Skip to main content

Golar Lng Ltd 6-K, filed Mar 17, 2020

Golar Lng Ltd (GLNG)

6-K 2020-03-17 For: 2020-03-17
View Original
Added on April 11, 2026

About this 6-K

Golar Lng Ltd filed this 6-K on March 17, 2020.

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549

Form 6-K

REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934

For the month of March 2020

Commission File Number: 000-50113

Golar LNG Limited (Translation of registrant's name into English)

2nd Floor S.E. Pearman Building 9 Par-la-Ville Road Hamilton HM 11 Bermuda (Address of principal executive office)

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F. Form 20-F [ X ]      Form 40-F [   ]

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1):

**Note:**Regulation S-T Rule 101(b)(1) only permits the submission in paper of a Form 6-K if submitted solely to provide an attached annual report to security holders.

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7):

**Note:**Regulation S-T Rule 101(b)(7) only permits the submission in paper of a Form 6-K if submitted to furnish a report or other document that the registrant foreign private issuer must furnish and make public under the laws of the jurisdiction in which the registrant is incorporated, domiciled or legally organized (the registrant's "home country"), or under the rules of the home country exchange on which the registrant's securities are traded, as long as the report or other document is not a press release, is not required to be and has not been distributed to the registrant's security holders, and, if discussing a material event, has already been the subject of a Form 6-K submission or other Commission filing on EDGAR.

On March 17, 2020, the Registrant issued a press release, a copy of which is attached hereto as Exhibit 99.1 and is incorporated herein by reference.

(c) Exhibit 99.1. Press release dated March 17, 2020

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

Golar LNG Limited
(Registrant)
Date: March 17, 2020 /s/ Graham Robjohns
Graham Robjohns
Chief Financial Officer and Deputy Chief Executive Officer

EdgarFiling

EXHIBIT 99.1

Golar Power completes 96 hour reliability test at 1.5GW Sergipe Power Plant

Golar Power Limited (“Golar Power”) has successfully completed today the final operational test at the 1.5GW Sergipe Power Plant.

The test involves supplying the maximum load of the plant (1.5 GW) to the National Interconnected System (SIN) for a period of 96 continuous hours. The test is the final requirement of the National System Operator (ONS) in order to start commercial operations under the 25-year power purchase agreements.

For the test, the three gas turbines, the steam turbine and three heat recovery boilers operated in a combined cycle and delivered a volume in excess of 1.5GW, for 96 continuous hours. The test was successfully completed this morning at 03:00am (GMT).

Hamilton, Bermuda

March 17, 2020