Skip to main content

6-K

Woodside Energy Group Ltd (WDS)

6-K 2025-05-09 For: 2025-05-09
View Original
Added on April 10, 2026

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

FORM 6-K

REPORT OF FOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR 15d-16

UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of May 2025

Commission File Number: 001-41404

Woodside Energy Group Ltd

(ABN 55 004 898 962)

(Registrant’s name)

Woodside Energy Group Ltd

Mia Yellagonga, 11 Mount Street

Perth, Western Australia 6000

Australia

(Address ofprincipal executive offices)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F ☑   Form 40-F ☐

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): ☐

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ☐

THIS REPORT ON FORM 6-K IS BEING FILED FOR THE PURPOSES OF INCORPORATION BY REFERENCE IN THE REGISTRATION STATEMENT ON FORM F-3 (FILE NOs. 333-277499 AND 333-277499-01). THIS REPORT SHALL BE DEEMED FILED AND INCORPORATED BY REFERENCE IN SUCH REGISTRATION STATEMENT AND SHALL BE DEEMED TO BE A PART THEREOF FROM THE DATE ON WHICH THIS REPORT IS FILED, TO THE EXTENT NOT SUPERSEDED BY DOCUMENTS OR REPORTS SUBSEQUENTLY FILED OR FURNISHED.

The documents included as exhibits to this report include portions from the previously-published announcement of Woodside Energy Group Ltd (the “Company”) for the purposes of incorporating certain information by reference into the Company’s Registration Statement on Form F-3 in accordance with the terms set out in that document. This document does not update or otherwise supplement the information contained in the previously published announcements identified below.

EXHIBIT INDEX

Exhibit <br>Number Description
99.1 First Quarter Report for the quarter ended March 31, 2025, containing operational and certain financial information for the quarter ended March 31, 2025.

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

Dated: May 9, 2025

WOODSIDE ENERGY GROUP LTD
By: /s/ Damien Gare
Damien Gare<br> <br>Corporate Secretary

EX-99.1

Exhibit 99.1

Disclaimer and important notice

Forward lookingstatements

This report contains forward-looking statements with respect to Woodside’s business and operations, market conditions, results of operations and financial condition, including for example, but not limited to, outcomes of transactions, statements regarding long-term demand for Woodside’s products, potential investment decisions, development, completion and execution of Woodside’s projects, expectations regarding future capital expenditures, the payment of future dividends and the amount thereof, future results of projects, operating activities and new energy products, expectations and plans for renewables production capacity and investments in, and development of, renewables projects, expectations and guidance with respect to production, capital and exploration expenditure and gas hub exposure. All statements, other than statements of historical or present facts, are forward-looking statements and generally may be identified by the use of forward-looking words such as ‘guidance’, ‘foresee’, ‘likely’, ‘potential’, ‘anticipate’, ‘believe’, ‘aim’, ‘aspire’, ‘estimate’, ‘expect’, intend’, ‘may’, ‘target’, ‘plan’, ‘strategy’, ‘forecast’, ‘outlook’, ‘project’, ‘schedule’, ‘will’, ‘should’, ‘seek’, and other similar words or expressions. Similarly, statements that describe the objectives, plans, goals or expectations of Woodside are forward-looking statements.

Forward-looking statements in this report are not guidance, forecasts, guarantees or predictions of future events or performance, but are in the nature of future expectations that are based on management’s current expectations and assumptions. Those statements and any assumptions on which they are based are subject to change without notice and are subject to inherent known and unknown risks, uncertainties, contingencies and other factors, many of which are beyond the control of Woodside, its related bodies corporate and their respective officers, directors, employees, advisers or representatives. Important factors that could cause actual results to differ materially from those in the forward-looking statements and assumptions on which they are based include, but are not limited to, fluctuations in commodity prices, actual demand for Woodside’s products, currency fluctuations, geotechnical factors, drilling and production results, gas commercialisation, development progress, operating results, engineering estimates, reserve estimates, loss of market, industry competition, sustainability and environmental risks, climate related transition and physical risks, changes in accounting standards, economic and financial markets conditions in various countries and regions, political risks, the actions of third parties, project delay or advancement, regulatory approvals, the impact of armed conflict and political instability (such as the ongoing conflicts in Ukraine and in the Middle East) on economic activity and oil and gas supply and demand, cost estimates, legislative, fiscal and regulatory developments, including but not limited to those related to the imposition of tariffs and other trade restrictions, and the effect of future regulatory or legislative actions on Woodside or the industries in which it operates, including potential changes to tax laws, and the impact of general economic conditions, inflationary conditions, prevailing exchange rates and interest rates and conditions in financial markets and risks associated with acquisitions, mergers, divestitures and joint ventures, including difficulties integrating or separating businesses, uncertainty associated with financial projections, restructuring, increased costs and adverse tax consequences, and uncertainties and liabilities associated with acquired and divested properties and businesses.

A more detailed summary of the key risks relating to Woodside and its business can be found in the “Risk Factors” section of Woodside’s Annual Report on Form 20-F for the year ended 31 December 2024 filed with the United States Securities and Exchange Commission. You should review and have regard to these risks when considering the information contained in this report.

If any of the assumptions on which a forward-looking statement is based were to change or be found to be incorrect, this would likely cause outcomes to differ from the statements made in this report.

1 First quarter report for period ended 31 March 2025

All forward-looking statements contained in this report reflect Woodside’s views held as at the date of this report and, except as required by applicable law, Woodside does not intend to, undertake to, or assume any obligation to, provide any additional information or update or revise any of these statements after the date of this report, either to make them conform to actual results or as a result of new information, future events, changes in Woodside’s expectations or otherwise.

Investors are strongly cautioned not to place undue reliance on any forward-looking statements. Actual results or performance may vary materially from those expressed in, or implied by, any forward-looking statements. None of Woodside nor any of its related bodies corporate, nor any of their respective officers, directors, employees, advisers or representatives, nor any person named in this report or involved in the preparation of the information in this report, makes any representation, assurance, guarantee or warranty (either express or implied) as to the accuracy or likelihood of fulfilment of any forward-looking statement, or any outcomes, events or results expressed or implied in any forward-looking statement in this report. Past performance (including historical financial and operational information) is given for illustrative purposes only. It should not be relied on as, and is not necessarily, a reliable indicator of future performance, including future security prices.

Other important information

All figures are Woodside share for the quarter ending 31 March 2025, unless otherwise stated.

All references to dollars, cents or $ in this report are to US currency, unless otherwise stated.

References to “Woodside” may be references to Woodside Energy Group Ltd and/or its applicable subsidiaries (as the context requires).

The conversion factors used throughout this report are set out under “Units of measure and conversion factors”, unless otherwise stated.

2 First quarter report for period ended 31 March 2025

FIRST QUARTER REPORT FOR PERIOD ENDED 31 MARCH 2025

LOGO

ASX: WDS | NYSE: WDS

Wednesday, 23 April 2025

Outstanding performance fromhigh quality assets

Operations

Maintained exceptional production from Sangomar of 78 Mbbl/day (Woodside equity interest) produced in the quarter.
Quarterly production of 49.1 MMboe (546 Mboe/day), down 4% from Q4 2024 due to weather impacts at NWS and unplanned outages at Pluto, partially offset by higher production at Shenzi and Atlantis. Quarterly<br>production increased 9% from Q1 2024 due to the addition of Sangomar production.
--- ---
Quarterly revenue of $3,315 million, down 5% from Q4 2024 primarily due to lower production and lower oil-linked prices. Quarterly revenue increased 13% from Q1 2024<br>due to Sangomar start-up in July 2024 and high gas hub-linked prices.
--- ---
Sold 25.4% of produced LNG at prices linked to gas hub indices in the quarter (9.4% of total equity production).
--- ---

Projects

Strong project execution for the quarter, with all projects on schedule and budget.
The Beaumont New Ammonia Project was 90% complete, with Phase 1 of the project on track for startup in the second half of 2025.
--- ---
The Scarborough Energy Project was 82% complete, and remains on track for first LNG cargo in the second half of 2026.
--- ---
The Trion Project was 26% complete, and remains on track for first oil in 2028.
--- ---

Portfoliodevelopments

Further streamlining Woodside’s portfolio and generating near-term cash flow by divesting the Greater Angostura assets.^1^
Subsequent to the quarter, entered an agreement for the sale of a 40% interest in Louisiana LNG Infrastructure LLC.^2^
--- ---
Subsequent to the quarter, signed LNG sale and purchase agreements with Uniper for the supply of up to two million tonnes per annum.^3^
--- ---

Woodside CEO Meg O’Neill said the company continued its focus on operational excellence and project delivery over the first quarter of 2025, while laying the foundation for Woodside’s next phase of value creation.

^1^ Completion of the transaction is subject to conditions precedent, including joint venture, government and<br>regulatory approvals.
^2^ Completion of the transaction is subject to conditions precedent, including final investment decision for the<br>Louisiana LNG development, requisite regulatory, legal and other customary approvals.
--- ---
^3^ The sale and purchase agreements are subject to Woodside’s final investment decision on the three train<br>16.5 Mtpa foundation development of Louisiana LNG.
--- ---
3 First quarter report for period ended 31 March 2025
--- ---

Comparative performance at a glance

Q1<br><br><br>2025 Q4 2024 Change<br><br><br>% Q1 2024 Change<br><br><br>% YTD<br><br><br>2025 YTD<br><br><br>2024 Change<br><br><br>%
Revenue^4^ $ million 3,315 3,484 (5%) 2,945 13% 3,315 2,945 13%
Production^5^ MMboe 49.1 51.4 (4%) 44.9 9% 49.1 44.9 9%
Gas MMscf/d 1,841 1,909 (4%) 1,929 (5%) 1,841 1,929 (5%)
Liquids Mbbl/d 223 224 —% 155 44% 223 155 44%
Total Mboe/d 546 559 (2%) 494 11% 546 494 11%
Sales^6^ MMboe 50.2 54.1 (7%) 45.6 10% 50.2 45.6 10%
Gas MMscf/d 1,962 2,129 (8%) 1,950 1% 1,962 1,950 1%
Liquids Mbbl/d 213 214 —% 159 34% 213 159 34%
Total Mboe/d 558 588 (5%) 501 11% 558 501 11%
Average realisedprice $/boe 65 63 3% 63 3% 65 63 3%

Operations

Pluto LNG

LNG reliability was 89.9% for the quarter due to the impact of three unplanned train outages, which were<br>rectified within days of each event. Facility performance continues to be proactively monitored to minimise the risk of future unplanned outages.
Completed maintenance activities during facility downtime to minimise future planned outages.<br>
--- ---
Successfully processed additional volumes through the Pluto-KGP<br>Interconnector, using capacity at the North West Shelf.
--- ---

North West Shelf (NWS) Project

Achieved strong quarterly LNG reliability of 96.5%.
Received approvals from the North West Shelf Joint Venture for long lead items on the Greater Western<br>Flank Phase 4 Project, a five-well subsea tie-back to existing NWS offshore facilities. The project will support the delivery of domestic gas into the WA market during a forecasted shortfall in supply<br>post-2028, with a final investment decision (FID) planned for the second half of 2025.
--- ---
Successfully completed remote operations of offshore assets during a significant cyclone event, which<br>limited the impact on production.
--- ---
Continued LNG Train 2 permanent retirement activities following cessation of production in Q4 2024, with<br>retirement work scopes being undertaken in a phased manner.
--- ---

Bass Strait

Woodside approved investment in the Kipper 1B Project and the Turrum Phase 3 Project. Through the<br>development of these projects, Woodside is expected to add more than 100 petajoules (Woodside equity interest) to the south-eastern Australian domestic gas market, supplying local manufacturers, power generators, and homes.
The Kipper 1B Project is expected to expand capacity from the Kipper field and deliver gas supplies ahead<br>of winter 2026 through the drilling of a subsea well and upgrades to the West Tuna platform.
--- ---
The Turrum Phase 3 Project is expected to deliver much-needed gas to south-eastern Australia by 2027 from<br>a five-well infill development of the Turrum and North Turrum fields and topsides modifications to the Marlin B platform. Once the project comes online, it will produce four times more gas than Queensland supplied to the southern states in 2024.<br>
--- ---
^4^ Revenue presented in this quarterly report reconciles to operating revenue, the IFRS measure presented in<br>Woodside Financial Statements. Comparative periods have been presented on the same basis.
--- ---
^5^ Q1 2025 includes 0.29 MMboe primarily from feed gas purchased from Pluto<br>non-operating participants processed through the Pluto-KGP Interconnector.
--- ---
^6^ Restated to exclude periodic adjustments reflecting the arrangements governing Wheatstone LNG sales of 0.22<br>MMboe in Q4 2024 and -0.28 MMboe in Q1 2024. Revenue presented in this quarterly report reconciles to operating revenue, the IFRS measure presented in Woodside Financial Statements. Comparative periods have<br>been presented on the same basis.
--- ---
4 First quarter report for period ended 31 March 2025
--- ---

Sangomar

Achieved exceptional production of 99 thousand barrels per day (Mbbl/d) (100% basis, 78 Mbbl/d<br>Woodside share) at 97.6% reliability, with production from the Sangomar field remaining at plateau for the quarter.
During the quarter, based on a positive response observed in S400 oil producers from water injection,<br>contingent resources were migrated to developed reserves. The reserve addition was 7.1 million barrels to proved (1P) reserves, Woodside share,^7^ and Woodside expects Sangomar’s<br>depreciation, depletion and amortisation (DD&A) rate for 2025 to decrease by 5 to 10% from its 2024 DD&A rate of approximately $56/boe.
--- ---
Cargoes were delivered to China, Europe, US and Senegal’s domestic refinery.
--- ---

United States of America

Achieved outstanding reliability of 99.8% at Shenzi.
Strong quarterly production at Shenzi was supported by a well returning to production in late 2024 and<br>ongoing optimisation efforts.
--- ---
Completed planned well intervention campaigns at Atlantis and commenced execution of an infill sidetrack<br>producer.
--- ---
Strong quarterly production from the Mad Dog field, Argos facility, with uplift seen from riser gas lift.<br>
--- ---

Marketing

Subsequent to the quarter, Woodside signed LNG sale and purchase agreements with Uniper for the supply of<br>1.0 million tonnes per annum (Mtpa) from Louisiana LNG LLC for up to 13 years from the commercial operations date (COD) of Louisiana LNG and up to 1.0 Mtpa from its global portfolio commencing with Louisiana LNG’s COD over a term until<br>2039.^8^
Signed a long-term sale and purchase agreement with China Resources Gas International Limited for supply<br>of approximately 0.6 million tonnes of LNG per year over 15 years on a delivered basis, commencing in 2027.
--- ---
Supplied 25.4% of produced LNG at prices linked to gas hub indices, realising a 23% premium compared to oil-linked pricing. This represents 9.4% of Woodside’s total equity production. Full-year guidance remains unchanged at 28-35% of produced LNG.
--- ---
Executed incremental Western Australian gas sales of 3.6 PJ for delivery in 2025 and 2026. Woodside<br>continues to engage with the Western Australian domestic market on additional supply requirements for 2025, 2026 and 2027.
--- ---
Delivered 526 TJ of trucked LNG, equivalent to 513 trailers, to customers in northern Western Australia.<br>
--- ---
Progressed preparations to release an expression of interest before 30 April 2025 for Australia east<br>coast natural gas supply to ensure compliance with the terms of Woodside’s Conditional Ministerial Exemption under the Gas Market Code.<br>
--- ---
^7^ Refer to Notes to petroleum reserves on page 19 for details of disclaimers.
--- ---
^8^ Completion of the transaction is subject to conditions precedent including final investment decision for the<br>Louisiana LNG development, requisite regulatory, legal and other customary approvals.
--- ---
5 First quarter report for period ended 31 March 2025
--- ---

Projects

Beaumont New Ammonia

Progress continued with Train 1 construction 90% complete at the end of the quarter and onsite workforce<br>reaching peak numbers. Train 1 of the project remains on track to achieve first production in the second half of 2025, with pre-commissioning activities anticipated to begin in Q2 2025.^9^
Commenced electrical subsystem completion, with the site expected to switch from temporary to permanent<br>power in Q2 2025.
--- ---

Scarborough Energy Project

The Scarborough and Pluto Train 2 Project was 82% complete at the end of the quarter (excluding Pluto<br>Train 1 modifications).
The floating production unit (FPU) hull exited its second dry dock, and the topsides were loaded onto a<br>transport barge in readiness for integration activities.
--- ---
Installation of the subsea production risers commenced.<br>Pre-installation of the FPU mooring chains was completed. Batch drilling of the intermediate sections of the development wells concluded.
--- ---
Activities at the Pluto Train 2 site are focused on piping and cable installation and preparing for pre-commissioning activities.
--- ---
Site works for Pluto Train 1 modifications continue and construction activity at the module yard ramped<br>up.
--- ---
In February 2025, the Scarborough Offshore Facility and Trunkline (Operations) Environment Plan was<br>accepted by the regulator.
--- ---
First LNG cargo is targeted for the second half of 2026.
--- ---

Trion

The Trion Project was 26% complete at the end of the quarter.
Completed the first steel cut for the three FPU topside modules in Korea and the floating storage and<br>offloading facility (FSO) disconnectable turret mooring system in China. Fabrication progressed on schedule, including the manufacturing of subsea equipment.
--- ---
Awarded the Operations and Maintenance contract for the FSO lease vessel.
--- ---
An Environmental Permit application has been submitted to the regulator, and progress is being made on the<br>submission of the HSE management system permit application.
--- ---

Louisiana LNG

Continued project scope under a limited notice to proceed with Bechtel. Site works include dry excavation,<br>clearing, area drainage improvements, mud mat installation, sheet piling and concrete work.
All high value orders and major purchase orders (equipment and bulk materials) for train 1 and 2 have been<br>released. Purchase orders for train 3 have also been placed.
--- ---
Subsequent to the quarter, Woodside entered into an agreement with Stonepeak for the sale of a 40% equity<br>interest in Louisiana LNG Infrastructure LLC. Under this transaction, Stonepeak has agreed to provide $5.7 billion towards the foundation development of Louisiana LNG on an accelerated basis, contributing 75% of the project capital expenditure<br>in both 2025 and 2026.^10^
--- ---
Woodside continues to work towards FID readiness on the three train foundation development.<br>
--- ---
^9^ Phase 1 handover from OCI to Woodside remains subject to cost, schedule, and performance guarantees from OCI.<br>With limited exceptions, such as changes requested by Woodside, OCI will expend the resources necessary to complete the project ensuring that it meets the agreed performance standards prior to hand over. OCI will also be responsible for limited<br>financial payments to Woodside if the project is delayed beyond September 2025.
--- ---
^10^ Completion of the transaction is subject to conditions precedent.
--- ---
6 First quarter report for period ended 31 March 2025
--- ---

Hydrogen Refueller @H2Perth^11^

Commenced construction work on the project with ready for startup targeted for Q4 2025.<br>

Decommissioning

Safely and successfully completed the removal of all facilities from Enfield, offshore Western Australia,<br>with the recovery of final infrastructure in February. With only survey activities remaining, this concludes the multi-year decommissioning program at Enfield.
Subsequent to the quarter, Woodside concluded the ten-well<br>Stybarrow plug and abandonment campaign.
--- ---
Subsequent to the quarter, a mobile offshore drilling unit arrived at the Minerva field, offshore<br>Victoria, and commenced preparations to plug and abandon the first of three Minerva wells.
--- ---
Commenced deconstruction of the Griffin Riser Turret Mooring at the Australian Marine Complex in<br>preparation for recycling and reuse.
--- ---
Continued decommissioning activities at Bass Strait, completing the plug and abandonment activities for 27<br>wells, including on the Bream B platform. Plug and abandonment activities commenced on the Kingfish A and Cobia platforms.
--- ---

Exploration and development

Browse

Work continued on the Browse to North West Shelf Project to optimise the development concept, advance key<br>regulatory approvals and progress commercial discussions to process Browse volumes through the Karratha Gas Plant.

Calypso

Progressed pre-front-end<br>engineering design (FEED) engineering studies and subsurface studies to mature the technical and commercial definition of the development concept.

Exploration

Woodside declined to exercise the option to acquire at least a 56% interest in the Namibian Petroleum<br>Exploration Licence 87.
^11^ The project has received funding from the Hydrogen Fuelled Transport Project Funding Process as part of the<br>Western Australian Government’s Renewable Hydrogen Strategy.
--- ---
7 First quarter report for period ended 31 March 2025
--- ---

New energy and carbon solutions

New energy

With the acquisition of Beaumont New Ammonia, plans for Woodside’s H2OK project are being reassessed.<br>Subsequent to the quarter, exit from the H2TAS project was formalised.
Commitment to existing climate targets remains firm with these decisions following a review of global new<br>energy opportunities to ensure there is alignment between Woodside’s corporate strategy, capital allocation framework, business priorities and external market conditions.
--- ---

Carbon capture and storage (CCS) opportunities

Angel CCS completed engineering studies as part of pre-FEED and<br>commenced engagement with potential customers for CCS services.

Corporate activities

Greater Angostura assets divestment

Woodside entered into an agreement in March 2025 with Perenco to divest its Greater Angostura assets in<br>Trinidad and Tobago for $206 million. The divestment is inclusive of Woodside’s interest in the shallow water Angostura and Ruby offshore oil and gas fields, associated production facilities and onshore terminal. The transaction provides<br>near-term cash flow to support ongoing investments and shareholder distributions and builds on the Australian asset swap announced in December 2024, further streamlining Woodside’s portfolio. The transaction is expected to close in Q3 2025,<br>with an effective date of 1 January 2025. Completion of the transaction is subject to conditions precedent.

Climate andsustainability

Woodside held a Sustainability Briefing on 3 April 2025, part of a structured program of engagement<br>with investors on the company’s approach to climate and other sustainability topics. The briefing was held following the release of Woodside’s Sustainability disclosures in February 2025.
Woodside awarded a A$35 million contract to Cherratta Lodge, a Traditional Owner operated business in<br>Karratha, Western Australia, for provision of accommodation to the workforce for Pluto Train 1 modifications. This is the first time Woodside has awarded a village accommodation contract to a Traditional Owner business and is part of the significant<br>local economic benefits arising from the project.
--- ---

Hedging

Of the 30 MMboe of 2025 oil production previously hedged at an average price of approximately $78.7 per<br>barrel, approximately 25% was delivered by the end of the quarter.
Woodside also has a hedging program for Corpus Christi LNG volumes designed to protect against downside<br>pricing risk. These hedges are Henry Hub (HH) and Title Transfer Facility (TTF) commodity swaps. Approximately 95% of 2025 and 87% of 2026 volumes have been hedged.
--- ---
The realised value of all hedged positions for the quarter ended 31 March 2025 is a pre-tax profit of approximately $14 million, with a $32 million profit related to oil price hedges offset by a $23 million loss related to Corpus Christi hedges, and a $5 million profit related<br>to other hedge positions. Hedging profit will be included in “other income” in the full-year financial statements.
--- ---

Fundingand liquidity

In the quarter, Woodside:
Entered into two $1,500 million short term liquidity facilities.
--- ---
Repaid a $1,000 million bond that matured during the quarter.
--- ---
Drew $800 million from available liquidity debt facilities.
--- ---
Following the payment of the 2024 final dividend on 2 April 2025, Woodside had liquidity of<br>$7,300 million.
--- ---
8 First quarter report for period ended 31 March 2025
--- ---

Annual General Meeting

Woodside’s hybrid meeting will be held on Thursday, 8 May 2025 at 10.00am (AWST) online and at the<br>Crown Ballroom at Crown Towers, Burswood, Western Australia.

Upcoming events 2025

May 8 Annual General Meeting
July 23 Second quarter 2025 report
August 19 Half-Year 2025 report
October 22 Third quarter 2025 report
9 First quarter report for period ended 31 March 2025
--- ---

2025 full-year guidance

Prior Current
Production MMboe 186 - 196 No change
Gas hubexposure^12^ % of produced LNG 28 - 35 No change
Unitproduction cost $/boe 8.5 - 9.2 No change
Property, plant andequipment<br> <br>depreciation and amortisation $ million 4,500 - 5,000 No change
Explorationexpense $ million 200 No change
Payments forrestoration $ million 700 - 1,000 No change
Capitalexpenditure^13^ $ million 4,500 - 5,000 No change
^12^ Gas hub indices include Japan Korea Marker (JKM), TTF and National Balancing Point (NBP). It excludes HH.<br>
--- ---
^13^ Capital expenditure includes the following participating interests; Sangomar (82%); Scarborough (74.9%), Pluto<br>Train 2 (51%), Trion (60%) and working interest equity prior to the completion of the asset swap with Chevron for NWS Project, NWS Oil Project, Wheatstone, Julimar-Brunello and Angel CCS assets. It includes the remaining Beaumont New Ammonia<br>acquisition expenditure. This guidance assumes no change to these participating interests in 2025. This excludes the impact of any subsequent asset sell-downs, future acquisitions or other changes in equity. It excludes Louisiana LNG expenditure.<br>
--- ---
10 First quarter report for period ended 31 March 2025
--- ---

Production summary

Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
Gas MMscf/d 1,841 1,909 1,929 1,841 1,929
Liquids Mbbl/d 223 224 155 223 155
Total Mboe/d **** 546 **** 559 **** 494 **** 546 **** 494
Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
AUSTRALIA
LNG
North West Shelf Mboe 6,395 7,117 8,192 6,395 8,192
Pluto^14^ Mboe 10,430 11,232 11,754 10,430 11,754
Wheatstone Mboe 2,422 2,460 2,357 2,422 2,357
Total Mboe 19,247 20,809 22,303 19,247 22,303
Pipeline gas
Bass Strait Mboe 3,192 3,140 2,359 3,192 2,359
Other^15^ Mboe 3,807 4,136 3,278 3,807 3,278
Total Mboe 6,999 7,276 5,637 6,999 5,637
Crude oil and condensate
North West Shelf Mbbl 1,106 1,250 1,412 1,106 1,412
Pluto^18^ Mbbl 857 911 931 857 931
Wheatstone Mbbl 441 423 462 441 462
Bass Strait Mbbl 402 482 492 402 492
Macedon & Pyrenees Mbbl 369 617 109 369 109
Ngujima-Yin Mbbl 725 1,143 886 725 886
Okha Mbbl 312 616 466 312 466
Total Mboe 4,212 5,442 4,758 4,212 4,758
NGL
North West Shelf Mbbl 230 274 290 230 290
Pluto^18^ Mbbl 52 58 54 52 54
Bass Strait Mbbl 668 740 832 668 832
Total Mboe 950 1,072 1,176 950 1,176
Total Australia^16^ Mboe **** 31,408 **** 34,599 **** 33,874 **** 31,408 **** 33,874
Mboe/d **** 349 **** 376 **** 372 **** 349 **** 372
^14^ Q1 2025 includes 2.04 MMboe of LNG, 0.10 MMboe of condensate and 0.05 MMboe of NGL processed at the Karratha<br>Gas Plant (KGP) through the Pluto-KGP Interconnector.
--- ---
^15^ Includes the aggregate Woodside equity domestic gas production from all Western Australian projects.<br>
--- ---
^16^ Q1 2025 includes 0.29 MMboe primarily from feed gas purchased from Pluto<br>non-operating participants processed through the Pluto-KGP Interconnector.
--- ---
11 First quarter report for period ended 31 March 2025
--- ---
Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
--- --- --- --- --- --- --- --- --- --- --- ---
INTERNATIONAL
Pipeline gas
USA Mboe 378 305 360 378 360
Trinidad & Tobago Mboe 2,416 2,425 2,503 2,416 2,503
Other^17^ Mboe 23 - - 23 -
Total Mboe 2,817 2,730 2,863 2,817 2,863
Crude oil and condensate
Atlantis Mbbl 2,472 2,238 2,441 2,472 2,441
Mad Dog Mbbl 2,577 2,607 2,765 2,577 2,765
Shenzi Mbbl 2,322 1,832 2,405 2,322 2,405
Trinidad & Tobago Mbbl 99 140 126 99 126
Sangomar Mbbl 7,010 6,901 - 7,010 -
Other^21^ Mbbl - 81 81 - 81
Total Mboe 14,480 13,799 7,818 14,480 7,818
NGL
USA Mbbl 398 320 393 398 393
Other^21^ Mbbl 12 - - 12 -
Total Mboe 410 320 393 410 393
Total International Mboe **** 17,707 **** 16,849 **** 11,074 **** 17,707 **** 11,074
Mboe/d **** 197 **** 183 **** 122 **** 197 **** 122
Total Production Mboe **** 49,115 **** 51,448 **** 44,948 **** 49,115 **** 44,948
Mboe/d **** 546 **** 559 **** 494 **** 546 **** 494
^17^ Overriding royalty interests held in the USA for several producing wells.
--- ---
12 First quarter report for period ended 31 March 2025
--- ---

Product sales

Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
Gas MMscf/d 1,962 2,129 1,950 1,962 1,950
Liquids Mbbl/d 213 214 159 213 159
Total Mboe/d **** 558 **** 588 **** 501 **** 558 **** 501
Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
AUSTRALIA
LNG
North West Shelf Mboe 6,887 6,753 8,008 6,887 8,008
Pluto Mboe 9,676 10,490 10,513 9,676 10,513
Wheatstone^18^ Mboe 2,217 2,503 2,308 2,217 2,308
Total Mboe 18,780 19,746 20,829 18,780 20,829
Pipeline gas
Bass Strait Mboe 3,299 3,320 2,570 3,299 2,570
Other^19^ Mboe 3,584 4,058 2,894 3,584 2,894
Total Mboe 6,883 7,378 5,464 6,883 5,464
Crude oil and condensate
North West Shelf Mbbl 1,229 1,203 1,214 1,229 1,214
Pluto Mbbl 705 1,093 640 705 640
Wheatstone Mbbl 334 319 329 334 329
Bass Strait Mbbl 534 518 597 534 597
Ngujima-Yin Mbbl 663 1,006 999 663 999
Okha Mbbl - 653 618 - 618
Macedon & Pyrenees Mbbl 499 472 496 499 496
Total Mboe 3,964 5,264 4,893 3,964 4,893
NGL
North West Shelf Mbbl 477 252 255 477 255
Pluto Mbbl 110 53 55 110 55
Bass Strait Mbbl 226 303 785 226 785
Total Mboe 813 608 1,095 813 1,095
Total Australia Mboe **** 30,440 **** 32,996 **** 32,281 **** 30,440 **** 32,281
Mboe/d **** 338 **** 359 **** 355 **** 338 **** 355
^18^ Revenue presented in this quarterly report reconciles to operating revenue, the IFRS measure presented in<br>Woodside Financial Statements. Comparative periods have been presented on the same basis.
--- ---
^19^ Includes the aggregate Woodside equity domestic gas production from all Western Australian projects.<br>
--- ---
13 First quarter report for period ended 31 March 2025
--- ---
Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
--- --- --- --- --- --- --- --- --- --- --- ---
INTERNATIONAL
Pipeline gas
USA Mboe 294 231 286 294 286
Trinidad & Tobago Mboe 2,274 2,802 2,457 2,274 2,457
Other^20^ Mboe 4 6 6 4 6
Total Mboe 2,572 3,039 2,749 2,572 2,749
Crude oil and condensate
Atlantis Mbbl 2,494 2,108 2,426 2,494 2,426
Mad Dog Mbbl 2,620 2,629 2,626 2,620 2,626
Shenzi Mbbl 2,202 1,730 2,352 2,202 2,352
Trinidad & Tobago Mbbl 43 53 52 43 52
Sangomar Mbbl 6,521 6,793 - 6,521 -
Other^24^ Mbbl 57 42 60 57 60
Total Mboe 13,937 13,355 7,516 13,937 7,516
NGL
USA Mbbl 371 303 413 371 413
Other^24^ Mbbl 2 4 3 2 3
Total Mboe 373 307 416 373 416
Total International Mboe **** 16,882 **** 16,701 **** 10,681 **** 16,882 **** 10,681
Mboe/d **** 188 **** 182 **** 117 **** 188 **** 117
MARKETING^21^
LNG Mboe 2,750 4,196 2,086 2,750 2,086
Liquids Mboe 104 160 571 104 571
Total Mboe 2,854 4,356 2,657 2,854 2,657
Total Marketing Mboe **** 2,854 **** 4,356 **** 2,657 **** 2,854 **** 2,657
Total sales Mboe **** 50,176 **** 54,053 **** 45,619 **** 50,176 **** 45,619
Mboe/d **** 558 **** 588 **** 501 **** 558 **** 501
^20^ Overriding royalty interests held in the USA for several producing wells.
--- ---
^21^ Purchased volumes sourced from third parties.
--- ---
14 First quarter report for period ended 31 March 2025
--- ---

Revenue (US$ million)

Q1<br><br><br>2025 Q4<br><br><br>2024 Q1<br><br><br>2024 YTD<br><br><br>2025 YTD<br><br><br>2024
AUSTRALIA
North West Shelf 535 497 592 535 592
Pluto 712 853 745 712 745
Wheatstone^22^ 199 213 199 199 199
Bass Strait 228 217 223 228 223
Macedon 52 49 51 52 51
Ngujima-Yin 57 84 92 57 92
Okha - 50 50 - 50
Pyrenees 44 40 44 44 44
TotalAustralia **** 1,827 **** 2,003 **** 1,996 **** 1,827 **** 1,996
INTERNATIONAL
Atlantis 191 156 196 191 196
Mad Dog 190 183 204 190 204
Shenzi 167 124 190 167 190
Trinidad & Tobago^23^ 66 66 61 66 61
Sangomar 481 484 - 481 -
Other^24^ 3 2 5 3 5
TotalInternational **** 1,098 **** 1,015 **** 656 **** 1,098 **** 656
Marketingrevenue^25^ 312 410 227 312 227
Total salesrevenue^26^ 3,237 3,428 2,879 3,237 2,879
Processing revenue 74 53 61 74 61
Shipping and other<br>revenue 4 3 5 4 5
Totalrevenue **** 3,315 **** 3,484 **** 2,945 **** 3,315 **** 2,945
^22^ Revenue presented in this quarterly report reconciles to operating revenue, the IFRS measure presented in<br>Woodside Financial Statements. Comparative periods have been presented on the same basis.
--- ---
^23^ Includes the impact of periodic adjustments related to the production sharing contract (PSC).<br>
--- ---
^24^ Overriding royalty interests held in the USA for several producing wells.
--- ---
^25^ Values include revenue generated from purchased LNG and Liquids volumes, as well as the marketing margin on the<br>sale of Woodside’s produced LNG and Liquids portfolio. Marketing revenue excludes hedging impacts and cargo swaps where a Woodside produced cargo is sold and repurchased from the same counterparty to optimise the portfolio. The margin for these<br>cargo swaps is recognised net in other income.
--- ---
^26^ Referred to as ‘Revenue from sale of hydrocarbons’ in Woodside financial statements. Total sales<br>revenue excludes all hedging impacts.
--- ---
15 First quarter report for period ended 31 March 2025
--- ---

Realised prices

Units Q4<br><br><br>2024 Q1<br><br><br>2024 Units Q4<br><br><br>2024 Q1<br><br><br>2024
LNG produced /MMBtu 10.6 10.8 10.4 /boe 67 69 67
LNG traded^27^ /MMBtu 13.7 12.6 9.1 /boe 86 80 59
Pipeline gas /boe 36 33 34
Oil and condensate /bbl 74 71 79 /boe 74 71 79
NGL /bbl 47 45 47 /boe 47 45 47
Liquids traded^31^ /bbl 70 67 60 /boe 70 67 60
Average realised price for pipeline gas:
Western Australia A/GJ 6.9 6.6 6.4
East Coast Australia A/GJ 14.0 12.7 13.7
International /Mcf 5.0 4.2 4.6
Average realised price /boe 65 63 63
Dated Brent /bbl 76 75 83
JCC (lagged three months) /bbl 78 86 92
WTI /bbl 71 70 77
JKM /MMBtu 14.7 13.5 11.9
TTF /MMBtu 14.6 12.8 9.8

All values are in US Dollars.

Average realised price increased 3% from the prior quarter reflecting higher Dated Brent and WTI.

^27^ Excludes any additional benefit attributed to produced volumes through third-party trading activities.<br>
16 First quarter report for period ended 31 March 2025
--- ---

Exploration or appraisal wells drilled

No exploration or appraisal wells were drilled in the quarter ended 31 March 2025.

Permits and licences

Key changes to permit and licence holdings during the quarter ended 31 March 2025 are noted below.

Region Permits or licence<br><br><br>areas Change in interest (%) Current interest (%) Remarks
Australia WA-536-P (65%) —% Licence expiry^28^
Egypt Red Sea Block 1 (45%) —% Licence expiry - subsequent to<br>the period
USA GB 895, GB 852, GB<br> <br>851, GB 806, GB 805,<br><br><br>GB 762, GB 677, GB<br> <br>676, GB 630, GB 760,<br><br><br>GB 716, GB 672, GB<br> <br>721 40% 100% Assignment
^28^ National Electronic Approval Tracking System (NEATS) will be updated when expiry has been published in the<br>Australian Government Gazette.
--- ---
17 First quarter report for period ended 31 March 2025
--- ---

Production rates

Average daily production rates (100% project) for the quarter ended 31 March 2025:

Woodsideshare^29^ Production rate(100% project,Mboe/d) Remarks
Mar2025 Dec2024
AUSTRALIA
NWS Project
LNG 30.29 % 235 258 Production was lower due to weather events.
Crude oil and condensate 30.41 % 40 45
NGL 30.35 % 8 10
Pluto LNG
LNG 90.00 % 104 109 Production was lower due to unplanned outages.
Crude oil and condensate 90.00 % 9 10
Pluto-KGP Interconnector
LNG 100.00 % 23 24
Crude oil and condensate 100.00 % 1 1
NGL 100.00 % 1 1
Wheatstone^30^
LNG 12.03 % 224 220 Production was higher due to increased reliability.
Crude oil and condensate 15.85 % 31 32
Bass Strait
Pipeline gas 46.62 % 76 85 Production was lower due to planned maintenance.
Crude oil and condensate 44.91 % 10 12
NGL 46.21 % 16 18
Australia Oil
Ngujima-Yin 60.00 % 13 21 Production was lower due to weather events.
Okha 50.00 % 7 13
Pyrenees 64.85 % 6 10
Other
Pipeline gas^31^ 42 45
^29^ Woodside share reflects the net realised interest for the period.
--- ---
^30^ The Wheatstone asset processes gas from several offshore gas fields, including the Julimar and Brunello fields,<br>for which Woodside has 65% participating interest and is the operator.
--- ---
^31^ Includes the aggregate Woodside equity domestic gas production from all Western Australian projects.<br>
--- ---
18 First quarter report for period ended 31 March 2025
--- ---
Woodsideshare^32^ Production rate(100% project,Mboe/d) Remarks
--- --- --- --- --- --- --- --- ---
Mar<br><br><br>2025 Dec<br><br><br>2024
INTERNATIONAL
Atlantis
Crude oil and condensate 38.50 % 71 63 Production was higher due to increased reliability and a successful intervention campaign.
NGL 38.50 % 4 4
Pipeline gas 38.50 % 8 5
Mad Dog
Crude oil and condensate 20.86 % 137 136
NGL 20.86 % 6 4
Pipeline gas 20.86 % 3 3
Shenzi
Crude oil and condensate 64.69 % 40 31 Production was higher due to increased reliability.
NGL 64.79 % 2 2
Pipeline gas 64.66 % 1 1
Trinidad &Tobago
Crude oil and condensate 79.13 %^33^ 1 3 Production was lower due to reservoir decline.
Pipeline gas 50.35 %^42^ 53 57
Sangomar
Crude oil 78.45 %^42^ 99 95 Production was higher due to increased reliability.

Notes to petroleum reserves and resources

1. The petroleum resource estimates are quoted as at the effective date of 31 March 2025, net Woodside share.<br>For details of Woodside’s year end 2024 reserves position, see the Reserves Statement included in Woodside’s Annual Report on Form 20-F for the year ended 31 December 2024.<br>
2. All numbers are internal estimates produced by Woodside. Estimates of reserves should be regarded only as<br>estimates that may change over time as additional information becomes available.
--- ---
3. The reference point is defined as the outlet of the floating production storage and offloading facility (FPSO).<br>
--- ---
4. ‘Reserves’ are estimated quantities of petroleum that have been demonstrated to be producible from<br>known accumulations in which the company has a material interest from a given date forward, at commercial rates, under presently anticipated production methods, operating conditions, prices, and costs. Woodside reports reserves inclusive of all fuel<br>consumed in operations. Woodside estimates and reports its proved reserves in accordance with SEC regulations which are also compliant with the 2018 Society of Petroleum Engineers (SPE)/World Petroleum Council (WPC)/American Association of Petroleum<br>Geologists (AAPG)/Society of Petroleum Evaluation Engineers (SPEE) Petroleum Resources Management System (PRMS) (SPE-PRMS) guidelines. Assessment of the economic value in support of an SPE-PRMS (2018) reserves and resources classification, uses Woodside Portfolio Economic Assumptions (Woodside PEAs). The Woodside PEAs are reviewed on an annual basis, or more often if required. The review is<br>based on historical data and forecast estimates for economic variables such as product prices and exchange rates. The Woodside PEAs are approved by the Woodside Board. Specific contractual arrangements for individual projects are also taken into<br>account.
--- ---
^32^ Woodside share reflects the net realised interest for the period.
--- ---
^33^ Operations governed by production sharing contracts.
--- ---
19 First quarter report for period ended 31 March 2025
--- ---
5. Woodside uses both deterministic and probabilistic methods for the estimation of reserves at the field and<br>project levels. All proved reserves estimates have been estimated using deterministic methods and reported on a net interest basis in accordance with the SEC regulations and have been determined in accordance with SEC Rule 4-10(a) of Regulation S-X.
--- ---
6. ‘MMboe’ means millions (10^6^) of barrels of<br>oil equivalent. Natural gas volumes are converted to oil equivalent volumes via a constant conversion factor, which for Woodside is 5.7 Bcf of dry gas per 1 MMboe. All volumes are reported at standard oilfield conditions of 14.696 psi (101.325 kPa)<br>and 60 degrees Fahrenheit (15.56 degrees Celsius).
--- ---
7. ‘Proved reserves’ are those quantities of crude oil, condensate, natural gas and NGLs that, by<br>analysis of geoscience and engineering data, can be estimated with reasonable certainty to be economically producible from a given date forward from known reservoirs and under existing economic conditions, operating methods, operating contracts, and<br>government regulations. Proved reserves are estimated and reported on a net interest basis in accordance with the SEC regulations and have been determined in accordance with SEC Rule 4-10(a) of Regulation S-X.
--- ---
8. ‘Undeveloped reserves’ are those reserves for which wells and facilities have not been installed or<br>executed but are expected to be recovered through future significant investments.
--- ---
9. The estimates of petroleum reserves are based on and fairly represent information and supporting documentation<br>prepared by, or under the supervision of, Mr Benjamin Ziker, Woodside’s Vice President Reserves and Subsurface, who is a full-time employee of the company and a member of the Society of Petroleum Engineers. The reserves estimates included in<br>this report have been approved by Mr Ziker. Mr Ziker’s qualifications include a Bachelor of Science (Chemical Engineering) from Rice University (Houston, Texas, USA) and 26 years of relevant experience.
--- ---

Glossary, units of measure and conversion factors

Refer to the information set forth under the heading “Glossary, units of measure and conversion factors” in Section 6.7 on pages 254-257 of the 2024 Annual Report, which is incorporated by reference into Woodside’s Annual Report on Form 20-F for the year ended 31 December 2024.

Product Unit Conversion factor
Natural gas 5,700 scf 1 boe
Condensate 1 bbl 1 boe
Oil 1 bbl 1 boe
Natural gas liquids 1 bbl 1 boe
Facility Unit LNG Conversion factor
Karratha Gas Plant 1 tonne 8.08 boe
Pluto Gas Plant 1 tonne 8.34 boe
Wheatstone 1 tonne 8.27 boe

The LNG conversion factor from tonne to boe is specific to volumes produced at each facility and is based on gas composition which may change over time.

20 First quarter report for period ended 31 March 2025
Term Definition
--- ---
bbl barrel
bcf billion cubic feet of gas
boe barrel of oil equivalent
GJ gigajoule
Mbbl thousand barrels
Mbbl/d thousand barrels per day
Mboe thousand barrels of oil equivalent
Mboe/d thousand barrels of oil equivalent per day
Mcf thousand cubic feet of gas
MMboe million barrels of oil equivalent
MMBtu million British thermal units
MMscf/d million standard cubic feet of gas per day
PJ petajoules
scf standard cubic feet of gas
TJ terajoule
21 First quarter report for period ended 31 March 2025
--- ---