Hudbay Minerals Inc. Q1 FY2020 Earnings Call
Hudbay Minerals Inc. (HBM)
Call artefacts
No matching 8-K earnings release linked yet.
No 10-Q stored for this quarter yet.
Call audio is not captured yet.
A slide deck is not captured yet.
Transcript
Auto-generated speakersGood morning, ladies and gentlemen. Thank you for standing by. Welcome to the Hudbay Minerals, Inc. First Quarter 2020 Results Conference Call. At this time, all participants are in listen-only mode. Following the presentation, we will conduct a question-and-answer session. I would like to remind everyone, that this conference call is being recorded today, May 15, 2020, at 8:00 AM Eastern Time. I will now turn the conference over to Candace Brûlé, Director of Investor Relations. Please go ahead.
Thank you, Operator. Good morning and welcome to Hudbay's 2020 first quarter results conference call. Hudbay's financial results were issued yesterday and are available on our website at www.hudbay.com. A corresponding PowerPoint Presentation is available, and we encourage you to refer to it during this call. Our presenter today is Peter Kukielski, Hudbay's President and Chief Executive Officer. Accompanying Peter for the Q&A portion of the call will be Cashel Meagher, our Senior Vice President and Chief Operating Officer; and Eugene Lei, our Senior Vice President, Corporate Development and Strategy, and Interim Chief Financial Officer. Please note that comments made on today's call may contain forward-looking information, and this information by its nature is subject to risks and uncertainties, and as such, actual results may differ materially from the views expressed today. For further information on these risks and uncertainties, please consult the company's relevant filings on SEDAR and EDGAR. These documents are also available on our website. As a reminder, all amounts discussed on today's call are in U.S. dollars, unless otherwise noted. And now, I'll pass the call over to Peter Kukielski, Peter?
Thank you, Candace. Good morning everyone, and thanks for joining us. I'd like to start out by saying that I hope everyone has been able to stay safe and healthy during this truly unprecedented time. We've been closely monitoring the rapidly-evolving environment and taking steps to protect our people, their families, and the communities in and around which we operate, while we implement measures to minimize the overall impact of this pandemic on our operations. I'll go into more detail about our specific actions, including all the work we've done to improve our financial strength after briefly touching on our first quarter financial and operating results. Following that, I'd like to take you through highlights of our Snow Lake gold strategy. Hudbay's first quarter results benefited from a solid operating quarter in Manitoba. Lalor achieved record mine production, with an 8% increase over the fourth quarter, averaging 4,632 tons per day in the first quarter, and exceeding targeted levels. Similarly, the Stall mill achieved superb results this quarter with a 19% increase from last quarter, averaging over 4,000 tons per day, which is yet another record quarter for Stall. Manitoba combined mill mine and G&A unit operating costs continued to decline quarter-over-quarter, and are currently tracking below the annual guidance range as a result of the company's focus on operating efficiencies and costs normalizing after the successful production ramp up to 4,500 tons per day at Lalor in 2019. I am very pleased to see the continued strong operating performance, production, and cost control in an environment of increased constraints from COVID-19-related protocols. I'd like to publicly thank the Manitoba team for their strong efforts in achieving these outstanding milestones while adapting to this challenging external environment and changing the way they work to keep themselves and those around them safe and healthy. In Peru, we temporarily suspended mining and processing activities at Constancia after the Peruvian government declared a state of emergency on March 15. The Peru team did a tremendous job in ramping down the operations in a safe and orderly fashion; they actively managed the situation during the shutdown to perform care and maintenance activities, optimized our critical supplies inventory levels, and successfully managed the safe movement of people. The team has also implemented various preparedness planning activities in order to facilitate a quick and efficient ramp-up. Prior to the mine suspension, Constancia was achieving targeted mill throughput and unit operating cost performance during the quarter. In addition, the mine continued to ship concentrate up until the day the shutdown commenced. On May 14, we received recognition and approval from the Peru Ministry of Energy and Mines for restart protocols, which I will touch on shortly. As a result of the lower copper production and sales volumes, coupled with the lower copper and zinc prices caused by the COVID-19 pandemic, operating cash flow and earnings in the first quarter were lower than the previous period. Our financials were also impacted by several one-time items, such as a write-down of inventory stockpiles in Peru resulting from current low copper prices, as well as some fixed overhead production costs that were expensed during the quarter rather than capitalized due to Constancia's temporary shutdown. We expect there will be a similar charge for fixed overhead costs during the mine suspension period in the second quarter. Despite these extraordinary impacts, the business had strong cost performance with cash costs and sustaining cash costs improving over the fourth quarter of 2019. We exited the quarter with $306 million in cash and cash equivalents in addition to $446 million available and undrawn under our revolving credit facilities. We continue to take prudent steps to manage our balance sheet and maintain a strong liquidity position. In February, and prior to the pandemic, we proactively renegotiated the covenants of our revolving credit facilities that included replacing total debt to EBITDA with net debt to EBITDA to allow us greater flexibility to allocate capital to our low risk high return investments in our business this year. This resulted in an increase of $443 million in liquidity available as of March 31. Subsequent to the quarter, we announced a gold prepay transaction that generated $115 million in cash proceeds to further improve our liquidity position and pre-fund the growth expenditures in Manitoba, which I'll describe in more detail shortly. The team has done a tremendous job managing our balance sheet, and we believe we are well positioned to meet our liquidity needs for 2020 and prudently grow our business. I'd now like to spend a few minutes talking about our business response efforts in the light of COVID-19. Following the onset of the pandemic, we began monitoring the situation very closely, and we kicked off our business response planning in January. As the virus outbreak worsened globally, our company-wide crisis response plans were activated in early March as part of our crisis management protocols. The plans were established based on two tiers of crisis response. The first tier is the corporate level with a focus on ensuring overall business stability, continuity, and coordination. This includes planning for the possible need to reduce or suspend operations and for the restart of suspended operations, as well as appropriately managing the company's liquidity. The second tier is at the business unit level where the response plans are developed based on the dynamics and context of the local situation. Our business units engaged with local communities, health authorities, government, and other stakeholders in each of our regions. Each of the business units has worked to develop site-specific measures to limit and identify COVID-19 exposure and transmission and maintain a safe environment for its workers and its communities. Site-specific measures include, but are not limited to, prescreening protocols, quarantine periods for incoming workers, workplace physical distancing protocols, adjustment of work rotation schedules, deferral of certain project activity, and working from home for office staff. These measures will continue to evolve as the status of the state of emergency changes in each of our operating regions, and we adapt our measures to the latest regional health authorities' restrictions and guidelines, including reopening protocols. While we recognize the situation is dynamic, we are extremely pleased with the extensive efforts our sites have taken to mitigate the risks of COVID-19. In Peru, as I mentioned earlier, the government declared a state of emergency on March 15, which remains in place but issued a decree on May 3 indicating the mining sector would reopen in May. While Hudbay operations remained suspended until May 14, we were able to take several additional measures to ensure an efficient restart. These include mine plan optimization activities, continuous supply chain management to ensure sufficient levels of critical supplies, and logistics and workforce planning initiatives, including successfully completing workforce shift changes during the suspension. We are happy to report that yesterday Constancia received approval for its restart protocols, and mine restart activities are underway due to proactive ramp-up planning. The mill is expected to reach normal levels over the next week, and we expect to provide an update to Peru's guidance with our second quarter results. In Manitoba, we continue to operate and ship concentrate and zinc metal despite the pandemic. The leadership team is actively engaging with employees, contractors, local communities, and public health authorities to manage the evolving situation and continuously adapt and implement its business response plan. We have also been working closely with various groups within our communities to identify where we can help those in need, and I'll touch more on these initiatives later in the presentation. Given the strong first quarter operating results despite the challenging environment, we are affirming our 2020 Manitoba production, operating cost, and capital expenditure guidance. Our Manitoba 2020 precious metals production is expected to benefit from the planned mining of approximately 90,000 tons from the gold zones as part of stope sequencing in preparation for the restart of the New Britannia gold mill, which will match well with the strong gold price environment. In Peru, due to the temporary suspension of operations at Constancia and the ongoing uncertainty around COVID-19, we have suspended our previously issued 2020 guidance. It is important to note that Peru sustaining capital expenditures are expected to be approximately $25 million lower than previously anticipated due to the temporary mine suspension and re-sequencing of capital activities such as tailings and capitalized stripping. Growth capital expenditures in Peru related to the Pampacancha community surface rights payment and project development capital have been impacted by the state of emergency. The majority of the Pampacancha growth expenditures will be spent once the negotiations with the land users have been completed and the land has been vacated. Due to the state of emergency, these negotiations have been put on hold, and therefore, the payments have been delayed. And as I already mentioned, now that Constancia has received approval of its restart plan, we expect to update our Peru guidance with second quarter results. On May 7, we executed a gold forward and prepay transaction, in which we received cash proceeds of $115 million, as I noted earlier. This further improves our liquidity position and pre-funds the entire investment for the low risk high return New Britannia gold mill refurbishment at attractive terms and a low cost of capital. Under the prepay, we have agreed to deliver a total of 79,954 gold ounces in 2022 and 2023, which were valued at the gold forward curve prices averaging approximately $1682 per ounce at the time of the transaction. The transaction offered an attractive cost of capital of approximately 5.95% per annum at the average forward price or an implied cost of capital of approximately 2.7% using current consensus gold prices for 2022 and 2023. The delivery ounces only represent approximately 25% of Lalor's forecasted annual gold production in each of 2022 and 2023, and approximately 3.6% of total Snow Lake gold reserves. Under the revolving credit facility and note indenture, the gold prepay will not be considered as debt. This is meaningful since the gold prepay adds to our cash balance and will be accretive to our credit facility availability under the recently renegotiated net debt to EBITDA conveyance. We are prudently managing the business and the impact of the pandemic through approximately $150 million in incremental liquidity this year from $115 million in cash proceeds from the gold prepay transaction, a $25 million deferral in Peru's 2020 sustaining CapEx and identified company-wide discretionary and input cost reductions of approximately $10 million. In addition, our forecasted cash flows are expected to benefit from the Canadian dollar cost structure of our Manitoba operations and the anticipated increase in cash flows from Lalor due to higher precious metals production expected this year based on current commodity prices and foreign exchange rates. Last month, we executed an amendment with our streaming partner Wheaton Precious Metals that extends the target date for mining 4 million tons of ore from Pampacancha by six months to June 30, 2021. This extension is another example of action we are taking to manage our business and liquidity during this time of uncertainty. The extension delays the potential penalty payments if the minimum tons aren't mined, and we were glad to have our long-term partner agree to this extension and continue to believe in our ability to execute and deliver on the development of Pampacancha. I would like to personally thank Wheaton for this consideration along with generous donations to our communities for COVID-related relief. Now I would like to walk you through some of the highlights of our recently announced Phase 2 of our Snow Lake gold strategy. We have demonstrated significant value in our Snow Lake gold business which offers investors an attractive counter-cyclic hedge to our base metals business in these volatile markets. Turning to slide eight, one thing that can be underappreciated is the size of our precious metals business at Hudbay. The Lalor Mine and the Snow Lake operations contribute the most exposure with 170,000 ounces of precious metals expected in 2022. In Peru, our precious metals production is expected to more than double by 2022 to 218,000 ounces and 50% of the gold remains unstreamed at Constancia. Similarly, looking at our resources, we have approximately 5 million ounces of contained precious metals to our account in our portfolio; that amount is not insignificant and is comparable to some standalone gold producers. Another way to view the meaningful size of our gold business is on slide nine, which shows that by 2022 precious metals are expected to account for one-third of our overall revenues, offering investors a unique investment vehicle with significant leverage to copper and growing counter-cyclical gold exposure. Slide 10 summarizes the highlights from our announcement on March 30, in which we announced the 35% increase in Snow Lake gold reserves to 2.2 million ounces and extended the mine life to 18 years. We also released an updated mine plan for Lalor that increased life of mine gold production by 41% compared to the previous 2019 mine plan, and more than doubled the average annual gold production to more than 150,000 ounces over the first eight years after the New Britannia mill is refurbished. Lalor's gold and copper gold zones are expected to be processed at the nearby New Britannia gold mill, which capitalizes on existing infrastructure. The $115 million refurbishment cost is a short payback, high return investment opportunity. The New Britannia mill is expected to achieve gold recoveries of approximately 93% compared to current gold recoveries of approximately 53% at Stall. This significant improvement in gold recovery unlocks increased reserves and increases the potential for future conversion of resources to reserves due to the increased value per ton of ore. The path to our Snow Lake gold strategy has been well planned and executed over the past several years. The first phase of our strategy was announced in February of last year, where we saw a 65% increase in Lalor's gold reserves, which transformed Lalor into a gold mine. The recently announced second phase demonstrated significant growth in the size of the gold reserves and resources, and further increased the annual gold production as I previously mentioned. Based on the 2020 updated reserve, Lalor will remain a low-cost gold mine with cash costs and all-in sustaining cash costs net of byproduct credits of approximately $480 and $655 per ounce respectively. Over the first eight years, once New Britannia is in production, positioning Lalor in the lowest quartile on the global cost curves as seen on slide 14. The New Britannia mill refurbishment activities are underway with detailed engineering approximately 60% complete and timelines on track with the original project schedule. Orders have been placed for long lead items and early works construction has commenced, including the construction of the pipeline between the New Britannia and Stall mills. The civil contractor for the flotation building has been mobilized and construction is expected to commence next week. Construction and refurbishment activities are expected to continue until August 2021, with planned commissioning and ramp up occurring during the second half of 2021. The low-cost, high-margin nature of Snow Lake gold and the meaningful annual gold production position Snow Lake gold favorably compared to other underground gold mines, as shown on slide 15. And on slide 16, utilizing the average trading multiples for gold companies, and the projected gross margins from Snow Lake gold, you can see that there is incredible value in this gold business. There remains another phase of potential value creation at Snow Lake gold. The third Phase of our strategy will look at several areas of potential upside; we are examining the potential to expand the New Britannia mill beyond the currently planned throughput rate of 1,500 tons per day. The mill historically operated in excess of 2,000 tons per day. So there remains the opportunity to increase the production, which is compelling given there remains approximately 1.3 million ounces of gold in inferred resources in Snow Lake, and further exploration upside exists both at Lalor and in the regional gold targets. As part of Phase 3, we are also examining the potential to further optimize the gold and copper recoveries at the Stall mill through the implementation of modern metallurgical technologies. Trade-off studies are underway. The updated resource model at Lalor includes 4.4 million tons of inferred resources, which have the potential to extend the Lalor mine life. You may recall that we use a more stringent approach to resource reporting for underground deposits, and this conservative approach has resulted in a high historical resource to reserve conversion ratio of greater than 80% at Lalor. As shown on slide 17 and 18, a new copper-gold lens called Lens 17 is included in the updated inferred resource estimate for Lalor. Lens 17 and other lenses at Lalor, including the copper-gold Lens 27 remain open down-plunge and offer opportunities to further expand Lalor's resource base once suitable underground drilling platforms have been established over the next two years. Slide 20 highlights the additional gold deposits; the additional gold potential at the recently discovered 1901 deposit. The 1901 deposit is located approximately halfway between the former Chisel North mine and the Lalor mine at a depth between 500 meters to 700 meters and within 1,000 meters of the existing haulage ramp to Lalor. The 1901 deposit could provide additional feed for the processing facilities in Snow Lake. Since publishing the initial inferred resource estimate in August 2019, we have considered various options to develop the 1901 deposit and we have completed a drill program aimed at converting a significant portion of the inferred resources to an indicated category and to define an initial inferred mineral resource for the gold mineralization previously intersected between two zinc-rich lenses. We intend to provide an update on the mineral resource estimates and development options for the 1901 deposit with our annual reserve and resource update in March 2021. In 2020 and 2021, additional technical studies and exploration activities will be conducted to confirm how the Lalor in-mine exploration targets and the regional gold and base metal satellite deposits could be incorporated in the consolidated business plan of the Snow Lake operations. Having now been with Hudbay for 10 months, I've seen that this company is truly an iconic Canadian mining company. There are two key elements that make it a quality company in my view: assets and people, and here we actually have both. I thought it would be worth spending a few moments talking about the strategic advantage that Hudbay offers, which can be summarized in six elements, as shown on slide 21. First, we have long-life assets located in mining-friendly jurisdictions in the Americas. We have a proven track record of operational excellence and low-cost mines that sit favorably on the global cash cost curves. We have a strong focus on free cash flow generation and prudent capital allocation through prudent balance sheet management and disciplined near-term investments in high return, short payback opportunities within our portfolio. We have a world-class management team with proven mining industry experience. We've demonstrated strong ESG performance, which is especially important during troubling times like these, and our diversified organic growth pipeline offers investors the unique opportunity of leverage to copper with increasing gold exposure as we discussed earlier. Our near-term priorities include refurbishing the new Britannia mill to increase gold production, delivering free cash flow from Pampacancha, and drilling Lalor gold to add reserves and extend the mine life. We're a disciplined growth-focused company, and as we look to deliver the second stage of growth at Hudbay, our priorities over the medium term will be to unlock value at our Rosemont and Mason properties in the United States, test the Constancia regional exploration targets, optimize value from Snow Lake gold, and pursue accretive acquisitions and partnerships that fit our strategic criteria while never losing focus on prudently managing our balance sheet. Our strong track record in ESG is just as important as our technical track record. Slide 23 highlights a few of our achievements and important initiatives in each of the environment, social impact, health, and safety governance areas. I think it is important that during these times we remember to recognize the struggles going on all around us, whether at site, the communities around our operations, or the cities we live in; everyone is facing unique challenges right now. We are working closely with the stakeholders within our communities to identify where we can help close immediate gaps and needs. In Manitoba, the company and our partners have donated to the local food bank, the Salvation Army, the Family Resource Center, and the Women's Safe Haven Resource Services, all of whom are providing various and much-needed forms of support to families who are struggling during this time. In Peru, we have donated biomedical equipment and supplies to regional hospitals, including electric clinical beds with mattresses, metal baskets for hospital bedding, masks, and surgical aprons. We have also donated more than 20 tons of basic needs, including rice, sugar, and noodles to seven rural communities in Chumbivilcas, which will support hundreds of families. In Toronto, we support multiple charities and have implemented additional matching incentives. I am also pleased to have our valued partners join us in coordinated relief efforts, including with generous donations from Wheaton Precious Metals to various community initiatives in Peru and Manitoba, and from RTS Minerals to a community service provider in Flin Flon, Manitoba. In closing, these recent times have no doubt been challenging for all of us, and the way we operate has changed, and will continue to change, but the strength of our business model and the continued prudent management of our balance sheet has demonstrated we have the ability to adapt and overcome these challenges. We believe we are well positioned, with a quality pipeline of assets at several different stages within our portfolio, and this unique pipeline provides significant growth potential. I know you've heard me say this before, but it's more true today than ever: we have the right team and core competencies to execute on our leading growth pipeline, deliver on our strategic priorities, and create real value for all of our stakeholders. So please be vigilant, take care of yourselves and others, and stay safe and healthy. And with that, I'd like to open up the lines for questioning.
Thank you. Ladies and gentlemen, we will now begin the question-and-answer session. Our first question comes from Fahad Tariq of Credit Suisse. Please go ahead.
Hi, good morning. Thanks for taking my questions. First on Pampacancha, can you talk about the timeline now to get to the high grade? I know previously it was the end of 2020, and I see the extension with Wheaton. Can you just talk about what that means for accessing the high-grade ore and the timing of it?
Sure, Fahad. Look, obviously there's a delay that's been associated with the suspension of activities at Constancia due to the state of emergency in Peru. So, with the two-month suspension of activities, clearly there has been no activity related to either the Consulta Previa process undertaken by the government of Peru, or by our negotiations with the users of the land belonging to the community of Chilloroya. Once the state of emergency is lifted, we anticipate it will still take some time for the government to remobilize the folks involved in negotiations; remember that this interaction is of an intensely personal nature requiring human contact. So, until social distancing protocols are relaxed, it will take some time to complete the Consulta Previa process. At the same time, we will continue with our negotiations with the possessors or users of the land, and we will continue with that in parallel with the Consulta Previa process. So, I think it's fair to say that we will not be producing or mining Pampacancha until the beginning of next year.
That's helpful. Thank you. And just switching gears to gold, so it's clear that gold is becoming a larger part of the strategy and composition of revenues, particularly given commodity prices right now. Can you talk about beyond this year and next year, what's the longer-term strategy with the gold exposure? Would you be open to streaming opportunities, or royalty opportunities, or doing more prepays? Any color on how gold fits in over the medium term? That would be helpful. Thanks.
Sure, that's a great question, and it's one that we are more frequently asked than ever before since we announced our updated resources and reserves in March. Look, we like our increasing exposure to gold; it offers a countercyclical hedge to the volatility of the base metals environment. We believe that there remains enormous value to be unlocked at Snow Lake gold, and the way that you unlock that value is you deliver the refurbishment of New Britannia and the completion of the related infrastructure between New Brit and the Stall mill. And only when you have done that, and you can demonstrate that you're actually producing at the level that we say we're going to do, and you have all of these reserves, which will likely be much more than we have today ahead of you, then you really unlock value and you have the optionality of what you do available to you now. Now, I believe we have lots of alternatives available to us with respect to creating and optimizing value at our gold business. We actually don't need to make a decision with respect to that right now, because we're focused razor-sharp on delivering New Brit refurbishment, and during the period between now and then, we will take a really close look at what it means to us and how it implies our business might look going forward after the completion of refurbishment.
Our next question comes from Orest Wowkodaw of Scotiabank. Please go ahead.
Hi, good morning. A couple of questions for me. First of all, with Constancia, so it's great that you got the permission to restart there. Can you give us an idea, are there any constraints that you see in terms of receiving required consumables from, I guess, various distributors and manufacturers within Peru? Like, are you ready to basically restart from day one?
Good morning, Orest, and that's a really good question. So, you may remember right at the point the state of emergency was announced in Peru, we made the decision to suspend operations for one primary reason, and that was in order to preserve our ability to ramp up quickly once the state of emergency was lifted. And a key component of that was to preserve the inventory of supplies that we had on hand, and during the period, the intervening period of our suspension, we have in fact undertaken a lot of activity in order to ensure that we have more than adequate supplies to allow us to operate for at least a month, during which time, we will be able to make sure that we work on strengthening the supply chain, making sure that we have access to everything that we need. So, in a nutshell, we have everything that we need in terms of supplies to be able to operate for over a month at Constancia.
Okay, that's great. Thank you. And in terms of the balance sheet, I recognize you renegotiated your debt covenants earlier this year, but at current copper pricing, on my estimates, you would still probably have a net debt-to-EBITDA that's above the current thresholds. I guess my question was, can you give us an idea of what definition of EBITDA is being used for the covenant? Is it the adjusted EBITDA, or is it just the gross EBITDA? I was just wondering, how to think about that?
Hi, Orest. Good morning, it's Eugene here. With respect to the availability under the revolver, we have proactively renegotiated those covenants in Q1, as you'll remember, that was a different copper price environment, and $2.75 going to $3 rather than $2.75 going towards $2. Since then, we've bolstered our liquidity by doing the prepay, and that gives us additional access to that revolver. In terms of the EBITDA calculation, it is an adjusted EBITDA calculation, and we can take that offline. We do believe that we have more than ample liquidity and the cash balance to sustain our business even into a sub-$2 environment. So, we feel confident with the prepay announcement, and the resulting effect on the revolver that we can actually operate down to a $1.90 environment without additional liquidity measures.
Okay. So, Eugene, I guess the right way to think about it is that you might go through a short period of time where the revolver is not available, but you don't actually think it matters because you have enough cash on hand?
You could interpret it that way, and we haven't drawn on the revolver in over four years. It's undrawn and unavailable; I think our idea is not to add more debt to the balance sheet here in this time, and so, it's a nice Rainy Day Fund that we can draw upon and we expect to have availability, but the goal here is not to add debt to the balance sheet at this time, and that's why we did the proactively renegotiated those covenants that allowed us to do that prepay.
Okay. And then, just finally, I was anticipating that your environmental provision liability would have decreased this quarter because of the significant mine life extension that you put on Manitoba. Can you give us a sense of why it didn't? Why that liability didn't go down; is that a timing issue or in terms of when that's reevaluated, or am I missing something there?
Actually, the liability, there are two adjustments to that DRO liability; the first one was actually because of lower discount rates, it actually increased liability by $40 million because of the lower discount rates used in that calculation, and that was offset partially by the stronger Canadian dollar, which netted that impact by about half of that. So, the increase was net 20, but there are two factors to that, and one was discount rate, and the other one, the moderating factor was the Canadian dollar.
Okay, but what about the idea that adding eight years to the mine life at Lalor would extend the closure costs and environmental liability? Is that not the case?
It's a complicated calculation, and again, we can take that offline. The eight years of mine life does extend the closure liabilities overall for Manitoba, but given the lower interest rate environment, there's a lower discount rate that's calculated, and that kind of overwhelmed that for this quarter; obviously, as interest rates change over the course of the year, that can be reversed.
Okay, thank you.
Our next question comes from Greg Barnes of TD Securities. Please go ahead.
Yes. Thank you, Eugene. A question for you as well, following up on what Orest's question about the credit facility. So I have similar numbers to Orest later this year in terms of the covenants, but does that mean the availability on the line shrinks, or does the availability disappear completely on the line if you go to the covenants?
It will decrease; as you know, we set the second quarter here with Constancia shut down for at least half of the quarter, will have the significant impact on our EBITDA, but the way that the covenant calculation is done is that there's a multiplier effect on the EBITDA that's actually greater than the speed that I can add cash to the balance sheet. So, I can add cash four-and-a-half times that rate. So, it will decrease, but we expect that given our success at negotiating the covenant package earlier this year in a different environment that we'll create some availability, but it will likely decrease, but we don't expect to have to draw upon it until we get into an average copper environment kind of in the $1.90 range. So, I think we've suspended this to the point where we don't need it, but certainly we expect we will get increased access with some renegotiation if we need it beyond that $1.90 level.
Okay, fair enough. And just again following up on Tariq's question earlier on about the gold business; in my experience anyway, gold production within a base metals company just simply doesn't get a gold multiple leaving a fraction of it. So, as you grow the gold business, you're not going to get full value in the market for it, in my views, which would imply that probably has to be divested, it will spun off somehow. Is that along the lines that you were thinking as well?
I think, as I said to Tariq, our focus is not so much on delivering future optimization of the asset, it's on actually delivering the value, and in the meanwhile evaluating or taking a look at what opportunities they offer us; there are a multitude of alternatives available to us, and some of them are what you mentioned, and of course, there are others, but I think in order to reach that target, we really have to deliver on this project, and delivery on this project involves not only construction and the commissioning activities, but it's dependent on everything that we do on the mine and in our business, and how we structure things. I just think that worrying too much now about how we maximize value post-completion of the New Brit refurbishment is a distraction, so we're just going to continue relentlessly to pursue execution of that strategy, and of course, there will come a point at which we have to decide how best to optimize or maximize value, but we don't have to do that right now.
Our next question comes from Jackie Przybylowski of BMO Capital Markets. Please go ahead.
Thanks very much. I just wanted to follow up on a comment, Peter, that you made in your prepared remarks at the beginning about expanding New Brit; I recognize what you just said to Greg about not wanting to be too distracted, but how large could New Brit be in a multiple phase, subsequent phase expansion? You mentioned 2,000 tons per day is where the plant ran in the past? Is that sort of a cap on where you think that plant could run in the future? And can you give us a little bit of a sense on what the timing would be for the way you're thinking about a subsequent phase in New Brit? Thanks.
Jackie, I'm going to let Cashel talk to that because he'll be more intelligent than I am, but basically, New Brit in the past used to run at over 2,000 tons per day, but Cashel is more familiar with it.
Yes, the install grinding capabilities between 2,200 tons a day. We have an engineering study commissioned to be able to evaluate that. Our focus though is on the delivery and execution of the current project, which we have labeled this 1,500 tons a day. I would say, though, that it's an integrated production area, the whole Snow Lake Camp, and we have an internal evaluation underway. They're sort of at a pre-feasibility level right now and we look forward to being able to give more detail on it in the future, but the optimization at the Stall Mill will add considerable number of ounces also. So between the two, we see the opportunity to increase recovered ounces out of these Snow Lake reserves in the future. So, one criteria we sort of looked at to evaluate whether or not Stall would be a good opportunity is simply the difference between the recovery we get in Flin Flon for gold in our copper concentrate versus what we get in Stall. Stall historically has been in and around 55% gold recovery and Flin Flon is in and around 65% recovery. So, we know that there's an opportunity to increase gold recovery there. So I think between those two engineering projects that are being managed by Peter Amelunxen, Vice President of Technical Services, those two projects will yield higher opportunity for gold recovery in the future, the throughput at Stall and New Brit and the increased gold recoveries at Stall. And I would mention obviously, we're really encouraged by Stall's performance in this last quarter with its increased throughput that it demonstrated over the quarter.
It sounds like it could be a couple of years before we see sort of the full potential of the whole camp; is that fair, like at least a couple of years?
No, I think the engineering studies would dictate that we would get forecasts and foresight into it probably within the next year, but maybe the execution of it would be phased in with Stall improvements over probably 2021, and then yes, whatever increases that happen to New Britannia would be implemented and the capital would be allocated after the commissioning of New Britannia.
That's great. Thanks. That's really helpful. And just another question, I know you mentioned earlier in the call that Constancia is planning to ramp up fairly soon and it sounds like you can ramp up fairly quickly. Can you maybe give us a little bit of insight or color into your thought process for why that guidance hasn't been updated yet? You said you'll do it with Q2 earnings, which is still I guess a quarter away now. What else do you need to see before you're comfortable reissuing that guidance?
Yes, it's a good question, Jackie. Look, I mean, there is quite a bit of uncertainty in Peru, and that uncertainty really relates to how the pandemic is going to play out and how the government reacts to that. So, I mentioned a little bit earlier what you've done with respect to sort of firming up availability of suppliers through ourselves for the next month or so, but we really do have to make sure that the supply chain doesn't become a bottleneck. It has the potential to do that, because the complexity of what the government has to do ahead of it and the coordination amongst the various levels of government is pretty intense, and that leads to some uncertainty. So, it's very, very difficult for us to be able to predict what uncertainty or uncertainties will face in the month ahead of us, but as we progress through the remainder of this pandemic in the second quarter, we'll get a much better idea of exactly what it's going to take. I believe that we have the most resourceful mining team in the business over there. They have been incredibly skillful at making sure that we maintain relationships with all of the communities down the supply chain so that we do have access, but I believe that they are going to be tested in the months ahead. And while they're being tested, I think it's premature to be able to offer guidance.
That's fair. Okay. Thanks very much, Peter and Cashel and the team. Those are all my questions. Thanks.
Our next question comes from Oscar Cabrera of CIBC. Please go ahead.
Thank you, Operator, and good morning everyone. I hope you and your families are staying safe during these unprecedented times. Peter, as you mentioned in an earlier question, you expect mining in Pampacancha to start in early next year. Could you remind me about the $70 million allocated for growth CapEx before COVID-19? Is that all for Pampacancha, or can you clarify the different components of that $70 million?
Yes, Oscar, thank you for your comments. The $70 million in capital expenditures is primarily linked to Pampacancha, which consists of two parts: payments to the community for land access and the actual development costs. We do expect to allocate that capital this year. However, we do not foresee utilizing all of the sustaining capital expenditures this year, as most of it pertains to capitalized stripping. Given that we have had a two-month pause in mining activities, we will initially be processing stockpile material, which will likely reduce the sustaining capital expenditures by about three months.
Thank you. Regarding the $25 million that you're deferring as mentioned in your press release, should we consider that to be allocated for the start of next year, assuming mining continues there?
Yes, that's correct.
That's correct. Okay. And then, in terms of availability on the revolving credit facility, if we enter the scenario that Eugene mentioned regarding the $1.90, how much of the credit facility would you have available?
Hi, Oscar. The credit availability, the revolver availability is a function of two things: both our current debt balance and also EBITDA, and EBITDA is really what you are predicting for the copper price and how much are we going to produce. If we were going to run out this year, and Constancia was going to continue to produce, it would obviously at these prices would reduce that availability. But again, as we've shown earlier this year, we believe we can get access to some of it by renegotiation with the banks and feel confident that we can do so, but I think I would go back to my earlier comments about proactively adding to the balance sheet. The best availability is actually cash on your balance sheet, and we have added without adding debt. So, I think we can attack it that way meanwhile having the revolver availability as a backup if necessary.
Right. Okay, thanks very much.
Our next question comes from Stefan Ioannou of Cormark Securities. Please go ahead.
Okay, thanks very much, and great to see the gold strategy unfolding with the prepay and stuff. Just maybe more of a housekeeping question, just you mentioned as of basically today the balance sheet has about $370 million cash on it. Just wondering presuming that includes the $115 million prepay, have you actually had a chance to sort of do any deep spending on the New Britannia mill yet, or is that sort I mean we are only sort of about a weekend since that announcement, or is that still to come?
Yes, so your presumption is correct, and I will just make sure that Eugene can confirm that, but we have not done any deep spending on New Brit yet because a lot of work has been associated with the engineering and procurement phase, but the spending is about to start.
The spending this year for New Britannia is $80 million, and approximately $10 million of that has been spent to date, leaving a balance of $70 million from a modeling perspective. Additionally, the approximately $170 million balance includes the proceeds from a prepay received last Monday.
Okay, great. Thanks so much, guys.
You are welcome.
Our next question comes from George Topping of Industrial Alliance. Please go ahead.
Okay. Thank you, Operator. Hello everyone. I am just wondering with the sudden drop in base metal prices, if you have any flexibility at all either operation to increase the mine grade through the year?
Good morning, George. We are definitely facing some constraints, but the guidance for the mine is quite innovative. The possibility of increasing the grade seems limited. We can't make any guarantees about our capacity to achieve that, but our team is resourceful and usually aims to optimize. We'll do our best, but predicting improved grades is not very feasible at this moment.
George, I would add that in our mine plan this year, we are mining 90,000 tons of gold, and that's backend weighted. So given the prevailing gold prices, we will see some nice tailwind from that as we as the current Canadian-U.S. exchange. So there are things inherent in our mine plan that will be beneficial given the current environment which combined with lower base metal prices, there are other counter effects like the higher gold price and lower Canadian dollar that are offsetting to that environment.
Yes, understood. Just, and then secondly, the worker response to the call back to operations, how is that going? I know it's only a day in, but everybody come back, no problems? No problems? Nobody asking for danger pay, etc.?
We planned for this well in advance and have extremely detailed protocols to manage exposure to the virus. Constancia's camp is likely one of the safest places in Peru with proper accommodations. There is adequate social distancing, limited population density, and we take significant precautions with hygiene. Individuals arriving at the site are quarantined for seven days before starting work and are tested for COVID-19, ensuring that only COVID-free personnel are brought on site. They also follow isolation protocols once there. Everyone is eager to return, but availability of personnel will be a challenge since everyone is competing for workers. It's not just about the willingness of personnel to work, but also the risk of them getting infected as they rotate through cities. While these risks exist, we currently have all the personnel we need on site, as we mobilized them before receiving permission to resume production. We're in good shape right now.
Yes, until they all come, no additional demands.
No.
Good, good to know. Thank you.
Our next question comes from Brian Lalli of Barclays. Please go ahead.
Hey, good morning everyone. I appreciate you fitting me in here. Maybe a couple of follow-ups for Eugene. Again, I apologize, a bit of beating a dead horse, but I think part of the issue is obviously you guys don't report specifically either. I appreciate that, that definition; it sounds like some change from total than that. And we can sort of run the numbers, but is there something around how EBITDA is defined as you think about compliance from that perspective? Obviously, you've gotten a few questions on this, I'd love to expand on and if that's fair, just in terms of understanding how that availability stays even in more dire scenarios. And then I have one follow-up. Thanks.
The definition of EBITDA remains the same as when we reported it during the high yield offering in 2016. I want to clarify that there has been no change in that definition; however, the definition of the revolver covenant has changed to a net debt-to-EBITDA ratio instead of a total debt-to-EBITDA ratio.
Got it. I guess just quickly on that, I mean typically with these covenants, it's something where is it based on availability? Is it only if you have drawn a certain amount? I guess that's again, part of that. The question I think people have though is if you're above that covenant for some period of time when you have to measure against, does the entire revolver availability go away? Again, we've seen it defined a bunch of different ways in different credit agreements. I think that would be helpful for the group if there's talk about that?
Sure. It's measured on a quarterly basis. So the numbers that we stated in this quarterly release at the $446 million available, so you'll know that the revolver has $550 million in total, and we have $446 million available based on the current calculation, and that will persist till we report next quarter.
Got it, but it is something where if you're above it, it does have an issue in terms of the entire availability, if you were to be above the covenant. Is that actually correct?
The covenant limits calculates what's available. So depending on where your EBITDA goes, and I can't predict where our EBITDA will be into Q2 at the moment. Yes, it's low. It's not like you have all availability or no availability; it floats the numbers, it's a calculated number.
Understand, okay. And then I guess my second follow-up, if I may, is just understanding to your point again, appreciate the answer on the New Brit CapEx is what the $70 million did you mind working or walking through, excuse me, some of the other kind of key cash flow items that you'd want to make sure we're modeling correctly? Obviously, the Peru CapEx has been suspended, but I think as people are working through their numbers, we can all figure out our own copper prices and EBITDA, but just making sure we have the right cash outflows as we think through your liquidity if there's a way to do that at a high level? That's all for me. Thanks so much.
We are pleased to reaffirm our guidance for Manitoba regarding production, operating costs, and capital for both sustaining and growth, which we shared two months ago. We are on track with all these metrics as discussed by Peter and Cashel. However, the guidance for Peru is temporarily suspended. We anticipate reinstating it by the end of the quarter but want to be responsible and assist the analyst community with capital expectations. It is important to note that we expect a $25 million reduction in success for Peru in addition to the suspension. Thus, at this time, we can only confirm that guidance for Peru will be at least $25 million lower. The remaining expenditures, as Peter mentioned, will depend on negotiations and the ramp-up of activities necessary to incorporate Pampacancha into the mine plan.
Got it. Thanks, Eugene.
Happy to discuss any other numbers offline, if there's some modeling numbers that you're missing.
Sure, that might be great. Thanks, Eugene. I appreciate it. Have a great day.
This concludes the question-and-answer session. I would like to turn the conference back over to Candace Brûlé for any closing remarks.
Thank you, operator, and thank you everyone for participating today. Please feel free to reach out to our Investor Relations team if you have any further questions. This concludes our call. You can now disconnect your lines.