6-K
Highlander Silver Corp. (HSLV)
UNITED STATESSECURITIES AND EXCHANGE COMMISSIONWashington, D.C. 20549
FORM 6-K
Report of Foreign Private Issuer
Pursuant to Rule 13a-16 or 15d-16 of
the Securities Exchange Act of 1934
For the month of April 2026
Commission File Number 001- 43170
Highlander Silver Corp.
(Translation of registrant’s name into English)
2500 – 100 King Street West
Toronto, Ontario, M5X 1A9 Canada
(Address of principal executive offices)
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40F:
Form 20-F ☐ Form 40-F ☒
The following documents are being submitted herewith:
| Exhibit | Description |
|---|---|
| 99.1 | News Release dated April 7, 2026 |
1
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
| Highlander Silver Corp. | ||
|---|---|---|
| (Registrant) | ||
| Date: April 7, 2026 | By: | /s/ Purni Parikh |
| Name: | Purni Parikh | |
| Title: | SVP Corporate Affairs and Corporate Secretary |
2
Exhibit99.1

Highlander Silver Provides Update; Drilling Commences at Corani Silver Project
Toronto,April 7, 2026 – Highlander Silver Corp. (TSX, NYSE American: HSLV) (“Highlander Silver” or the “Company”) is pleased to provide a portfolio update following the successful completion of its combination with Bear Creek Mining (see press release dated February 26, 2026).
Daniel Earle, President and CEO of Highlander Silver, commented:
“HighlanderSilver is well positioned to fast-track project advancement across its portfolio of high-quality silver assets. This includes a focuson high-impact exploration, project optimization, and site preparation for development of Corani, the largest fully permitted primarysilver project in the world, as well as permitting at San Luis, one of the highest M&I resource grade projects in both the gold andsilver sectors.
Asof March 31, the Company had an unaudited cash balance of approximately US$100 million and no debt. The Mercedes gold-silver mine alsomade a positive cash contribution in its first month of operations following restructuring under our stewardship. We provide a summaryof our baseline plans below and forecast a year-end cash balance of approximately US$60 million. This reflects a disciplined approachto spending that delivers on our core objectives while preserving flexibility to scale up our exploration programs later in the year.”
CoraniSilver Project – Puno, Peru
Personnel
| ● | Carlos<br> Ojeda appointed Vice President & General Manager — Mr. Ojeda has held increasingly<br> senior roles leading teams of up to 500 people in engineering, construction, ramp-up and<br> optimization at Anglo American’s major Quellaveco open pit mine in Peru, with prior<br> experience at other major open pit mines in the country, including Antamina, Mina Justa and<br> Constancia |
|---|
Exploration
The Company will provide a standalone exploration update later this quarter that includes early results from the exploration programs listed below:
| ● | First-ever<br> airborne magnetic survey totaling 620 line km, covering the majority of the land package<br> completed |
|---|---|
| ● | 54<br> km of planned 60 km induced polarization survey completed, with program expanded to 96 km<br> to cover additional potential extensions interpreted from results |
| --- | --- |
| ● | First<br> exploration drilling program in over a decade is now underway with the first of four planned<br> rigs targeting high-impact exploration, resource growth, infill and oxide drilling, as well<br> as technical drilling to support optimization studies |
| --- | --- |
SitePreparation and De-risking
| ● | Earthworks<br> for internal roads and platforms commenced |
|---|---|
| ● | Camp<br> and facility improvements underway |
| --- | --- |
| ● | Long-lead-time<br> equipment orders will be placed in late Q2/26 |
| --- | --- |
| ● | Substation<br> construction underway, with powerline to commence in late Q2/26 |
| --- | --- |
| ● | Access<br> road rehabilitation underway, with new road construction to commence in late Q2/26 |
| --- | --- |
Studies,Consultants and Contractors
| ● | Updated<br> Feasibility Study based on staged-development approach completed by the end of Q3/26 aiming<br> to maximize returns on a per share basis while mitigating capital expenditure, funding, timeline<br> and execution risks |
|---|---|
| ● | Respected<br> international and specialist-Peruvian consultants and contractors appointed for the majority<br> of the main work packages, with further appointments to follow: |
| --- | --- |
| ○ | Resource,<br> reserves and mine planning — MINSYS Mining Systems |
| --- | --- |
| ○ | Processing<br> plant and infrastructure — Ausenco Engineering |
| --- | --- |
| ○ | Contractors<br> — ApuCorp, Xplomine and CumbrEx |
| --- | --- |
MercedesGold-Silver Mine – Sonora, Mexico
Personnel
| ● | Orlando<br> Chumpitaz appointed Vice President & General Manager — Mr. Chumpitaz has held senior<br> roles with leading companies operating major underground mines globally, including Senior<br> Mine Manager for Lundin Gold at its 5,000 tpd Fruta del Norte gold mine in Ecuador, Project<br> Manager for Endeavour Mining at its 6,000 tpd Mana Mine in Burkina Faso, General Manager<br> for Minera Volcan at its 5,500 tpd Animon mine in Peru, and Operations Director for Fortuna<br> Mining at its 3,000 tpd San Jose mine in Mexico |
|---|
Restructuring
| ● | Extinguished<br> excessive gold stream and settled debt such that we expect the Mercedes mine to generate<br> free cash flow net of the critical investments detailed below |
|---|---|
| ● | Restored<br> working capital, settled overdue payables and in the process of settling minor unpaid taxes<br> and establishing bonding program |
| --- | --- |
| ● | Settled<br> union agreements |
| --- | --- |
2
Recapitalization
Mercedes produced 30 koz of gold in 2025. Significant improvement across worker safety, production and operating costs are expected in the coming years with a rejuvenated workforce operating under the proven leadership of Mr. Chumpitaz, and the following programs planned:
| ● | Infill<br> and definition drilling to support an improved reserve model |
|---|---|
| ● | Accelerated<br> mine development to improve access and enhance operational productivity |
| --- | --- |
| ● | Upgrading<br> critical infrastructure including ventilation, electrical systems, surface water management<br> and underground pumping capacity |
| --- | --- |
| ● | Geotechnical<br> drilling and implementation of support systems to improve safety and reduce dilution |
| --- | --- |
| ● | Cost<br> assessment and right-sizing mine contractor deployment to enhance productivity |
| --- | --- |
| ● | Tailings<br> Management Facilities expansion to support mine life extensions |
| --- | --- |
| ● | Resumption<br> of greenfield and brownfield exploration campaigns across extensive land package in geologically<br> favorable and prospective areas |
| --- | --- |
On behalf of Highlander Silver
“Daniel Earle”
President and CEO
Information contact
Arun Lamba, Vice President Corporate Development
alamba@highlandersilver.com
About Highlander Silver
Highlander Silver is a high-quality silver-growth company developing a portfolio of advanced-stage assets in Peru which includes the Corani silver project, the largest fully-permitted silver deposit in the world, and the bonanza-grade San Luis gold-silver project, which ranks among the 10 highest-grade projects globally in both gold and silver categories.^1^ The Company also operates the Mercedes gold-silver mine in Mexico. Highlander Silver’s major shareholders include the Augusta Group, Lundin family, and Eric Sprott.
| ^1^ | S&P<br>Global rankings including the Corani silver project and San Luis gold-silver project. |
|---|
3
Forward-looking statements
Certaininformation contained in this news release constitutes “forward-looking information” under Canadian securities legislation.This includes, but is not limited to, forecasting a year-end cash balance of approximately US$60 million; the Company will provide astandalone exploration update later this quarter that includes early results from the exploration programs; Long lead time equipmentorders to be placed in late Q2/26; powerline to commence in late Q2/26; new road construction to commence in late Q2/26; Updated FeasibilityStudy based on staged-development approach completed by the end of Q3/26; we expect the Mercedes mine to generate free cash flow netof the critical investments; significant improvement across worker safety, production and operating costs are expected in the comingyears with a rejuvenated workforce operating under the proven leadership of Mr. Chumpitaz; and the Mercedes recapitalization program.Such forward looking information or statements can be identified by the use of words such as “ramp up”, “attempting”,“intends”, “believes”, “plans”, “suggests”, “targets” or “prospects”or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “will”be taken, occur, or be achieved. Forward-looking information involves known and unknown risks, uncertainties, and other factors whichmay cause the actual results, performance, or achievements of the Company and/or its subsidiaries to be materially different from anyfuture results, performance, or achievements expressed or implied by the forward-looking information. Such factors include, among others,general business, economic, competitive, political and social uncertainties, the actual results of current exploration activities, changesin project parameters as plans continue to be refined, future prices of precious and base metals, accident, labour disputes and otherrisks of the mining industry, and delays in obtaining governmental or stock exchange approvals or financing. Although the Company hasattempted to identify important factors that could cause actual actions, events or results to differ materially from those describedin forward-looking information, there may be other factors that could cause actions, events or results to differ from those anticipated,estimated or intended. Forward-looking information contained herein are made as of the date of this news release. There can be no assurancethat forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipatedin such statements. The Company undertakes no obligation to update forward-looking information if circumstances or management’sestimates or opinions should change, except as required by applicable securities laws. Accordingly, the reader is cautioned not to placeundue reliance on forward-looking information.
4