Golar Lng Ltd 6-K, filed Nov 19, 2026
Golar Lng Ltd (GLNG)
6-K
2026-11-19
For: 2026-09-30
View Original
Added on
November 19, 2026
About this 6-K
Golar Lng Ltd filed this 6-K on November 19, 2026.
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 6-K
REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13A-16 OR 15D-16 OF THE
SECURITIES EXCHANGE ACT OF 1934
For the month of November 2026
Commission File Number: 000-50113
(Translation of registrant’s name into English) |
2nd Floor S.E. Pearman Building 9 Par-la-Ville Road Hamilton HM 11 Bermuda |
(Address of principal executive office) |
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.
Form 20-F [ X ] Form 40-F [ ]
INFORMATION CONTAINED IN THIS FORM 6-K REPORT
Included is the Overview, Operating and Financial Review for the nine months ended September 30, 2026 and the unaudited
consolidated condensed financial statements of Golar LNG Limited (the “Company” or “Golar”) as of and for the nine months
ended September 30, 2026.
The information contained in this Report on Form 6-K (this “Report”) is hereby incorporated by reference into the Company’s
registration statement on Form F-3 ASR (File No. 333-294621), which was filed with the U.S. Securities and Exchange
Commission (the “Commission”) on March 26, 2026.
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this Report to be signed on
its behalf by the undersigned, thereunto duly authorized.
GOLAR LNG LIMITED | ||
(Registrant) | ||
Date: November 19, 2026 | By: | /s/ Eduardo Maranhão |
Name: | Eduardo Maranhão | |
Title: | Principal Financial Officer | |
1
UNAUDITED INTERIM FINANCIAL REPORT
Forward-Looking Statements
Matters discussed in this Report may constitute forward-looking statements. The Private Securities Litigation Reform Act of
1995 provides safe harbor protections for forward-looking statements in order to encourage companies to provide prospective
information about their business. Forward-looking statements include statements concerning plans, objectives, goals, strategies,
future events or performance, and underlying assumptions and other statements, which are other than statements of historical
facts.
We desire to take advantage of the safe harbor provisions of the Private Securities Litigation Reform Act of 1995 and are
including this cautionary statement in connection with this safe harbor legislation. This Report and any other written or oral
statements made by us or on our behalf may include forward-looking statements, which reflect our current views with respect to
future events and financial performance. When used in this Report, the words “believe,” “anticipate,” “intend,” “estimate,”
“forecast,” “projected,” “plan,” “potential,” “continue,” “will,” “may,” “could,” “should,” “would,” “expect”, “target” and
similar expressions identify forward-looking statements.
The forward-looking statements in this Report are based upon various assumptions, many of which are based, in turn, upon
further assumptions, including without limitation, management’s examination of historical operating trends, data contained in
our records and other data available from third parties. Although we believe that these assumptions were reasonable when
made, because these assumptions are inherently subject to significant uncertainties and contingencies which are difficult or
impossible to predict and are beyond our control, we cannot assure you that we will achieve or accomplish these expectations,
beliefs or projections. As a result, you are cautioned not to rely on any forward-looking statements.
In addition to these important factors and matters discussed elsewhere herein, important factors that, in our view, could cause
actual results to differ materially from those discussed in the forward-looking statements include, among other things:
•our ability to fulfill our obligations under our commercial agreements, including the 20-year Lease and Operate Agreement
(the “LOA”) for the FLNG Gimi (“FLNG Gimi”);
•our ability to perform under our agreements with Southern Energy S.A. (“SESA”) for the deployment of FLNG Hilli
(“FLNG Hilli”) and FLNG Esperanza (“FLNG Esperanza”) in Argentina, including the timely completion of
redeployment, conversion and commissioning activities, as well as SESA’s and SMP's ability to meet their commitments to
us;
•our ability to complete the FLNG Esperanza conversion and FLNG Hilli refurbishment in a timely manner and within
budget;
•that an attractive deployment opportunity, or any of the opportunities under discussion for our second 3.5 MTPA MKII-
design FLNG unit (“FLNG four”), will be converted into a suitable contract. Failure to secure a contract in a timely manner
or at all could result in losses on our investment in the long-lead items, milestone payments made to date, the cost of
acquiring the donor vessel (Grace Dahlia) and applicable termination fees. Even if a satisfactory contract is secured,
changes in project capital expenditures, foreign exchange rates and commodity prices, could materially affect the expected
amount and timing of our return on investment;
•an increase in tax liabilities in the jurisdictions where we are currently operating, have previously operated or expect to
operate;
•our ability to obtain additional financing or refinance existing debt on acceptable terms or at all;
•any failure of shipyards to comply with work standards, project schedules, performance specifications or agreed prices;
•the outcome and timing of the Company’s strategic review process, including the possibility that the review may not result
in any transaction, strategic alternative, or other outcome; the potential for disruption to operations, commercial activities,
financings or relationships during the review process; the ability to identify and execute transactions or structural
alternatives that enhance shareholder value or accelerate the FLNG growth pipeline; market, regulatory, financing, and
counterparty conditions affecting any potential transaction; and costs, opportunity costs, management distraction, or other
uncertainties associated with the process;
•global economic trends, cybersecurity risks, competition, and geopolitical risks, including actions by the U.S. government,
trade tensions or conflicts such as those between the U.S. and China or the U.S. and Iran, related sanctions, and the
potential effects of any Russia-Ukraine or U.S.-Iran peace settlement on liquefied natural gas (“LNG”) supply and demand;
•continuing volatility in the global financial markets, including commodity prices, foreign exchange rates, interest rates and
global trade policy;
•changes in general domestic and international political conditions, particularly where we operate, or where we seek to
operate;
2
•changes in our ability to retrofit vessels as FLNGs, including the availability of donor vessels to purchase, lead times for
critical components and the time it takes to build new vessels;
•increases in operating costs as a result of inflation or trade policy, including salaries and wages, insurance, crew and related
costs, repairs and maintenance and spares;
•any material decline or prolonged weakness in tolling rates for FLNGs;
•any failure of our contract counterparties to comply with their agreements with us or other key project stakeholders;
•continuing uncertainty resulting from potential future claims from our counterparties of purported force majeure under
contractual arrangements, including our future projects and other contracts to which we are a party;
•the ability of certain parties to meet their respective obligations to us, including indemnification obligations;
•claims made or losses incurred in connection with our continuing obligations;
•our ability to close potential future transactions in relation to equity interests in our vessels or to monetize our remaining
investments on a timely basis or at all;
•changes to rules and regulations applicable to FLNGs or other parts of the natural gas and LNG supply chain;
•rules on climate-related disclosures promulgated by the European Union, including but not limited to disclosure of certain
climate-related risks and financial impacts, as well as greenhouse gas emissions;
•actions taken by regulatory authorities that may prohibit the access of FLNGs to various ports and locations; and
•other factors listed from time to time in registration statements, reports or other materials that we have filed with or
furnished to the Commission, including our annual report on Form 20-F for the year ended December 31, 2025, filed with
the U.S. Securities and Exchange Commission (“U.S. SEC”) on March 26, 2026 (the “2025 Annual Report”).
We caution readers of this Report not to place undue reliance on these forward-looking statements, which speak only as of their
dates. These forward-looking statements are not guarantees of our future performance, and actual results and future
developments may vary materially from those projected in the forward-looking statements.
All forward-looking statements included in this Report are made only as of the date of this Report and, except as required by
law, we assume no obligation to revise or update any written or oral forward-looking statements made by us or on our behalf as
a result of new information, future events or other factors. If one or more forward-looking statements are revised or updated, no
inference should be drawn that additional revisions or updates will be made in the future.
3
Management’s Discussion and Analysis of Financial Condition and Results of Operations
The following is a discussion of our financial condition and results of operations for the nine months ended September 30, 2026
and 2025. Throughout this Report, unless the context indicates otherwise, the “Company”, “Golar”, “Golar LNG”, “we”,
“us” and “our” all refer to Golar LNG Limited or any one or more of its consolidated subsidiaries, including Golar
Management Ltd, or to all such entities. Unless otherwise indicated, all references to “USD” and “$” in this Report are to U.S.
dollars. You should read the following discussion and analysis together with the unaudited condensed consolidated financial
statements and related notes included elsewhere in this Report. For additional information relating to our operating and
financial review and prospects, including definitions of certain terms used herein, please see our 2025 Annual Report.
Overview
Our strategy is to provide market-leading FLNG operations and maintain balance sheet flexibility to maximize shareholder
returns through accretive FLNG projects. We offer gas resource holders a proven, capital efficient and timely solution to
monetize stranded, associated, flared or otherwise underutilized gas reserves. Our industry leading FLNG operational track
record and FLNG growth prospects allow gas resource holders, developers and customers access to a low-cost, low-risk, rapidly
deployable solution for natural gas liquefaction.
FLNG projects provide a solution for gas reserves where geographical, technical, political and economic constraints limit
monetization through traditional infrastructure. Our standardized FLNG units can be redeployed to new opportunities after
producing a field and offer a viable economic alternative to large-scale land-based projects. Our liquefaction solution and
accelerated execution model place liquefaction technology onboard an existing LNG carrier, converting such carriers into a
fully commissioned FLNG. As of November 19, 2026, we are currently the only company with a proven track-record to deliver
FLNG as a service to gas resource owners.
Recent and Other Developments
In addition to the other information set forth in this Report on Form 6-K, please see our previous Reports on Form 6-K
furnished during 2026 and “Item 5 - Operating and Financial Review and Prospects - Significant Developments since January
1, 2026” of our 2025 Annual Report.
Since September 30, 2026, the following non-recognized events have occurred:
•Purchase of donor vessel for FLNG four
In October 2026, we entered into an agreement with Nippon Yusen Kabushiki Kaisha (“NYK Line”) to acquire the 2013-
built LNG carrier, Grace Dahlia. The vessel was delivered to the CIMC shipyard in November 2026 for conversion into
our fourth FLNG, with redelivery expected in 2029. The acquisition and conversion are within our $2.45 billion budget for
FLNG 4. As of the date of this report, we had spent approximately $324.5 million of capital expenditures in connection
with the FLNG 4 conversion, including the acquisition of Grace Dahlia.
•2026 Senior Unsecured Notes
On October 8, 2026, we issued $500 million aggregate principal amount of the 7.5000% senior unsecured notes (the “2026
Senior Unsecured Notes”), maturing December 15, 2031. The 2026 Senior Unsecured Notes were issued at 99% of the
principal amount and bear interest at a rate of 7.500% per annum, payable semi-annually in arrears.
The net proceeds from the offering amounted to $487.3 million, after deducting the initial purchasers’ discount and
estimated offering expenses. This will be used to fund the construction of FLNG Esperanza and our FLNG four, further
FLNG growth units and other general corporate purposes.
•SMP capital contributions
In October 2026, we made an additional investment of $3.9 million in San Matias Pipeline S.A. (“SMP”) through an
irrevocable contribution against the future subscription of shares. Following this contribution, Golar continues to hold a
10% equity interest in SMP.
4
•FLNG Esperanza letter of credit
On October 8, 2026, the outstanding balance of the letter of credit issued in favor of B&V with Yantai CIMC Raffles
Offshore Ltd (“CIMC Raffles”) in connection with the FLNG Esperanza's Engineering, Procurement, and Construction
(“EPC”) contract decreased from $100.0 million to $25.0 million. The reduction was made in accordance with the terms of
the EPC contract.
•Long-Lead Equipment reservation
In October 2026, we entered into a Limited Notice to Proceed (“LNTP”) with Nuovo Pignone International S.r.l. for the
reservation of long-lead equipment. The LNTP authorizes the procurement of long-lead components and secures
reservations for manufacturing slots of multiple gas generators.
•Amendment to FLNG Hilli sale and leaseback facility
On November 18, we entered into an agreement to amend and extend FLNG Hilli’s existing sale-leaseback facility with an
affiliate of CSSC (Hong Kong) Shipping Company Limited (“CSSC entity”). The amended facility will provide financing
of up to $960 million, with an extended maturity to 2038 and a reduced financing margin. The transaction is expected to
close in December 2026.
•Dividends
On November 18, 2026, we declared a dividend of $0.25 per share in respect of the three months ended September 30,
2026 to shareholders of record on November 30, 2026, which will be paid on or around December 9, 2026.
Operating and Financial Review
The Company's results for the nine months ended September 30, 2026 are affected by several significant operational changes
compared with the same period in 2025:
•Within our FLNG segment, FLNG Gimi achieved Commercial Operations Date (“COD”) and commenced operations in
mid-June 2025. Accordingly, the nine months ended September 30, 2026 reflects a full nine months of operations,
compared with approximately three and a half months of operations for the nine months ended September 30, 2025. In
addition, FLNG Hilli completed her eight-year Liquefaction Tolling Agreement (“LTA”) in July 2026, contributing seven
months of operations in 2026 compared to a full nine months in 2025.
•Within our Corporate and other segment, comparability is affected by the termination of the O&M agreement for FSRU
LNG Croatia in December 2025 and the termination of the O&M agreement for FSRU Italis LNG following the sale of our
entire shareholding in Gaslin S.r.l. (“Gaslin”) in April 2026. Accordingly, revenue for the nine months ended September
30, 2026 only includes three and a half months of O&M revenue from FSRU Italis LNG and no revenue from FSRU LNG
Croatia, compared with a full nine months of O&M revenue from both O&M contracts in the corresponding period of
2025.
5
See note 4 “Segment Information” of the unaudited condensed consolidated financial statements included herein for additional
information on our segments. Reconciliations of consolidated net income to Adjusted EBITDA for the nine months ended
September 30, 2026 and 2025 are as follows:
(in thousands of $) | 2026 | 2025 |
Net income | 199,719 | 89,428 |
Income tax expense | 4,124 | 2,406 |
Income before income tax | 203,843 | 91,834 |
Depreciation and amortization | 42,129 | 37,052 |
Unrealized loss on oil and gas derivative instruments | 4,625 | 72,549 |
Other non-operating income | (658) | (29,981) |
Interest income | (27,322) | (23,651) |
Interest expense, net | 61,988 | 9,289 |
(Gains)/losses on derivative instruments, net | (30,322) | 10,091 |
Other financial items, net | 4,862 | 4,166 |
Net income from equity method investments | (2,054) | (9,960) |
Sales-type lease receivable in excess of interest income | 31,659 | 12,222 |
Adjusted EBITDA (1) | 288,750 | 173,611 |
(1) Adjusted EBITDA is a non-U.S. GAAP financial measure and is calculated by taking net income before income taxes, depreciation and
amortization, unrealized losses on oil and gas derivative instruments, other non-operating income, interest income, interest expense, net,
(gains)/losses on derivative instruments, net, other financial items, net, net income from equity method investments, and sales-type lease
receivable in excess of interest income. Adjusted EBITDA is a financial measure used by management and investors to assess our total
financial and operating performance. Adjusted EBITDA increases the comparability of our operational performance from period to period and
against the operational performance of other companies without regard to our financing methods or capital structure. Adjusted EBITDA
should not be considered as an alternative to net income or any other measure of our financial performance calculated in accordance with U.S.
GAAP.
Discussed below are the material changes of our consolidated results of operations for the nine months ended September 30,
2026 compared against the nine months ended September 30, 2025:
Income taxes: The increase of $1.7 million for the nine months ended September 30, 2026 compared to the same period in
2025 was primarily due to:
•a $3.1 million increase given a full nine months of taxable income generated under the Gimi LOA during the nine months
ended September 30, 2026, compared to approximately three and a half months in the same period in 2025, following
FLNG Gimi's COD on June 12, 2025. Pursuant to the LOA, taxes incurred in connection with FLNG Gimi's operations are
reimbursed by bp, with the related credit recognized within sales-type lease revenue and vessel management fees; and
•partially offset by a $1.0 million release of the deferred tax liability during the nine months ended September 30, 2026,
following the completion of the buy-out of our UK defined pension scheme in March 2026, through the purchase of
individual annuity contracts, resulting in a settlement of the plan obligations. No comparable tax benefit was recognized in
the same period in 2025.
Depreciation and amortization: The increase of $5.1 million for the nine months ended September 30, 2026 compared to the
same period in 2025 was primarily due to net $5.6 million increase in depreciation relating to FLNG Hilli's mooring equipment
following remeasurement of the associated asset retirement obligation (“ARO”) in January 2026 (note 17). As of September 30,
2026, the mooring equipment was fully amortized and subsequently derecognized upon completion of the LTA.
6
Unrealized gain/(loss) on oil and gas derivative instruments: The mark-to-market (“MTM”) movements recognized during the
six months ended June 30, 2026 remained unrealized at that date, which was subsequently realized upon completion of the LTA
in July 2026.
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Unrealized gain/(loss) on FLNG Hilli’s oil derivative instrument | 2,983 | (43,749) |
Unrealized loss on FLNG Hilli’s gas derivative instrument | (7,608) | (28,800) |
Unrealized loss on oil and gas derivative instruments | (4,625) | (72,549) |
•Unrealized gain/(loss) on FLNG Hilli’s LTA oil derivative instrument in Cameroon: This reflects the MTM movements
related to the changes in the fair value of the FLNG Hilli’s oil derivative instrument embedded in the LTA which was
estimated using the discounted future cash flows of the additional payments due to us as a result of Brent linked crude oil
prices moving above a contractual oil price floor over the remaining term of the LTA. The decrease in unrealized loss of
$46.7 million for the nine months ended September 30, 2026, compared to an unrealized loss for the same period in 2025
was primarily driven by movements in realized and forward Brent linked crude oil prices, changes in price volatility.
•Unrealized loss on FLNG Hilli’s LTA gas derivative instrument in Cameroon: This reflects the MTM movements related to
the changes in the fair value of the FLNG Hilli’s gas derivative instrument embedded in the LTA which was estimated
using the discounted future cash flows of the additional payments due to us for the 0.2 MTPA incremental LNG capacity
over the remaining term of the LTA which is linked to the Dutch Title Transfer Facility (“TTF”) gas prices and forecast
Euro/USD exchange rates. The decrease in unrealized loss of $21.2 million for the nine months ended September 30, 2026
compared to the same period in 2025 was primarily driven by movements in realized and forward TTF linked gas prices,
changes in price volatility.
Other non-operating income: The decrease of $29.3 million in other non-operating income for the nine months ended
September 30, 2026 was primarily due to:
•the recognition of the non-recurring $29.9 million gain on the FLNG Gimi sales type lease during the nine months ended
September 30, 2025. There was no comparable gain for the same period in 2026; and
•a net gain of $0.4 million on the disposal of investments during the nine months ended September 30, 2026, comprising a
$3.1 million gain on the sale of our 2.69% interest in OLT Offshore LNG Toscana S.p.A (“OLT-O”) to SNAM S.p.A.
(“OLT-O”), which was fully impaired in 2019, partially offset by $2.7 million loss on the disposal of our investment in
Gaslin. There was no comparable gain for the same period in 2025.
Interest income: The increase of $3.7 million for the nine months ended September 30, 2026 compared to the same period in
2025 was primarily due to:
•a $5.1 million increase in interest income from higher short-term money-market deposits, with balances of $535.5 million
as of September 30, 2026 compared to $499.7 million as of September 30, 2025; and
•partially offset by a $1.1 million decrease in interest income on a shareholder loan to First FLNG Holdings (“FFH”), which
was fully repaid in March 2025.
Interest expense, net: The $52.7 million increase in interest expense for the nine months ended September 30, 2026 compared
to the same period in 2025 was primarily due to:
•higher corporate debt interest expense inclusive of the amortization of related deferred financing costs, following the
issuance of the $575 million 2025 Convertible Bonds in June 2025, the $500 million 2025 Senior Unsecured Notes in
October 2025 and the refinancing of the $700 million Gimi facility with a new $1.2 billion Gimi facility in November
2025; and
•changes in the capitalization of borrowing costs following the achievement of COD of FLNG Gimi in June 2025, after
which borrowing costs ceased to qualify for capitalization and were subsequently recognized as an expense, partially offset
by higher capitalization of borrowing costs attributable to FLNG four following the execution of EPC in August 2026 and
to our equity investments in SESA and SMP, which met the criteria for qualifying assets.
7
Gains/(losses) on derivative instruments, net:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Unrealized MTM adjustment for interest rate swap (“IRS”) derivatives | 29,064 | (13,712) |
Net interest income on undesignated IRS derivatives | 1,258 | 3,621 |
Gain/(loss) on derivative instruments, net | 30,322 | (10,091) |
•Unrealized MTM adjustment for IRS derivatives: This reflects the MTM movements related to the changes in the fair value
of our IRS derivatives. As of September 30, 2026 and 2025, none of our IRS are designated as hedges for accounting
purposes. The $42.8 million increase in unrealized MTM gains for the nine months ended September 30, 2026 compared to
an unrealized MTM loss in the same period in 2025 was primarily driven by changes in the contractual terms of the IRS,
including higher notional values from $387.9 million to $571.9 million, maturity date extended from November 2029 to
November 2032, and a higher fixed interest rate from 1.93% to 3.43%. These increases were partially offset by fair value
adjustments reflecting our creditworthiness and that of our counterparties.
•Net interest income on undesignated IRS derivatives: This reflects the net interest exposure in relation to our IRS
derivatives. The decrease of $2.4 million net interest income for the nine months ended September 30, 2026 compared to
the same period in 2025 was driven largely by the movements in the SOFR.
Net income from equity method investments: This represents our share of earnings from our equity method investments, as
well as gains or losses on disposals related to these investments. The net decrease of $7.9 million for the nine months ended
September 30, 2026 was primarily due to a lower gain on the disposal of an equity method investment compared with the same
period in 2025. During the nine months ended September 30, 2026, we recognized a $4.6 million gain on the disposal of our
58% shareholding in Logística e Distribuição de Gás S.A. (“LOGAS”) in April 2026, compared with a $10.3 million gain on
the disposal of our 23.4% shareholding in Avenir in February 2025.
Sales-type lease receivable in excess of interest income: Amounts recognized as sales type lease revenue represents the interest
income component earned, while the principal amortization is treated as a reduction to the lease receivable balance presented in
“Net investment in sales-type lease” in the unaudited consolidated balance sheet. “Sales-type lease receivable in excess of
interest income” represents the lease receivable principal amortization component of the total amounts invoiced under the
FLNG Gimi sales-type lease. We included the total invoiced amounts comprising both interest income and principal repayment
in our FLNG Adjusted EBITDA to reflect the total cash earnings and economic performance of the FLNG Gimi. This amount is
eliminated from the unaudited consolidated statements of operations in accordance with U.S. GAAP.
Nine months ended September 30, 2026 | |||||
(in thousands of $) | FLNG | Corporate and other | Total Segment Reporting | Elimination | Consolidated Reporting |
Liquefaction services revenue | 127,506 | — | 127,506 | — | 127,506 |
Sales-type lease revenue | 142,400 | — | 142,400 | — | 142,400 |
Vessel management fees and other revenues | 74,568 | 7,287 | 81,855 | — | 81,855 |
Total operating revenues | 344,474 | 7,287 | 351,761 | — | 351,761 |
Vessel operating expenses | (109,776) | (2,786) | (112,562) | — | (112,562) |
Administrative expenses | (571) | (30,675) | (31,246) | — | (31,246) |
Project development expenses | (5,727) | (36) | (5,763) | — | (5,763) |
Realized gain on oil and gas derivative instruments, net | 46,714 | — | 46,714 | — | 46,714 |
Other operating income/(loss) | 8,810 | (623) | 8,187 | — | 8,187 |
Sales-type lease receivable in excess of interest income | 31,659 | — | 31,659 | (31,659) | — |
Adjusted EBITDA | 315,583 | (26,833) | 288,750 | (31,659) | 257,091 |
8
Nine months ended September 30, 2025 | |||||
(in thousands of $) | FLNG | Corporate and other | Total Segment Reporting | Elimination | Consolidated Reporting |
Liquefaction services revenue | 168,171 | — | 168,171 | — | 168,171 |
Sales-type lease revenue | 46,925 | — | 46,925 | — | 46,925 |
Vessel management fees and other revenues | 25,144 | 19,594 | 44,738 | — | 44,738 |
Time and voyage charter revenues | — | 876 | 876 | — | 876 |
Total operating revenues | 240,240 | 20,470 | 260,710 | — | 260,710 |
Vessel operating expenses | (85,707) | (22,076) | (107,783) | — | (107,783) |
Administrative expenses | (939) | (23,396) | (24,335) | — | (24,335) |
Project development expenses | (13,071) | (3,140) | (16,211) | — | (16,211) |
Realized gain on oil and gas derivative instruments, net | 51,034 | — | 51,034 | — | 51,034 |
Other operating loss | — | (2,026) | (2,026) | — | (2,026) |
Sales-type lease receivable in excess of interest income | 12,222 | — | 12,222 | (12,222) | — |
Adjusted EBITDA | 203,779 | (30,168) | 173,611 | (12,222) | 161,389 |
Adjusted EBITDA: Total segment reporting Adjusted EBITDA increased by $115.1 million for the nine months ended
September 30, 2026 compared to the same period in 2025, primarily reflecting a full nine months of operations under the FLNG
Gimi LOA in 2026, compared with approximately three and a half months following COD in June 2025. FLNG Gimi
contributed a net increase of $135.2 million, comprising of $164.3 million in operating revenues including sales-type lease
receivable in excess of interest income, partially offset by a $29.1 million increase in vessel operating expenses.
Additionally, our Adjusted EBITDA benefited from:
•$7.3 million attributable to reimbursements received from bp in connection with the settlement of outstanding pre-
COD matters of $4.8 million and services provided to SESA of $2.5 million; and
•$4.8 million following the termination of the O&M Agreement with LNG Hrvatska for FSRU LNG Croatia in
December 2025, the disposal of Golar Arctic in March 2025 and termination of the O&M Agreement for the FSRU
Italis LNG in April 2026.
These increases were partially offset by a $38.5 million net decrease in Adjusted EBITDA from FLNG Hilli, following the
completion of its eight-year LTA in July 2026, reflecting seven months of operations in 2026 compared to nine months in 2025.
On a consolidated basis, Adjusted EBITDA increased by $95.7 million for the nine months ended September 30, 2026
compared to the same period in 2025, due to the accounting impact of the sales-type lease receivable, whereby revenue
recognized in excess of interest income is eliminated upon consolidation. These movements reflect consolidated changes across
all segments. Further details and material movements within specific reportable segments are discussed below.
9
FLNG segment
Below relates to the operations of our FLNG fleet and our other FLNG projects.
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Liquefaction services revenue | 127,506 | 168,171 |
Sales-type lease revenue | 142,400 | 46,925 |
Vessel management fees and other revenues | 74,568 | 25,144 |
Total operating revenues | 344,474 | 240,240 |
Vessel operating expenses | (109,776) | (85,707) |
Administrative expenses | (571) | (939) |
Project development expenses | (5,727) | (13,071) |
Realized gain on oil and gas derivative instruments, net | 46,714 | 51,034 |
Other operating income | 8,810 | — |
Sales-type lease receivable in excess of interest income | 31,659 | 12,222 |
Adjusted EBITDA | 315,583 | 203,779 |
Liquefaction services revenue: The decrease of $40.7 million for the nine months ended September 30, 2026 compared to the
same period in 2025 was primarily due to completion of FLNG Hilli's eight-year LTA in July 2026, reflecting seven months of
operations in 2026 compared to nine months in 2025.
Liquefaction services revenue comprises of the following components:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Base tolling fee | 111,596 | 152,022 |
Amortization of Day 1 gains | 6,845 | 9,380 |
Incremental base tolling fee | 2,728 | 3,717 |
Amortization of deferred commissioning period revenue | 2,246 | 3,081 |
Net variable consideration | 4,397 | — |
Other | (306) | (29) |
Liquefaction services revenue | 127,506 | 168,171 |
•Base tolling fee: This reflects the services invoiced under the FLNG Hilli LTA in Cameroon based on the contractual base
rate applicable when oil prices are at or below $60 per barrel.
•Amortization of Day 1 gains: This reflects the amortization of Day 1 gains recognized upon the initial recognition of FLNG
Hilli’s embedded oil and gas derivative instruments, amortized over the contract term in Cameroon.
•Incremental base tolling fee: This relates to the additional tolling fee associated with the increased annual contracted
capacity under the FLNG Hilli LTA in Cameroon.
•Amortization of deferred commissioning period revenue: This reflects the amortization of customer billings received during
FLNG Hilli’s commissioning period, prior to vessel acceptance and commencement of the LTA in Cameroon, which were
deferred and recognized over the contract term.
•Net variable consideration: Following the completion of FLNG Hilli's eight-year LTA in Cameroon in July 2026, net
variable consideration of $4.4 million was invoiced during the nine months ended September 30, 2026, relating to 2026
production reconciliation and liquefaction services provided through completion of the final lifting.
10
Sales-type lease revenue: The increase of $95.5 million for the nine months ended September 30, 2026 compared to the same
period in 2025 was primarily driven by a full nine months of FLNG Gimi operations in 2026, compared with approximately
three and a half months following COD in June 2025.
Sales-type lease revenue comprises of the following components:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Sales-type lease revenue | 83,001 | 34,398 |
Variable lease revenue | 51,629 | 9,828 |
Accretion of unguaranteed residual value | 4,632 | 1,787 |
Other | 3,138 | 912 |
Sales-type lease revenue | 142,400 | 46,925 |
•Sales-type lease revenue: This reflects the interest income recognized on the net investment in the sales-type lease on
FLNG Gimi, calculated using the implicit rate in the lease.
•Variable lease revenue: This reflects variable payments not included in the fixed consideration of the lease including
overproduction, underutilization, and other operational adjustments invoiced since commencement of operations.
•Accretion of unguaranteed residual value: This relates to the periodic accretion in the present value of the unguaranteed
residual value of FLNG Gimi, recognized over the lease term using the effective interest method.
•Other: This reflects taxes that are reimbursable under the LOA and accrued demurrage costs.
Vessel management fees and other revenues: Vessel management fees and other revenues comprise primarily of the non-lease
component of the FLNG Gimi LOA, representing O&M services. The increase of $49.4 million for the nine months ended
September 30, 2026 compared to the same period in 2025 was primarily driven by a full nine months of operations for FLNG
Gimi in 2026, compared with approximately three and a half months following COD in June 2025.
Vessel management fees and other revenues comprises of the following components:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
FLNG O&M service revenue | 71,267 | 25,169 |
Amortization of deferred pre-COD cash flows | 1,379 | 561 |
Other | 1,922 | (586) |
Vessel management fees and other revenues | 74,568 | 25,144 |
•O&M service revenue: This reflects the non-lease O&M services component in relation to FLNG Gimi's LOA.
•Amortization of deferred pre-COD cash flows: This reflects the amortization of the non-lease component of pre-COD cash
flows received from bp in relation to FLNG Gimi's LOA, recognized over the term of the LOA on a straight-line basis.
•Other: This reflects taxes reimbursable under the LOA and accrued demurrage costs.
Realized gain on oil and gas derivative instruments:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Realized gain on FLNG Hilli’s oil derivative instrument | 29,966 | 28,196 |
Realized gain on FLNG Hilli’s gas derivative instrument | 16,748 | 22,838 |
Realized gain on oil and gas derivative instruments, net | 46,714 | 51,034 |
11
•Realized gain on FLNG Hilli’s LTA oil derivative instrument in Cameroon: This reflects the billings above the FLNG
Hilli’s base tolling fee when the Brent linked crude oil price is greater than $60 per barrel. The increase of $1.8 million for
the nine months ended September 30, 2026, compared to the same period in 2025, was driven by:
◦higher three-month look-back average Brent crude oil price of $84.18/barrel for the seven months ended July 2026
compared to $72.15/barrel for the nine months ended September 30, 2025;
◦partially offset by a shorter operating period for FLNG Hilli in 2026, reflecting seven months of operations
compared to nine months in 2025; and
◦realization of oil derivative assets of $6.2 million as of June 30, 2026. Following the completion of FLNG Hilli's
LTA in July 2026, these derivative assets were realized by September 30, 2026, resulting in a reduction in gains
recognized in relation to billings.
•Realized gain on FLNG Hilli’s LTA gas derivative instrument in Cameroon: This reflects the tolling fee in excess of the
contractual floor rate, linked to TTF prices and the Euro/USD foreign exchange movements. The decrease of $6.1 million
for the nine months ended September 30, 2026, compared to the same period in 2025, was driven by:
◦a shorter operating period for FLNG Hilli in 2026, reflecting seven months of operations compared to nine months
in 2025;
◦realization of gas derivative assets of $1.9 million as of June 30, 2026. Following the completion of FLNG Hilli's
LTA in July 2026, these derivative assets were realized by September 30, 2026, resulting in a reduction in gains
recognized in relation to billings; and
◦partially offset by higher one-month look-back average TTF price of €40.51 ($47.04) for the seven months ended
July 2026, compared to a TTF price of €39.78 ($44.41) for the nine months September 30, 2025.
Nine months ended September 30, | ||
2026 | 2025 | |
Other Financial Data: | ||
Liquefaction services revenue | 127,506 | 168,171 |
Sales-type lease revenue | 142,400 | 46,925 |
Vessel management fees and other revenues | 74,568 | 25,144 |
Total operating revenues | 344,474 | 240,240 |
Realized gain on oil and gas derivative instruments, net | 46,714 | 51,034 |
Amortization of deferred commissioning period revenue, Day 1 gains and deferred pre-COD cash flows, accretion of unguaranteed residual value, accrued tax receipt, over/underproduction, accrued revenue and accrued demurrage | (7,882) | (16,082) |
Sales-type lease receivable in excess of interest income | 31,659 | 12,222 |
FLNG tariff, net (1) | 414,965 | 287,414 |
(1) FLNG tariff, net is a non-U.S. GAAP financial measure that represents the total cash inflow and economic performance generated by our
FLNGs during a given period. It is calculated by taking the total amount invoiced for FLNG services, including liquefaction services revenue,
sales-type lease revenue, vessel management fees and other revenue, realized gains on oil and gas derivative instruments, net adjusted for the
amortization of deferred commissioning period revenue, Day 1 gains (deferred revenues) and deferred pre-COD cashflows allocated to the
non-lease component, the unwinding of liquidated damages, the accretion of unguaranteed residual value and other timing-related items
including tax reimbursements, underutilization, overproduction revenue, accrued revenue, and accrued demurrage cost. Following the
completion of FLNG Hilli's LTA in July 2026, the previously recognized oil and gas derivative asset of $8.1 million as of June 30, 2026, were
realized by September 30, 2026 and adjusted for deriving FLNG tariff, net. FLNG tariff, net is intended to enhance the comparability of our
FLNG performance across periods and with other operational FLNGs in the industry. FLNG tariff, net should not be considered as an
alternative to total operating revenue of the FLNG segment or any other performance measure of our financial performance calculated in
accordance with U.S. GAAP.
12
FLNG Tariff, net: The increase of $127.6 million for the nine months ended September 30, 2026, compared to the same period
in 2025, was primarily driven by a full nine months of FLNG Gimi operations in 2026, compared to approximately three and a
half months following commencement of operations in 2025. The increase was partially offset by a shorter operating period for
FLNG Hilli following the completion of its eight-year LTA in July 2026, reflecting seven months of operations in 2026
compared to nine months in 2025.
Vessel operating expenses: The increase of $24.1 million for the nine months ended September 30, 2026 compared to the same
period in 2025 was primarily due to:
•a $34.9 million increase in FLNG Gimi's operating expenses following commencement of operations in June 2025,
primarily reflecting higher crew-related costs, repairs and maintenance, spares, and consultancy costs;
•partially offset by a $5.8 million decrease in FLNG Gimi's operating expenses resulting from the 2025 commissioning
activities, wherein certain costs incurred toward COD did not meet the criteria for capitalization and instead were deemed
essential operating costs to maintain the vessel's exclusive availability and operational readiness. No comparable costs were
incurred in 2026; and
•a $4.9 million decrease in FLNG Hilli's operating expenses following the completion of its eight-year LTA in July 2026,
reflecting seven months of operations in 2026 compared to nine months in 2025.
Project development expenses: This is comprised of non-capitalizable project-related expenses such as legal, professional and
consultancy costs for FLNG projects in the exploratory stages. The decrease of $7.3 million for the nine months ended
September 30, 2026 compared to the same period in 2025 was primarily due to:
•$4.1 million lower costs incurred for Front-End Engineering Design (“FEED”) study costs in connection with the potential
development of a modified MKI and MKIII FLNG for the nine months ended September 30, 2026 compared to the same
period in 2025;
•$1.6 million lower costs incurred on pursuing FLNG contracting opportunities in the nine months ended September 30,
2026 compared to 2025; and
•$1.6 million lower costs incurred in relation to the FLNG Hilli redeployment project during the nine months ended
September 30, 2026, as cost incurred following the Final Investment Decision (“FID”) for the redeployment of FLNG Hilli
under a 20-year agreement with SESA were capitalized rather than expensed when incurred.
Other operating income: The $8.8 million other operating income for the nine months ended September 30, 2026 was primarily
due to:
•$4.8 million settlement of outstanding pre-COD matters with bp, comprising a $4.0 million reimbursement for gas
generator, and capital spares and consumables procured during the conversion and commissioning of the FLNG Gimi in
connection with the LOA and a $0.8 million reimbursement following the final reconciliation of pre-COD fuel purchases;
•$2.5 million reimbursement from SESA for costs previously incurred by Golar; and
•$1.6 million reimbursement from Perenco following the final reconciliation of heel LNG upon the completion of FLNG
Hilli’s LTA.
There were no comparable amounts in 2025.
13
Corporate and other segment
This segment includes our legacy shipping activities, vessel management, floating storage and regasification unit services for
third parties, LNG carrier transportation operations, administrative services to affiliates and third parties, corporate overhead
costs and other strategic investments. We have offices in Bermuda, London and Oslo, which provide corporate management,
commercial, technical, accounting, treasury and administrative support.
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Vessel management fees and other revenues | 7,287 | 19,594 |
Time and voyage charter revenues | — | 876 |
Total operating revenues | 7,287 | 20,470 |
Vessel operating expenses | (2,786) | (22,076) |
Administrative expenses | (30,675) | (23,396) |
Project development expenses | (36) | (3,140) |
Other operating loss | (623) | (2,026) |
Adjusted EBITDA | (26,833) | (30,168) |
Vessel management fees and other revenues: The decrease of $12.3 million for the nine months ended September 30, 2026,
compared to the same period in 2025, was primarily due to lower O&M fees following the termination of the O&M agreements
for the FSRU LNG Croatia in December 2025 and the FSRU Italis LNG following the sale of our entire shareholding in Gaslin
in April 2026.
Time and voyage charter revenues: The $0.9 million revenue for the nine months ended September 30, 2025 relates to Fuji
LNG, which ceased upon its arrival at CIMC Raffles’ yard for conversion in February 2025, with no comparable transactions in
2026.
Vessel operating expenses: The decrease of $19.3 million for the nine months ended September 30, 2026 compared to the same
period in 2025 was primarily due to:
•a $16.7 million decrease following the disposal of Golar Arctic, termination of the O&M Agreement with LNG Hrvatska
for the FSRU LNG Croatia in December 2025 and termination of the O&M agreement for the FSRU Italis LNG in April
2026;
•a $1.2 million decrease attributable to crew management fees charged to FLNG Hilli and FLNG Gimi, which is eliminated
on consolidation; and
•a $0.9 million reduced operational activity for the Fuji LNG following its arrival at CIMC Raffles’ yard for conversion.
Administrative expenses: The increase of $7.3 million for the nine months ended September 30, 2026, compared to the same
period in 2025, was primarily driven by:
•an $11.2 million increase in employee compensation and benefits, professional services and travel expenses and the
completed buy-out of our UK defined benefit pension scheme through the purchase of individual annuity contracts in
March 2026, resulting in a settlement of the plan obligations and the recognition of a settlement loss of $2.4 million during
the nine months ended September 30, 2026, compared to the same period in 2025; and
•partially offset by a $5.5 million higher allocation of management and consultancy fees to vessel operating expenses and
project development expenses in our FLNG segment reflecting time spent on FLNG activities, which is eliminated on
consolidation.
14
Project development expenses: The decrease of $3.1 million in project development expenses was primarily driven by lower
professional and consultancy costs incurred for existing business ventures for the nine months ended September 30, 2026
compared to the same period in 2025.
Other operating loss: The decrease of $1.4 million in other operating loss for the nine months ended September 30, 2026
compared to the same period in 2025 was primarily due to:
•$0.9 million decrease in credit loss allowance on the Higas Holdings Limited (“Higas”) shareholder loan, reflecting a lower
outstanding balance of $2.6 million as of September 30, 2026 (September 30, 2025: $6.3 million); and
•a $0.5 million loss on disposal of the Golar Arctic in 2025, with no comparable loss in 2026.
Liquidity and Capital Resources
Our short-term liquidity requirements are primarily for the servicing of our debt, working capital, potential investments, FLNG
Hilli redeployment capital expenditures, and conversion projects (including FLNG Esperanza and FLNG four project related
commitments). We believe that our existing cash and cash equivalents and short-term bank deposits, cash flow from operations
and our planned liquidity-enhancing initiative (see note 1 of our unaudited condensed consolidated financial statements
included herein), will be sufficient to support our liquidity and capital requirements for at least the next 12 months.
As of September 30, 2026, we had cash and cash equivalents (including short-term deposits) of $710.7 million, of which $38.3
million is restricted cash. Included within restricted cash is $37.2 million which relates to amounts held in a debt service reserve
for Gimi facility. Refer to note 10 “Restricted Cash” of our unaudited condensed consolidated financial statements included
herein for additional details.
Since September 30, 2026, transactions impacting our cash flows include:
Receipts of:
•$487.3 million of net proceeds in relation to closing of the 2026 Senior Unsecured Notes in October 2026.
Payments of:
•$237.3 million of additions to the asset under development, including acquisition of donor vessel, the FLNG four;
•$123.9 million of additions to the asset under development, the FLNG Esperanza;
•$22.5 million of capital expenditure on the FLNG Hilli redeployment, in relation to upgrades and life extension works;
•$3.9 million capital contribution for our equity interest in SMP; and
•$3.6 million capital contribution for our equity interest in SESA.
Borrowing activities
As of September 30, 2026, we were in compliance with all our covenants under our various loan agreements. See note 15
“Debt” in our unaudited condensed consolidated financial statements included herein for additional information.
15
Security, Debt and Lease Restrictions
Certain of our financing agreements are collateralized by vessel liens. Our existing financing agreements impose certain
operating and financing restrictions which may significantly limit or prohibit, among other things, our ability to incur additional
indebtedness, create liens, sell capital shares of subsidiaries, make certain investments, engage in mergers and acquisitions,
purchase and sell vessels, buy-back additional shares in excess of existing allowances or distribute dividends. In addition,
lenders may accelerate the maturity of indebtedness under existing financing agreements and foreclose upon the collateral
securing the indebtedness upon the occurrence of certain events of default, including a failure to comply with any of the
covenants contained in our debt agreements. We have also provided guarantees and indemnities to certain equity method
investees, wherein our exposure is limited to our proportionate share of the underlying obligations, most of which are subject to
future effective dates or contractual conditions precedent. Our debt agreements and parental guarantees, contain certain
covenants which require compliance with certain financial ratios and liquidity thresholds. Such covenants include maintaining a
positive working capital ratio, a tangible net worth covenant, minimum free cash restrictions and minimum liquidity level. With
regards to our cash restrictions, we have agreed to retain at least $50.0 million of cash and cash equivalents on a consolidated
basis.
Cash Flows
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Net cash provided by operating activities | 231,120 | 340,902 |
Net cash provided by discontinued operations | — | — |
Net cash used in investing activities | (510,500) | (661,651) |
Net cash (used in)/provided by financing activities | (225,373) | 281,754 |
Net decrease in cash and cash equivalents and restricted cash | (504,753) | (38,995) |
Cash and cash equivalents and restricted cash at the beginning of the period | 1,215,417 | 716,582 |
Cash and cash equivalents and restricted cash at the end of the period | 710,664 | 677,587 |
Operating activities
Our primary source of cash is generated from the operations of FLNG Gimi and FLNG Hilli, with FLNG Hilli contributing
seven months of operating cash flows following the completion of its eight-year LTA in July 2026. Historically, we also
generated cash flows from vessel management services and FSRU O&M contracts, with the latter ceasing following the
termination of the LNG Croatia and Italis LNG O&M agreements in December 2025 and April 2026, respectively. Cash used in
operating activities primarily relates to crew expenses, repairs and maintenance, spares, stores and consumables, and insurance.
Additional operating cash outflows include employee compensation and benefits, audit and accounting fees, legal expenses,
general corporate overhead, and project development costs for both existing and prospective FLNG business growth initiatives.
Net cash provided by operating activities decreased by $109.8 million for the nine months ended September 30, 2026,
compared to the same period in 2025, primarily driven by higher operating expenses following FLNG Gimi COD in June 2025,
reduced revenue contribution from FLNG Hilli, reflecting seven months of operations in 2026 compared to nine months in
2025, and the general timing of working capital during the nine months ended September 30, 2026 compared with the same
period in 2025.
Investing activities
Cash used in investing activities primarily reflects expenditures related to FLNG conversion projects, loans to related parties,
and other equity investments. Conversely, cash provided by investing activities is mainly comprised of proceeds from equity
subscriptions, disposals of equity investments and long-lived assets, as well as repayments of loans by related parties.
16
Net cash used in investing activities decreased by $151.2 million for the nine months ended September 30, 2026 compared with
the same period in 2025, primarily attributable to $283.9 million of lower capital expenditures for our FLNG projects,
principally reflecting reduced spending on the FLNG Gimi conversion following the achievement of COD in mid-June 2025,
partially offset by cost related to FLNG Hilli redeployment and FLNG four conversion following the execution of the EPC
contract in August 2026. The decrease was partially offset by a $50.2 million reduction in proceeds from disposals of
investments and long-lived assets, $43.3 million of higher contributions to equity investments and advances to related parties,
and the absence of $39.0 million of prior-year cash inflows from an equity subscription by a noncontrolling interest in Gimi MS
Corporation and repayments of related-party loans.
Financing activities
Cash provided by financing activities primarily consists of proceeds from short-term and long-term debt issuances. Conversely,
cash used in financing activities mainly reflects repayments of debt, dividend payments, financing costs, and repurchases of our
common shares.
Net cash used in financing activities increased by $507.1 million for the nine months ended September 30, 2026 compared with
the same period in 2025, primarily driven by the absence of the issuance of the 2.75% convertible senior unsecured notes and
treasury share repurchases completed in 2025 which generated net proceeds of $461.5 million. The increase in net cash used
was further driven by increase in scheduled debt repayments of $21.7 million and dividends paid to both Golar LNG and Gimi
MS Corporation shareholders of $20.6 million during the nine months ended September 30, 2026.
GOLAR LNG LIMITED
INDEX TO THE UNAUDITED CONDENSED CONSOLIDATED FINANCIAL STATEMENTS
PAGE | ||||
Unaudited Consolidated Statements of Operations for the nine months ended September 30, 2026 and 2025 | ||||
Unaudited Consolidated Statements of Comprehensive Income for the nine months ended September 30, 2026 and 2025 | ||||
Unaudited Consolidated Balance Sheets as of September 30, 2026 and December 31, 2025 | ||||
Unaudited Consolidated Statements of Cash Flows for the nine months ended September 30, 2026 and 2025 | ||||
Unaudited Consolidated Statements of Changes in Equity for the nine months ended September 30, 2026 and 2025 | ||||
Notes to the Unaudited Condensed Consolidated Financial Statements | ||||
17
GOLAR LNG LIMITED
UNAUDITED CONSOLIDATED STATEMENTS OF OPERATIONS
(in thousands of $, except per share data) | Notes | Nine months ended September 30, | |
2026 | 2025 | ||
Liquefaction services revenue (including related party of $ $ | |||
Sales-type lease revenue | |||
Vessel management fees and other revenues (including related party of $ 2026 and $ | |||
Time and voyage charter revenues | |||
Total operating revenues | 4, 5 | ||
Vessel operating expenses (including related party of $ million in 2025) | 4 | ( | ( |
Administrative expenses | 4 | ( | ( |
Project development expenses | 4 | ( | ( |
Depreciation and amortization | ( | ( | |
Total operating expenses | ( | ( | |
Realized and unrealized gain/(loss) on oil and gas derivative instruments (including related party of $ | 4, 7 | ( | |
Other operating income/(loss) (including related party of $ million in 2025) | 4, 20 | ( | |
Total other operating income/(losses) | ( | ||
Operating income | |||
Other non-operating income | 4 | ||
Total other non-operating income | |||
Interest income (including related party of $ | 9, 19, 20 | ||
Interest expense, net | 4 | ( | ( |
Gains/(losses) on derivative instrument, net | 8 | ( | |
Other financial items, net | 8 | ( | ( |
Net financial (loss)/income | ( | ||
Income before taxes and net income from equity method investments | |||
Income tax expense | 4 | ( | ( |
Net income from equity method investments | 13 | ||
Net income | |||
Net income attributable to non-controlling interests | ( | ( | |
Net income attributable to stockholders of Golar LNG Limited | |||
Basic earnings per share ($) | 6 | $ | $ |
Diluted earnings per share ($) | 6 | $ | $ |
The accompanying notes are an integral part of these unaudited condensed consolidated financial statements.
18
GOLAR LNG LIMITED
UNAUDITED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
(in thousands of $) | Notes | Nine months ended September 30, | |
2026 | 2025 | ||
Net income | |||
Other comprehensive income: | |||
Gains associated with pensions, net of tax | |||
Share of equity method investment’s comprehensive income(1) | |||
Net other comprehensive income | |||
Comprehensive income | |||
Comprehensive income attributable to: | |||
Stockholders of Golar LNG Limited | |||
Non-controlling interests | |||
Comprehensive income | |||
(1) No tax impact for the nine months ended September 30, 2026 and 2025.
The accompanying notes are an integral part of these unaudited condensed consolidated financial statements.
19
GOLAR LNG LIMITED
UNAUDITED CONSOLIDATED BALANCE SHEETS
2026 | 2025 | ||
Notes | September 30, | December 31, | |
(in thousands of $) | Unaudited | Audited | |
ASSETS | |||
Current assets | |||
Cash and cash equivalents | |||
Restricted cash | 10 | ||
Trade accounts receivable and accrued income | 19 | ||
Amounts due from related parties | 20 | ||
Current portion of net investment in sales-type lease | 5 | ||
Other current assets | 11 | ||
Total current assets | |||
Non-current assets | |||
Restricted cash | 10 | ||
Equity method investments | 13 | ||
Assets under development | 12 | ||
Vessels and equipment, net | 4, 14, 17 | ||
Net investment in sales-type lease | 5 | ||
Intangible assets | |||
Non-current amounts due from related parties | 20 | ||
Other non-current assets | 14 | ||
Total assets | |||
LIABILITIES AND EQUITY | |||
Current liabilities | |||
Current portion of long-term debt and short-term debt | 15 | ( | ( |
Trade accounts payables (including related party of $ | 19 | ( | ( |
Accrued expenses | 16 | ( | ( |
Amounts due to related parties | 20 | ( | |
Other current liabilities | 17 | ( | ( |
Total current liabilities | ( | ( | |
Non-current liabilities | |||
Long-term debt | 15 | ( | ( |
Other non-current liabilities | 18 | ( | ( |
Total liabilities | ( | ( | |
EQUITY | |||
Stockholders’ equity | ( | ( | |
Non-controlling interests | ( | ( | |
Total liabilities and equity | ( | ( |
The accompanying notes are an integral part of these unaudited condensed consolidated financial statements.
20
GOLAR LNG LIMITED
UNAUDITED CONSOLIDATED STATEMENTS OF CASHFLOWS
Notes | Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 | |
OPERATING ACTIVITIES | |||
Net income | |||
Adjustments to reconcile net income to net cash provided by operating activities: | |||
Depreciation and amortization | |||
Sales-type lease receivable in excess of interest income | 4 | ||
Compensation cost related to employee stock awards | |||
Amortization of deferred financing costs and debt guarantees, net | |||
Net foreign exchange losses | 8 | ||
Provision for credit loss | 4, 20 | ||
Net income from equity method investments | 13 | ( | ( |
Dividend received from equity method investments | |||
Net gain on disposal of investments | 4 | ( | |
Gain on deemed sale of FLNG Gimi | ( | ||
Loss on disposal of long-lived asset | 4 | ||
Change in fair value of derivative instruments (interest rate swaps) | 8 | ( | |
Change in fair value of oil and gas derivative instruments, commodity swaps and amortization of day 1 gains | |||
Changes in assets and liabilities: | |||
Trade accounts receivable and accrued income | ( | ||
Other current and non-current assets | ( | ( | |
Amounts due from/to related parties | ( | ||
Trade accounts payables | ( | ||
Accrued expenses | |||
Other current and non-current liabilities | ( | ||
Net cash provided by operating activities | |||
INVESTING ACTIVITIES | |||
Additions to assets under development | ( | ( | |
Additions to equity method investments | ( | ( | |
Additions for Hilli redeployment | ( | ( | |
Loan advanced to related party | 20 | ( | ( |
Additions to intangibles | ( | ||
Proceeds from sale of equity method investments | 13 | ||
Proceeds from sale of investments | 4 | ||
Proceeds from repayment of loan advanced to related party | |||
Proceeds from subscription of equity interest in Gimi MS | 9 | ||
Consideration received for the sale of long-lived asset | 4 | ||
Net cash used in investing activities | ( | ( | |
21
Notes | Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 | |
FINANCING ACTIVITIES | |||
Repayments of short-term and long-term debt | ( | ( | |
Cash dividends paid | ( | ( | |
Financing costs paid | ( | ( | |
Proceeds from exercise of share options | |||
Purchase of treasury shares | ( | ||
Proceeds from long-term debt | |||
Net cash (used in)/provided by financing activities | ( | ||
Net decrease in cash and cash equivalents and restricted cash | ( | ( | |
Cash and cash equivalents and restricted cash at the beginning of the period | |||
Cash and cash equivalents and restricted cash at the end of the period | |||
Supplemental note to the unaudited consolidated statements of cash flows
The following table identifies the balance sheet line-items included in cash, cash equivalents and restricted cash presented in the unaudited
consolidated statements of cash flows:
(in thousands of $) | September 30, 2026 | December 31, 2025 | September 30, 2025 | December 31, 2024 |
Cash and cash equivalents | ||||
Restricted cash | ||||
Restricted cash (non-current portion) | ||||
The accompanying notes are an integral part of these unaudited condensed consolidated financial statements.
22
GOLAR LNG LIMITED
UNAUDITED CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
(in thousands of $) | Share Capital | Treasury Shares | Additional Paid-in Capital | Contributed Surplus (1) | Accumulated Other Comprehensive Loss (2) | Accumulated Retained Earnings/ (Losses) | Non- Controlling Interest | Total Equity |
Balance at December 31, 2024 (Audited) | ( | |||||||
Net income | — | — | — | — | — | |||
Dividends | — | — | — | — | — | ( | — | ( |
Exercise of share options | — | — | — | — | — | |||
Stock compensation | — | — | — | — | — | — | ||
Forfeiture of employee stock compensation | — | — | ( | — | — | — | — | ( |
Restricted stock units | — | ( | — | — | — | — | ||
Proceeds from subscription of equity interest in Gimi MS Corporation | — | — | — | — | — | — | ||
Repurchase and cancellation of treasury shares | ( | — | — | — | — | ( | ( | |
Reacquisition of common units of Hilli LLC (3) | — | — | — | — | ( | ( | ||
Other comprehensive income | — | — | — | — | — | |||
Balance at September 30, 2025 | ( | ( | ||||||
(in thousands of $) | Share Capital | Treasury Shares | Additional Paid-in Capital | Contributed Surplus (1) | Accumulated Other Comprehensive Loss (2) (4) | Accumulated Retained Earnings/ (Losses) | Non- Controlling Interest | Total Equity |
Balance at December 31, 2025 (Audited) | ( | ( | ( | |||||
Net income | — | — | — | — | — | |||
Dividends | — | — | — | — | — | ( | ( | ( |
Exercise of share options | — | — | — | — | — | |||
Stock compensation (5) | — | — | — | — | — | — | ||
Forfeiture of employee stock compensation | — | — | ( | — | — | — | — | ( |
Restricted stock units | — | ( | — | — | — | — | ||
Repurchase and cancellation of treasury shares | ( | — | — | — | ( | — | ||
Other comprehensive income | — | — | — | — | — | — | ||
Balance at September 30, 2026 | ( | ( | ||||||
(1) Contributed Surplus is “capital” that can be returned to stockholders without the need to reduce share capital, thereby giving us greater flexibility when it
comes to declaring dividends.
(2) As at September 30, 2026 and 2025, our accumulated other comprehensive loss consisted of (i) $0.3 million and $1.5 million losses in relation to our
pension and post-retirement benefit plan and (ii) $nil and $0.7 million for our share of equity method investment’s comprehensive losses, respectively. During
the nine months ended September 30, 2026 and 2025, cumulative translation adjustments of $0.9 million and $29 thousand were reclassified from accumulated
other comprehensive loss to earnings upon disposal of our investment in LOGÁS in April 2026 and Avenir in February 2025, respectively, and were included
within the gain on disposal recognized in “Net income from equity method investments”.
(3) This relates to the receipt of waived dividend distribution in relation to the repurchases of the minority interests in Hilli LLC.
(4) In March 2026, we completed the buy-out of our UK defined benefit pension plan through the purchase of individual annuity contracts, resulting in a
settlement of the plan obligations and recognition of a settlement loss of $2.4 million in “Administrative expenses” and the release of the related deferred tax
liability of $1.0 million in “Other comprehensive income” into the consolidated statement of operations. Following the transaction, there is no remaining net
pension assets or liabilities associated with the UK defined benefit pension scheme.
(5) This relates to the vested component of the stock compensation to third-party consultants in the form of restricted stock units (“RSUs”) in relation to our
FLNG business development activities. The first tranche of the RSUs vested on grant date and the corresponding amount was capitalized as “Other non-current
assets” in the unaudited consolidated balance sheet (note 14). The remaining RSUs will vest upon the achievement of specified project milestones, including
performance conditions linked to the commercial operations date (“COD”) of our two FLNG vessels under the respective lease arrangements.
The accompanying notes are an integral part of these unaudited condensed consolidated financial statements.
23
GOLAR LNG LIMITED
CONDENSED NOTES TO THE UNAUDITED CONSOLIDATED FINANCIAL STATEMENTS
1.GENERAL
Golar LNG Limited (the “Company” or “Golar”) was incorporated in Hamilton, Bermuda on May 10, 2001. Golar is listed on
the Nasdaq under the ticker symbol: “GLNG”.
We design, construct, own and operate marine infrastructure for the liquefaction of natural gas and are the leading provider of
floating liquefaction natural gas (“FLNG”) as a service to gas resource owners. We believe that natural gas has a critical role to
play in providing cleaner energy for many years to come. Our pioneering infrastructure solutions are designed to provide safe,
competitive and more sustainable ways of liquefying gas across the world. We provide market leading FLNG operations and
utilize our balance sheet flexibility to maximize shareholder returns through accretive FLNG projects. We offer gas resource
holders, developers, and customers a proven, low-cost, and low-risk solution to quickly monetize stranded gas reserves through
our industry-leading FLNG operational track record and strong FLNG growth prospects.
As of September 30, 2026, our fleet consisted of one operational FLNG vessel, one FLNG vessel under refurbishment and two
additional FLNG units under development:
•FLNG Gimi (the “FLNG Gimi”) which is operating offshore Mauritania and Senegal, remains under contract until
June 2045;
•FLNG Hilli Episeyo (the “FLNG Hilli”) is currently undergoing upgrades and life-extension work at Seatrium’s
Singapore shipyard before being redeployed under a 20-year charter with Southern Energy S.A. (“SESA”) in
Argentina, commencing in 2027, following the completion of the liquefaction tolling agreement (the “LTA”) with
Perenco Cameroon S.A. and Société Nationale des Hydrocarbures (“SNH”) in July 2026;
•FLNG Esperanza (formerly referred to as the “MKII FLNG”) is currently under development pursuant to an
Engineering, Procurement, and Construction (“EPC”) contract with Yantai CIMC Raffles Offshore Ltd (“CIMC
Raffles”). In May 2025, we entered into definitive agreements with SESA for a 20-year charter of the converted FLNG
Esperanza, targeted to begin upon COD in 2028; and
•In August 2026, we entered into an EPC contract with CIMC Raffles for a 3.5 MTPA MKII-design FLNG unit
(“FLNG four”) with an estimated fully delivered cost of approximately $2.45 billion and improved payment terms
compared to the FLNG Esperanza. FLNG four represents the earliest available newbuild FLNG capacity, with
delivery by end of 2029.
As used herein and unless otherwise required by the context, the terms “Golar”, the “Company”, “we”, “our”, “us” and words
of similar import refer to Golar or any one or more of its consolidated subsidiaries, or to all such entities.
Going concern
The unaudited condensed consolidated financial statements have been prepared on a going concern basis.
The Company’s execution of the EPC agreement for its FLNG four, the current FLNG Esperanza EPC agreement with CIMC
Raffles, the refurbishment of FLNG Hilli in preparation for 20-year redeployment in Argentina, and capital contributions to its
equity method investments in SESA and San Matias Pipeline S.A. (“SMP”) reflect the Company’s continued investment in
long-term contracted infrastructure and complementary investments. These activities have resulted in significant capital
expenditure commitments through 2031, including commitments falling within the Company’s going concern period.
To assess the Company’s ability to meet liquidity requirements and satisfy its obligations as they become due, management
prepared a cash flow forecast covering the twelve-month period from the date of these financial statements. The forecast
incorporates assumptions regarding the timing and magnitude of capital commitments, operating expenses, expected operating
cash inflows, debt service obligations, other liabilities as they become due, and available sources of financing. In July and
October 2026, the Company entered into a $600 million senior secured revolving credit facility with a syndicate of banks in
connection with FLNG Esperanza (the “FLNG Esperanza RCF”) and issued $500 million of senior unsecured notes (the “2026
Senior Unsecured Notes”), respectively. In November 2026, we signed an agreement to amend the current FLNG Hilli sale and
leaseback facility provided by CSSC (Hong Kong) Shipping Entity Limited (“CSSC entity”). The amended sale and lease back
facility will provide financing of up to $960 million, providing $472 million of liquidity and extends maturity to 2038.
24
Accordingly, based on the abovementioned executed financing initiatives, we will have sufficient resources to satisfy our
obligations throughout the twelve-month period following the date of these financial statements. In addition, we continue to
pursue a long-term asset-level financing for FLNG Esperanza and other alternative new debt facilities, including the issuance of
new corporate debt, subject to capital market and economic conditions. The strong fundamentals of the Company’s FLNG
assets including their long-term contracted cash flows and favorable leverage metrics together with the successful issuance of
$1.1 billion of corporate bonds in 2025, $1.2 billion refinancing of the Gimi debt facility, the recent completion of the
$600 million FLNG Esperanza RCF, issuance of the $500 million 2026 Senior Unsecured Notes and the upsizing of the FLNG
Hilli sale and leaseback facility, give management increased confidence in its ability to successfully execute one or more of
these liquidity-enhancing initiatives.
2.ACCOUNTING POLICIES
These unaudited condensed consolidated financial statements are prepared in accordance with accounting principles generally
accepted in the United States of America (“U.S. GAAP”). These unaudited condensed consolidated financial statements do not
include all of the disclosures required under U.S. GAAP in annual consolidated financial statements, and should be read in
conjunction with our audited consolidated annual financial statements for the year ended December 31, 2025, which are
included in our annual report on Form 20-F for the fiscal year ended December 31, 2025, filed with the U.S. Securities and
Significant accounting policies
The accounting policies adopted in the preparation of these unaudited condensed consolidated financial statements for the nine
months ended September 30, 2026 are consistent with those followed in the preparation of our audited consolidated financial
statements for the year ended December 31, 2025.
The preparation of our unaudited condensed consolidated financial statements requires management to make estimates,
judgments and assumptions that affect the reported amounts of assets and liabilities and disclosure of contingent assets and
liabilities at the balance sheet date, and the reported amounts of revenue and expenses during the reporting period. We base our
estimates, judgments and assumptions on our historical experience and on information that we believe to be reasonable under
the circumstances at the time they are made. Estimates and assumptions about future events and their effects cannot be
perceived with certainty and these estimates may change as new events occur, as more experience is acquired, as additional
information is obtained and as our operating environment changes. Actual results could differ from these estimates. Estimates
are used for, but are not limited to, determining the recoverability of our vessels, our assets under development, the accounting
for the LOA for the FLNG Gimi, including determining the allocation of consideration between lease and non-lease
components and the fair value of underlying assets in sales-type lease arrangements, and the valuation of our oil and gas
derivative instruments. In assessing the recoverability of our vessels and assets under development carrying amounts, we make
assumptions regarding estimated future cash flows, estimates in respect of residual values, hire rates and vessel operating
25
3.RECENTLY ISSUED ACCOUNTING STANDARDS
as of September 30, 2026:
Standard | Description | Date of Adoption | Effect on our unaudited Consolidated Financial Statements or Other Significant Matters |
ASU 2024-03 Income Statement—Reporting Comprehensive Income—Expense Disaggregation Disclosures (Subtopic 220-40) | The amendments require public business entities to provide additional disaggregated disclosures of certain expense captions presented on the face of the income statement. The ASU does not change the expense captions required to be presented in the income statement; rather, it requires entities to disclose specified categories of expense information in the notes to the consolidated financial statements in order to improve transparency and comparability. | January 1, 2027 | We are still assessing the impact of this ASU. Upon adoption, the impact will be limited to additional disclosure requirements in our annual financial statements. |
ASU 2025-03 - Business Combinations (Topic 805) and Consolidation (Topic 810) - Determining the Accounting Acquirer in the Acquisition of a Variable Interest Entity | The amendments require entities to consider the guidance in Topic 805 when determining the accounting acquirer in the acquisition of a VIE that is a business and the transaction is primarily effected by the exchange of equity interests. The ASU is intended to improve consistency in the determination of the accounting acquirer for certain VIE transactions and does not change the accounting for acquisitions of VIEs that are not a business. | January 1, 2027 | We are still assessing the impact of this ASU. |
ASU 2025-04 - Compensation —Stock Compensation (Topic 718) and Revenue from Contracts with Customers (Topic 606) Clarifications to Share-Based Consideration Payable to a Customer | The amendments clarify the accounting for share- based payment awards granted by an entity as consideration payable to a customer. The ASU revises certain definitions and guidance within Topics 606 and 718, including clarifying the definition of a performance condition and eliminating the policy election related to forfeitures for service conditions associated with share-based consideration payable to a customer. The amendments are intended to reduce diversity in practice and improve consistency in application. | January 1, 2027 | We are still assessing the impact of this ASU. |
ASU 2025-06 - Intangibles, Goodwill and Other Internal- Use Software | The amendments modernize the guidance for internal-use software by removing references to development stages and clarifying when capitalization of software development costs should begin. Capitalization commences once management authorizes and commits to funding a software project and it is probable that the project will be completed and used as intended. The ASU also introduces guidance for assessing the probable-to- complete threshold, including consideration of development uncertainty. | January 1, 2027 | We are still assessing the impact of this ASU. |
The FASB have issued further updates not included above. We do not currently expect any of these updates to have a material
impact on our Consolidated Financial Statements and related disclosures either on transition or in future periods.
26
4.SEGMENT INFORMATION
We have identified two distinct services that constitute our reportable segments: “FLNG” and “Corporate and other”. Our key
performance indicator is Adjusted EBITDA.
(in thousands of $) | 2026 | 2025 |
Net income | ||
Income tax expense (1) | ||
Income before income tax | ||
Depreciation and amortization | ||
Unrealized loss on oil and gas derivative instruments (note 7) | ||
Other non-operating income (2) | ( | ( |
Interest income | ( | ( |
Interest expense, net (3) | ||
(Gains)/losses on derivative instruments, net (note 8) | ( | |
Other financial items, net (note 8) | ||
Net income from equity method investments (note 13) | ( | ( |
Sales-type lease receivable in excess of interest income (12) | ||
Adjusted EBITDA |
(1) Includes taxes relating to FLNG Gimi's operations under the lease and operate agreement (“LOA”) which are reimbursed by bp, with the
corresponding income recognized within sales-type lease revenue and vessel management fees.
(2) Includes gains/(losses) on disposals of investments and other non-operating items. During the nine months ended September 30, 2026, this
primarily comprised a $3.1 million gain on the disposal of our 2.69 % interest in OLT Offshore LNG Toscana S.p.A., which had been fully
impaired in 2019, partially offset by a $2.7 million loss on the disposal of our investment in Gaslin S.r.l.. During the nine months ended
September 30, 2025, this primarily comprised a $30.0 million gain on the deemed sale of FLNG Gimi upon commencement of the 20-year
lease with bp (note 5).
(3) Includes interest incurred on the Company's debt facilities, including the amortization of deferred financing costs. Borrowing costs
directly attributable to qualifying assets are capitalized, including the FLNG Esperanza conversion project, FLNG four following the
execution of EPC in August 2026 and our equity method investments in SESA and SMP, which met the criteria for capitalization during the
nine months ended September 30, 2026 (notes 13 and 15).
Our two distinct reportable segments are as follows:
•FLNG – includes the operations of our FLNG vessels and projects. We convert LNG carriers into FLNG vessels or build
new FLNG vessels and subsequently contract them to third parties. We currently have one operational FLNG, FLNG
Gimi, and one FLNG vessel under refurbishment, FLNG Hilli. We also have two FLNGs undergoing conversion, FLNG
Esperanza and FLNG four (note 12).
•Corporate and other – includes our legacy shipping segment activities, vessel management, floating storage and
regasification unit (“FSRU”) services for third parties, LNG carrier transportation operations, administrative services to
affiliates and third parties, our corporate overhead costs and other strategic investments.
27
Nine months ended September 30, 2026 | |||||
(in thousands of $) | FLNG | Corporate and other (4) | Total Segment Reporting | Elimination | Consolidated Reporting |
Statement of Operations: | |||||
Liquefaction services revenue | |||||
Sales-type lease revenue | |||||
Vessel management fees and other revenues | |||||
Total operating revenues | |||||
Vessel operating expenses (5)(6) | ( | ( | ( | ( | |
Administrative expenses (7) (8) | ( | ( | ( | ( | |
Project development expenses (9) | ( | ( | ( | ( | |
Realized gain on oil and gas derivative instruments, net (note 7) | |||||
Other operating income/(loss) (10) (11) | ( | ||||
Sales-type lease receivable in excess of interest income (12) | ( | ||||
Adjusted EBITDA | ( | ( | |||
Net (loss)/income from equity method investments (note 13) | ( | ||||
Balance Sheet: | September 30, 2026 | ||
(in thousands of $) | FLNG | Corporate and other (4) | Total assets |
Total assets | |||
Equity method investments (note 13) | |||
Nine months ended September 30, 2025 | |||||
(in thousands of $) | FLNG | Corporate and other (4) | Total Segment Reporting | Elimination | Consolidated Reporting |
Statement of Operations: | |||||
Liquefaction services revenue | |||||
Sales-type lease revenue | |||||
Vessel management fees and other revenues | |||||
Time and voyage charter revenues | |||||
Total operating revenues (note 5) | |||||
Vessel operating expenses (5) | ( | ( | ( | ( | |
Administrative expenses (7) | ( | ( | ( | ( | |
Project development expenses (9) | ( | ( | ( | ( | |
Realized gain on oil and gas derivative instruments, net (note 7) | |||||
Other operating loss (11) (13) | ( | ( | ( | ||
Sales-type lease receivable in excess of interest income (12) | ( | ||||
Adjusted EBITDA | ( | ( | |||
Net (loss)/income from equity method investments (note 13) | ( | ||||
28
Balance Sheet: | December 31, 2025 | ||
(in thousands of $) | FLNG | Corporate and other (4) | Total assets |
Total assets | |||
Equity method investments (note 13) | |||
(4) Includes inter-segment eliminations arising from vessel and administrative management fees revenue between segments.
(5) Includes crew, repairs and maintenance, spares, stores and other consumables, and insurance costs. In relation to our vessel operation and
maintenance services, we may arrange for goods or services to be provided on behalf of the customer. Amounts relating to these arrangements
are presented on a net basis.
(6) In connection with the conclusion of the LTA with Perenco and FLNG Hilli’s subsequent departure from Cameroon, we recognized
$5.4 million of employee-related termination benefits under local labor laws during the nine months ended September 30, 2026.
(7) Includes employee compensation and benefits, audit, accounting and tax advisory fees, legal fees and other corporate costs, which are
managed centrally under our “Corporate and other” segment.
(8) In March 2026, we completed the buy-out of our UK defined benefit pension scheme through the purchase of individual annuity contracts,
resulting in a settlement of the pension scheme obligations and the recognition of a settlement loss of $2.4 million in “Administrative
expenses”.
(9) Includes costs incurred for early-stage development activities, feasibility studies, and business development efforts for projects not yet at
Final Investment Decision (“FID”) stage.
(10) Includes (i) $4.8 million settlement of outstanding pre-COD matters with bp, comprising $4.0 million reimbursement for gas generator,
capital spares and consumables procured during the conversion and commissioning of the FLNG Gimi in connection with the LOA and
$0.8 million reimbursement following the final reconciliation of pre-COD fuel purchases for FLNG Gimi; (ii) $2.5 million reimbursement
from SESA for costs previously incurred by Golar; and (iii) $1.6 million reimbursement from Perenco following the final reconciliation of
heel LNG upon the completion of FLNG Hilli’s LTA.
(11) As of September 30, 2026 and 2025, management evaluated the expected credit losses related to its shareholder loan to Higas Holdings
Limited (“Higas”) (note 20). Based on our assessment of Higas’ financial condition and the continued uncertainty regarding Higas’ potential
inclusion to Sardinia’s regulatory framework as of the reporting date, allowance for credit losses of $0.6 million and $1.5 million were
presented within “Other operating loss” in the unaudited consolidated statements of operations for the nine months ended September 30, 2026
and 2025, respectively.
(12) Amounts recognized as revenue represents the interest income component earned, while the principal amortization is treated as a
reduction to the lease receivable balance presented in “Net investment in sales-type lease” in the unaudited consolidated balance sheet.
“Sales-type lease receivable in excess of interest income” represents the lease receivable principal amortization component of the total
amounts invoiced under the FLNG Gimi sales-type lease which commenced in June 2025. We included the total invoiced amounts comprising
both interest income and principal repayment in our FLNG Adjusted EBITDA to reflect the total cash earnings and economic performance of
the FLNG Gimi (note 5.2). This amount is eliminated from the unaudited consolidated statements of operations in accordance with U.S.
GAAP.
(13) In March 2025, we completed the sale of our remaining LNG carrier, the Golar Arctic including its unused fuel onboard for a net
consideration of $24.8 million resulting in a loss on disposal of $0.5 million, which was presented within “Other operating loss” in the
5.REVENUE
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Liquefaction services revenue (note 5.1) | ||
Vessel management fees and other revenues (note 5.1) | ||
Sales-type lease revenue (note 5.2) | ||
Time and voyage charter revenues (note 5.2) | ||
Total operating revenues | ||
29
5.1 Revenue from contracts with customers
ended September 30, 2026 and 2025. Revenue from liquefaction services provided under the FLNG Hilli LTA which
completed in July 2026, is included within the “FLNG” segment. Vessel management fees and other revenues are included
within both the “FLNG” and “Corporate and other” segments, depending on the nature of the service provided.
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Base tolling fee (1) | ||
Amortization of Day 1 gains (2) | ||
Incremental base tolling fee (3) | ||
Amortization of deferred commissioning period revenue (4) | ||
Net variable consideration (5) | ||
Other | ( | ( |
Liquefaction services revenue | ||
FLNG Operation and Maintenance Agreement (“O&M”) service revenue (6) | ||
Management fees revenue (7) | ||
Amortization of deferred pre-COD cash flows (8) | ||
Other (9) | ( | |
Vessel management fees and other revenues | ||
(1) The LTA entered into in connection with the FLNG Hilli billed at a base rate when the oil prices were at or below $60 per barrel, with an
increased rate when prices exceed $60 per barrel. The oil price above the base rate was recognized as a derivative and included in “Realized
and unrealized (loss)/gain on oil and gas derivative instruments” in the unaudited consolidated statements of operations (note 7).
(2) Day 1 gains result from amount established on the initial recognition of the FLNG Hilli’s oil derivative instrument embedded in the LTA
and the FLNG Hilli’s gas derivative instruments pursuant to the third amendment to the LTA (“LTA Amendment 3”) (note 17). These
amounts were deferred on initial recognition and amortized evenly over the contract term.
(3) In July 2021, we entered into LTA Amendment 3 to increase the FLNG Hilli's annual contracted capacity by 0.2 million tonnes for 2022.
In July 2022, Perenco Cameroon S.A. (“Perenco”) and Société Nationale des Hydrocarbures (“SNH”), (together, the “Customer”) exercised
their option for an additional 0.2 million tonnes (out of 0.4 million tonnes) from January 2023 until completion of the LTA in July 2026,
increasing the annual base capacity to 1.4 million tonnes. The tolling fee was linked to Dutch Title Transfer Facility (“TTF”) and the Euro/
U.S. Dollar foreign exchange movements. The contractual floor rate was recognized in “Liquefaction services revenue” and the tolling fee
above the contractual floor rate was recognized as a derivative in “Realized and unrealized (loss)/gain on oil and gas derivative instruments,”
in the unaudited consolidated statements of operations (note 7).
(4) Customer billing during the commissioning period of the FLNG Hilli, prior to vessel acceptance and commencement of the LTA was
deferred (note 17) and recognized evenly until completion of the LTA in July 2026.
(5) Following the completion of FLNG Hilli's eight-year LTA in July 2026, net variable consideration of $4.4 million was invoiced during the
nine months ended September 30, 2026, relating to 2026 production reconciliation.
(6) The FLNG Gimi's LOA contains both a lease component (the use of the FLNG Gimi) and a non-lease component (the O&M services).
The total contract consideration is allocated between the lease and non-lease components based on their relative stand-alone selling prices
determined at commencement date of the LOA. The non-lease component is recognized over time as the O&M services are performed, based
on the pattern of services provided during each billing period in accordance with the LOA.
(7) Comprised of revenue earned from various ship management, administrative and vessel O&M services we provide to external customers,
including services under the FSRU LNG Croatia agreement, which terminated in December 2025, and the FSRU Italis LNG agreement,
which ceased following the sale of our entire shareholding in Gaslin in April 2026.
(8) In August 2024, we and bp agreed to a series of pre-COD payments to address project delays and align on commissioning milestones.
Following COD in June 2025, the non-lease component of the pre-COD cash flows amounting to $36.8 million was deferred and classified
within “Other current liabilities” and “Other non-current liabilities” on our unaudited consolidated balance sheet (notes 17 and 18) which will
be recognized as revenue evenly over the duration of the LOA consistent with the timing of the related O&M services.
30
(9) “Other” consists primarily of (i) non-lease component of reimbursable taxes by lessee under the LOA (ii) accrued demurrage costs
pursuant to FLNG Gimi's LOA and (iii) revenue earned under the mooring system contract supervision (“MSCSA”) agreement with SESA for
supervision and technical oversight services in connection with its infrastructure project (note 20).
Contract assets and liabilities
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Contract assets | ||
Current contract liabilities | ( | ( |
Non-current contract liabilities | ( | ( |
Total contract liabilities (1) | ( | ( |
The movement of our contract liabilities are as follows:
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Opening contract liability balance | ( | ( |
Deferral of revenue | ( | |
Recognition of unearned revenue | ||
Closing contract liability balance (1) | ( | ( |
(1) As of September 30, 2026, the closing contract liability balance was comprised of:
•deferred pre-COD cash flows in relation to the FLNG Gimi LOA amounting to $34.5 million (December 31, 2025: $35.9 million)
(note 17 and 18). We expect to recognize vessel management fee and other revenue evenly over the remaining LOA contract term
of 18.7 years; and
•deferred commissioning revenue in relation to the FLNG Hilli of $nil following the completion of the LTA in July 2026 (December
31, 2025: $2.2 million) (note 17).
5.2 Lease revenues
Our lease revenue includes income from both sales-type leases and operating leases based on the classification of each
arrangement at lease commencement. Sales-type lease revenue relates to the FLNG Gimi, which achieved COD in June 2025.
Operating lease revenue relates to our legacy time and voyage charter arrangements and are recognized on a straight-line basis
over the lease term or as the service is rendered, depending on the specific terms of each charter.
Sales-type lease revenue is included under our “FLNG” segment while time and voyage charter revenues are under our
“Corporate and other” segment.
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Sales-type lease revenue (1) | ||
Variable sales-type lease revenue (2) | ||
Accretion of unguaranteed residual value (3) | ||
Other (4) | ||
Sales-type lease revenue | ||
Operating lease revenue | ||
Variable operating lease revenue | ||
Time and voyage charter revenues | ||
(1) Relates to the interest income recognized on the net investment in the sales-type lease for FLNG Gimi, calculated using the rate implicit in
the lease.
31
(2) Comprised of variable consideration of the lease including overproduction, underutilization, and other operational adjustments invoiced
during the period. Variable lease revenue may fluctuate period to period depending on vessel availability and performance under the LOA.
(3) Relates to the periodic accretion in the present value of the unguaranteed residual value of FLNG Gimi, recognized over the lease term
using the effective interest method.
(4) “Other” consists primarily of (i) taxes that are reimbursable by the lessee under the LOA and (ii) accrued demurrage costs.
Maturity analysis of the Net investment in sales-type lease
The minimum future revenues included below are based on the fixed components and do not include variable or contingent
revenue.
Pursuant to the LOA, bp holds certain termination rights that are subject to defined conditions and are not unilateral. Based on
management’s assessment of the contractual framework and current commercial and operational circumstances, it is not
reasonably expected that these termination rights will be exercised. Accordingly, the lease term has been determined to be 20
years, and the maturity analysis has been prepared on that basis.
(in thousands of $) | |
2026 (1) | |
2027 | |
2028 | |
2029 | |
2030 | |
2031 and thereafter | |
Total minimum lease receivable | |
Unguaranteed residual value | |
Gross investment in sales-type lease | |
Less: unearned interest income | ( |
Net investment in sales-type lease as of September 30, 2026 (2) | |
Less: current portion of net investment in sales-type lease | ( |
Non-current portion of net investment in sales-type lease |
(1) For the three months ending December 31, 2026.
(2) Our net investment in sales-type lease includes an unguaranteed residual value which exposes us to residual value risk at the end of the
lease term. We manage this risk through periodic monitoring of the underlying asset’s estimated market value, including reference to
independent broker valuations. As of September 30, 2026, management determined that the fair value of the underlying asset exceeds the net
investment in sales-type lease related to FLNG Gimi, therefore, the impact of any expected credit loss is not significant. In addition, the vessel
is covered by customary insurance which further mitigates our exposure to residual asset risk.
6.EARNINGS PER SHARE
Basic earnings per share “EPS” is calculated with reference to the weighted average number of common shares outstanding
during the period.
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Net income attributable to stockholders of Golar LNG Limited - basic and diluted | ||
32
The components of the denominator for the calculation of basic and diluted EPS are as follows:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Basic: | ||
Weighted average number of common shares outstanding | ||
Dilutive: | ||
Dilutive impact of share options and RSUs | ||
Dilutive impact of 2025 Convertible Bonds (1) | ||
Weighted average number of common shares outstanding | ||
EPS are as follows:
Nine months ended September 30, | ||
2026 | 2025 | |
Basic earnings per share ($) | $ | $ |
Diluted earnings per share ($) | $ | $ |
(1) On June 30, 2025, we issued $575 million of 2.75 % convertible senior unsecured notes (the “2025 Convertible Bonds”), maturing
December 15, 2030. The initial conversion rate is 17.3834 common shares per $1,000 principal amount of the bonds, equivalent to conversion
price of approximately $57.53 per common share. The time-weighted potential dilutive impact of the issuance using the if-converted method
7. REALIZED AND UNREALIZED GAIN/(LOSS) ON OIL AND GAS DERIVATIVE INSTRUMENTS
Nine months ended September 30, | ||
2026 | 2025 | |
Realized gain on FLNG Hilli’s oil derivative instrument | ||
Realized gain on FLNG Hilli’s gas derivative instrument | ||
Realized gain on oil and gas derivative instruments | ||
Unrealized gain/(loss) on FLNG Hilli’s oil derivative instrument (note 11) | ( | |
Unrealized loss on FLNG Hilli’s gas derivative instrument (note 11) | ( | ( |
Unrealized loss on oil and gas derivative instruments | ( | ( |
Realized and unrealized gain/(loss) on oil and gas derivative instruments | ( | |
The realized gain/(loss) on oil and gas derivative instruments results from monthly billings above the FLNG Hilli base tolling
fee and the incremental capacity increase pursuant to respective LTA amendments, whereas the unrealized gain/(loss) on oil
and gas derivative instruments results from movements in forecasted oil and natural gas prices and Euro/U.S. Dollar exchange
rates.
As of June 30, 2026, FLNG Hilli had current oil and gas derivative assets of $6.2 million and $1.9 million, respectively.
Following the completion of FLNG Hilli’s LTA in July 2026, these derivative assets were realized by September 30, 2026,
resulting in a reduction in gains recognized in relation to billings.
33
8. GAIN/(LOSS) ON DERIVATIVE INSTRUMENTS AND OTHER FINANCIAL ITEMS, NET
(in thousands of $) | Nine months ended September 30, | |
2026 | 2025 | |
Unrealized MTM adjustment for interest rate swap (“IRS”) derivative | ( | |
Net interest income on undesignated IRS derivative | ||
Gain/(loss) on derivative instrument, net | ( | |
(in thousands of $) | Nine months ended September 30, | |
2026 | 2025 | |
Financing arrangement fees and other related costs | ( | ( |
Foreign exchange loss on operations | ( | ( |
Amortization of debt guarantees | ||
Others | ( | ( |
Other financial items, net | ( | ( |
9. VARIABLE INTEREST ENTITIES (“VIEs”)
9.1 Lessor VIE
As of September 30, 2026 and December 31, 2025, we leased one vessel from a CSSC entity as part of a sale and leaseback
agreement. The CSSC entity is a wholly-owned, special purpose vehicle. We sold our vessel, the FLNG Hilli and then
subsequently leased back the vessel on a bareboat charter. We have an option to repurchase the vessel at a fixed predetermined
amount during its charter period and an obligation to repurchase the vessel at the end of the vessel’s lease period.
lessor VIE as of September 30, 2026, is shown below:
(in thousands of $) | 2026 (1) | 2027 | 2028 | 2029 | 2030 | 2031+ |
Hilli (2) |
(1) For the three months ending December 31, 2026.
(2) The payment obligations above include contractual capital and variable rental payments due under the lease.
September 30, 2026 and December 31, 2025, are as follows:
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Assets | ||
Restricted cash | ||
Liabilities (1) | ||
Accrued expenses | ( | ( |
Other non-current liabilities (note 18) | ( | ( |
Current portion of long-term debt and short-term debt (2) | ( | ( |
(1) The creditors of the lessor VIE have no recourse to the general credit of Golar.
(2) This relates to debt of our lessor entity, net of deferred financing cost (for which legal ownership resides with a financial institution) that
we are required to consolidate into our financial statements as a VIE (note 15).
34
unaudited consolidated statements of cash flows for the nine months ended September 30, 2026 and 2025 are as follows:
Nine months ended September 30, 2026 | ||
(in thousands of $) | 2026 | 2025 |
Statement of operations | ||
Other financial items, net (note 8) | ||
Interest income | ( | ( |
Interest expense | ||
Statement of cash flows | ||
Net debt repayments | ( | ( |
9.2Gimi MS Corporation
Following the closing of the sale of 30 % of the common shares of Gimi MS to First FLNG Holdings (“FFH”) in April 2019, we
determined that (i) Gimi MS is a VIE and (ii) we are the primary beneficiary and retain sole control over the most significant
activities and the greatest exposure to variability in residual returns and expected losses from the FLNG Gimi. Thus, Gimi MS
continues to be consolidated into our financial statements.
Summarized financial information of Gimi MS
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Balance sheet | ||
Current assets | ||
Non-current assets | ||
Current liabilities | ( | ( |
Non-current liabilities | ( | ( |
The most significant impact of Gimi MS VIE’s operations on our unaudited consolidated statements of operations and
unaudited consolidated statements of cash flows for the nine months ended September 30, 2026 and 2025 are as follows:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Statement of cash flows | ||
Additions to asset under development | ||
Net debt repayments | ( | ( |
Proceeds from subscription of equity interest | ||
Cash dividends paid to non-controlling interest (1) | ( | |
(1) During the nine months ended September 30, 2026 and 2025, Gimi MS Corporation paid $73.8 million and nil , respectively, to all its
shareholders.
35
10. RESTRICTED CASH
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Restricted cash in relation to the FLNG Gimi (1) | ||
Restricted cash relating to office lease | ||
Restricted cash held by lessor VIE (2) | ||
Restricted cash relating to the LNG Hrvatska O&M Agreement (3) | ||
Total restricted cash | ||
Less: Amounts included in current restricted cash | ( | ( |
Non-current restricted cash |
(1) The restricted balance relates to amounts held in a debt service reserve account under the $1.2 billion Gimi facility (note 15), which is
required to be maintained throughout the term of the facility.
(2) This is held by lessor VIE that we are required to consolidate (note 9).
(3) In January 2026, performance guarantees under the LNG Hrvatska O&M Agreement were released following the discharge of those
guarantees in connection with the deed of termination, with no further obligations thereafter.
11.OTHER CURRENT ASSETS
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Prepaid expenses | ||
Interest receivable from money market deposits and bank accounts (note 19) | ||
Inventories | ||
Receivable from IRS derivatives (note 19) | ||
Oil derivative instrument (note 7 and 19) (1) | ||
Gas derivative instrument (note 7 and 19) (1) | ||
Other | ||
Other current assets |
(1) As of September 30, 2026, the balances of FLNG Hilli’s oil and gas derivative instruments were fully realized following the completion of
the FLNG Hilli's LTA in July 2026 (December 31, 2025: $3.2 million and $9.5 million, respectively).
36
12.ASSETS UNDER DEVELOPMENT
September 30, 2026 | December 31, 2025 | ||||||
(in thousands of $) | FLNG Esperanza | FLNG four | Total | FLNG Esperanza | FLNG Gimi (1) | Total | |
Opening balance | |||||||
Additions | |||||||
Interest costs capitalized | |||||||
Transferred from vessels and equipment, net and other non- current assets (note 14) | |||||||
Reimbursement of capital spares invoiced to bp at COD | ( | ( | |||||
Derecognition on commencement of sales-type lease (note 5) | ( | ( | |||||
Closing balance | |||||||
(1) FLNG Gimi achieved COD on June 12, 2025, commencing the 20-year LOA with bp. Upon COD, the asset under development was
12.1 FLNG Esperanza
In September 2024, we entered into an EPC agreement with CIMC Raffles for the conversion of FLNG Esperanza with an
annual liquefaction capacity of 3.5 MTPA. In February 2025, Fuji LNG, the donor vessel for the FLNG Esperanza, arrived at
CIMC Raffles' yard for conversion. Concurrently, the net book value of the vessel of $76.3 million previously included within
“Vessels and equipment, net” was reclassified to “Asset under development”.
In September 2024, we issued a $100.0 million letter of credit (“LC”) in favor of B&V with CIMC Raffles. Under the
provisions of the LC, the profile reduces over time to reflect payments made by CIMC Raffles under the EPC agreement. There
is no associated cash collateral, however a 1.5 % upfront fee was paid and a 1.75 % annual margin is payable on the outstanding
balance which expires in January 2028.
The total budget for the FLNG Esperanza conversion is estimated at $2.2 billion, inclusive of the donor vessel, yard
supervision, spares, crew, training, contingencies, initial bunker supply and voyage related costs to deliver the FLNG to its
operational site, excluding financing costs. The FLNG Esperanza is expected to achieve COD in H2 2028.
and $47.7 million are presented within “Trade accounts payable” and “Accrued expenses”, respectively, in the unaudited
consolidated balance sheets:
(in thousands of $) | |
2026 (1) | |
2027 | |
2028 | |
2029 | |
Total |
(1) For the three months ending December 31, 2026.
37
12.2 FLNG four
In August 2026, we entered into an EPC agreement with CIMC Raffles for the conversion of our second MKII-design FLNG
with an annual liquefaction capacity of 3.5 MTPA. Consequently, the execution of the binding EPC reinforces the likelihood of
the FLNG four conversion to be virtually certain to proceed and accordingly, $14.5 million of long-lead equipment, was
reclassified from “Other non-current assets” to “Assets under development” in the unaudited consolidated balance sheet.
The total estimated budget for the FLNG four conversion is $2.45 billion, inclusive of the donor vessel, yard supervision,
spares, crew, training, contingencies, initial bunker supply and voyage related costs to deliver the FLNG to its operational site,
excluding financing costs. The FLNG four redelivery is expected by the end of 2029.
and $99.9 million are presented within “Trade accounts payable” and “Accrued expenses”, respectively, in the unaudited
consolidated balance sheet:
(in thousands of $) | |
2026 (1) | |
2027 | |
2028 | |
2029 | |
2030 | |
2031 | |
Total |
(1) For the three months ending December 31, 2026.
13. EQUITY METHOD INVESTMENTS
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Gain on disposal | ||
Share of net loss of equity method investments | ( | ( |
Net income from equity method investments | ||
The carrying values of our equity method investments as of September 30, 2026 and December 31, 2025 are as follows:
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Southern Energy S.A. (“SESA”) (1) | ||
Egyptian Company for Gas Services S.A.E (“ECGS”) | ||
San Matías Pipeline S.A. (“SMP”) (2) | ||
Aqualung Carbon Capture AS (“Aqualung”) | ||
Logística e Distribuição de Gás S.A. (“LOGAS”) (3) | ||
Others | ||
Equity method investments |
(1) During the nine months ended September 30, 2026, we contributed an additional $49.4 million of capital to SESA, bringing our total gross
capital contribution to $79.5 million, representing a 10 % equity interest. As SESA continued its activities necessary to bring its assets to the
condition required for their planned principal operations, SESA was considered a qualifying asset, accordingly, $2.8 million of interest costs
was capitalized during the nine months ended September 30, 2026 and included in the carrying amount of our equity method investment in
SESA.
(2) During the nine months ended September 30, 2026, we contributed $5.1 million of capital to SMP, representing 10 % equity interest. As
SMP continued its activities necessary to bring its assets to the condition required for their planned principal operations, SMP was considered
a qualifying asset, accordingly, $40.8 thousand of interest costs was capitalized during the nine months ended September 30, 2026 and
included in the carrying amount of our equity method investment in SMP.
38
(3) In April 2026, Macaw Energies Brasil Serviços de Gás Natural Ltda. completed the sale of its entire 58 % shareholding in LOGAS to J&F
S.A. for a consideration of BRL 55.0 million ($10.7 million), and recognized $4.6 million gain on the disposal presented in “Net income from
equity method investments” in the consolidated statements of operations. Following the sale, we no longer have significant influence over
LOGAS and have ceased accounting for the investment under equity method.
14. OTHER NON-CURRENT ASSETS
(in thousands of $) | September 30, 2026 | December 31, 2025 |
MTM asset on IRS derivatives (note 19) | ||
Pre-operational assets (1), (2), (3) | ||
Operating lease right-of-use-assets (4) | ||
Other (5) | ||
Other non-current assets |
(1) As of September 30, 2026, “Pre-operational assets” comprised of:
•$8.3 million relating to Macaw’s flare-to-gas mobile kit project, including engineering and other directly attributable costs
(December 31, 2025: $8.3 million); and
•$1.0 million relating to securing a shipyard slot for potential additional MKI- or MKII-design FLNG.
(2) Following the completion of FLNG Hilli's LTA in July and its entry into Seatrium's Singapore shipyard, $119.6 million (December 31,
2025: $38.5 million) of shipyard and engineering costs, including long-lead items, incurred in preparation for her 20-year bareboat charter
agreement with SESA, was reclassified cumulatively from “Other non-current assets” to “Vessel and equipment, net” in the unaudited
consolidated balance sheet as of September 30, 2026.
(3) In June 2026, the Board of Directors approved up to $22.0 million for FLNG four long lead equipment. In August 2026, the execution of
the binding EPC reinforces the likelihood of the FLNG four conversion to be virtually certain to proceed and accordingly, $14.5 million of
long-lead equipment was reclassified from “Other non-current assets” to “Assets under development” in the unaudited consolidated balance
sheet.
(4) Relates to our office premises leases in London and Oslo and warehouse lease in Nouakchott.
(5) Included in “Other” as of September 30, 2026 are:
•$34.4 million of capitalized initial direct costs in connection with the FLNG Hilli and FLNG Esperanza bareboat charter
agreements with SESA, of which, $26.6 million relates to the settlement agreement described below, with the remaining
$7.8 million comprising initial direct costs related to the redeployment of FLNG Hilli.
In January 2026, we entered into a settlement agreement relating to success-based fees payable to third-party consultants in
connection with our Latin America FLNG business development activities. The settlement agreement became effective upon
satisfaction of the related conditions precedent in April 2026. The settlement consideration consisted of a $10.0 million cash
payment and 750,000 RSUs, of which 300,000 RSUs amounting to $16.6 million vested upon grant. The final vesting milestone for
the remaining RSUs is the COD for the two FLNGs to operate in Argentina, thereby aligning the consultants’ interests with our
objective of achieving COD on schedule;
•$14.0 million of aggregate financing costs in connection with FLNG Esperanza revolving credit facility and 2026 senior unsecured
notes offering. These costs will be reclassified to deferred financing costs upon the revolving credit facility becoming available and
completion of the 2026 senior unsecured notes offering, both in October 2026 (note 15 and 22);
•$5.0 million investment in pooled investment fund entity, measured at cost; and
•$4.8 million prepaid insurance relating to FLNG Esperanza (December 31, 2025: $2.4 million).
39
15.DEBT
(in thousands of $) | September 30, 2026 | December 31, 2025 |
FLNG Gimi facility | ( | ( |
2025 Convertible Bonds | ( | ( |
2025 Senior Unsecured Notes | ( | ( |
2024 Unsecured Bonds | ( | ( |
Subtotal (excluding lessor VIE debt) | ( | ( |
CSSC VIE debt - FLNG Hilli facility (1) | ( | ( |
Total debt (gross) | ( | ( |
Less: Deferred financing costs | ||
Total debt, net of deferred financing costs | ( | ( |
At September 30, 2026, our debt, net of deferred financing costs, is broken down as follows:
Golar debt | VIE debt | Total debt | |
(in thousands of $) | |||
Current portion of long-term debt and short-term debt | ( | ( | ( |
Long-term debt | ( | ( | |
Total | ( | ( | ( |
(1) This relates to debt of our lessor VIE (for which legal ownership resides with a financial institution) that we are required to consolidate
into our financial statements (note 9). As of September 30, 2026, Golar's underlying contractual debt under the bareboat charter with the
lessor VIE inclusive of our repurchase obligation, which is eliminated on consolidation, is $482.3 million.
FLNG Esperanza RCF
In July 2026, we entered into a $600 million senior secured revolving credit facility with a syndicate of banks in connection
with FLNG Esperanza. The facility has an 18-month tenor commencing October 1, 2026. Amounts drawn under the facility
bear interest at three-month SOFR plus a margin of 3.00 % per annum. During the availability period, a commitment fee is
payable on the undrawn balance at a rate equal to 35 % of the applicable margin, or 1.05 % per annum. As of September 30,
16. ACCRUED EXPENSES
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Vessel related (1) | ( | ( |
Finance related (2) | ( | ( |
Administrative related (3) | ( | ( |
Accrued expenses | ( | ( |
(1) “Vessel related” accrued expenses is comprised of engineering and yard-related conversion costs and vessel operating expenses such as
crew wages, supplies, routine repairs, maintenance, lubricating oils and insurance. As of September 30, 2026, “Vessel related” accrued
expenses comprised $47.7 million related to FLNG Esperanza conversion, $99.9 million related to the FLNG four conversion, $12.1 million
related to FLNG Hilli redeployment, and $nil related to carry-over FLNG Gimi commissioning works (December 31, 2025: $12.3 million,
$nil , $nil and $5.8 million, respectively).
(2) “Finance related” accrued expenses comprised of accrued interest and financing costs in relation to our debt facilities (note 15).
(3) “Administrative related” accrued expenses comprised of general overhead, including personnel costs, legal and professional fees, costs
associated with project development, property costs and other office and general expenses.
40
17. OTHER CURRENT LIABILITIES
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Asset retirement obligation (“ARO”) (1) | ( | ( |
Current portion of operating lease liability | ( | ( |
Current portion of deferred pre-COD cash flows (2) | ( | ( |
Day 1 gain deferred revenue - current portion (3) | ( | |
Deferred revenue (4) | ( | |
Other | ( | ( |
Other current liabilities | ( | ( |
(1) In connection with FLNG Hilli’s LTA completion in July 2026, the ARO was remeasured in January 2026 to reflect current cost estimates
and the revised timing of ARO settlement. Consequently, the ARO liability increased by $6.6 million to $13.6 million (December 31, 2025:
$6.8 million) with a corresponding increase to mooring equipment in “Vessels and equipment, net” in our unaudited consolidated balance
sheet. Given the short period until settlement, the impact of discounting was assessed to be immaterial and, accordingly, no discounting was
applied to the revised cash flows. During the nine months ended September 30, 2026, we recognized $7.6 million of decommissioning costs
against the ARO liability and recognized $6.6 million of additional depreciation. The related mooring equipment was fully depreciated and
derecognized upon completion of the LTA.
(2) In August 2024, we and bp agreed to a series of pre-COD payments to address project delays and align on commissioning milestones
which was allocated between lease and non-lease components on commencement of the sales type lease accounting of the LOA. As of
September 30, 2026, the deferred non-lease component amounted to $34.5 million (December 31, 2025: $35.8 million), comprising
$1.8 million in “Other current liabilities” and $32.7 million (December 31, 2025: $34.0 million) in “Other non-current liabilities” (note 18).
(3) Current portion of Day 1 gain deferred on initial recognition of FLNG Hilli's oil and gas derivative instruments embedded in the LTA and
the FLNG Hilli's gas derivative instruments pursuant to LTA Amendment 3. As of September 30, 2026, the current portion of the deferred
revenue relating to FLNG Hilli’s oil and gas derivative instruments were fully realized following the completion of the FLNG Hilli's LTA in
July 2026 (December 31, 2025: $5.3 million and $1.5 million, respectively).
(4) Customer billing during the commissioning period of FLNG Hilli, prior to vessel acceptance and commencement of the LTA, were
deferred and recognized evenly over the contract term. As of September 30, 2026, the remaining deferred revenue balance was $nil
(December 31, 2025: $2.2 million) following the completion of the FLNG Hilli's LTA in July 2026.
18. OTHER NON-CURRENT LIABILITIES
(in thousands of $) | September 30, 2026 | December 31, 2025 |
VIE dividend payable (1) | ( | ( |
Deferred pre-COD cash flows (note 17) | ( | ( |
Pension obligations | ( | ( |
Non-current portion of operating lease liabilities | ( | ( |
Other | ( | ( |
Other non-current liabilities | ( | ( |
(1) In December 2024, the lessor VIE declared a dividend of $184.0 million to a CSSC entity. The unpaid dividend is unsecured, interest free
and due for payment in 2033. Given we are the primary beneficiary of the VIE, this amount has been fully consolidated into our financial
19. FINANCIAL INSTRUMENTS
Fair values
We recognize our fair value estimates using a fair value hierarchy based on the inputs used to measure fair value. The fair value
hierarchy has three levels based on reliability of inputs used to determine fair value as follows:
Level 1: Quoted market prices in active markets for identical assets and liabilities.
Level 2: Observable market-based inputs or unobservable inputs that are corroborated by market data.
41
Level 3: Unobservable inputs that are not corroborated by market data.
The Company's maximum exposure to credit risk is represented by the carrying amounts of the financial assets included in the
financial instruments presented below.
follows:
September 30, 2026 | December 31, 2025 | ||||
(in thousands of $) | Fair value hierarchy | Carrying value | Fair value | Carrying value | Fair value |
Non-Derivatives: | |||||
Cash and cash equivalents (1) (2) | Level 1 | ||||
Restricted cash (1) (3) | Level 1 | ||||
Trade accounts receivable and accrued income (3) (4) | Level 1 | ||||
Interest receivable from money-market deposits and bank accounts (3) | Level 1 | ||||
Receivable from IRS derivatives (3) | Level 1 | ||||
Trade accounts payables (3) (5) | Level 1 | ( | ( | ( | ( |
Current portion of long-term debt and short-term debt (3) (6) (7) | Level 2 | ( | ( | ( | ( |
Long-term debt (6) (7) | Level 2 | ( | ( | ( | ( |
Long-term debt - 2024 Unsecured Bonds (6) (8) | Level 1 | ( | ( | ( | ( |
Long-term debt - 2025 Senior Unsecured Notes (6) (8) | Level 1 | ( | ( | ( | ( |
Long-term debt - 2025 Convertible Bonds (6) (9) (10) | Level 2 | ( | ( | ( | ( |
Derivatives: | |||||
Oil and gas derivative instruments (11) | Level 2 | ||||
Asset on IRS derivatives (12) | Level 2 | ||||
(1) These instruments carrying value are highly liquid and deemed reasonable estimates of fair value.
(2) Included within cash and cash equivalents of $672.3 million and $1,151.2 million are $535.5 million and $920.5 million held in short-term
money-market deposits as of September 30, 2026 and December 31, 2025, respectively. During the nine months ended September 30, 2026
and 2025, we earned interest income on short-term deposits of $26.9 million and $21.8 million, respectively.
(3) These instruments are considered to be equal to their estimated fair value because of their near term maturity.
(4) As of September 30, 2026 and December 31, 2025, trade receivables and accrued income totaled to $54.9 million and $35.5 million,
respectively, primarily relates to amounts due from bp under the Gimi LOA. bp is a publicly listed, investment-grade counterparty with no
prior history of default. Accordingly, we consider the credit risk associated with this balance to be remote as of September 30, 2026.
(5) As of September 30, 2026, trade accounts payables primarily comprised of amounts payable related to FLNG four conversion, FLNG
Esperanza conversion, FLNG Hilli's redeployment and operations and FLNG Gimi's carry-over commissioning works of $144.2 million,
$127.4 million, $15.1 million and $nil , respectively (December 31, 2025: $nil , $91.0 million, $14.1 million and $5.0 million, respectively).
(6) Our debt obligations are recorded at amortized cost. The amounts presented in the table above are gross of the deferred financing costs of
$39.9 million and $47.0 million at September 30, 2026 and December 31, 2025, respectively (note 15).
(7) The estimated fair values for both the floating long-term debt and short-term debt are considered to be equal to the carrying value since
they bear variable interest rates, which are adjusted on a quarterly basis.
(8) The estimated fair values of our 2024 Unsecured Bonds and 2025 Senior Unsecured Notes are based on their quoted market prices as of
the balance sheet date (note 15).
(9) The estimated fair value of our 2025 Convertible Bonds reflects observable market inputs and is classified as Level 2 in the fair value
hierarchy (note 15).
(10) Interest expense related to the 2025 Convertible Bonds for the nine months ended September 30, 2026, comprised contractual interest
and amortization of deferred financing costs of $12.0 million and $1.6 million, respectively (September 30, 2025: $4.1 million and
$0.6 million, respectively).
42
(11) The fair value of the oil and gas derivative instruments, which are presented on a gross basis (none of which have been designated as
hedges), was determined using the estimated discounted cash flows of the additional payments due to us as a result of oil and gas prices
moving above the contractual floor price over the remaining term of the LTA. Significant inputs used in the valuation of the oil and gas
derivative instruments included the Euro/U.S. Dollar exchange rates based on the forex forward curve for the gas derivative instrument and
management’s estimate of an appropriate discount rate and the length of time necessary to blend the long-term and short-term oil and gas
prices obtained from quoted prices in active markets. Following the expiry of the FLNG Hilli LTA in July 2026, the oil and gas derivative
instruments were realized. Cash flows arising from these derivative instruments are presented within “operating activities” in the condensed
consolidated statements of cash flows.
(12) The fair value of certain derivative instruments, which are presented on a gross basis (none of which have been designated as hedges), is
the estimated amount that we would receive or pay to terminate the agreements at the balance sheet date, taking into account current interest
rates, foreign exchange rates, closing quoted market prices and our creditworthiness and that of our counterparties. The credit exposure of
certain derivative instruments is represented by the fair value of contracts with a positive value at the end of each period, reduced by the
effects of master netting arrangements. The cash flows in relation to the settlement of these derivative instruments are presented within
“operating activities” in the condensed consolidated statements of cash flows.
(13) The following methods and assumptions were used to estimate the fair value of our other classes of financial instruments:
•the carrying values of loan receivables and working capital facilities approximate fair values because of the near-term maturity of
these instruments (notes 11, 17 and 20). These instruments are classified within Level 1 of the fair value hierarchy.
in exchange for SOFR as summarized below:
Instrument | Notional value (in thousands of $) | Maturity date | Fixed interest rates |
Interest rate swaps: | |||
Receiving floating, pay fixed | November 2032 |
20.RELATED PARTY TRANSACTIONS
a) Transactions with Perenco:
Perenco has been considered a related party since June 2025, when Naria Inc., a Perenco-affiliated entity and our largest
shareholder, met the definition of a principal owner. Accordingly, outstanding balances with Perenco are presented as
“Amounts due from/to related parties”. As of September 30, 2026, Naria Inc. held beneficial ownership of 10.07 %.
contractual arrangements with Perenco. Amounts for the nine months ended September 30, 2025 have been prorated from when
Perenco became a related party. The amounts recognized for the nine months ended September 30, 2026 and 2025 consists of
the following:
Nine months ended September 30, | ||
(in thousands of $) | 2026 | 2025 |
Liquefaction services (1) | ||
Realized gain on oil and gas derivative instruments (2) | ||
Other operating income (3) | ||
Vessel operating expenses (4) | ( | ( |
Total | ||
(1) Liquefaction services – This relates to services invoiced under the LTA, including base tolling fee, incremental base tolling fee and net
variable consideration (note 5).
(2) Realized gain on oil and gas derivative instruments - This relates to the commodity linked earnings under the LTA (note 7).
(3) Other operating income/(loss) - This relates to reimbursement from Perenco following the final reconciliation of heel LNG upon the
completion of FLNG Hilli's LTA.
43
(4) Vessel operating expenses – This relates to costs incurred under the tug sharing agreement for a chartered tug provided by Perenco to
support our offshore operations in Cameroon, including the transportation of personnel and equipment. The tug is shared between the parties
subject to operational requirements. These costs are presented within “Vessel operating expenses” in the unaudited consolidated statements of
operations.
During the nine months ended September 30, 2026, we incurred $0.7 million in connection with the decommissioning of FLNG Hilli’s
mooring in Cameroon, which reduced the ARO liability (note 17) and $0.7 million of fuel and vessel hire costs in connection with the
mobilization of FLNG Hilli for its redeployment refurbishment project in preparation for her 20-year bareboat charter agreement with SESA,
which were capitalized within “Vessels and equipment, net.”
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Balance due from Perenco | ||
Balance due to Perenco | ( | ( |
b) Transactions with existing related parties:
(in thousands of $) | September 30, 2026 | December 31, 2025 |
SESA (1) | ||
Higas (2) |
(1) SESA – In February 2026, we entered into a credit agreement under which we agreed to provide SESA, as borrower, with a credit facility
of up to $5.6 million, which was fully drawn as of September 30, 2026. Amounts drawn bear interest at Term SOFR plus a margin of 3.875 %,
payable semi-annually. The loan matures on April 15, 2029, with principal repayable in two equal semi-annual installments. Interest income
for the nine months ended September 30, 2026 was $0.2 million, compared with $nil for the nine months ended September 30, 2025.
During the nine months ended September 30, 2026, $4.1 million was invoiced for cost incurred by Golar in relation to SESA's infrastructure
project, of which $2.5 million was presented within “Other operating income/(loss)” and $1.6 million within “Vessel operating expenses” in
the unaudited consolidated statements of operations. Additionally, we invoiced $0.6 million for supervision and technical oversight services
under the MSCSA during the nine months ended September 30, 2026, which was presented within “Vessel management fees and other
revenues” in the unaudited consolidated statements of operations.
(2) Higas – Amounts due from Higas consist of outstanding principal under a revolving shareholder loan facility. In June 2026, the revolving
credit facility increased from $2.5 million to $4.0 million and its maturity was extended from February 2027 to February 2028. As of
September 30, 2026, the undrawn commitment under the facility amounted to $0.7 million. Interest income for the nine months ended
September 30, 2026 and 2025 was $nil and $0.4 million, respectively. A provision for expected credit losses of $0.6 million and $1.5 million
was recognized for the nine months ended September 30, 2026 and 2025, respectively, within “Other operating income/(loss)” in the
unaudited consolidated statements of operations.
(3) FFH - In August 2024, we granted a shareholder loan to FFH through Gimi MS, with a maximum facility amount of $20.0 million to
enable FFH to fund its portion of Gimi MS’s funding requirements. The shareholder loan carried an interest rate of 12 % per annum,
compounded monthly, which increased to 22 % per annum effective January 1, 2025. For the period from January 1, 2025 to March 28, 2025,
the loan generated interest income of $1.0 million. On March 28, 2025, FFH repaid the shareholder loan and accrued interest in full. There
21. OTHER COMMITMENTS AND CONTINGENCIES
(in thousands of $) | September 30, 2026 | December 31, 2025 |
Book value of vessel secured against loans (1) |
(1) This excludes the following vessels:
•FLNG Gimi which was derecognized on COD with the concurrent recognition of “Net investment in sales-type lease” (note 5.2),
secured against its specific debt facility (note 15).
•FLNG Esperanza which is presented under “Asset under development” (note 12) and secured against FLNG Esperanza RCF (note
44
Other Commitments and Contingencies
•FLNG Hilli redeployment
In connection with the FID for the redeployment of FLNG Hilli under a 20-year agreement with SESA, the Board of Directors
approved total expenditures of up to $350.0 million in May 2025 to support the vessel’s preparation and redeployment
activities. In addition, in February 2026 the Board approved expenditures of up to $13.6 million specifically for the
decommissioning of the FLNG Hilli mooring equipment upon the completion of LTA (note 17).
•SMP and SESA
Pursuant to the shareholders' agreement for SESA and SMP, in connection with our respective 10 % equity interests, we have
committed to fund our proportionate share of the required infrastructure funding and related capital contributions. As of
September 30, 2026, our remaining funding commitments were $19.8 million and $32.6 million for SESA and SMP,
respectively.
We have also provided certain guarantees and indemnities in support of SMP's and SESA's financing and contractual
obligations. As of September 30, 2026, some of these guarantees were not yet effective, as they remained subject to substantive
conditions precedent. Upon satisfaction of the applicable conditions precedent, our maximum potential exposure would be
approximately $6.5 million and $124.8 million for SMP and SESA, respectively.
We also guarantee certain of SESA's payment obligations under its gas transportation arrangements with SMP, limited to our
management assessed the likelihood of payment under these guarantee arrangements as remote.
•FLNG business developments
In 2026, we entered into contingent success fee arrangements with third-party consultants in connection with FLNG business
development opportunities. Any fees payable under these arrangements are contingent upon the successful award of the
underlying contracts and are determined in accordance with the respective agreements. As of September 30, 2026, no
obligations had arisen under these arrangements as the relevant contractual milestones had not been achieved.
In August 2026, we entered into a Letter of Intent (“LOI”) with Seatrium Energy (Americas) Pte Ltd (“Seatrium”) securing a
shipyard slot for a potential additional MKI or MKII design FLNG. As of September 30, 2026, the remaining commitment is
$1.0 million.
•Gimi MS Corporation (“Gimi”) Mixed Tax Unit (“MTU”) tax assessment
In October 2026, Gimi MS Corp received a preliminary tax assessment notice of $35.0 million relating to prior periods. While
we believe we have meritorious defenses against the tax assessment, the ultimate resolution of the matter, which is expected to
occur within one year may result in a loss of up to the assessment amount. Pursuant to the LOA, taxes properly and necessarily
incurred are contractually recoverable from the lessee.
45
22.SUBSEQUENT EVENTS
Since September 30, 2026, the following non-recognized events have occurred:
•Purchase of donor vessel for FLNG four
In October 2026, we entered into an agreement with Nippon Yusen Kabushiki Kaisha (“NYK Line”) to acquire the 2013-
built LNG carrier, Grace Dahlia. The vessel was delivered to the CIMC shipyard in November 2026 for conversion into
our fourth FLNG, with redelivery expected in 2029. The acquisition and conversion are within our $2.45 billion budget for
FLNG 4. As of the date of this report, we had spent approximately $324.5 million of capital expenditures in connection
with the FLNG 4 conversion, including the acquisition of Grace Dahlia.
•2026 Senior Unsecured Notes
On October 8, 2026, we issued $500 million aggregate principal amount of the 2026 Senior Unsecured Notes, maturing
December 15, 2031. The 2026 Senior Unsecured Notes were issued at 99 % of the principal amount and bear interest at a
rate of 7.50 % per annum, payable semi-annually in arrears.
The net proceeds from the offering amounted to $487.3 million, after deducting the initial purchasers’ discount and
estimated offering expenses. This will be used to fund the construction of FLNG Esperanza and our FLNG four, further
FLNG growth units and other general corporate purposes.
•SMP capital contributions
In October 2026, we made an additional investment of $3.9 million in SMP through an irrevocable contribution against the
future subscription of shares. Following this contribution, Golar continues to hold a 10 % equity interest in SMP.
•FLNG Esperanza letter of credit
On October 8, 2026, the outstanding balance of the letter of credit issued in favor of B&V with CIMC Raffles in
connection with the FLNG Esperanza EPC contract decreased from $100.0 million to $25.0 million. The reduction was
made in accordance with the terms of the EPC contract.
•Long-Lead Equipment reservation
In October 2026, we entered into a Limited Notice to Proceed (“LNTP”) with Nuovo Pignone International S.r.l. for the
reservation of long-lead equipment. The LNTP authorizes the procurement of long-lead components and secures
reservations for manufacturing slots of multiple gas generators.
•Amendment to FLNG Hilli sale and leaseback facility
On November 18, we entered into an agreement to amend and extend FLNG Hilli’s existing sale-leaseback facility with an
affiliate of CSSC (Hong Kong) Shipping Company Limited (“CSSC entity”). The amended facility will provide financing
of up to $960 million, with an extended maturity to 2038 and a reduced financing margin. The transaction is expected to
close in December 2026.
•Dividends
On November 18, 2026, we declared a dividend of $0.25 per share in respect of the three months ended September 30,
2026 to shareholders of record on November 30, 2026, which will be paid on or around December 9, 2026.