulfuric acid. The byproduct credit has benefited from the adjustment on open molybdenum sales of $93 million, which represented an extra cash credit of $0.18 per pound in the fourth quarter of 2022. Net income in the fourth quarter of 2022 was $902 million, which represented an 8% increase compared to the $833 million registered in the fourth quarter of 2021. The net income margin in the fourth quarter of last year was 32% versus 30% in the fourth quarter of 2021. Let me point out that net income in the fourth quarter of last year reflected a 74% increase compared to the $519 million registered in the third quarter of last year. For the full year 2022, net income was $2,638 million which is 22% lower than the mark for 2021. The net income margin in 2022 was 26% versus 31% in 2021. Cash from operations. Cash flow from operating activities in the fourth quarter was $1,082 million, which represented an increase of 83% over the $590 million posted in the third quarter of 2022 and a decrease of 12% over the $1,220 million posted in the fourth quarter of 2021. Looking into capital investments, as you know, Southern Copper's investment philosophy is not based on the outlook for copper prices but on the quality of the assets that we operate and develop. For years, our strong financial discipline has consistently allowed us to make ongoing investments in our considerable asset portfolio. Our current capital investment program for this decade exceeds $15 billion and includes investments in the Buenavista Zinc, Pilares, El Pilar, and El Arco projects in Mexico, and in the Tia Maria, Los Chancas, and Michiquillay projects in Peru. This capital forecast includes several infrastructure investments, including key investments to bolster the competitiveness of the El Arco projects. In 2022, we spent $948 million in capital investment, which reflected a 6% increase year-on-year and represented 36% of net income in 2021. For our Mexican projects, we have the Buenavista zinc concentrator in the Sonora state. This project is located between the Buenavista deposit. We are building a new concentrator to process zinc. This facility has a production capacity of 100,000 tons of zinc and 20,000 tons of copper per year. We have completed the engineering study and have all the necessary permits. When operating, this facility will double the company's zinc production capacity and provide more than 2,000 operational jobs. As I mentioned before, we're expecting a significant contribution from zinc production this year, over 50,000 tons, and for 2024, over 200,000 tons of additional zinc production for the company. For project updates, the capital budget for the project is $416 million, most of which has already been invested. We expect to initiate product operations in the second half of 2023 at this point. The Pilares project is located 6 kilometers from La Caridad. This project consists of an open pit mine operation with another production capacity of 35,000 tons of copper concentrated. This project will significantly improve the ore grade, considering the 0.78% expected from Pilares compared to the 0.29% from La Caridad. The budget for Pilares is $159 million, most of which has already been spent. The project is currently operating and delivering copper mineral oxides to the SX-EW facilities of the La Caridad operation. We expect to produce mineral for the La Caridad concentrator at full capacity in the second quarter of 2023. El Pilar. This is a low capital-intensive copper greenfield project, which is strategically located in Sonora, Mexico, approximately 45 kilometers from our Buenavista mine. Its copper oxide mineralization contains estimated proven and probable reserves of 317 million tons of ore with an average copper grade of 0.25%. We anticipate that El Pilar will operate as a conventional open-pit mine with an annual production capacity of 36,000 tons of copper cathodes. This operation will use highly cost-efficient and environmentally friendly SX-EW technology. The budget for Pilar is $310 million. Project update: The results from experimental paths in the leaching process have confirmed adequate levels of copper recovery. The basic engineering study is finished and the company continues to develop the project and engage in all site environmental activities. The SX-EW plant EPCM project contract has been awarded to a contractor and has started. We expect production to begin in 2024, and the mine life is estimated at 13 years. El Arco, it's a world-class copper deposit located in the central part of the Baja California peninsula with reserves of over 1,230 million tons with an average ore grade of 0.4% and 141 million tons of leach material with an average ore grade of 0.27%. The project includes an open-pit mine combining concentrator and SX-EW operations, and our production is expected to total 190,000 tons of copper and 105,000 ounces of gold per year. Project update: The company has completed the environmental baseline study for the mine and industrial facilities and is reviewing the basic engineering analysis to request the environmental impact permit. For the Peruvian projects, we have the Tia Maria project, which is a greenfield project located in Arequipa in the Arequipa region in Peru. This project will use state-of-the-art SX-EW technology with the highest international environmental standards to produce 120,000 tons of refined copper per year. The estimated capital budget for the project is $1.4 billion. Southern Copper has been consistently working to promote the welfare of the population of this province. As part of these efforts, we have implemented successful social programs in education, health care, and productive development to improve the quality of life in the region. We have also promoted agriculture and livestock activities in the Tambo Valley and supported growth in manufacturing, fishing, and tourism. In the case of Los Chancas, we have a project update that the following. As of December 31, 2022, part of the project's plan continues to be occupied by illegal miners, some of whom have irregularly registered their stakes in the integral registry of mining formalization. The company has filed criminal complaints and other legal remedies which have resulted in new claims against 70 illegal miners, while five cases remain open. You can see it's quite a minor number, and we hope to resolve this issue shortly. For the Michiquillay project, in the fourth quarter of 2022, the company informed MINEM that it has begun exploration activities and initiated an assessment of the existing mineral resource at depth. In 2022, in accordance with our social agreements with the Michiquillay and La Encañada communities, the company hired unskilled labor and paid for the use of surface land. SCC will continue to make surface land payments in 2023 and plans to support social programs in both communities as it rolls out additional exploration activities. For environmental, social, and governance investments, Southern Copper is committed to improving its ESG record by adopting best practices and informing the investment community and other stakeholders about our progress in this matter. In line with best practice, the Board of Directors has approved the formation of a new sustainability committee chaired by an independent director. The purpose of this committee is to support the Board of Directors of Southern Copper Corporation in developing and monitoring the company's compliance with ongoing commitments to environment, health, safety, communities, human rights, and corporate governance. This is a significant step in our pledge to robust and strong ESG performance. The Sustainable Development Committee held several sessions in the fourth quarter of 2022. During these meetings, our counselors reviewed our advances in terms of our main performance indicators and provided recommendations for the climate change strategy we are building. Progress on the corporate sustainability assessment front: S&P Global increased SEC's rating by 13% year-on-year in its corporate sustainability assessment in 2022. This situates the company among the top 8% of best performance in the mining sector and places SEC 50% above the average rate. These results reflect the upward trend the company is experiencing in sustainability and reaffirm SEC's listing in the Dow Jones Sustainability Index for the Latin American integrated market, known as Mila. This is the fourth consecutive year in which we have achieved this listing. Our ongoing improvement has been driven by positive performance in areas such as cybersecurity, water management, operations closure, occupational safety, and health, among others. The open-pit mine of La Caridad and the Sonora metallurgical complex, both smelter-refineries at this context, received Copper Mark certification. Both units were assessed by this independent assurance system to demonstrate that SEC copper is produced responsibly and highlights the company's contribution to achieving the sustainable development goals of the United Nations in five main areas: business and human rights, community, working conditions, environment, and governance. SEC's goal is to ensure that copper production at all of our units meets Copper Mark criteria. Additionally, La Caridad received the Molybdenum Mark. The aforementioned pilot programs were implemented by Copper Mark and the International Molybdenum Association. So producers have a framework of reference for the most leadership regarding sustainability and responsible production practices. The occupational safety programs of the mining chamber of commerce of Mexico and the national accounting to regulate and certify workplace practices awarded first place to the rescue class of the Charcas and Santa Barbara units in the categories of underground rescue and first aid, respectively, during the sixth national competition of underground mining rescues, first aid, and hazard materials. Fundacion Grupo Mexico organized a volunteer day, which was attended by 8,000 volunteers in 13 states of Mexico and five regions of Peru. Efforts benefit more than 40 institutions near our operations with a focus on improving the quality of life at the community, family, and environmental levels. Dividend announcement. Regarding dividends, as you know, it is the company's policy to review our cash position, expected cash flow generation from operations, capital investment plans, and other financial needs at each Board meeting to determine the appropriate cash dividend. Accordingly, as announced to the market on January 26, the Board of Directors authorized a cash dividend of $1 per share of common stock payable on March 1 to shareholders of record at the close of business on February 14 of this year. Ladies and gentlemen, with these comments, we would like to end our presentation today. Thank you very much for joining us. We would now like to open the forum for questions.
Operator, Operator
Our first question comes from Matthew Murphy from Barclays.
Matthew Murphy, Analyst
I have a question about your CapEx estimates for long-term projects. I'm wondering if we should be adjusting those for inflation. I noticed Grupo Mexico's disclosures used to talk about investments of $10 billion in long-term projects, and that's now $15 billion, including El Arco infrastructure. So I'm just wondering what has changed there and how it might impact the CapEx spending profile in the next few years?
Raul Jacob, CFO
The figure that I mentioned, the $15 billion, refers to what we expect to spend in the next 10 years, through 2030. We have been adjusting some of our budgets. We have been including some new expenditures related to our projects. That's basically what we're thinking. Let me give you the estimate of CapEx that we have for the next five years that will give some color on what we're seeing now. For this year, we're expecting to spend $1.1 billion in capital; for next year, $2 billion; in 2025, $1.8 billion; 2026, $2.5 billion; and 2027, $2.8 billion.
Matthew Murphy, Analyst
Okay. And the timing of the projects. So Los Chancas and Michiquillay have been pushed out, I guess, three years. Can you just address the reason for those changes? And how that reflects in the CapEx budget? Has there been any reordering of your project pipeline?
Raul Jacob, CFO
No, not in the ordering, but we have been looking into the projects and seeing how they have advanced. In the case of Los Chancas, for instance, we have this problem with illegal mining inside the concession that we are very close to solving, and that has stopped our work on this project for a while, even though we have been doing some cabinet work regarding the environmental permitting for Los Chancas, but that has affected our forecast. In the case of Michiquillay, given the delay that we had in signing the social contracts and beginning the exploration season that we are currently doing, we decided to make an adjustment to the timelines for these two projects. That's why we moved the start-up for both of them a little bit. Obviously, if we see opportunities to advance them in time, we'll take that and inform when appropriate. But that’s currently our view on the projects.
Operator, Operator
Our next question comes from the line of Timna Tanners from Wolfe Research.
Timna Tanners, Analyst
I wanted to ask just a follow-up on the CapEx detail. Does that include a potential Cuajone expansion? And does it include Tia Maria? So can you quantify those a bit, please?
Raul Jacob, CFO
For now, it does not include the Cuajone expansion, Timna, and it does include Tia Maria.
Timna Tanners, Analyst
Okay. One about...
Raul Jacob, CFO
Let me add that we expect to have more clarity on the Cuajone project this year and will inform the market regarding that.
Timna Tanners, Analyst
Okay. Excellent. Molybdenum has obviously been an outperformer and you see continued strength there. Your run rate in Q4 is higher than what you're calling for into 2023. I'm just wondering, broadly, if you can help us understand that change. And also are there opportunities to maybe shift production a little higher or shift your focus there a bit given the better outlook in May?
Raul Jacob, CFO
Yes. Molybdenum has surprised positively, given the price we are seeing now is $35 per pound, which is much higher than the $21 per pound reported for the fourth quarter. So if you do the math, it’s over 50% increase in price for molybdenum. We are looking for ways to produce a little bit more. Our mining plans are made considering copper as the main product; there are opportunities to improve the production of ore products. In this case, we're looking into how we can produce a little bit more molybdenum without affecting our copper forecast for 2023 and beyond.
Timna Tanners, Analyst
Okay. Excellent. If I could just squeeze in one more. There's a lot of questions we're getting about the implications to Southern Copper of Grupo Mexico's reported bid for Banamex. Is that something that you can comment on one way or another? It would be very helpful.
Raul Jacob, CFO
I think that question should be posed to Grupo Mexico. From our side, we haven't seen anything, and we have nothing to report about that.
Operator, Operator
Our next question comes from the line of Gabriel Simoes from Goldman Sachs.
Gabriel Simoes, Analyst
So the first one would be — it would be interesting to hear your thoughts on the realized prices for the quarter, not only for copper, but also for the other commodities as well. So may I get here be to understand what drove the much better-than-expected prices that we saw as the benchmark prices didn’t grow as much as what was implied in your numbers. Was that a matter of timing for the sales of molybdenum or anything? Are there any other effects that you'd like to highlight here? And the second question is regarding costs, right? So the costs for byproducts are already decreasing. So we already saw that trend this quarter as we were guiding for, but they're still above the $2 per ton mark. So my question is then, has something changed in your outlook for costs? Or should we expect costs to continue changing downward towards the $1.9 per pound that you spoke about earlier last year?
Raul Jacob, CFO
Okay. Let me start with your second question on cost. What we're seeing in the fourth quarter and now is that some of the much higher costs we had before are somehow adjusting downward, particularly in the case of gas and explosives. But mainly, that's where we're seeing some adjustments and reductions. At the same time, we will be increasing our production from 895,000 tons last year to 926,000 tons this year. This should have a positive benefit on our cash cost before byproduct credits. We expect it to be a little bit more than $2 and hopefully less than $2 as we go through 2023. For the byproducts, we are expecting, as you mentioned, molybdenum prices are supported by a combination of higher demand and some supply pressures from primary production or primary mines of molybdenum that are having troubles in China and other locations. For zinc, we are very positive on the market. The price currently is over $1.50 per pound, which is much higher than what we recorded in the last fourth quarter. We are seeing a very good demand for zinc refinancing and we are obviously very encouraged by the beginning of our new concentrator that will produce about 100,000 tons of zinc per year and 20,000 tons of copper plus some silver. Those are positive signs for us. We see good demand for zinc and we’re hopeful for delivering on the new facility for zinc production at full speed by the third quarter. Also, we see on the positive side that our mines are turning into or getting into a better ore grade area, yielding more production. Now for gold and silver, I think that it's much more complicated to make a forecast, so I will stop there. Also, I have mentioned that we had very good sulfuric acid sales in both volume and prices in 2022, and I expect this trend to continue, although prices are not as good as the average of last year, we’re still seeing a very positive market for sulfuric acid sales in 2023.
Operator, Operator
Our next question comes from the line of Alfonso Salazar from Scotiabank.
Alfonso Salazar, Analyst
One question on production. As you mentioned, production for 2023 copper production. Can you give us the outlook or your expectations for the years 2024 to 2027? And the second one is on El Arco. It seems to me that once again, El Arco from the big projects that you have in the pipeline is becoming the one that can move faster. So just wondering if this is the case? And also, if you can talk about the challenges that you see ahead, especially environmental ones, it will require operation of an open-pit mine and also infrastructure, the legal challenges, anything that you can mention about El Arco, please.
Raul Jacob, CFO
Yes. Thank you for your question. The forecast that we have for the next five years is as follows: for 2023, 925,800 tons; 2024, 1,061,000 tons; 2025, 1,021,000 tons; 2026, 1,108,000 tons; and 2027, 1,070,000 tons. Regarding El Arco, it is indeed a very good project. We're working on it. We have secured all the land required for the project. We have been looking into the infrastructure required for the project to advance it, as well as the environmental permits we need. Obviously, in relation to some of these permits, there are challenges we need to overcome. But we are very positive. This is a genuinely good project, and we believe we can develop it at a good pace in due time.
Operator, Operator
Our next question comes from the line of John Tumazos from Very Independent Research.
John Tumazos, Analyst
Could you refresh my memory? In Peru, there's a statutory requirement to share a certain amount of profits with the employees, labor participation. Could you please refresh my memory as to that formula and review your social programs in Peru and some of the programs associated with your three major projects? I think that maybe there could even be a short line in railroad, for example, with Tia Maria. And then help us to explain the communications efforts to the community to understand these benefits and advance your projects for permitting and social license and community approval. We know you work very hard on these things.
Raul Jacob, CFO
Thank you for your question. Let's start with profit sharing. We are legally required in both Mexico and Peru to have a profit-sharing program. In Peru, it's 8% of profit before taxes; in Mexico, it's 10% of profit before taxes. Mexico has some adjustments given the need to take a 3-year average to provide benefits to the labor force, but that's basically how it works. In terms of our social programs, I want to point out that we are in an area of the country with currently some social challenges. Our operations have not been affected by them so far, and we are making significant efforts to maintain them operating at full capacity. In the case of our projects, we have been developing several initiatives on the social front to maintain a good relationship with the local communities. In some cases, we don’t have a community nearby, but there are populations. That's the case, for instance, with the Tia Maria project, where we have the province population with no close-knit community. For the other two projects, Los Chancas and Michiquillay, we do have communities nearby. In the case of Los Chancas, we had an incident last year where a group of illegal miners entered our concession and damaged our facilities. We have been working to recover our operational capacity for this project. I want to point out that we have evidence that no members of the communities participated in this act; it was driven by individuals seeking to engage in illegal mining activities. We are pursuing all legal options to remove those individuals from our premises, having successfully resolved around 70 cases by canceling their permits with the government. There are still five cases remaining, and we will be able to fully resume our operations shortly. In the case of Michiquillay, last year, we signed social contracts with the two communities that are there. These social contracts have several initiatives, including hiring commitments for local workers during exploration efforts. We also have a program to provide rental compensation for the use of certain facilities in these areas, and we are moving forward with these programs, which also include additional initiatives we are considering. Furthermore, we have been developing several impactful and powerful programs in our current operations at Toquepala and Cuajone, and we are extending them to the three projects I just mentioned. For instance, we have programs that develop skills such as heavy machinery operation, electrical work, and various civil works. These skills can then be utilized within our operations or the projects. Overall, maintaining robust communication with the communities is essential as we strive for better development and successful project outcomes over time.
John Tumazos, Analyst
If I could follow up, please, in Peru or in Mexico, roughly— in very round numbers, how much is the statutory profit sharing per employee when copper is at $4 in cash costs or $0.45? It must be very positive.
Raul Jacob, CFO
For Peru, this year should be about— let me put it in terms of monthly salaries, around 5x the monthly salary this year as profit sharing. In Mexico, the number varies but is also quite attractive.
Operator, Operator
Our next question comes from the line of Hernan Kisluk from MetLife.
Hernan Kisluk, Analyst
It's related to the revenues of the quarter. So if I do the math for the quarter, multiplying the volume sold of each product by the reference price, I still have a very large gap compared to the reported revenues of about $450 million. I would like to know if there is any kind of effect such as provisional pricing or any other factors that are distorting the revenue for the quarter?
Raul Jacob, CFO
Well, it's not distorting, but we're recognizing the value of the sales that we have at open sales. In the case of molybdenum, for instance, the adjustment on open sales uses the last price quoted by the market. The adjustment was significant, over $92 million for molybdenum. We also have other revenue sources that are often overlooked, such as forecasted revenues. We had very good sulfuric acid prices throughout this past quarter and for the year, which positively impacted the corporation's revenue. These factors have contributed to the revenues in the fourth quarter this year.
Hernan Kisluk, Analyst
Okay. Is there some effect of this on the copper side of the business? Or is it just modified with other products?
Raul Jacob, CFO
No, there is also an adjustment on operating copper open sales, but we have future pricing in copper while in molybdenum, we just have the end-of-month price, no future prices. So in copper, there is also an adjustment, but it's not as significant as that $92 million. Overall, to give you an idea, in 2021, we had $83 million of sales forecasted, and in 2022, that number went up to $212 million, reflecting an important increase.
Operator, Operator
Our next question comes from the line of Camilla Barder for Bradesco BBI.
Camilla Barder, Analyst
My question has just been addressed. Thank you.
Operator, Operator
At this time, I am showing no further questions. I would like to turn the conference back over to Victor Pedraglio for closing remarks.
Victor Pedraglio, Not Specified
Well, with this, we conclude our conference call for Southern Copper's Fourth Quarter of 2022 and full year results. We certainly appreciate your participation and hope to have you back with us when we report the first quarter of 2023. Thank you very much, and have a nice day.