Seabridge Gold says the BC Supreme Court quashed the Substantially Started Designation for its KSM Project while sending it back for reconsideration. The KSM environmental assessment certificate is not affected. AI summary
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 6-K
REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER
THE SECURITIES EXCHANGE ACT OF 1934
For the month of November 2026
Commission File Number 1-32135
SEABRIDGE GOLD INC.
(Name of Registrant)
106 Front Street East, Suite 400, Toronto, Ontario, Canada M5A 1E1
(Address of Principal Executive Office)
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.
Form 20-F [ ] Form 40-F [X]
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.
| Seabridge Gold Inc. | ||
| (Registrant) | ||
| By: | /s/ Gregory Martin | |
| Name: | Gregory Martin | |
| Title: | Chief Financial Officer | |
| Date: November 19, 2026 | ||
EXHIBITS
| Exhibit | Description | |
| 99.1 | News Release dated November 19, 2026 |

News Release
| Trading Symbols: TSX: SEA | FOR IMMEDIATE RELEASE |
| NYSE: SA | November 19, 2026 |
Court Decision on Court Orders Leaves Environmental Assessment
Approval Unaffected but Confirms Substantially Started Determination for
Seabridge Gold's KSM Project in British Columbia was Quashed
Toronto, Canada - Seabridge Gold Inc. ("Seabridge" or the "Company") (TSX:SEA) (NYSE:SA) reported today that the British Columbia Supreme Court (the "Court") has released a decision (the "November Ruling") settling the Court Orders in respect of the Petitions brought challenging the Substantially Started Designation ("SSD") for its KSM Project in Northwest BC. Although in the November Ruling the Court ruled that when it directed the SSD back to BC's Environmental Assessment Office ("EAO") for "reconsideration" it quashed the SSD, the status of the KSM Project's environmental assessment certificate is not affected by the November Ruling and the Tahltan and Nisga'a Nations continue to strongly support the KSM Project. If, after its reconsideration of the SSD, the EAO again concludes the KSM Project was substantially started, the KSM environmental assessment certificate will continue in place and not be subject to expiry.
Seabridge Chair and CEO Rudi Fronk stated that "the legal status of KSM has not changed as of the November Ruling. We are very confident that KSM has more than met the requirements for a Substantially Started designation. We also have the full support of the principal First Nations who have recognized traditional territory and Treaty rights, respectively, in the area of KSM and with whom we have impact benefit agreements."
KSM received the SSD on July 24, 2024 in respect of the work completed at the KSM Project to that date. In its reconsideration of whether the KSM Project has been substantially started, the EAO will also consider the additional work completed at the KSM Project between July 24, 2024 and July 29, 2026. This additional data was submitted to the EAO in September and increased the construction investment at KSM from $444 million to more than $700 million.
The SSD was challenged by the Tsetsaut Skii km Lax Ha ("TSKLH") and SkeenaWild Conservation Trust ("SCT"). The Court's ruling on June 8, 2026 required the EAO to commence a reconsideration of the SSD following an additional 90-day consultation period with the TSKLH. The 90-day consultation period concluded on September 28, 2026. The Court, in the November Ruling, also declared that the SCT Petition was dismissed without a ruling on the reasonableness of the SSD.
In the November Ruling the Court also ruled on the extent of the consultation with TSKLH required in the reconsideration process. The Company will seek information from the EAO as to whether this November Ruling will impact the time the EAO expects to take to reach a new substantially started determination but is encouraging the EAO to conclude it promptly.
About Seabridge Gold
Seabridge Gold holds a 100% interest in several North American gold projects. Its principal assets are the KSM and Bronson Corridor projects in British Columbia's Golden Triangle. Additional projects include Snowstorm in Nevada's Getchell Gold Belt, and the 3 Aces project in the Yukon. Further information on Seabridge's mineral reserves and resources is available at www.seabridgegold.com.
Neither the Toronto Stock Exchange, New York Stock Exchange, nor their Regulation Services Providers accepts responsibility for the adequacy or accuracy of this release.
| ON BEHALF OF THE BOARD | |
| "Rudi Fronk" | |
| Chair & C.E.O. |
For further information please contact:
Rudi P. Fronk, Chair and C.E.O.
Tel: (416) 367-9292 • Fax: (416) 367-2711
Email: info@seabridgegold.com