Skip to main content

6-K

Namib Minerals (NAMM)

6-K 2026-06-02 For: 2026-06-02
View Original
Added on June 03, 2026

UNITEDSTATES

SECURITIESAND EXCHANGE COMMISSION

Washington,D.C. 20549

Form6-K

REPORTOF FOREIGN PRIVATE ISSUER

PURSUANTTO RULE 13a-16 OR 15d-16

UNDERTHE SECURITIES EXCHANGE ACT OF 1934

Forthe month of June 2026

CommissionFile Number 001-42685

NamibMinerals

(Translation of registrant’s name into English)


Suite210, 2nd Floor, Windward III, Regatta Office Park

POBox 500

GrandCayman, Cayman Islands, KY1-1106

(Addressof principal executive office)


Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F.

Form 20-F ☒            Form 40-F ☐

INFORMATIONCONTAINED IN THIS FORM 6-K REPORT

Issuance of Press Release

On June 2, 2026, Namib Minerals (the “Company”) issued a press release regarding an operational update.

This report on Form 6-K, including the press release being furnished in this report as Exhibit 99.1, shall not be deemed to be “filed” for the purposes of Section 18 of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), or otherwise subject to the liabilities of that section, and shall not be deemed to be incorporated by reference into any filing of the Company under the Securities Act of 1933, as amended, or the Exchange Act except to the extent specifically provided in such a filing.

EXHIBITINDEX


Exhibit No. Description
99.1 Press Release of the Company, dated June 2, 2026.
| 1 |

| --- |

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

NAMIB MINERALS
By: /s/<br> Siphesihle Mchunu
Name: Siphesihle Mchunu
Title: General Counsel

Date: June 2, 2026

| 2 |

| --- |

Exhibit 99.1


NamibMinerals –Operational Update


New York, June 02, 2026 (GLOBE NEWSWIRE) -- Namib Minerals (Nasdaq: NAMM) (“Namib Minerals” or the “Company”) today provided an update on the Mill Expansion Project at How Mine, a key component of the Company’s strategy to expand processing capacity and grow gold output at its flagship asset.

The Company is pleased to announce that the civil works on the mill installation are at an advanced stage. The raft foundation, mill plinth and tower foundations have been completed.

Furthermore, the principal mechanical components have been delivered to site, including the mill shell, which will help ensure that the project remains on pace to be completed on time. In respect of power, factory acceptance tests for the project transformer and starter have been completed

Civil, mechanical and electrical installation works on site are underway, with engineering, procurement and contractor management activities continuing across the project workstreams.

The Company remains on track to complete the construction and commissioning within the timeline previously communicated, namely, H2 2026. The Company will provide further updates as additional project milestones are achieved.

The is an update on work completed to date and the present status of equipment and contracts.


Forward-LookingStatements

This update may include forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Any statements that refer to estimates, forecasts or other characterizations of future events or circumstances, including any underlying assumptions, are also forward-looking statements. Forward-looking statements include, without limitation, our management teams’ expectations regarding the timeline to complete the Mill Expansion Project at How Mine. The forward-looking statements are based on our current expectations and are inherently subject to uncertainties and changes in circumstance and their potential effects and speak only as of the date of such statement. There can be no assurance that future developments will be those that have been anticipated. These forward-looking statements involve a number of risks and uncertainties including that unexpected delays in obtaining materials, completing project milestones or from accidents may occur. You should carefully consider the foregoing factors, any other factors discussed in this press release and the other risks and uncertainties described in the filings we make with Securities and Exchange Commission. We caution you against placing undue reliance on forward-looking statements, which reflect current beliefs and are based on information currently available as of the date a forward-looking statement is made.