Rio Tinto PLC 6-K, filed Mar 1, 2022
Rio Tinto PLC (RIO)
6-K
2022-03-01
For: 2022-02-28
View Original
Added on
April 06, 2026
About this 6-K
Rio Tinto PLC filed this 6-K on March 1, 2022.
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, DC 20549
FORM 6-K
REPORT OF FOREIGN PRIVATE ISSUER
PURSUANT TO RULE 13A-16 OR 15D-16 OF
THE SECURITIES EXCHANGE ACT OF 1934
Month of February 2022
| Commission file number: 001-10533 | Commission file number: 001-34121 | ||||
| Rio Tinto plc | Rio Tinto Limited | ||||
| ABN 96 004 458 404 | |||||
| (Translation of registrant’s name into English) | (Translation of registrant’s name into English) | ||||
| 6 St. James’s Square | Level 7, 360 Collins Street | ||||
| London, SW1Y 4AD, United Kingdom | Melbourne, Victoria 3000, Australia | ||||
| (Address of principal executive offices) | (Address of principal executive offices) | ||||
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F:
Form 20-F ☒ Form 40-F ☐
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): ☐
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ☐
Indicate by check mark whether by furnishing the information contained in this Form, the registrant is also thereby furnishing the information to the Commission pursuant to
Rule 12g3-2(b) under the Securities Exchange Act of 1934.
Yes ☐ No ☒
If "Yes" is marked, indicate below the file number assigned to the registrant in connection
with Rule 12g3-2(b): 82- ________
EXHIBITS
99.1Stock Exchange announcement dated 1 February 2021 entitled ‘Total voting rights and issued capital’
99.7Stock Exchange announcement dated 23 February 2021 entitled ‘Our approach to climate change 2021’
99.14Stock Exchange announcement dated 28 February 2021 entitled ‘Requisitioned resolution withdrawn’
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrants have duly caused this report to be signed on their behalf by the undersigned, thereunto duly authorised.
| Rio Tinto plc | Rio Tinto Limited | ||||||||||
| (Registrant) | (Registrant) | ||||||||||
| By | /s/ Steve Allen | By | /s/ Steve Allen | ||||||||
| Name | Steve Allen | Name | Steve Allen | ||||||||
| Title | Company Secretary | Title | Joint Company Secretary | ||||||||
| Date | 1 March 2022 | Date | 1 March 2022 | ||||||||
EXHIBIT 99.1
Notice to ASX/LSE

Total voting rights and issued capital
1 February 2022
In accordance with the Financial Conduct Authority’s (FCA) Disclosure Guidance and Transparency Rule 5.6.1R, Rio Tinto plc notifies the market that as of 31 January 2022:
1.Rio Tinto plc’s issued share capital comprised 1,255,805,686 Ordinary shares of 10p each, each with one vote.
2.7,583,499 ordinary shares of 10p each are held in treasury. These shares are not taken into consideration in relation to the payment of dividends and voting at shareholder meetings.
Accordingly the total number of voting rights in Rio Tinto plc is 1,248,222,187. This figure may be used by shareholders (and others with notification obligations) as the denominator for the calculation by which they will determine if they are required to notify their interest in, or a change to their interest in, Rio Tinto plc under the FCA’s Disclosure Guidance and Transparency Rules.
Note:
As at the date of this announcement:
(a)Rio Tinto plc has also issued one Special Voting Share of 10p and one DLC Dividend Share of 10p in connection with its dual listed companies (‘DLC’) merger with Rio Tinto Limited which was designed to place the shareholders of both companies in substantially the same position as if they held shares in a single enterprise owning all of the assets of both companies;
(b)the Special Voting Share facilitates joint voting by shareholders of Rio Tinto plc and Rio Tinto Limited on joint electorate resolutions; and
(c)there are 371,216,214 publicly held Rio Tinto Limited shares in issue which do not form part of the share capital of Rio Tinto plc.
LEI: 213800YOEO5OQ72G2R82
Classification: 2.5 Total number of voting rights and capital disclosed under article 15 of the Transparency Directive
This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary.
Steve Allen Group Company Secretary | |||||
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 | |||||
Rio Tinto releases external review of workplace culture 01 February 2022 MELBOURNE, Australia--(BUSINESS WIRE)-- Rio Tinto today published a comprehensive external review of its workplace culture, commissioned as part of its commitment to ensure sustained cultural change across its global operations. The review, which was carried out by former Australian Sex Discrimination Commissioner Elizabeth Broderick, identified disturbing findingsof bullying, sexual harassment, racism and other forms of discrimination throughout the company. The review is part of the work being undertaken by Rio Tinto’s Everyday Respect task force, which was launched in March 2021 to better understand, prevent and respond to harmful behaviours in the workplace. The eight-month study saw more than 10,000 people share their experiences, views and insights via an online survey, as well as through more than 100 group listening sessions, 85 confidential individual listening sessions and close to 140 individual written submissions. The report, which outlines 26 detailed recommendations, will inform work being carried out to improve how the company prevents and responds to discrimination and unacceptable workplace behaviour. Rio Tinto will implement all recommendations from the report, with a focus on three key areas: EXHIBIT 99.2 Notice to ASX/LSE
A commitment from the company’s leadership to create safe, respectful and inclusive working environments to prevent harmful behaviours and better support people in vulnerable situations. This includes increasing diversity within the company. Ensuring the company’s camp and village facilities are safe and inclusive. This includes making sure the company is applying the same safety and risk processes that it uses to prevent harm in operations to create a safe environment for all employees and contractors. Making it as easy and as safe as possible for all people to call out unacceptable behaviours, highlight issues when they happen and receive support. This includes introducing early intervention options and improving how the company responds to formal complaints in the workplace. The actions are a response to the report’s findings which show in the last five years: Bullying and sexism are systemic across Rio Tinto worksites, with almost half of the people experiencing bullying; 28.2% of women and 6.7% of men have experienced sexual harassment at work; 21 women reported actual or attempted rape or sexual assault; Racism is common across a number of areas, with the survey indicating people working in a country different to their birth experienced high rates of racism, and that 39.8% of men and 31.8% of women who identify as Aboriginal or Torres Strait Islander in Australia experienced racism. The full report can be viewed here: https://www.riotinto.com/-/media/Content/Documents/Sustainability/People/RT- Everyday-respect-report.pdf Rio Tinto Chief Executive Jakob Stausholm said, “The findings of this report are deeply disturbing to me and should be to everyone who reads them. I offer my heartfelt apology to every team member, past or present, who has suffered as a result of these behaviours. This is not the kind of company we want to be. “I feel shame and enormous regret to have learned the extent to which bullying, sexual harassment and racism are happening at Rio Tinto. “I am determined that by implementing appropriate actions to address the recommendations, and with the management team’s commitment to a safe, respectful and inclusive Rio Tinto in all areas, we will make positive and lasting change and strengthen our workplace culture for the long term. “I am grateful to everyone who has come forward to share their experiences as we go about this vital work.” The report also found there is strong appetite for cultural change within the company, including at senior leadership levels, and that there was a visible shift in attitudes and behaviour over the last 12 months. Elizabeth Broderick said, “This report is not a reason for reduced confidence in Rio Tinto. By proactively commissioning this study, one of the largest of its kind within the resources industry, it demonstrates a very clear commitment to increased transparency, accountability and action. The high levels of confidence among employees that a significant impact can be made in the next two years are an encouraging sign that change can happen. “In my interactions with the Rio Tinto leadership team, I have observed a strong desire for transformational change, as well as to make positive contributions to the societal shifts that we need to see. There is clear recognition, however, that new approaches are needed to solve these issues.” The report was informed by research that shows lasting cultural change can only happen through engaging with people who have been impacted by harmful behaviours, allowing them to share their stories and design solutions together to prevent a recurrence. It set out to understand the prevalence of bullying, sexual harassment and racism within the company, to understand people’s individual experiences and to determine the most appropriate and effective approaches for prevention.
About Elizabeth Broderick AO, Principal, Elizabeth Broderick & Co Elizabeth was Australia’s longest serving Sex Discrimination Commissioner (from 2007 to 2015), is Founder and Convenor of the Champions of Change Coalition, Adjunct Professor at The University of Sydney and an independent expert to the UN Working Group on Discrimination against Women and Girls. This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary. riotinto.com View source version on businesswire.com: https://www.businesswire.com/news/home/20220131005967/en/ Please direct all enquiries to media.enquiries@riotinto.com Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 Category: General Source: Rio Tinto
Notice to ASX/LSE 2 February 2022 Rio Tinto notes ERA update on Ranger mine Rio Tinto notes Energy Resources of Australia Ltd (ERA) today released the preliminary findings from its reforecast of the cost and schedule for the Ranger rehabilitation project in Australia’s Northern Territory, which have been subject to independent review (www.energyres.com.au). This release follows ERA’s announcements on 27 September 2021, 8 October 2021 and 19 November 2021 where ERA forecast cost and schedule overruns for the Ranger rehabilitation project. Rio Tinto is reviewing the preliminary findings of this reforecast and has advised ERA that it is committed to working with the company to ensure the rehabilitation of the Ranger Project Area is successfully achieved to a standard that will establish an environment similar to the adjacent Kakadu National Park. EXHIBIT 99.3
Notice to ASX/LSE Page 2 of 2 Contacts Please direct all enquiries to media.enquiries@riotinto.com Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948 Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary. riotinto.com
EXHIBIT 99.4
Media release

DOE backs Rio Tinto led team to explore carbon storage at Tamarack

14 February 2022
TAMARACK, Minn.--(BUSINESS WIRE)-- The US Department of Energy has awarded $2.2 million of funding to a Rio Tinto-led team to explore carbon storage potential at the Tamarack nickel joint venture in central Minnesota.
Rio Tinto has assembled a team of climate innovation and research leaders to explore new approaches in carbon mineralisation technology as a way to safely and permanently store carbon as rock. Rio Tinto will contribute $4 million in funding for the 3-year project, in addition to the funding from the Department of Energy’s ARPA-E Innovation Challenge.
Carbon mineralisation uses natural chemical reactions to convert captured carbon dioxide (CO2) into rock and store it underground. It has the potential to be an important technology in meeting global climate goals and is now being used at large scale by the world’s leading carbon mineralisation company Carbfix in Iceland.
Rio Tinto’s technical experts will work with partners including the Department of Energy’s Pacific Northwest National Laboratory (PNNL), which has demonstrated carbon mineralisation technology in Washington state; Columbia University; Carbfix; and Advantek Waste Management Services. Talon Metals, the majority owner and operator of the Tamarack Nickel Project and Rio Tinto’s joint venture partner, is contributing ore body knowledge and land access for scientific field work.
Rio Tinto Chief Scientist Dr Nigel Steward said “Our aim is to deliver carbon storage solutions that can help to meet climate targets by reducing and offsetting emissions from our operations and in other industries, and to explore the emerging commercial opportunities carbon storage may offer at Rio Tinto sites around the world. We will be working with leading researchers and innovators to prove the carbon storage potential of the Tamarack site and develop mineralisation solutions that can be used not just here but at other similar locations.”
PNNL CO2 subsurface sequestration expert Todd Schaef said “This work will leverage the knowledge gained from PNNL’s Wallula Basalt Carbon Storage Pilot Project, the only supercritical CO2 injection in basalt demonstration in the world. We will be developing forward-looking carbon storage strategies with Rio Tinto and the broader team. PNNL stewards a suite of capabilities that allow us to look at real-time CO2 interactions with rocks under extreme conditions. We are proud to bring interdisciplinary expertise with computational scientists, geochemists, and engineers who have been researching the subsurface mineralisation of CO2 for decades.”
Columbia Climate School Founding Dean Sir Alex Halliday said “We are truly excited by the opportunity that this partnership brings to rapidly advance carbon management technologies at scale. This is an important project and a superb example of the work for which the Columbia Climate School was established; bringing climate knowledge to action through transdisciplinary projects with critical public and private partnerships. We look forward to much more to come.”
Carbfix CEO Dr. Edda Aradottir said “This project will bring together leading industrial players, academics and experts demonstrating the international partnerships needed for accelerated climate action. Carbfix is a global pioneer in carbon mineralization with a proprietary technology that can play a vital role in climate action, having over a decade long experience in safely injecting and storing CO2 from emission sources as well as the atmosphere. We are excited to bring our expertise to this partnership and help find solutions for the unique geological conditions found at the Tamarack site.”
Talon Metals CEO Henri van Rooyen said “Rio Tinto has assembled a uniquely qualified team of scientists and innovators to explore new approaches to harness carbon mineralisation as a way to safely and permanently store carbon sourced from hard-to-abate industries and carbon removed from the atmosphere.
“Talon is pleased to host this project here in Aitkin County Minnesota, which will be at the forefront of new approaches to climate science.”
Analyses by the UN Intergovernmental Panel on Climate Change show that billions tons of CO2 must be removed from the atmosphere in order to keep global warming to less than 2°C, and that this will not only require deep reductions in emissions but also carbon dioxide removal technologies. While Rio Tinto is prioritising emissions reductions at mines and smelters, it is also exploring the potential role of carbon capture and mineralisation to safely and permenantly store carbon in solid form.
Notes to editors
Tamarack is a nickel, copper and cobalt project located in central Minnesota that is currently progressing towards feasibility studies. The project is managed by Rio Tinto’s joint venture partner Talon Metals, which holds a 51 per cent share and has a right to earn-in to acquire up to 60 per cent.
Until now, large scale carbon mineralisation projects have focussed on areas with certain types of rock formations known as basaltic lava geology, such as Carbfix’s sites in Iceland. In contrast, the Tamarack Nickel Project includes a large bowl of what is known as porous ultramafic rock. While this bowl sits outside the resource of nickel and other battery minerals, it has the potential to safely store hundreds of millions of tons of carbon in solid form through natural reactions.
The project will include laboratory studies and field work to confirm the carbon storage potential of the site, understand the area’s hydrology and assess different carbon mineralisation technologies, developing a roadmap by 2025 to guide decisions on implementation.
The Tamarack site is also planned to host the first deployment of climate technology start-up Carbon Capture’s innovative Direct Air Capture technology, which captures carbon dioxide from the atmosphere and offers a potential supply source of carbon for mineralisation. Rio Tinto has invested $4 million in Carbon Capture to support the development of its technology and feasability studies for the deployment at Tamarack are now underway.
Rio Tinto is also partnering with Carbfix to help deliver the world’s first carbon mineral storage hub in Iceland and implement carbon capture and mineral storage at the ISAL aluminium smelter.

View source version on businesswire.com: https://www.businesswire.com/news/home/20220214005477/en/
| Contacts | Please direct all enquiries to media.enquiries@riotinto.com | ||||
Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 | Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948 | ||||
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 | Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 | ||||
riotinto.com
EXHIBIT 99.5
Media release

Yinhawangka people and Rio Tinto agree new social, cultural heritage plan

14 February 2022
PERTH, Australia--(BUSINESS WIRE)-- Yinhawangka Aboriginal Corporation (YAC) and Rio Tinto have agreed on a new co-designed management plan to ensure the protection of significant social and cultural heritage values as part of Rio Tinto’s proposed development of the Western Range iron ore project in the Pilbara region of Western Australia.
The Social, Cultural Heritage Management Plan (SCHMP) is the result of strong collaboration over the past year between the Yinhawangka people and Rio Tinto including ‘on-Country’ visits, archaelogical and ethnographic surveys and workshops. As a result of that collaboration, the mine was designed to reduce impacts on social and cultural heritage values.
The SCHMP outlines protocols for joint decision making on environmental matters, mine planning and closure. It also outlines support for the Yinhawangka Ranger programme as well as plans to increase participation in “on-Country’ environmental and other cultural heritage management activites.
It is the first time Rio Tinto and Yinhawangka have jointly developed a plan of this type. Rio Tinto continues work to improve its approach to social and cultural heritage management with Traditional Owners in the Pilbara and is engaging with other Traditional Owner groups to develop similar plans.
Yinhawangka Aboriginal Corporation CEO Kupa Teao said, “We are grateful to Rio Tinto for working collaboratively with YAC and the Yinhawangka people throughout this comprehensive engagement process; providing YAC with the necessary support to enable our team to focus on ensuring the Yinhawangka people have their voice embedded in the SCHMP.
“Together, we have ensured the expectations of the Yinhawangka people are clearly incorporated in to the obligations moving forward.”
Rio Tinto Iron Ore Chief Executive Simon Trott said, “We are appreciative of the Yinhawangka people for the opportunity to work together on this important plan which provides a new framework for working in partnership on-Country.
“We know we haven’t always got this right in the past. We have learned and continue to learn a lot from this co-designed process which is the manner in which we want to work with all Traditional Owners.
“This is an important milestone for the Western Range project, allowing the Yinhawangka people and Rio Tinto to move forward together.”
The SCHMP was submitted to Western Australia’s Environmental Protection Authority (EPA) on 1 February 2022. It forms part of Rio Tinto’s submission to the EPA regarding the Greater Paraburdoo Iron Ore Hub Proposal.

View source version on businesswire.com: https://www.businesswire.com/news/home/20220213005027/en/
Please direct all enquiries to media.enquiries@riotinto.com
Media Relations, Australia
Jonathan Rose
M +61 447 028 913
Matt Chambers
M +61 433 525 739
Jesse Riseborough
M +61 436 653 412
Jamie Macdonald
M +61 467 725 517
Kate Barcham
M +61 438 990 238
Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885
Rio Tinto Limited
Bevel 7, 360 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404
Category: Pilbara
Source: Rio Tinto
EXHIBIT 99.6
Media release

Tasmania and Rio Tinto partner for a strong and sustainable future at Bell Bay

20 February 2022
MELBOURNE, Australia--(BUSINESS WIRE)-- The Tasmanian Government and Rio Tinto will work together to ensure a strong and sustainable future economy for George Town, the Tamar Valley region and Tasmania, in a new partnership signed today at the Bell Bay Aluminium smelter.
The partnership will seek to drive economic growth and employment outcomes in the State and support the Tasmanian Government’s target of doubling renewable electricity generation by 2040.
Under the Memorandum of Understanding (MOU), the Tasmanian Government and Rio Tinto will jointly investigate how the smelter’s manufacturing capability and electricity demand can help support the development of new industries and more renewable energy supply in the region.
Rio Tinto has also committed to look at how it could further decarbonise Bell Bay Aluminium and investigate options for future investment to secure the competitiveness of the smelter.
The MOU was signed at Bell Bay by Tasmanian Premier Peter Gutwein and Rio Tinto Chief Executive Jakob Stausholm.
Peter Gutwein said “This MOU is a strong demonstration of our shared commitment to Tasmania’s economic and industrial future and reinforces the State’s renewable energy credentials.
“Rio Tinto has been a figurehead of local industry here for some 67 years, directly employing more than 500 Tasmanians and more than 700 indirectly, and this agreement reaffirms Rio Tinto’s long-term commitment to our state.”
Jakob Stausholm said “Aluminium is essential for the global transition to a low-carbon economy, and we are excited about the contribution our Bell Bay smelter can make both towards this transition and to the region’s future.
“We want to help ensure a strong and vibrant future for Bell Bay, where we have been part of the community for well over half a century and where we are actively working with the Tasmanian Government on a shared vision for the future.”
Bell Bay Aluminium General Manager Shona Markham said “Bell Bay Aluminium has been an important part of George Town and the northern Tasmanian economy for nearly 70 years.
“Today’s announcement is exciting news for our 514 direct employees, and the hundreds of other Tasmanians and Tasmanian businesses who work with us. It is a strong endorsement that Rio Tinto and the Tasmanian Government see a positive and sustainable future for Bell Bay beyond 2025.”

View source version on businesswire.com: https://www.businesswire.com/news/home/20220219005008/en/
| Contacts | Please direct all enquiries to media.enquiries@riotinto.com | ||||
Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 | Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Amar Jambaa M +61 472 865 948 | ||||
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 | Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 | ||||
riotinto.com
Notice to ASX 23 February 2022 Our approach to climate change 2021 Attached is the Rio Tinto climate report, 'Our approach to climate change 2021', including our Climate Action Plan. This is also available at www.riotinto.com/climatereport. In addition, the Sustainability Fact Book 2021 and Sustainability Glossary 2021 are available at www.riotinto.com/sustainabilityreport and the Scope 1, 2 and 3 Emissions Calculation Methodology 2021 and the Industry Associations Disclosure 2021 are available at www.riotinto.com/climatereport. EXHIBIT 99.7 /LSE
Notice to ASX/LSE Page 2 of 2 Contacts Please direct all enquiries to media.enquiries@riotinto.com Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Amar Jambaa M +61 472 865 948 Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary. riotinto.com
Our Approach to Climate Change 2021
Chief Executive’s statement 2 Our business at a glance 4 Our strategy and approach to climate change 5 Part 1: Progress in 2021 Producing materials essential for the low-carbon transition 6 Reducing the carbon footprint of our operations 10 Partnering to reduce the carbon footprint of our value chains 12 Enhancing our resilience to physical climate risk 14 Part 2: Our Climate Action Plan Implementing our Climate Action Plan Scope 1 and 2 targets and roadmap 18 Scope 3 goals and customer engagement 21 Capital allocation alignment with our decarbonisation strategy 26 Climate policy engagement 27 Climate governance 28 Just transition 29 TCFD disclosure 30 Emissions and energy data 31 Assurance statement by KPMG 34 Visit riotinto.com to find out more Contents Cover | Iron Ore Company of Canada (IOC) operations
Highlights from our Climate Action Plan Commitment to implement the TCFD recommendations and CA100+ Net Zero Company Benchmark Phase out purchase of diesel haul trucks and locomotives by 2030 Net zero emissions from shipping by 2050 and 40% reduction in intensity by 2025 five years ahead of IMO ambition Progress abatement projects for emissions from process heat, mobile diesel, anodes and reductants Climate performance linked to executive remuneration $75 / t CO2e internal carbon price to incentivise efficiency and new mitigation projects Scale up the ELYSISTM technology for installation from 2024 Deploy solar and wind at scale targeting 1GW in the Pilbara and green repowering solutions for our Boyne Island and Tomago smelters External third-party assurance of our emissions and alignment of target with 1.5°C $200m annual climate-related opex expected to reduce as energy efficiency work matures Customer partnerships with Baowu, Nippon Steel, POSCO and BlueScope on steel decarbonisation 75% renewable power today at managed operations, mostly from hydro-power Disclose our policy positions and review all our industry associations’ positions and advocacy annually $7.5bn capital in carbon abatement projects our best estimate of capital spend on mitigation to 2030, of which $1.5bn in 2022-2024 Investment in multiple low-carbon steel technology pathways coordinated by dedicated steel decarbonisation team 15% reduction by 2025 and 50% by 2030 aligned with stretch goal of Paris Agreement AGM advisory vote every three years annual reporting on our progress Up to $3bn growth capital in materials enabling the energy transition in 2023 and 2024 Commitment to engage with iron ore and bauxite customers to share decarbonisation plans and seek collaboration Net zero by 2050 across our operations Governance, policy engagement and disclosure Portfolio and capital allocation Scope 3 emissionsScope 1 and 2 emissions 1Our Approach to Climate Change 2021 | riotinto.com
While there is broad consensus on the need to tackle climate change, there has not yet been sufficient action globally. Governments, civil society organisations, companies and investors converged at COP26 to reset their ambition to reduce emissions and work in partnerships to transform our economy to net zero. I was fortunate to attend the summit and came away from it more convinced than ever that Rio Tinto is an integral part of the solution to climate change. It was clear in Glasgow that this is the decade for action. The determination for action from the world’s largest economies was particularly significant. In 2021, we launched our new business strategy, with the low-carbon transition at its heart. Through this strategy, we are ready to make an increasingly important contribution. The rapid shift to a lower-carbon world offers a unique opportunity for us to grow in the materials that will enable the energy transition and remain an attractive investment for decades to come. It will create additional demand for our products including copper, lithium, high-grade iron ore and aluminium, which are all vital for low-carbon infrastructure. However, we recognise that the carbon footprint of metals and minerals is significant, so we must decarbonise our operations and work with our customers on our strategy to tackle emissions across the full value chain. This is an important part of what we consider impeccable environmental, social and governance (ESG) performance – we can gain competitive advantage by providing low-carbon products that enable our customers to decarbonise. Chief Executive’s statement We have set out a Climate Action Plan and have a clear and challenging decarbonisation strategy to achieve our targets. We now need to see our strategy translating into actions – this won’t be easy; inevitably there are risks and dependencies to delivering our mitigation projects. Our people understand our operations best, and they will bring innovation and solutions to the challenge of reaching net zero over the coming decades. This is why I am focused on building a culture where all our people feel trusted and empowered to drive change. With the world’s focus on tackling climate change, there’s no better time to be at Rio Tinto. Jakob Stausholm Chief Executive Our Approach to Climate Change 2021 | riotinto.com2
We are ready to make an important contribution to tackling climate change and have put the low-carbon transition at the heart of our business strategy. 3Our Approach to Climate Change 2021 | riotinto.com
Our business at a glance Iron ore Aluminium Copper Minerals Mines 17 4 3 6 Smelters 0 14 1 0 Processing plants2 & refineries 0 4 0 4 Mt CO2 emissions 3.0mt 21.9mt 2.2mt 3.4mt Rio Tinto share of production Iron ore 266.8Mt (2020:275.5mt) Bauxite 54.3mt (2020:56.1mt) Aluminium 3,151kt (2020:3,180kt) Mined copper 493.5kt (2020:527.9kt) Titanium dioxide slag 1,014kt (2020:1,120kt) Underlying EBITDA $27.6bn (2020:$18.8bn) $4.4bn (2020:$2.2bn) $4.0bn (2020:$2.1bn) $2.6bn (2020:$1.7bn) 1. Excluding China and Japan. 2. Covering processing plants engaged in the material transformation of input products with total Scope 1 and 2 emissions greater than 100,000 tonnes CO2 Consolidated sales revenue by destination Gross revenue by product Our key assets are located in close proximity to our major markets: 57% 8% 5% 8% 13% 9% $63.5bn 59% 10% 12% 19% $66.6bn Iron ore $39.6bnChina Copper $7.8bnJapan Aluminium $12.7bnAsia1 United States of America Minerals $6.5bnEurope Other Our business comprises a portfolio of world-class assets that help meet society's needs and generate strong cash flow through the cycle. Our Approach to Climate Change 2021 | riotinto.com4
Our strategy is informed by a deep analysis and understanding of global megatrends across dimensions related to geopolitics, society and technology. These trends set the context for our industry and influence commodity choices for the future of our business as well as expectations about how we produce them. Climate change has formed part of our strategic thinking and investment decisions for over two decades and was a fundamental component in our strategy development process in 2021. Recently, there has been a rapid shift in the external context on tackling climate change. This includes the increasingly ambitious emissions targets set by many governments in the lead up to COP26; developments in low-carbon technologies, such as renewables and electric vehicles, and their falling costs; as well as the increasing international co-ordination on climate policies, including carbon pricing. In parallel, society’s expectations continue to rise. Companies extracting minerals must reduce their impact on the environment and host communities and go beyond regulatory obligations to drive the development of more sustainable value chains. An emerging theme in tackling these issues is the circular economy, which is built around avoiding and reducing waste and pollution, keeping products and materials in use, and regenerating natural systems. The highly recyclable nature of our products, potential utilisation of waste streams, and re-use of assets could create considerable near- and long-term growth and partnership opportunities as the world tackles climate change. We have put the low-carbon transition at the heart of our business strategy: combining investments in commodities that enable the energy transition with actions to decarbonise our operations and value chains. As a result of this, our strategy and approach to climate change are supported by strong governance, and we are building our processes and capabilities to enable us to reach net zero emissions by 2050. Part 1 of this report, our fourth in line with the recommendations of the Task Force on Climate-related Financial Disclosures (TCFD), details our 2021 performance on climate change across four areas: – Producing materials essential for the low-carbon transition – Reducing the carbon footprint of our operations – Partnering to reduce the carbon footprint of our value chains – Enhancing our resilience to physical climate risk In Part 2, we outline our updated Climate Action Plan, targets, goals and priorities for the short, medium and long term towards our commitment to reach net zero by 2050. Our scenarios and 1.5°C We use global scenarios in our strategy and capital allocation processes to stress test our portfolio and investment decisions under alternative macroeconomic settings and commodity outlooks. We do this with a comprehensive and robust scenario framework structured around three global forces: geopolitics, society and technology. One of our three scenarios has a temperature outcome of well below 2°C, and although this is aligned with the goals of the Paris Agreement it is not as ambitious as a 1.5°C trajectory. These scenarios are reviewed every year as part of our Group strategy engagement with the Board and inform our efforts to build a strong and resilient business as well as leverage new trends and opportunities. As part of our scenario process we also consider external scenarios, such as the IEA new NZE2050 scenario which has a temperature outcome of 1.5°C. This scenario shows that the primary energy intensity of global GDP would need to fall by 4.5% each year to 2030, electricity share of final energy demand would need to rise to 28% by 2030, and emissions from the power sector would need to fall by 60% over the same period. This would represent a much faster energy transition over the next decade than is assumed in our scenarios, requiring a very high level of co-ordination in climate policies across sectors and countries. Our scenario analysis shows that our portfolio is well positioned to perform strongly in the low-carbon transition, with significant upside potential for commodities such as copper, hydro-based aluminium and battery minerals if the transition outpaces our scenario expectations. For further details see our 2020 Climate Change Report: https://www.riotinto.com/invest/reports Our strategy and approach to climate change Introduction 5Our Approach to Climate Change 2021 | riotinto.com
Low-carbon transition materials At COP26, over 40 countries, including the UK, US, China, India, Japan and Australia, launched the Breakthrough Agenda – a commitment to work together to accelerate the development and deployment of clean technologies and sustainable solutions by 2030. The Glasgow Breakthroughs focus on four key sectors considered vital in meeting the Paris Agreement goals: clean power, zero emissions vehicles, low-emission steel and green hydrogen. Our portfolio is intrinsically linked to these technologies. Each commodity we produce has a vital role to play in the low-carbon transition. Copper demand will rise with the renewable electrification of energy, and lithium will be a fundamental ingredient in electric vehicle batteries and grid-firming energy storage solutions. Demand for aluminium will grow for uses like energy-efficient lightweight vehicles, and steel will also be essential in a range of applications, from high-speed rail networks, to wind and solar support structures and green hydrogen production facilities. Our commodities will also continue to support urbanisation and the creation of energy-efficient urban centres. Cities in China, India and across Africa will continue to expand, with an additional 2.3 billion people expected to urbanise globally by 2050. This, along with growing incomes, will increase demand for materials essential for everyday life. Sustainable and circular value chains In many important applications, there are no practical alternatives to the commodities we produce. With increasing material needs for the energy transition, it is vitally important that we work with our partners and customers to create “greener” products and more transparent and sustainable value chains. Beyond our emissions footprint, we incorporate a broad range of environmental and social considerations in every investment decision and will continue to assess our contribution towards the United Nations Sustainable Development Goals (UN SDGs). We also have an important role to play in the circular economy. Aluminium and copper are in essence infinitely recyclable. Furthermore, steel is currently one of the most widely recycled materials and is commonly used in long-life applications. By keeping our products in use, minimising waste and regenerating natural systems we can help develop more sustainable value chains in the longer term. While the circular economy presents a risk to primary metal demand growth in some markets, it also offers new development opportunities for our business. Producing materials essential for the low-carbon transition One of the three key elements of our business strategy is to grow in materials enabling the energy transition. Reaching net zero emissions globally will ultimately rely on increasing the supply of a range of metals and minerals supporting the development of clean technologies and associated infrastructure. Part 1 Progress in 2021 Our Approach to Climate Change 2021 | riotinto.com6
Part 1: Progress in 2021 Materials for low-carbon transition Demand by sector 13% 56% 19% 12% 12% 25% 24% 19% 8% 12% 16% 34% 10% 25% 15% Construction and infrastructure Global Rio Tinto Power / Electrical Auto (transport) Machinery & Equipment Consumer durables Other 1. Ore- and Scrap-based steel are notional categories based on Rio Tinto estimates of raw material inputs for different steel production pathways 2. Smelter Grade Alumina only 3. Copper ore product before processing 4. Rio Tinto total iron ore emissions include equity-basis emissions from our Pilbara operations and from IOC Sources: Rio Tinto analysis and estimates, CRU, Wood Mackenzie, International Aluminium Institute Finished Steel 1,780Mt Aluminium 92Mt Copper 30Mt Iron ore / steel Aluminium Copper Total emissions 958Mt CO2e 10.4 tCO2e/t Total emissions 3,120Mt CO2e 1.8 tCO2e/t Total emissions 107Mt CO2e 3.6 tCO2e/t 26Mt 13Mt CO2e 0.5 tCO2e/t Al Secondary aluminium 700Mt 350Mt CO2e 0.5 tCO2e/t steel Scrap-based steel1 9.5Mt 4.7Mt CO2e 0.5 tCO2e/t Cu Secondary copper 12,000Mt Total material moved 10,000Mt Total material moved 1,000Mt Total material moved8t 16t 600t 130Mt2 7.9Mt 160Mt CO2e 1.2 tCO2e2/t Al2O3 5.7Mt CO2e 0.7 tCO2e/t Al2O3 Alumina2t 67Mt 3.2Mt 780Mt CO2e 11.6 tCO2e/t Al 15.4Mt CO2e 4.9 tCO2e/t Al Primary aluminium 1,250Mt 2,700Mt CO2e 2.2 tCO2e/t steel Ore-based steel1 20.5Mt 0.2Mt 32Mt CO2e 1.6 tCO2e/t Cu 0.2Mt CO2e 1.1 tCO2e/t Cu Primary refined copper1t 1t 1t 360Mt @47% Al2O3 54Mt @49% Al2O3 4.7Mt CO2e 0.02 tCO2e/t ore 0.8Mt CO2e 0.01 tCO2e/t ore Bauxite 4,300Mt @0.6% Cu 100Mt @0.6% Cu 70Mt CO2e 2.7 tCO2e/t Cu 2.0Mt CO2 3.3 tCO2e/t Cu Copper ore3 2,400Mt @63% Fe 277Mt @61% Fe 70Mt CO2e 0.03 tCO2e/t ore 3.6Mt CO2e4 0.01 tCO2e/t ore Iron ore2t 5t 210t Product Emissions Product Emissions Product Emissions 7Our Approach to Climate Change 2021 | riotinto.com
Producing materials essential for the low-carbon transition continued Lithium We approved funding of the Jadar project in Serbia, subject to receiving all relevant approvals, and agreed to acquire the Rincon project in Argentina Low-carbon aluminium We announced an investment to add 16 new smelting cells at our AP60 smelter in the Saguenay Copper In early 2022, we reached a new agreement with our partners at Oyu Tolgoi and approved commencement of underground operations High-grade iron ore We are engaging with key stakeholders as we pursue pathways to develop Simandou Key developments across our portfolio in 2021 Although climate change presents clear growth opportunities for our commodities, it also presents both physical and transition risks to our portfolio. The transition to a low-carbon economy will have profound implications not only on the commodities we produce, but how we produce them – particularly when considering fossil-fuel-based steel and aluminium production. This creates considerable opportunities for our business, but also presents clear risks if we fail to align our projects and products with a net zero future. Our portfolio risks and opportunities in the low-carbon transition Role in the low-carbon transition Opportunities Risks Copper is an essential ingredient in renewable electrification. Its superior electrical conductivity makes it vital for use in most low-carbon technologies. Electric vehicles typically contain four times more copper than internal combustion engine vehicles. Meanwhile, solar and wind power systems consume 3-6 tonnes of copper per megawatt of installed capacity versus around 1 tonne for thermal power. – World-class greenfield and brownfield copper project pipeline – Recovery of additional copper and by-products from existing orebodies and legacy tailings – Stringent environmental and social approval constraints for new projects (near- to long-term risk) Lithium is a vital ingredient in lithium-ion batteries used in electric vehicles and other energy storage applications such as grid firming for renewable projects. In a net zero trajectory, over 50% of vehicle sales could be electric by as early as 2030 – reaching up to 65 million units. This would imply around 3 million tonnes of lithium demand compared with just 350,000 tonnes today. – Strong market outlook for lithium projects – Recovery of critical minerals by-products from existing orebodies – Uncertainty surrounding the evolution of different battery technologies (long-term risk) – Stringent environmental and social approval constraints for new projects (near- to long-term risk) Aluminium is essential for light-weighting of energy-efficient transport solutions and is infinitely recyclable. 60% of the world’s aluminium production in 2020 was powered by coal. The competitiveness of green aluminium relative to fossil-fuel-based aluminium will escalate in a carbon-constrained world, leading to strong demand for cleaner sources. – Low-cost hydro-based smelters will grow their distinct structural advantage – Opportunities from ELYSISTM technology – Improved traceability and accreditation – Ability to secure competitive large-scale firmed renewable electricity to re-power coal-based aluminium smelters (medium-term risk) Steel is the fundamental building block of energy-efficient urban centres and a vital ingredient for low-carbon infrastructure and transport. Green steel will require high-grade iron ore. Replacing of conventional coal-based steel and cement with green steel will allow substantial reductions in greenhouse gas emissions, including a potential 60% reduction in China’s construction sector. – Strong resilience from high grade iron ore products from the Pilbara, Iron Ore of Canada (IOC) and Simandou – Opportunities to target direct reduction ores and green-hydrogen-based iron in renewable advantaged regions – Accelerated scrap utilisation reducing primary iron demand (near- to long-term risk) – Pressure on lower-grade ore with higher level of impurities (medium-term risk) Our Approach to Climate Change 2021 | riotinto.com8
Part 1: Progress in 2021 Last year 24% of our revenues came from assets in the lowest carbon segment of our framework – low emissions projects that produce materials essential to the low-carbon transition. Crucially, we have continued to direct almost all of our growth capex to this segment. We also announced our ambition to increase our growth capital up to $3 billion annually in 2023 and 2024 with a priority focus on commodities that are essential for the drive to net zero. This will ensure we maintain a strong growth pipeline as more governments and customers commit to ambitious emissions reduction targets. 1. Excludes sustaining and replacement capex. Lo w er S co pe 1 & 2 ri sk Lower Scope 3 risk Percentage share of Group: Revenue (%) Growth capex1 (%) Operating assets (%) IOC: Iron Ore Company of Canada (high-grade iron ore pellets, high-grade concentrate) RTFT: Rio Tinto Fer et Titane (Sorel-Tracy Quebec metallurgical complex produces iron and titanium with materials from QMM) QMM: QIT Madagascar Minerals (based in south eastern Madagascar, produces ilmenite, rutile, zircon) MRN: Mineração Rio do Norte, a bauxite mine in Brazil (joint venture) Alumar: Alumina refinery in Sao Luis Brazil (joint venture) CBG: Compagnie des Bauxites de Guinée (joint venture) 2% – 1% From coal-based aluminium smelters 24% 99% 46% From all copper assets, hydro-based aluminium smelters 1% – 3% From RBM 9% 1% 8% From IOC, RTFT, CBG, MRN, Alumar 0% 64% – 42% From Pilbara, Amrun, Pacific alumina assets 0% 0% 0% 0% Type 5 (Highest risk): Carbon in product sold and widely substitutable in the short term (eg thermal coal) Type 4 Carbon in product sold, but hard to substitute today, but longer-term substitution risk (eg metallurgical coal) Type 3 No carbon in product sold but CO2 intensive processing today and short- to medium-term substitution risks from scrap and higher-grade feedstocks (eg iron ore fines and lump, and bauxite and alumina for coal- based aluminium) Type 2 No carbon in product sold and best-in-class process CO2 intensity today with limited substitution risks due to scarcity of high-grade products (eg iron ore direct reduction pellets, bauxite and alumina for hydro- based aluminium, high-grade TiO2) Type 1 (Lowest risk): No carbon in product sold and a critical enabler of the low-carbon transition, with low process CO2 intensity and limited substitution risks (eg copper, aluminium and battery minerals including lithium and nickel) High transition risks (not in our portfolio) Classifying our portfolio Transition risks are linked to value-chain emissions – or Scope 3 risks – associated with each commodity. We classify commodities into five categories: 9Our Approach to Climate Change 2021 | riotinto.com
Reducing the carbon footprint of our operations Our Scope 1 and 2 emissions in 2021 Our absolute emissions in 2021 were 31.1Mt CO2e (2020: 31.5Mt CO2e), 4% below our 2018 equity emissions baseline. The reductions achieved since 2018 are primarily the result of switching to renewable electricity contracts at Kennecott copper in the US and the Escondida mine in Chile (managed by BHP; Rio Tinto owns 30%), and also relate to unplanned operational disruptions in 2021 at Richards Bay Minerals (RBM) in South Africa and the Kitimat aluminium smelter in Canada. The four most significant sources of our operational emissions are electricity 45% (both purchased and generated), carbon anodes and reductants in aluminium smelting and titanium dioxide furnaces 21%, fossil fuels for heat at our processing plants and alumina refineries 18%, and diesel consumption in our mining equipment and rail fleet 13%. The carbon intensity of our assets varies widely across our portfolio, and largely reflects the balance between mining and processing activities. Most of our assets already sit at the low end of their respective commodity carbon intensity curves. Operations with a predominant mining and logistics focus are less carbon intensive, while refining and smelting operations are high-temperature, energy-intensive processes. Consequently, approximately 70% of our emissions today are from our aluminium business. Largely because of the high energy intensity of the aluminium business, our Group-wide consumption of electricity is about four times that of other global diversified mining majors. However, our share of renewable electricity – 75% (2020: 75%) across our managed operations – remains significantly higher than our peers. In 2021, we further integrated our Scope 1 and 2 decarbonisation strategy and review of asset-by-asset mitigation options with our financial planning process. We progressed studies across a broader range of emissions reduction opportunities at all our product groups and approved 0.26Mt CO2e of new abatement projects. This was above the target 0.22Mt CO2e of approvals set in our Group ESG short-term incentive plan (STIP) objectives for 2021. The approved projects included small renewable projects at Weipa, QIT Madagascar Minerals (QMM) and Kennecott, as well as several energy efficiency projects and small low-carbon technology pilots. With a renewed focus on our more ambitious 2025 and 2030 targets, and as the maturity of our abatement projects pipeline continues to develop, we expect a significant step-up in abatement projects approvals in 2022. Our short-, medium- and long-term decarbonisation strategy is set out in the Climate Action Plan in Part 2 of this report2. We first set emissions intensity targets in 2010 for the period to 2015 covering more than 95% of our Scope 1 and 2 emissions from our managed assets. These targets were subsequently raised and extended to 2020. In 2020, we set new targets to reduce absolute emissions by 15% and emissions intensity by 30% relative to our 2018 equity emissions baseline by 2030, including both managed and non-managed operations. As part of our new Group strategy, we now aim to achieve the 15% absolute reduction target five years earlier, by 2025, and have more than tripled our 2030 target to reduce emissions by 50%. These targets replace our emissions intensity target. We will continue to adjust the 2018 baseline to exclude reductions achieved by divesting assets in future, and to account for acquisitions. Article 2 of the Paris Agreement sets out its main aims, which include holding the increase in global average temperature to well below 2°C above pre-industrial levels and pursuing efforts to limit the temperature increase to 1.5°C. In the Glasgow Climate Pact adopted at COP26, governments resolved to pursue efforts to limit the global temperature increase to 1.5°C. The Pact states that this “requires rapid, deep and sustained reductions in global greenhouse gas emissions, including reducing global carbon dioxide emissions by 45 per cent by 2030 relative to the 2010 level and to net zero around mid-century, as well as deep reductions in other greenhouse gases”. This is consistent with the IPCC’s Special Report on 1.5°C that sets out multiple pathways to limiting warming to 1.5°C which average around net zero emissions by 2050. While there is no universal standard for determining the alignment of targets with the Paris Agreement goals, we assessed the alignment of our targets with 1.5°C with the following: – Estimated equity emissions in 2010 were 44.5Mt CO2e. Subtracting divestments between 2010 and 2018 brings this total to 35.0Mt CO2e. Our 2030 target is therefore equivalent to a 53% reduction from our 2010 equity emissions (excluding divestments). – Our 2030 target exceeds the resolution made by governments at COP26 to reduce emissions by 45% by that date. – Our commitment to reach net zero emissions by 2050 and our interim targets align with the science-based pathways set out in the IPCC’s Special Report on 1.5°C. – The Science Based Targets initiative (SBTi) states that “the minimum reduction required for targets in line with 1.5°C scenarios is 4.2% in annual linear terms”. Although we do not expect a linear trajectory to our target, this equates to 50% reductions over the period 2018-2030 (to the nearest percentage)1. – Carbon offsets and removals are expected to form a limited part of our decarbonisation strategy. Based on this assessment, we conclude that our Scope 1 and 2 targets for 2030 are aligned with efforts to limit warming to 1.5°C which is aligned with the stretch goal of the Paris Agreement. We are accelerating the decarbonisation of our assets to strengthen our alignment with the goals of the Paris Agreement and aim to reduce our emissions by 50% by 2030. In 2021, our Scope 1 and 2 emissions fell to 31.1Mt CO2e, equivalent to a 4% reduction against our 2018 equity emissions baseline. 1. SBTi Corporate Manual V2.0 (December 2021): While the Science Based Targets initiative has additional criteria on the inclusion of Scope 3 and the exclusion of offsets, the only reference we make here to their method is the minimum linear reduction in their Absolute Contraction Approach. https://sciencebasedtargets.org/resources/files/SBTi-Corporate-Manual.pdf 2. We define short-term as 1 year, medium-term as up to 2030 and long-term as beyond 2030. Our Approach to Climate Change 2021 | riotinto.com10
Part 1: Progress in 2021 Aluminium: The aluminium smelting process requires significant quantities of electricity and produces emissions from the use of carbon anodes. Although most of our smelters are supplied by renewable electricity, the Boyne and Tomago smelters in eastern Australia are supplied predominantly by coal-fired power generators. The two main sources of emissions in the alumina refining process are from the coal and natural gas used for heat and calcination. In 2021, our Aluminium product group’s absolute greenhouse gas emissions (21.9Mt CO2e) were 1% lower than in 2018. Contributions to this reduction include improvements in processing efficiency, an increased use of hydroelectric boilers in refining, and a reduction of production at the Kitimat smelter due to a labour action. The 2021 emissions intensity of our managed Atlantic smelters, powered by hydroelectricity, was 2.17t CO2e per tonne of aluminium compared with a global average of approximately 11.6t CO2e per tonne of aluminium. The carbon intensity of our Vaudreuil refinery is the lowest in the world today at 0.26t CO2e per tonne of alumina – compared to a global average of 1.2t CO2e per tonne of alumina. At Weipa, we continued to advance the decarbonisation of our bauxite business, with approval to install an additional 4MW of solar and a 4MW / 4MWh battery. This will more than triple the local electricity network’s solar generation capacity. Minerals: Our titanium dioxide business is energy intensive and sources hydropower in Canada but relies on coal-fired power at RBM in South Africa. The titanium smelting process also consumes carbon electrodes. In 2021, our Minerals product group’s absolute greenhouse emissions were 3.4 Mt CO2e, a reduction of approximately 8% from 2018 levels. The decrease in emissions was mainly driven by reductions in production and energy at RBM due to halted operations. We are introducing a renewable energy plant that will power our QIT Madagascar Minerals (QMM) operations. In July 2021, QMM signed an agreement with CrossBoundary Energy for a 6MWAC solar plant and 12MW wind turbine facility. The plant will also supply the majority of the power to the town of Fort-Dauphin. Construction for the solar plant is expected to begin in 2022 with the start of operations scheduled in the same year. Construction of the wind power plant is planned to commence in 2022 and will become operational by 2023. Iron Ore: Emissions from our iron ore operations in the Pilbara, Western Australia, are related to the natural gas used to generate power for the mines and processing plants, and from the diesel consumed by our mining and rail fleet. In 2021, our Iron Ore product group’s absolute greenhouse gas emissions were 3.0Mt CO2e (on an equity basis), an increase of 0.34Mt CO2e compared to the 2018 emissions baseline, driven largely by an increase in diesel emissions due to increased haul distances, waste-to-ore ratios and material movement. Construction of our first 34MW solar plant at the Gudai-Darri mine and 45MW battery system at Tom Price continued in 2021 and marks an important step in reducing our carbon footprint in the Pilbara. The solar plant will deliver approximately one third of Gudai-Darri’s average electricity demand1 and is a first step in a broader programme to leverage the Pilbara’s natural advantages in solar and wind resources and deploy renewable power at the gigawatt scale. Copper: Diesel for trucks and electricity are the main sources of emissions in our copper business. Our Kennecott copper mine in the US purchases renewable electricity certificates, and Escondida in Chile started to transition to renewable power in 2021. The Oyu Tolgoi mine in Mongolia is currently supplied by coal-fired power from China. In 2021, our Copper product group’s greenhouse gas emissions were 2.2Mt CO2e, a reduction of 1.2Mt CO2e or 35% compared to our 2018 emissions baseline. At Kennecott, we approved the replacement of eight haul trucks with lower emission engines, as well as a trial to understand the potential for using renewable diesel, for completion in 2022. We also received approval for the detailed design of a 30MW solar power plant to be constructed in two phases: 5MW to be completed by 2022, and the plant to be expanded by 25MW by 2025. In 2021, we worked with ENGIE on an emissions reduction pilot study at the Winu project in Australia to better understand existing and emerging technologies for improving renewable power to our operations. Electricity1 45% Anodes & Reductants 21% Process Heat 18% Mobile Diesel Other 13% 3% % of total Aluminium 50% Bauxite & alumina 20% Minerals 11% Iron ore 10% Copper 7% Other 2% 31.1 Mt CO2e 1. In the press release dated 16 February 2020, the solar plant was stated as delivering approximately 65% of Gudai-Darri’s average electricity demand. Since the announcement, changes in Gudai-Darri’s demand profile have occurred and the solar plant contribution has reduced to one-third. 2021 Scope 1 and 2 emissions by operations and source (equity basis) 11Our Approach to Climate Change 2021 | riotinto.com
Partnering to reduce the carbon footprint of our value chains Our products are essential enablers of the energy transition and a net zero world. We operate in energy- and carbon-intensive value chains – particularly steel and aluminium production – and are working with our customers on the technologies needed to address the resulting emissions. Steel is a vital material for industry, construction, transportation and low-carbon infrastructure and, with limits to the availability of recyclable steel, our iron ore products have an important future role to play – but we must support our customers as they work to decarbonise steel production. Emissions related to the processing of the iron ore, bauxite and alumina sold to our customers in the steel and aluminium sectors remain by far our largest sources of Scope 3 emissions. These are the value chains that we have prioritised for our partnership approach and we provide more detail in our Climate Action Plan on each of these sectors, including our Scope 3 goals and customer engagements plans. Just as we are stepping up our Scope 1 and 2 reduction efforts, we are also sharpening our focus on our Scope 3 goals, which are explicitly linked to executive remuneration. Our approach is based on global collaboration and close partnerships with our customers, suppliers and even competitors, to develop innovative technologies to reduce carbon emissions. In 2019, we launched our flagship partnership with China Baowu Steel Group (Baowu) and Tsinghua University, and we now have partnerships and initiatives with POSCO, Nippon Steel, BlueScope and others focused on the transition to net zero emissions across our value chain. Our specific goals and 2022 objectives for these partnerships are set out in Part 2 of this report. Our Scope 3 emissions in 2021 Our Scope 3 emissions were 554Mt CO2e in 2021 (down from 570Mt CO2e in 2020) and around 95% of this is from the processing of iron ore, bauxite and other products by our customers. 94% of these processing emissions take place at our customer facilities in China, South Korea, Japan and other countries that have pledged to be carbon neutral by around mid-century. As our customers start to align with their governments’ pledges, we note that about 28% of our iron sales are directly to steel producers that have already set public targets for their Scope 1 and 2 emissions (our Scope 3), and have ambitions to reach net zero by around mid-century. Estimating our Scope 3 emissions remains challenging. In most cases we cannot directly measure relevant inputs and relevant customer- and supplier-specific emissions reporting is not accessible. In 2021, we continued to enhance our approach to quantifying our Scope 3 emissions with more representative emission factors for the aluminium value chain. We now use factors that are specific to the region where our products are processed. This is more accurate than using the global average factor and reflects the higher emission intensity of aluminium production in Asia. In addition, we now consider all bauxite and alumina we buy and sell instead of just the net bauxite and alumina sold. Consequently, we are accounting for more tonnes of product processed through our value chain, both upstream and downstream. Overall, these changes increased our reported 2020 bauxite and alumina Scope 3 emissions from 116 to 154Mt CO2e for that year. This dropped to 144Mt CO2e in 2021 due to improvements in the carbon intensity of refining and smelting, as well as a reduction in bauxite sold. Scope 3 emissions related to our iron ore fell from 376Mt CO2e in 2020 to 365Mt CO2e in 2021, due to changes in product mix and a reduction in iron ore sold. The full details of our updated approach to estimating Scope 3 emissions and our assumptions are available in our separate 2021 Scope 1, 2 and 3 Emissions Calculation Methodology Report on our website. 2021 Scope 3 emissions by category (equity basis) 554Mt CO2e Processing of iron ore 364.6 Mt CO2e Processing of bauxite and alumina 144.5 Purchased goods 16.3 Capital goods 1.9 Fuel-related activities 2.9 Upstream and intercompany transportation 5.9 Downstream transportation 2.7 Processing of salt 7.2 Processing of TiO2 feedstocks 4.9 Processing of copper concentrate 0.5 Processing other sold products 1.6 Travel, commuting and waste 0.5 2021 Scope 3 emissions from product processing by country 523Mt CO2e China 399.0 Mt CO2e Japan 41.3 South Korea 20.8 Other countries with net zero pledges 30.6 Other countries without net zero pledges 31.6 Our Approach to Climate Change 2021 | riotinto.com12
Part 1: Progress in 2021 2021 progress on our Scope 3 goals Our 2020 Climate Change Report set out our Scope 3 goals, medium-term targets and 2021 objectives. Progress on our 2021 objectives, which formed part of our Group ESG short-term incentive plan (STIP) metrics, is summarised below. We met all objectives except number two. 2021 objective Progress 1.a Progress low-carbon steelmaking projects and research with Baowu as part of $10 million commitment in late 2020 to advance our partnership with Baowu and Tsinghua University During 2021, the partnership has implemented the Rio Tinto-Baowu Climate Change Collaborative Agreement and the parties have agreed to invest in a microwave lump drying pilot plant. In December, the partnership held its second “China low-carbon steel conference”, bringing together representatives across the China steel industry to identify transition pathways for the sector. In addition, we joined the Global Low-Carbon Metallurgical Innovation Alliance, established by Baowu and comprising 62 companies, universities and research institutions from 15 countries. 1.b Develop work programme and identify joint low-carbon steelmaking technology projects with Nippon Steel Corporation (Nippon Steel) in Japan, as part of climate MoU signed in December 2020 During 2021, we further developed our scope of work and have started work on seven projects that will continue into 2022, including short-term blast furnace improvement projects and collaboration on marine transportation of iron ore between the two parties. 1.c Establish new steel value chain partnership We established a partnership with POSCO and are exploring decarbonisation opportunities including integrating Rio Tinto’s iron ore processing technology with POSCO’s steelmaking technology. We established a partnership with BlueScope Steel (BlueScope) and plan to assess the use of green hydrogen at the Port Kembla Steelworks in Australia in a direct reduction process with Pilbara iron ores and then separate the slag in an electric melter to produce molten iron suitable for use in basic oxygen steelmaking process. 2 Assess feasibility of green hot briquetted iron (HBI) production with hydrogen from hydro-electricity in Canada with Paul Wurth and SHS Steel We reconsidered our approach to assessing the feasibility of green hydrogen- based direct reduced iron in eastern Canada and unwound our collaboration with Paul Wurth and SHS by mutual agreement. Instead we started a Rio Tinto-led order of magnitude study for a plant producing up to 2 million tonnes of green hot briquetted iron (HBI). Completion of the study has been delayed into early 2022. Prime potential sites have been identified, and a more comprehensive understanding of the available hydrogen and direct reduction technology options has been gained. Early engagement with key project stakeholders has also been made, with positive feedback. 3 Progress industrial-scale ELYSISTM technology research and development following construction of first industrial pilot in late 2020 In 2021, the ELYSISTM Industrial Research and Development Center passed a significant milestone in the development of this new technology with the first industrial-scale smelting of zero-carbon aluminium. This uses a full industrial design at a size comparable to small smelting cells operating in the industry today. In November, we also announced the start of construction of larger commercial-size cells at our Alma aluminium smelter in Quebec. These prototype cells are expected to become operational in 2023. 4 Approve introduction of LNG dual-fuel vessels to our shipping portfolio In 2021, we signed charterparty contracts to add nine LNG dual-fuel Newcastlemax vessels to the portfolio from the second half of 2023, which will deliver lifecycle CO2e reductions of 15-20% (50kt CO2e per annum). 13Our Approach to Climate Change 2021 | riotinto.com
Enhancing our resilience to physical climate risk Taking and managing risk responsibly is essential to operating and growing our business safely, effectively and sustainably. Managing our risks effectively ensures we deliver our strategic priorities and strengthen our social licence by focusing on becoming the ‘best operator’, achieving impeccable ESG performance and excelling in development. Our Group’s strategy, values and risk appetite inform and shape our risk management and internal controls framework. We embed risk management at every level of the organisation to effectively manage threats and opportunities to our business, host communities and our impact on the environment. While risk management is the accountability of our leaders, all employees are empowered to identify and manage risks at the point that they arise in their business (within the first line). Our Board and Executive Risk Management Committee provide oversight of our principal risks and the Audit Committee monitors the overall effectiveness of our system of risk management and internal controls. The Principal Risks and Uncertainties section of our Annual Report considers both physical climate risks and low-carbon transition risks. We measure and mature the effectiveness of our risk management practices through our risk management system. This system is built up of six core elements that are continually improved to ensure that we are effectively managing current risks and preparing for emerging risks. Our assets, infrastructure, communities and broader value chains are exposed to the impacts of extreme weather events associated with climate change, as evidenced by our experience of events such as drought, flooding, heat waves and fires that are occurring globally. While the immediate exposure to extreme weather events (acute climate risk) is addressed by product-group-level risk assessments and study guidance, the longer-dated risk exposure to chronic changes in climate is less well understood given the inherent uncertainty in future climate projections. Managing physical climate change risk through risk-based adaptation practices is essential to enhance the resilience of assets and communities. Capability and culture Risk capability is built through coaching and training for leaders and teams across our business. A risk culture of actively managing risks is embedded into how we run our business. A risk culture fosters the collective ability to identify, understand, escalate and then openly discuss and respond to current and future risks. Risk analysis and management Risks are measured, monitored and managed, which requires critical controls performance to also be measured, monitored and managed. Risks and their control information are current, transparent and connected. The analysis and management are led by leaders. Systems, technology and data analytics We leverage systems and data analytics to support risk and control analysis, management and oversight. Reporting and insights Oversight is supported by proactive and regular reporting to relevant Executive and Board committees. Decision making is supported by connected and insightful risk and control analysis. Risk assurance We ensure that risks and critical controls are being implemented and managed effectively. Risk management framework Group roles and responsibilities, standards, procedures and guiding principles for effective, consistent and integrated risk management. Risk management effectiveness Our Approach to Climate Change 2021 | riotinto.com14
Part 1: Progress in 2021 As such, we set expectations that all our leaders and team members understand their risks, assess them in line with our values and Group policies and procedures, and respond. Where risks are material to the Group, they are escalated to the Risk Management Committee for oversight, and, as appropriate, to the relevant Board committees and the Board. Enhancing our resilience to physical climate risks is an important component of our climate change strategy. We use scenarios such as those developed by the Intergovernmental Panel on Climate Change (including the Representative Concentration Pathway 8.5 which has the highest warming) to inform our assessments of the probability and potential impact of these physical risks in the future. A desktop physical risk exposure assessment was conducted in 2018 and a summary of this assessment was published in our 2019 Climate Change Report. The analysis highlights that some of our operations have a high exposure to physical climate risk variables, and that these are material to Group revenue. Developing physical risk guidance in 2021 Following the Group-wide exposure assessment, the next stage has been to conduct asset-level risk assessments to confirm the effectiveness of our controls. This work was paused in 2020 due to the prioritisation of the COVID-19 response and restrictions on travel to our sites. In 2021, the Energy and Climate Change Centre of Excellence and Risk Area of Expertise have been preparing to engage the product groups for detailed risk assessments in 2022. Activities undertaken include: – Developing a physical risk assessment guidance note to support product groups on how to conduct a physical risk assessment. This leverages existing risk management processes and systems for tracking actions. – Piloting a physical risk assessment at the Winu copper project in Western Australia. The methodology was piloted with a physical risk assessment being conducted over the project’s scope of operations, logistics route to the port, and the port. The assessment highlighted the importance of participants having access to physical climate projections in a form that is readily understandable. A second key learning was the importance of community participation in the process to ensure risks were adequately identified and addressed. Lastly, the Winu assessment highlighted that many climate risk exposures identified were in fact causes or risk multipliers for existing risks. – Prioritising assets for future physical risk assessments. The Pilbara and the Saguenay (aluminium and hydro assets) were identified as priority areas for assessment in 2022, which aligns with the findings of the 2018 exposure assessment. Physical risk programme implementation in 2022 The Pilbara is an area with exposure to extreme weather including cyclones, flooding, drought and extreme heat. In mid-2022, the Iron Ore product group will conduct three workshops (depending on COVID-19 restrictions) to separately cover coastal port and mine operations, inland mining operations and infrastructure (power, rail and roads). The Aluminium product group has identified priority assessments at Vaudreuil and in the Saguenay where hydro-reservoir exposure to future climate variability could impact operations through both too little and too much water. Managing acute physical risk in the Pilbara Our 2019 report describes the series of controls in place to manage the threat of extreme weather at our iron ore operations in the Pilbara in Western Australia. In 2020, we continued our work to enhance asset resilience at these operations and started site construction works for a project to strengthen the Cape Lambert A jetty and wharf, and this work continued during 2021. These works also include replacing berthing and mooring dolphins, longitudinal strengthening of the jetty and protective coating remediation. The replacement of berthing and mooring dolphins is well advanced and is expected to be complete in early 2022 followed by the longitudinal strengthening works and finally the protective coating remediation of the jetty by mid-2022 to bring these current projects to an end. These controls will result in a significant improvement in structural integrity and asset life associated with our operations in the marine port environment. The Dampier Resilience Project has moved into implementation and is progressing through engineering and procurement activities with a site mobilisation in mid-2022. The project is forecast to be completed in late 2023. The scope of the project is to upgrade the 220kV transmission line between the Yurrayli Maya power station and Port Dampier, and develop a new bulk supply substation at Kangaroo Hill and 33kV distribution connections to Dampier. This critical project replaces assets at end-of-life with new, fit-for-purpose and resilient infrastructure to ensure power network stability, reliability and security. 15Our Approach to Climate Change 2021 | riotinto.com
In 2021, the Board announced its intention to put a Climate Action Plan (CAP) before shareholders and seek a non-binding advisory vote on the company’s ambitions, emissions targets and actions to achieve them. We will continue to publish our progress on climate change annually in line with the recommendations of the TCFD. This will include details of in-year implementation against the CAP and we are committed, as a matter of course in any given year, to regular engagement with shareholders and other stakeholders on our low-carbon transition strategy and its implementation. In view of the time horizons contemplated by the CAP, it is proposed that we would hold an advisory vote in relation to the CAP every three years. If we propose significant changes to the plan, we would put the amended plan to an advisory vote at the next AGM. The Board is fully aligned with this action plan and believes it will deliver value for our shareholders, our customers and wider society. 1. Scope 1 and 2 emissions targets and roadmap We have committed to reach net zero by 2050 and have set ambitious interim targets relative to our 2018 equity emissions baseline: – to reduce greenhouse gas (GHG) emissions by 15% by 2025; and – to reduce GHG emissions by 50% by 2030. Actions We will review and update our marginal abatement cost (MAC) curve annually to maintain a comprehensive technical and commercial assessment of our mitigation options. To achieve our 50% reduction target by 2030, we aim to: – Deploy solar and wind renewables at scale: – Install 1GW renewables to support supply to our Pilbara iron ore operations; and – Work with state and federal governments, power companies, and renewable developers to dramatically increase renewables generation in eastern Australia, aiming to develop green repowering solutions for the Boyne Island and Tomago smelters. – Advance the abatement projects in our MAC curve such as the deployment of zero emissions trucks and the use of hydrogen at our alumina refineries. – Use a $75/t CO2e internal carbon price to incentivise energy- efficiency investments and identify new mitigation projects. – Scale up the ELYSISTM technology to be available for installation from 2024. ELYSISTM is currently constructing the first commercial- scale prototype cells of the inert anode technology, at Rio Tinto’s Alma smelter in the Saguenay. – Build capability to develop carbon offset projects using nature- based solutions and CO2 mineralisation at or near our operations. We will follow the mitigation hierarchy and expect offsets to play a limited part in our decarbonisation strategy. As noted in the implementation plan, there are risks and dependencies to delivering the projects needed to achieve our 2025 and 2030 targets. In support of our roadmap and as we look beyond 2030, we are also investing and partnering in the development of new technologies needed for the decarbonisation of our hard-to-abate emissions. 2. Scope 3 emissions goals and customer engagement The best way for Rio Tinto to contribute to the net zero transition is to work in partnerships to help shape demand for low-carbon metals and minerals. Our approach to addressing Scope 3 emissions is to engage with our customers on climate change and work with them to develop and scale up the technologies to decarbonise steel and aluminium production. Steel value chain The future trajectory of our Scope 3 emissions is dependent on our customers’ decarbonisation roadmaps, which in turn will be guided by technology development and government policies, including carbon pricing. The Net Zero Steel Initiative (NZSI) has developed a set of scenarios to explore such potential pathways in the steel sector. Should the industry follow the NZSI Tech Moratorium scenario, we estimate that Rio Tinto’s iron ore-related Scope 3 emissions would fall by 23% by 2035 and 42% by 2040, relative to our 2020 emissions. Close to 95% of our Scope 3 emissions are generated in countries that have carbon neutrality pledges and about 28% of our iron sales are directly to steel producers that have already set public targets for their Scope 1 and 2 emissions (our Scope 3), and have ambitions to reach net zero by around mid-century. We will monitor this metric and report progress on an annual basis. In 2022, we commit to engage with all our direct iron ore customers, representing approximately 75% of our iron ore sales and related Scope 3 emissions, to share information on our respective climate change goals and roadmaps, and actively seek areas of mutual collaboration on pathways to net zero, such as those highlighted in our iron and steel decarbonisation goals. Our Climate Action Plan Part 2 Our Approach to Climate Change 2021 | riotinto.com16
Part 2: Our Climate Action Plan These engagements will add to our current approach to work in partnerships with customers, including Baowu, Nippon Steel, POSCO and BlueScope, as well as technology providers, research institutes and universities to progress the following iron and steel decarbonisation goals: – Support our customers’ blast furnace optimisation, with potential carbon emission reductions of up to 30%. – Explore future carbon neutral pathways for our Pilbara iron ores through: – existing and new technologies to beneficiate Pilbara ores; – a proprietary low-carbon research project using microwave energy and sustainable biomass as a reductant; and – assessing a mid-grade direct reduced iron (DRI) produced with green hydrogen and processed in an electric melter. – Pursue a project to produce hot briquetted iron (HBI) with high- grade iron ore and hydro-based green hydrogen in Canada. – Find a pathway to develop Simandou to meet the future demand of high-quality iron ore for low-carbon steelmaking technologies. Aluminium value chain As a leading producer of low-carbon aluminium, we are actively involved in the decarbonisation of the value chain from bauxite to alumina and primary metal production. About 74% of our Scope 3 emissions related to the downstream processing of bauxite and alumina sold to our customers is from the use of electricity, predominantly in China. The remainder is from the energy use for process heat at the alumina refineries of our bauxite customers and from the use of carbon anodes in aluminium smelting. Our plan is to address these through: – A commitment to engage with all our bauxite customers to seek areas of mutual collaboration in alumina decarbonisation projects, leveraging existing technical support relationships; – The continued development of the ELYSISTM inert anode technology, with the goal to have it available for installation at our smelters from 2024, following construction of large-scale commercial prototype cells at our Alma smelter in the Saguenay by 2023; and – Leveraging START, a new standard we launched in 2021 for transparency and traceability across the aluminium value chain, to support customer and consumer demand for sustainable products. Shipping We have an ambition to reach net zero emissions from shipping of our products by 2050 and expect to meet the International Maritime Organization (IMO) decarbonisation goal of 40% reduction in shipping emissions intensity by 2025, five years ahead of the IMO deadline. We expect to introduce net zero emission vessels into our portfolio by 2030, and in the meantime we are focusing on: – Improving existing vessels’ efficiency, including for our own vessels; – Increasing our use of transition fuels that deliver short to medium- term carbon emission reductions, through biofuel trials and the introduction of LNG dual-fuel vessels in our chartered fleet; and – Partnering to support the development of fuels that have the potential to deliver net zero solutions, such as green ammonia. 3. Capital allocation alignment with our 1.5°C decarbonisation strategy We are committed to align our future capital expenditure with our 2025 and 2030 Scope 1 and 2 emissions targets. Our Scope 1 and 2 targets and our commitment to reach net zero emissions by 2050 are aligned with efforts to limit warming to 1.5°C, which is aligned with the stretch goal of the Paris Agreement. We estimate that we will invest $7.5 billion in capital between 2022 and 2030 to deliver our decarbonisation strategy (approximately $1.5 billion over the period 2022 to 2024). We also expect our incremental operating expenditure to support the CAP to be in the order of $200 million per year, including research and development initiatives. For example, we plan to spend about $50 million on our iron and steel decarbonisation initiatives in 2022. We aim to phase out the purchase of diesel haulage trucks and locomotives by 2030. We are focusing our growth capex on commodities that enable the energy transition, including copper, battery materials, aluminium and high-grade iron ore. 4. Climate policy engagement We continue to encourage our industry associations to align their advocacy with the goals of the Paris Agreement. We review the climate advocacy of our industry associations each year, publish this review on our website and consider it when we decide whether to renew our membership. This review includes: – The purpose of the association and the value that the membership may provide to Rio Tinto and its investors; – The adequacy of governance structures within the industry association; and – The policy positions and advocacy of the industry association. 5. Climate governance The Board approves the Group’s approach to climate change and monitors progress in the delivery of the strategy. The Chief Executive is responsible for developing the Group’s business strategy, planning, investment, risk management and delivering the CAP approved by the Board. In the short-term incentive plan (STIP), safety, environment, social and governance matters including climate change are now assigned an explicit performance weighting of 35%, of which 20% relates to safety. The “E” component is 5% of the STIP and relates entirely to climate change performance objectives. In 2022, we will assess these at the Group level against two categories of objectives: – Progress on our Scope 1 and 2 targets: deliver our Group-wide short-term abatement target for Scope 1 and 2 emissions of 0.8Mt CO2e in 2022 (2.5% of STIP) – the utilisation of offsets is not included in these remuneration outcomes; and – Progress on our Scope 3 goals: the achievement of specific milestones relating to steel decarbonisation, zero-carbon aluminium, and shipping (2.5% of STIP). 6. Just transition We are committed to supporting a just transition to a low-carbon economy that is socially inclusive and provides decent work and livelihoods. Our commitment to implementing core business and human rights standards, including the UN Guiding Principles on Business and Human Rights (UNGPs), will continue to be integrated into our decarbonisation plans and actions. 7. TCFD disclosure We support the TCFD recommendations and are committed to aligning our disclosures with the Climate Action 100+ (CA100+) Net Zero Company Benchmark by 2023. There are some elements of the benchmark that are still under development and we will work with CA100+ and our investors to develop an approach that is applicable to the diversified mining sector. 17Our Approach to Climate Change 2021 | riotinto.com
Scope 1 and 2 targets and roadmap In early 2021, our Executive Committee embarked on a new strategy process, taking into consideration changes to our external context and a detailed diagnostic of our business. This review gave us the confidence that we could, and should, accelerate the transition of our operations towards net zero by 2050 and set more ambitious medium-term targets. The rapid shift in the external context on climate change was a key component of the strategy development process. This includes the increasingly ambitious emissions targets that many governments set in the lead up to COP26; developments in low-carbon technology and the falling costs of many of them, particularly renewables and electric vehicles; and changes in consumer sentiment. Our new ambitions were also informed by our latest analysis and understanding of decarbonisation projects and opportunities across the Group, captured in our marginal abatement cost curves. Our 2025 and 2030 targets We have brought forward our target of a 15% reduction in absolute Scope 1 and 2 emissions from 2030 to 2025 and established a new target to achieve a 50% reduction by 2030. Our four main sources of emissions are related to electricity, process heat, anodes and reductants, and diesel. Our 2030 targets are informed by a bottom-up, asset-by-asset analysis of mitigation options considering each of these sources. Our Energy & Climate Change Centre of Excellence worked with our product groups to develop the business-as-usual baseline and the analysis of potential emissions reduction opportunities across our portfolio. Between now and 2030, the Group-wide analysis highlights that the two most important decarbonisation levers are: first, switching the electricity we generate and purchase to renewables; and secondly, optimising processing plants in our alumina and minerals operations to reduce emissions from process heat. These reduction opportunities are: – Pilbara renewables (1.1Mt CO2e); – Pacific Aluminium Operations repowering (approximately 5.2Mt CO2e); – The projects included in our marginal abatement cost (MAC) curve which is updated each year (4.3Mt CO2e); and – Energy efficiency reductions that are too small for the MAC curve and other options such as the reductions achieved by the initial deployment of ELYSISTM and offsets (4.1Mt CO2e). We also have several initiatives under way to develop low-carbon solutions that will reduce and displace the use of diesel in our rail and mobile fleets, but at this stage we do not expect material emission reductions from these before 2030. There are risks and dependencies to delivering the projects to achieve our 2025 and 2030 targets. Many of the abatement projects identified are at early stages of development and it may be months or years before they reach final investment decision, construction and operation. Others may be dependent on local approvals or require collaboration with a wide range of stakeholders to achieve the large-scale low-carbon transformation that we are aiming for. Pilbara renewables In the Pilbara, we have one of the world’s largest micro grids, underpinned by 480MW of gas-based power capacity. The solar plant we approved at Gudai-Darri in 2020 is expected to come online in 2022, avoiding emissions of approximately 90,000t CO2e per year. We want to accelerate the transition by targeting the rapid deployment of 1GW of wind and solar renewables. Delivery of 1GW of renewables in the Pilbara will support abatement of approximately 1Mt CO2, with two-thirds driven by the displacement Implementing our Climate Action Plan Decarbonisation roadmap to 2030 0 5 10 15 20 25 30 35 20181 Business-as-usual2 Pilbara renewables M ill io n to nn es o f C O 2e Pacic Aluminium Operations repowering MACC projects2 Other3 2030 32.5 1.5 1.1 5.2 4.3 4.1 16.3 -50% 1. 2018 Scope 1 and 2 emissions equity baseline, adjusted for divestments. 2. The business-as-usual changes in emissions are the result of volume growth, asset closures and other operational factors. 3. Projects from our Marginal Abatement Cost Curve. 4. Other, including energy efficiency, ELYSISTM and carbon offsets. Our Approach to Climate Change 2021 | riotinto.com18
Part 2: Our Climate Action Plan Renewables Mobile diesel Process heat Anodes and reductants 200 0.5 100 -100 4.52.51.5 0 300 4.0 -150 -50 1.0 250 2.0 3.53.0 50 150 $/ tC O 2e Mt CO2e of gas-fired power generation, and the remaining abatement through the early electrification of our mobile fleet and the transition away from diesel. Beyond 2030, the full electrification of our Pilbara system, including all trucks, mobile equipment and rail operations, will require further gigawatt scale renewable deployment combined with advances in fleet technologies. Pacific Aluminium Operations repowering The Boyne smelter and Gladstone power station in Queensland and the Tomago smelter in New South Wales all operate in coal-based power grids. These facilities account for 28% of our Scope 1 and 2 emissions and more than half of our emissions from electricity use. Green repowering solutions are essential to the long-term sustainability of these operations. The scale of the smelters’ electricity use means that their transition must take into account the impacts on the broader grid and overall system requirements. This requires complex technical, commercial and political negotiations balancing the needs of multiple stakeholders. In October 2021, as an initial step in this process, we signed a Statement of Cooperation with the Queensland government to develop central Queensland into an industrial and advanced manufacturing hub, helping to deliver a more sustainable future for the area by fast-tracking renewables and attracting new green industries. The Marginal Abatement Cost curve Our updated 2021 MAC curve to 2030 includes 63 projects with potential abatement of 4.3Mt CO2e. The highest cost abatement opportunities are shown on the right side of the chart and require carbon price support to break even. Our longer-term net zero analysis indicates that higher carbon prices than shown here are needed for projects that will address harder-to-abate emissions post-2030. Although our abatement portfolio has increased in size since 2020, the abatement achieved by projects with a positive NPV (at a carbon price of $0) has stayed relatively consistent at 2.4Mt CO2e. In addition, about 30% of the reductions are from projects that require further technology development and more than 40% of the reductions are from projects at the conceptual stage of execution readiness. So, we face continuing challenges to improve the commercial returns and overall readiness of many of our abatement projects. The commercial returns of abatement projects will also be influenced by the level of local carbon prices, which currently remain relatively low in many of the countries where we operate. Marginal Abatement Cost Curve for Scope 1 and 2 emission abatement to 2030 Energy efficiency and other projects As a significant consumer of energy, we will use an internal carbon price of $75 per tonne of CO2 to drive improvements in energy efficiency across our assets and to identify new abatement projects. These are likely to be smaller projects or changes in operating practices that can reduce our energy costs and our emissions and are not included in the MAC curve. This final category also includes the reductions achieved by the initial deployment of ELYSISTM and limited use of offsets from projects developed at and near our sites. Progress towards our 2025 target We have so far reduced our Scope 1 and 2 emissions by 1.4Mt CO2 against our target baseline, from 32.5Mt CO2 in 2018 to 31.1Mt CO2 in 2021. The switch to renewable contracts at the Kennecott and Escondida copper operations accounted for about 1.2Mt CO2 of those reductions to date. Temporary operational disruptions, such as at Richards Bay Minerals and Kitimat, have also contributed to lower emissions in 2021. We expect these to bounce back as operations return to full production, and we also expect carbon emissions increases at some of our sites as we grow production between 2021 and 2025. Overall, we therefore estimate a need to plan, develop and implement 4.4Mt CO2 of abatement projects to meet our 15% emissions reduction target by 2025. This is an ambitious target with just three years for design, planning and physical construction of these projects to generate carbon reductions in 2025. We still have much work to do to progress our abatement projects and successfully deliver on our target. At the start of 2022, the maturity of our abatement projects pipeline is reflected by the following categorisation of the 4.4Mt CO2 of abatement required by 2025: – 0.3Mt CO2 from projects already approved but not yet executed; – 1.1Mt CO2 from projects yet to be approved but in advanced planning; – 3.0Mt CO2 from projects in early stages of design and planning or yet to be fully identified. Note: excl. PacOps repowering, ELYSIS and energy efficiency improvements 19Our Approach to Climate Change 2021 | riotinto.com
Net zero by 2050 In addition to the extensive work to progress and execute projects to meet our 2030 targets, we are also setting up the foundations for the next wave of abatements needed to reach net zero emissions across our operations by 2050. Although we have the outline of a broad pathway to net zero, we do not have all the solutions today. We are investing in research and development of many different low-carbon technologies across our carbon footprint, including plasma torches, alternative fuels, zero emission vehicles, inert anodes and the use of hydrogen. Decarbonising power A continued shift to renewables is central to meeting our 2030 targets and will remain an important area of focus beyond 2030, as we increasingly electrify our processes and mobile fleets – these will need to be supplied by green energy. Further repowering with renewables must be done in a way that reduces costs and maintains security of supply. Integration technologies and storage will be critical to the success of achieving a higher penetration of renewable energy. Long duration (>8 hours to <150 hours) energy storage will be required as we decarbonise our businesses through the adoption of renewable power from wind and solar sources as they become the dominant source of energy. In 2021 we became an anchor member of the newly created Long Duration Energy Storage Council that was launched at COP26. Through the Long Duration Energy Storage Council, we aim to partner with technology providers, industry and services customers, equipment manufacturers, capital providers and low energy system integrators and developers to discover how these technologies and their materials’ requirements can support us and society to decarbonise our energy systems. The Oyu Tolgoi (OT) Board, comprising Rio Tinto, Turquoise Hill Resources (TRQ) and the Government of Mongolia, reached an agreement that will move the underground copper project forward. It also approved an Electricity Supply Agreement to provide OT with a long-term source of power from the Mongolian grid. In meeting OT’s commitment to sourcing power domestically, Rio Tinto will work with the Government to support long-term renewable energy generation in support of the Mongolian grid. Decarbonising anodes and reductants Emissions from the use of anodes such as in our aluminium smelters are 6.4Mt CO2e today and a longer-term challenge. We established the ELYSISTM partnership in 2018 with Alcoa and with support from Apple and the governments of Canada and Quebec to develop the world’s first carbon-free aluminium smelting process, using inert anodes instead of carbon. Having achieved the first industrial scale smelting of zero-carbon aluminium at the ELYSISTM Industrial Research and Development Center, work is now focused on scaling up of the ELYSISTM technology towards the demonstration of even larger commercial-size cells in 2023. Construction of these prototype cells is underway at the end of an existing potline at Rio Tinto’s Alma smelter. The smelting cells will operate on an electrical current of 450 kA, which is the commercial scale for many large, modern aluminium smelters. Decarbonising process heat Our Processing Centre of Excellence is particularly focused on our process heat challenge, which will likely play out over several decades in some of our harder-to-abate operations in alumina, iron ore pelletisation and titanium dioxide. Technologies like hydrogen or plasma torches, which can use renewable energy, may provide a pathway to replace fossil fuels for heat and steam. Our current focus is to develop technologies and look for opportunities to pilot them. Four plasma torches were ordered in 2021 for a trial at the pelletising plant at IOC in Canada. In 2021, we formed two partnerships to research using hydrogen to reduce emissions in alumina refining: a study with the Australian Renewable Energy Agency to assess hydrogen use in industry and support a co-ordinated approach to developing a local supply chain, and a study with Sumitomo Corporation into building a hydrogen pilot plant at our Yarwun alumina refinery in Gladstone, Australia. Decarbonising mobile diesel (vehicles and rail) Mobile diesel is our fourth-highest carbon emission source at approximately 13% of total emissions. We completed analysis and concept modelling of emissions sources and energy needs at our fleet and have identified and prioritised zero emissions pathways. We are working to accelerate development of the required technology for switching to clean energy sources. In 2021 we launched the Charge On Innovation Challenge as Founding Patrons, alongside Vale and BHP and facilitated by Austmine. This global initiative challenges technology innovators to develop concepts for large-scale haul truck electrification systems to help the mining sector to reduce its consumption of diesel fuel and significantly cut emissions from surface mine operations. We are also fast-tracking the development of zero-emission mining haulage solutions, including autonomous haul trucks, through partnerships with key suppliers Komatsu and Caterpillar. We are also trialling the use of battery-electric trains to address the emissions from our rail fleet. We have purchased four 7MWh FLXdrive battery-electric locomotives ahead of initial trials in the Pilbara in early 2024. The locomotives, used to carry ore from the company’s mines to its ports, will be recharged at purpose-built charging stations at the port or mine. They will also be capable of generating additional energy while in transit through a regenerative braking system. Offsets and CO2 mineralisation Given the high cost of emissions reductions and lack of commercially viable low-carbon alternative technology for parts of our business, our long-term commitment is for our operations to be net zero emissions by 2050, rather than zero emissions. While we are prioritising emissions reductions at mines and smelters, we are also exploring the potential role of Nature-Based Solutions (NBS) and carbon capture and mineralisation. Carbon offsets and removals are expected to form a limited part of our decarbonisation strategy – as they are at the bottom of the mitigation hierarchy – and we are developing our internal capability to create a portfolio of offset projects. In 2021 we conducted a Group-wide assessment of the biodiversity and carbon potential of our landholding. We have identified several opportunities to develop carbon offsets at and near our sites such as in Madagascar, near QMM operations. These projects could also bring community and biodiversity benefits and we will continue to assess the opportunity in 2022. We are starting to explore carbon capture and mineralisation options leveraging our exploration and geological expertise. Carbon mineralisation is now being used at large scale in Iceland and promises to be a key technology in meeting global climate goals. We partnered with Carbfix to capture carbon and permanently store it underground at our ISAL aluminium smelter in Iceland. We have also launched a partnership with climate technology and research bodies to develop the ability to store carbon as rock at the Tamarack nickel project in Minnesota. The geology of the Tamarack site holds the potential to permanently store large amounts of carbon captured from the atmosphere or from hard-to-abate industries by mineralising it through natural chemical reactions. Implementing our Climate Action Plan continued Our Approach to Climate Change 2021 | riotinto.com20
Part 2: Our Climate Action Plan Scope 3 goals and customer engagement The best way for Rio Tinto to contribute to the low-carbon transition is to work with our customers to help shape demand for low-carbon metals and minerals. We need to tackle our Scope 3 emissions, as we fully appreciate that to thrive in the long term, we need to be part of net zero value chains. Our approach to addressing Scope 3 emissions is to engage with our customers on climate change and work with them to develop the technologies to decarbonise steel and aluminium production. Our ability to control these emissions is limited, so we want to work in partnerships, as the best solutions will come from global collaboration. In addition, we are working with our suppliers and shipowners to reduce emissions from other parts of our value chain. In 2022, we are committing to step up our engagements with our iron ore and bauxite customers, aiming to cover over 50% of our total Scope 3 emissions. The steel value chain Steel is one of the most efficient construction materials and has an essential role to play in the development of low-carbon infrastructure, transportation and buildings. Steel has a similar carbon footprint to hydro-based aluminium today, on a per tonne of product basis. However, with close to 2 billion tonnes of crude steel produced globally in 2021, the industry overall emits over 3 billion tonnes of CO2 annually, equivalent to around 8% of global carbon emissions. The transition of the steel value chain towards net zero carbon emissions will require an increased use of recycled scrap material to optimise the current blast furnace process route in the near term as well as the development of new technologies with net zero carbon potential for deployment over the medium to longer term. We anticipate an increase in the use of steel scrap, especially in China as the scrap pool rises, although this will depend on quality and quantity. However, we expect that more than half of future crude steel production will remain based on iron ore (compared to about two thirds today). Meanwhile, blast furnace optimisation will be driven by the use of higher-grade ores, including iron ore lumps and pellets, as well as the replacement of pulverised coal injection with hydrogen and the oxygen enrichment of the blast air enabling gas recycling. There is no proven process route at industrial scale to produce a net zero solution to steel today, but the industry is pursuing the development and scaling up of a range of new technologies, including hydrogen-based direct reduction iron feeding directly into an electric arc furnace or into a basic oxygen furnace via an intermediary melter step, direct smelting, the use of sustainable biomass, carbon capture, storage and use (CCSU), as well as more speculative technologies such as electrolysis. The speed and scale of deployment of these new technologies will be dependent on technological breakthroughs, trends in capital intensity to close the cost gap with existing production methods, and government policies, including carbon prices. The low-carbon transition pathway of the steel industry is uncertain today, but can be explored and better understood through scenarios. One such example is the scenario analysis presented in the Net-Zero Steel Sector Transition Strategy report1 published in October 2021 by the Net Zero Steel Initiative (NZSI). NZSI is an industry platform, part of the Mission Possible Partnership, that brings together stakeholders across the whole steel supply chain to help put the sector on a path to net zero emissions by mid-century. In this report, NZSI considers 20 technology archetypes and the decision making process to deploy these at individual steel plants based on lowest total cost of ownership. The analysis compares two pathways that deliver net zero emissions from the steel sector by 2050 against a baseline business-as-usual scenario: – Carbon Cost scenario: with a global carbon price (or policies equivalent to a carbon price) applied across all emissions and all geographies, rising globally from $9/t CO2 in 2023 to $250/t CO2 by 2050. – Tech Moratorium scenario: restricting major investment decisions post-2030 to technologies that are compatible with reaching a net zero outcome by 2050. 1. https://missionpossiblepartnership.org/wp-content/uploads/2021/10/MPP-Steel-Transition-Strategy-Oct-2021.pdf 21Our Approach to Climate Change 2021 | riotinto.com
Implementing our Climate Action Plan continued 1. Blast Furnace / Basic Oxygen Furnace 2. Direct Reduced Iron 3. Electric Arc Furnace Carbon Cost Tech Moratorium Baseline G t C O 2/ ye ar 2020 2025 2030 2035 2040 2045 2050 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0 2600 2020 2025 2030 2035 2040 2045 2050 2400 2200 2000 1800 1600 1400 1200 1000 800 600 400 200 Scrap + EAF Other new technologies DRI + EAF DRI + Melter + BOF Blast furnace optimisation0 M t S te el p ro du ct io n pe r y ea r DRI2 + Melter + BOF Natural gas based Natural gas with CCS/U 100% green hydrogen Blast furnace (BF/BOF1) Average technology Best available technology (BAT) BAT with H2 injection BAT with carbon capture and storage of utilisation (CCS/U) DRI2 + EAF3 Natural gas based Natural gas and bio-methane Natural gas and green hydrogen 100% green hydrogen Natural gas and CCS/U Other new technologies Smelting reduction Smelting reduction with CCS/U Electrolysis + EAF Electrowinning + EAF NZSI Tech Moratorium Scenario Technology Pathway Steel sector carbon emissions by NZSI scenario Our Approach to Climate Change 2021 | riotinto.com22
Part 2: Our Climate Action Plan The two NZSI net zero-aligned scenarios result in different carbon emission pathways for the steel industry, ranging from 15% to 37% emission reductions by 2030 (in Tech Moratorium and Carbon Cost respectively), and in excess of 55% by 2040, compared to the NZSI 2020 baseline. Assuming that the steel industry follows the NZSI Tech Moratorium scenario, our own analysis indicates that Rio Tinto’s iron ore-related Scope 3 emissions would fall by 23% by 2035 and 42% by 2040 from our 2020 baseline of 376Mt CO2, accounting for expected production growth at our Pilbara operations in Western Australia and the Iron Ore Company of Canada, and assuming the development of our Simandou project in Guinea. The NZSI analysis presents one view on a global basis and does not capture all the regional and commercial constraints to the deployment of new technologies. Nevertheless, it is a credible and useful illustration of the complexity and challenges faced by the steel industry to reach net zero by 2050. Asset-by-asset choices across a range of technology options will be dependent on local factors including capital intensity and the availability of competitive renewable energy, hydrogen, sustainable biomass or CO2 storage. We recognise we have a role to play to support the development of technologies that can accelerate the transition of the steel sector towards net zero. Our approach is to pursue and support a range of decarbonisation options aligned with the technology pathways highlighted by the NZSI analysis, through proactive partnerships with our customers, suppliers, universities and research institutes. We have consolidated these initiatives under six focus areas, with coordination from a dedicated steel decarbonisation team within our Commercial group. In 2019, we launched our flagship partnership with China Baowu Steel Group and Tsinghua University in China, and we have since announced collaborations with Nippon Steel in Japan, POSCO in South Korea and BlueScope in Australia. These partnerships are encouraging the sharing of ideas, deepening collaborations and focused on individual projects that cut across the overall decarbonisation priorities of the steel industry. Beyond these four partnerships we are also working across the value chain with other customers, technology providers, universities and research institutes as well as engaging with governments regionally and nationally to progress our iron ore and steel decarbonisation goals. These are summarised below, together with short-term objectives for 2022. In addition, we are engaging our iron ore customers about their Scope 1 and 2 emissions, decarbonisation plans and targets. There has been a rapid shift in sentiment in the sector in the past two years and this topic is often at the top of the agenda in our meetings with customers. More than 90% of our iron ore-related Scope 3 emissions are from customers in countries that have pledged to reach carbon neutrality by 2050-60. Today, about 28% of our iron sales are directly to steel producers that have already set public targets for their Scope 1 and 2 emissions (our Scope 3), with ambitions to reach net zero emissions by around mid-century and interim targets for the 2030s. We will update this percentage in future reports. These producers include the customers with whom we are already partnering to find technology solutions to decarbonise steel production. In 2022, we commit to engage with all our direct iron ore customers, approximately 75% of our sales and iron ore Scope 3 emissions, to share information on our respective climate change goals and roadmaps, and actively seek areas of mutual collaboration on pathways to net zero, such as those highlighted in our iron and steel decarbonisation goals. Beyond our direct sales we will also seek to engage with customers who buy our iron ore on a spot basis, through trading companies or from our China portside operations, recognising the greater challenges in tracking the point of final consumption and therefore sharing information. Our focus areas for iron and steel decarbonisation Multiple projects 1 Blast furnace optimisation Institutions and universities 2 Pilbara benefication Future pathways for Pilbara iron ore Pilbara pathway 1 3 Low-carbon research project Pilbara pathway 2 4 H2 DRI and melter Project – study phase 5 H2 DRI Canada High-quality iron ore 6 Simandou Customer partnerships We have a dedicated steel decarbonisation team 23Our Approach to Climate Change 2021 | riotinto.com
Goals Partnerships 2022 objectives 1. Blast furnace optimisation 99% of our iron ore is processed through the blast furnace route today, the optimisation of which could result in potential carbon emission reductions of up to 30%. We must work with our customers to help them generate those savings as an intermediary step. Our existing partnerships with Baowu, Nippon Steel and POSCO are largely focused on blast furnace optimisation as an initial stage, especially around the optimal use of lump ores and pellets. We are participating in the funding of a microwave lump drying pilot plan at one of Baowu’s production sites. With Nippon Steel, we will conduct some lab-scale test work for lump ores and explore a new grade of pellets. 2. Pilbara beneficiation Our Pilbara blend products have been optimised for the blast furnace process route and have impurities that might be more difficult to manage in emerging green steel technologies. These impurities must be removed upfront via beneficiation or during processing. Our goal is to explore how much upgrading of the ore can be done effectively prior to metallurgical processing. We are working with institutions and universities such as the Australian National University (ANU), together with our in-house Bundoora Technical Development Centre, on the development of new technologies to characterise and process Pilbara iron ores. We plan to complete a review of the qualities and characteristics of iron ore products suited to future low-carbon process routes, and the cost implications of producing those in the Pilbara. Based on this analysis we will prioritise and start testing a range of product options in lab-scale and pilot plant settings across different technology solutions. 3. Low-carbon research project Over the past decade we have been researching a method of processing Pilbara ores using microwave energy and sustainable biomass as a reductant. The process produces a pig iron type product for either an electric arc furnace or basic oxygen furnace. The overall steelmaking process has the potential to be carbon neutral or even carbon negative with additional carbon capture and storage. The low-carbon research project is based on proprietary technology, which we have been developing together with the University of Nottingham in the United Kingdom and tested at a lab-scale facility in Germany. We plan to complete laboratory test work using Pilbara ores in the first half of 2022, with a subsequent third-party review of results. We plan to start scaling up the technology and design a continuous pilot plant (CPP) for approval before the end of 2022. 4. Pilbara H2 DRI and melter An alternative to the beneficiation of Pilbara ores is the production of a mid-grade DRI product, with an intermediary electric melter step to remove impurities before processing into steel in an electric arc furnace or basic oxygen furnace. The use of renewable electricity and green hydrogen in the DRI process provides a pathway to net zero iron and steel. Our partnership with BlueScope is to investigate the use of green hydrogen to directly reduce Pilbara iron ores into a product that could then be processed in an electric melter. The partnership leverages BlueScope’s experience in using electric melters in New Zealand, and our knowledge in ore preparation and direct reduction. We plan to conduct a joint concept study to investigate the scale, process details and economics of constructing a pilot plant at BlueScope Port Kembla Steelworks in Australia to produce molten iron from our Pilbara ores via a green hydrogen direct reduction and renewable energy electric melter route. 5. Canada H2 DRI The direct reduction of high-grade iron ore pellets is already an available technology today using natural gas as a reductant to produce a low-carbon iron product that can be directly processed in an electric arc furnace. Switching from natural gas to green hydrogen would make this a net zero process route. We are engaging with direct reduction technology providers, leading hydrogen producers and the Governments of Canada and Quebec as we pursue early-stage studies of a project to produce HBI with hydro-based green hydrogen and high-grade iron ore pellets from the Iron Ore Company of Canada (IOC). We plan to complete an order of magnitude study in early 2022 and subject to reviews and approvals we expect to commence the next phase of study for this project by the middle of 2022, including the consideration of partnership options. 6. Simandou The shift to new, green, technologies will require more high-quality iron ore and we pursuing pathways to developing our high-grade Simandou deposit in Guinea. The resource contains a significant proportion of ore that can meet direct reduction specifications. Rio Tinto is pursuing the Simandou project in joint venture with the Government of Guinea as well as Chinese partners through Chalco Iron Ore Holdings, including Chinalco and Baowu. We continue to engage with key stakeholders, including the Government of Guinea. A new drilling programme has commenced and some early development works are expected to be carried out in 2022. Implementing our Climate Action Plan continued Our Approach to Climate Change 2021 | riotinto.com24
Part 2: Our Climate Action Plan The aluminium value chain Aluminium is a lightweight material essential to the low-carbon transition across a range of end-use sectors including transportation, green energy infrastructure, packaging and buildings. However, the aluminium smelting process is energy intensive and across its full value chain the aluminium industry emits about 1 billion tonnes of CO2e annually. As one of the leading global producers of low-carbon aluminium, our effort to further decarbonise our assets is core to our engagement with the industry and our customers on Scope 3 emissions from the sale of our bauxite and alumina. We operate assets across each step of the aluminium value chain, and have committed to decarbonise these assets as part of our 1.5°C aligned Group-level targets. In addition, we are actively involved with the International Aluminium Institute (IAI) and the Aluminium Stewardship Initiative (ASI) in the development of a 1.5°C pathway for the aluminum industry, and we are committed to support the transition. The key steps are broadly defined in the IAI “Aluminium Sector Greenhouse Gas Pathways to 2050”1 report published in September 2021 and cover the decarbonisation of electricity and direct emissions as well as a focus on recycling and resource efficiency. Recycling and resource efficiency Aluminium is infinitely recyclable, without loss of properties, and with a significantly reduced carbon footprint compared to primary production. The recycling of post-consumer scrap today is estimated to avoid about 300 million tonnes of annual CO2e emissions. Increased recycling rates and reduced metal losses during processing and melting activities are expected to further reduce the carbon intensity of the sector. However, aluminium recycling rates are already high, in excess of 90% in some key end-use sectors, and the production of primary aluminium is therefore expected to continue to grow in the coming decades to meet overall demand. Electricity decarbonisation Over 60% of the primary aluminium industry’s carbon emissions are related to the use of electricity in the smelting process, of which more than two thirds originate from China given the country’s share of global production and its predominant reliance on coal-based power. As a large proportion of our bauxite and alumina sales are to customers in China, indirect emissions from the use of electricity account for 74% of our related Scope 3 emissions. Our ability to influence emissions from these sources is extremely limited, especially regarding the overall decarbonisation process of China’s power grid. Some aluminium producers in China currently draw power from captive thermal power stations and have already started to relocate some production capacity to regions such as southwest China with hydro-based power options today. In addition, as the overall power grid decarbonises it is possible that some smelters will shift from captive to grid power over time. Renewable power solutions such as wind and solar are readily available, although a challenge for the aluminium industry is the sourcing of firmed green power given the limited interruptibility of the aluminium smelting process. Direct emissions Beyond the use of electricity, emissions are mostly related to the combustion of carbon anodes in the aluminium smelting process and the use of energy for process heat in the alumina refining process. These emissions sources each account for about 14% and 12% respectively of Scope 3 emissions related to our bauxite and alumina sales. Our work on inert anode technology through the ELYSISTM joint venture is progressing towards industrial scale and is also part of our Scope 1 and 2 decarbonisation roadmap. Construction of large commercial-scale demonstration cells operating on an electric current of 450kA is underway at the end of an existing potline at our Alma aluminium smelter in Quebec, keeping the development pathway on track for the technology to be available for installation from 2024. Meanwhile, in the context of alumina refining, we lead the way in the use of renewable electricity at our Vaudreuil refinery in Quebec and are exploring hydrogen calcining technology at Yarwun in Australia. In addition, an essential element of our marketing offering in bauxite and alumina is technical support. Our technical teams continuously engage with our customers to support optimal processing conditions of our products in their facilities. In China, we see continued positive engagement in this area, strengthened by China’s environmental protection initiatives and stated peak carbon and carbon neutral goals. We commit to actively engage in 2022 with all our bauxite customers to explore more opportunities to improve the energy efficiency of their alumina refining processes and seek potential areas of mutual collaboration in alumina decarbonisation projects. Beyond our Scope 3 boundary, we are also engaging with our customers’ customers further downstream in the value chain. End users in the transport, packaging and electronic sectors are seeking a transparent, sustainable and verifiable supply chain – this is driven by consumer demand as well as our customers’ own commitments towards net zero. In 2021, we launched START, a new standard in transparency and traceability for the aluminium industry, enabling customer demand for low or zero carbon products to be supported through verifiable ESG credentials via secure blockchain technology. Direct/indirect emissions apportioning indicative using International Aluminium Institute (IAI) Primary aluminum life cycle 1. https://international-aluminium.org/resource/aluminium-sector-greenhouse-gas-pathways-to-2050-2021/ 86% direct emissions 14% indirect emissions from electricity 16% direct emissions Rio Tinto bauxite sales Customers’ alumina reneries Customers’ aluminium smelters 15Mt alumina38Mt bauxite 3Mt alumina Rio Tinto alumina sales 124Mt CO2e 20Mt CO2e 84% indirect emissions from electricity Downstream bauxite and alumina Scope 3 emissions 25Our Approach to Climate Change 2021 | riotinto.com
Shipping In 2021, emissions from the bulk maritime shipping of our products were 7.6Mt CO2. This includes Scope 3 emissions of 4.9Mt CO2 from about 230 chartered vessels and 2.3Mt CO2 from customer-managed freight, as well as Scope 1 emissions of 0.4Mt CO2 from 17 Rio Tinto-owned vessels. Over 72% of our total bulk shipping emissions are related to the shipping of iron ore, 22% to the shipping of bauxite and the remainder related to other products and raw materials supply. We have an ambition to reach net zero emissions from shipping of our products by 2050 and expect to meet the International Maritime Organization (IMO) decarbonisation goal of 40% reduction in shipping emissions intensity by 2025, five years ahead of the IMO deadline. We expect to introduce net zero emission vessels into our portfolio by 2030, and in the meantime we are focusing on: – improving existing vessels’ efficiency; – increasing our use of transition fuels that deliver short- to medium-term carbon emission reductions; and – partnering to support the development of fuels that have the potential to deliver net zero solutions. Vessel efficiency Between 2022 and 2024, we plan to conduct a range of modifications to Rio Tinto’s owned vessels, which are collectively expected to deliver more than 10% of carbon emission reduction. These include applying high-performance paints to reduce friction, modifications of the propellers, and installing swirl ducts enhancing energy efficiency. In addition, we continue to work with our shipowners to improve the operational and technical efficiency of our chartered vessels and we plan to test new innovative solutions. Transition fuels In 2021, we signed charterparty contracts for nine LNG dual-fuel Newcastlemax vessels which will be delivered in the second half of 2023. We will also be starting an extended biofuel trial with one of our owned vessels in early 2022. We will use a B30 biofuel blend of vegetable oils (excluding palm oil or palm oil residues), waste oils, and animal fats, with the potential to reduce lifecycle CO2e emissions by 26%. Net zero fuels Green ammonia has the potential to support net zero shipping, but engines to use ammonia as a fuel are not yet available, and significant efforts will be required to develop appropriate regulation, scale up fuel production, and support bunkering infrastructure. In 2021, we joined an industry group led by ITOCHU to study common issues related to the use of ammonia as a maritime fuel. Further to this, in January 2022 we signed a Joint Development Agreement in partnership with ITOCHU, K-Line, NS United and Nihon Shipyard to develop an ammonia vessel design and further collaborate on the development of the ammonia supply chain. Implementing our Climate Action Plan continued Capital allocation alignment with our decarbonisation strategy We will align our capital expenditure plans with our long-term carbon emissions reduction targets, which are in line with the Paris Agreement’s objective of limiting global warming to 1.5°C. Having divested the last of our coal businesses in 2018, we are orienting our growth capex towards materials that enable the energy transition, including copper, lithium and high-grade iron ore. Our ambition is to increase our growth capital up to $3 billion per year in 2023 and 2024, developing new options and finding innovative ways of bringing projects onstream faster. We expect to invest around $500 million in each of the years from 2022 to 2024 on decarbonisation projects, mainly relating to the repowering of the Pilbara. Decarbonisation investment across the rest of the Group will accelerate from 2025, bringing our best estimate to around $7.5 billion this decade. This capex includes full decarbonisation of the Pilbara electricity system, an initial deployment of ELYSISTM and other abatement projects. These projects will deliver a range of economic outcomes but in aggregate are value accretive at a very modest carbon price. Most importantly, they safeguard the integrity of our assets over the longer term and reduce the risk profile of our cash flows. We will also work with third parties through long-term contracts. For our standalone Pilbara system, at least initially, it makes sense for us to fund renewables, but we may also leverage third-party investments, particularly where our assets are grid connected. This is the more likely solution for our two coal-powered smelters in Australia, which would require the deployment of 4-6GW of solar and wind power on an equity basis as well as robust firming, so this is not included in the $7.5 billion capital expenditure noted above. These decisions will of course go through the same rigorous investment process we have for all our projects and we will remain open-minded about the right mix of direct investment and third-party contracts. We have introduced an internal carbon price of $75/t CO2 to provide the incentive to accelerate the delivery of capital investment in abatement projects and energy-efficiency improvements. There will be incremental operating expenditure on building new capabilities, energy-efficiency initiatives, and research and development in the order of $200 million a year. In 2022, we plan to spend about $50 million on our iron and steel decarbonisation initiatives. This does not include spend for the replacement of carbon-intensive opex with zero-carbon alternatives. Having divested the last of our coal businesses, we are also phasing out investment in some other carbon-intensive assets. By 2030, we aim to phase out the purchase of diesel haulage trucks and locomotives. Our Approach to Climate Change 2021 | riotinto.com26
Part 2: Our Climate Action Plan Climate policy engagement In 2015, we supported the adoption of the Paris Agreement and the long-term goal to limit global average temperature rise to well below 2°C and to pursue efforts to limit warming to 1.5°C. Government policy that creates the right framework for change is critical, coupled with real business action and societal shifts. A challenge as serious as climate change requires transparency, collaboration and a shared contribution to the solution. Summary of our positions on climate and energy policy 1 We accept the mainstream climate science assessed by the Intergovernmental Panel on Climate Change. 2 We support the Paris Agreement and ambitions to reach net zero by 2050. We acknowledge that in the Glasgow Climate Pact, governments resolved to pursue efforts to limit the global temperature increase to 1.5°C which “requires rapid, deep and sustained reductions in global greenhouse gas emissions, including reducing global carbon dioxide emissions by 45 per cent by 2030 relative to the 2010 level and to net zero around mid- century, as well as deep reductions in other greenhouse gases”. 3 We acknowledge that business has a role to play in addressing and managing the risks and uncertainties of climate change. 4 We believe that effective climate policies should incentivise the private sector to invest in low-carbon technology while maintaining the competitiveness of trade-exposed industries. 5 We recognise the importance of adaptation and resilience to a changing climate. 6 Where climate policies are implemented, we support the use of market mechanisms, including carbon prices. 7 We do not advocate for policies that undermine the Paris Agreement or discount Nationally Determined Contributions (NDCs). 8 We promote our climate and energy policy positions in discussions with our industry associations. Significant global and regional progress on climate change will only happen when everyone – business, governments, investors, civil society organisations and consumers – plays their part. Our own approach to climate change requires active engagement on relevant policies with a range of stakeholders in the countries where we operate. Working with our industry associations Industry associations play an important role in policy development, sharing best practice and developing standards. Our approach to engaging with industry associations has been approved by the Rio Tinto Board. Responsibility for comparing Rio Tinto’s positions with those of individual industry associations is delegated to management on a “comply or explain” basis. In 2021, our Chief Executive chaired a subcommittee of CEOs at the International Council on Mining and Metals (ICMM) to review and update ICMM’s position statement on climate change. A coordinated, joint response by the whole industry is essential to meet the challenge of climate change, and the statement reaffirms our commitment to the goal of net zero emissions by 2050 or sooner. We have made this collective commitment because we believe many of the sustainability challenges facing our industry, and the planet, require collective action to solve. The ICMM statement also includes a commitment for all members of ICMM to set Scope 3 targets by the end of 2023, such as the ones we have proposed in our Climate Action Plan. Recognising that industry associations’ views will not always be the same as ours, we monitor the advocacy of all our industry associations and periodically review our memberships. This assessment includes: – the purpose of the association and the value that membership may provide to Rio Tinto and its investors; – the adequacy of governance structures within the industry association; and – policy positions and advocacy. In 2021, we supported a shareholder-requisitioned resolution on industry association memberships and enhanced our approach to reviewing and engaging with our industry associations on climate advocacy. Our annual review of all our industry association memberships supplements this report and can be found on our website. Industry association policy and advocacy alignment Where our membership is significant, we will work in partnership with industry associations to ensure that their policy positions and advocacy are consistent with our own public position and the Paris Agreement. In accordance with the provisions governing the monitoring of our industry association memberships, we will review our support and membership of industry associations where they do not align with our own public position and the Paris Agreement. 27Our Approach to Climate Change 2021 | riotinto.com
Implementing our Climate Action Plan continued Climate governance Climate change is a material and strategic topic for Rio Tinto and is therefore part of ongoing discussion and analysis at the most senior levels of management and the Board. It is also a key topic when the Board and Executive Committee engage with investors and civil society organisations. The Board approves our overall strategy, our policy positions and the Climate Change Report. It sets the short-, medium- and long-term emissions targets and monitors performance against the targets and operational resilience. The Chairman is the Board member responsible for our overall approach to climate change. The Sustainability Committee has oversight of key sustainability areas that may be impacted by climate change, such as biodiversity and water, including the effectiveness of associated controls. The Sustainability Committee also reviews industry association engagement. Other Board committees also address particular climate issues such as how we consider our scenarios in our Financial Statements (Audit Committee) or the integration of climate-related performance metrics into short-term incentive plans (Remuneration Committee). We base our appointments to the Board on merit, and on objective selection criteria, with the aim of bringing a range of skills, knowledge and experience to Rio Tinto. We aim to appoint people who will help us address the operational and strategic challenges and opportunities facing the company and ensure that our Board is diverse in terms of gender, nationality, social background and cognitive style. The key skills and experience of our Board are set out in the Annual Report. This explicitly assesses Board competencies for climate-related threats and opportunities, using the following criteria: knowledge and understanding of climate science, low-carbon and energy transition and climate-related public policy. Six directors meet one or more of the criteria above. The Chief Executive is responsible for delivering the strategy approved by the Board. Risk management, portfolio reviews, capital investments, annual financial planning and our approach to government engagement all integrate our approach to climate change and target execution considerations. The Chief Executive led a strategy process with the Executive Committee in mid-2021 which puts the low-carbon transition at the heart of our business strategy. The Planning Review Committee focuses on our short-term (12 months) and medium-term (up to 10 years) plans and integrates the new growth and decarbonisation strategy into the financial planning process. The Chief Technology Officer, the Executive Committee member accountable for delivering our Scope 1 and 2 emissions targets, works closely with the product group Chief Executives to implement the mitigation projects. The Chief Technology Officer also oversees the Energy & Climate Change Centre of Excellence, a newly established Energy Development team (which focuses on developing large-scale renewable power options) and the low-carbon research and development work led by the Chief Scientist. Strengthening the link between executive remuneration and our climate performance Since 2018, our Chief Executive’s performance objectives in the short-term incentive plan have included delivery of the Group’s strategy on climate change. These are cascaded down into the annual objectives of relevant members of the Executive Committee, including the product group Chief Executives, and other members of senior management. In 2021, the business achieved the approval of 0.26Mt CO2 of abatement projects (and exceeded the total 0.5Mt CO2e targeted for 2020 and 2021). The approved projects included small renewable projects at Weipa, QIT Madagascar Minerals (QMM) and Kennecott, as well as several energy efficiency projects and small low-carbon technology pilots. We also delivered three out of the four Scope 3 goals. In 2022, safety, environment, social and governance matters, including climate change, are assigned an explicit performance weighting of 35% in the STIP, of which 20% relates to safety. The ‘E’ component is 5% of the STIP and relates entirely to climate change performance objectives. In 2022, we will assess these at the Group level against two categories of objectives: 1. Progress on our Scope 1 and 2 targets (2.5%) Total projects to be approved in 2022 are expected to reduce emissions in 2025 by 0.8Mt CO2e. Over half of the abatement is from renewables and the average scale of these projects is higher than in 2021. 2. Progress on our Scope 3 goals (2.5%) Steel decarbonisation – Commence phase 2 of a study to produce hot briquetted iron production with green hydrogen in Eastern Canada; – Complete laboratory test work on low-carbon research project using Pilbara ores and obtain a third-party review of the results. Present and communicate these results to customers and the market. Obtain approval to commence construction of the continuous pilot plant. Zero-carbon aluminium – Identify potential sources of raw material feedstock for inert anodes, define a work plan to develop a viable electrode production process, and determine technology deployment plan across our smelters. Shipping – Collaborate with shipowners to enhance the reporting of emissions with actual figures rather than factored estimates. Further detail is available in the remuneration section of our 2021 Annual Report. Board engagement on climate change in 2021 Climate change and the low carbon transition are routinely on the Board’s agenda, including as part of strategy discussions, risk management, accounting and executive remuneration. – Endorsed our strategy to put the low-carbon transition at the heart of our business – Approved 2025 and 2030 Scope 1 and 2 targets, our net zero commitment and our Scope 3 goals – Remuneration Committee approved revisions to the way climate change is integrated into executive incentives – Engaged with investors and civil society organisations following the publication of our strategy and new 2030 targets – Approved 2020 Climate Change Report and approach to industry associations – Approved the decision to put a non-binding, advisory Say on Climate resolution to the 2022 AGMs, and endorsed the approach to be taken on the resolution Our Approach to Climate Change 2021 | riotinto.com28
Part 2: Our Climate Action Plan Just transition As the world continues to advance the Paris Agreement, managing the human risks to, and opportunities generated by the transition to a low-carbon economy will be crucial. The Paris Agreement highlights this point, emphasising the need to take “into account the imperatives of a just transition of the workforce and the creation of decent work”. We are committed to supporting a just transition that is fair, socially inclusive, recognises the specific risks to marginalised and Indigenous groups within host communities, and that helps provide opportunities for continued access to decent work, good health and sustainable livelihoods. We have an important role to play in this transition, including through early and ongoing identification of risks and opportunities within our operations and in our value chain; engaging in social dialogue and stakeholder engagement to support fair and inclusive practices; and participating in relevant and emerging policy developments. As we further evolve our business strategy to contribute to, and thrive in, a low-carbon future, we will work to understand any potential impacts – positive and negative – on human rights, particularly those of vulnerable groups, as we navigate how advancements in new low-carbon technologies and new operational processes change the way we work. This includes engaging with Traditional Owners as we develop and scale up wind and solar projects that occupy large areas of land. Identifying such impacts is part of our human rights due diligence process and is consistent with our broader commitment to implement core business and human rights standards into our decarbonisation plans and actions – including the UN Guiding Principles on Business and Human Rights, the ILO Declaration on Fundamental Principles and Rights at Work, and the UN Declaration on the Rights of Indigenous Peoples. In some cases, accelerating emission reductions could lead to early plant closures and in turn, reducing employment opportunities with our company. This could have a particularly negative impact on remote communities that rely on mining and industrial activities for their livelihoods. In these situations, we will engage as early as possible with host governments and communities to identify potential adverse impacts and facilitate their options for ongoing social and economic benefit. We will to support our workers to transition to other opportunities either with Rio Tinto, other resource companies in different locations, or to transition to new industries altogether. The recently closed Argyle Diamond mine provides an example of how we are partnering with Indigenous representative organisations to support future business. We have awarded over $60 million of contracts to Traditional Owner businesses to support the assets’ transition to their next use, which is likely to be Traditional Owner-led agribusiness. We have also actively worked to redeploy our Argyle employees to other Rio Tinto sites or supported them to transition to other jobs through our `Life after Argyle Program’. Each of our operations is required to develop a closure plan prior to the commencement of operations and to maintain this across the life of asset, informed by community, Traditional Owners and regulator expectations regarding future land use and their social, cultural and environmental objectives for the transition to viable post-mining land use. This plan forms the basis to calculate the closure liability at each of our assets, which is publicly reported as the Group closure provision. This year we have enhanced our disclosure on provisions for close- down and restoration costs and environmental clean-up obligations, which at 31 December 2021, were $14.5 billion (31 December 2020: $13.3 billion). To further support communities in the social and economic transition post-closure, in 2021 we committed to investing $18 million over the next 10 years to support the work of the Cooperative Research Centre for Transition in Mining Economies and have invested over $10 million on innovation to improve the ongoing social and economic opportunities from closed sites. We also co-founded Regeneration Enterprises in 2021, a joint venture with US-based NGO RESOLVE. The enterprise will help deliver enhanced environmental and community outcomes from our closed and legacy sites through remining wastes and developing carbon and biodiversity credits to provide ongoing economic benefits to host communities while delivering enhanced environmental outcomes. Our initial $2 million start-up investment in 2021 will be supplemented with additional project-related investment of over $14.5 million in 2022. Another important way we can support progress toward a just transition is by actively and constructively collaborating with others. For this reason, in addition to working with civil society, supply chain partners, host communities and governments, in 2022 we will also join with like-minded global companies in a collaboration by Business for Social Responsibility (BSR) and the B Team. This coalition will create tools and guidance to help enable a more worker- and community- centred transition to a net zero economy. 29Our Approach to Climate Change 2021 | riotinto.com
TCFD disclosure We support the recommendations from the TCFD and also welcomed the CA100+ Net Zero Company Benchmark when it was published in 2020. We are committed to continue to align our climate change disclosures with both these frameworks. We are also working with CA100+ as it develops its approach to evaluating diversified mining companies against that benchmark. The CA100+ calls on companies to reduce emissions by 45% relative to 2010 levels by 2030, which aligns with the emissions pathway described in the Intergovernmental Panel on Climate Change report on 1.5°C. Our target to reduce absolute Scope 1 and 2 emissions by 50% compared with 2018 levels1 by 2030 exceeds this objective. How we have considered our climate change scenarios in our Financial Statements The Directors have considered the relevance of the risks of climate change and transition risks associated with achieving the goals of the Paris Agreement when preparing and signing off the company’s accounts. The narrative reporting on climate-related matters is consistent with the accounting assumptions and judgments made in this report. The Audit Committee reviews and approves all material accounting estimates and judgments relating to financial reporting, including those where climate issues are relevant. 1. Our 2030 target covers >95% of our Scope 1 and 2 emissions and is relative to our 2018 equity emissions baseline. Implementing our Climate Action Plan continued In developing its commodity price forecasts, the Group considers three strategic scenarios with differing underlying assumptions about geopolitics, technology and society. As existing climate policies in many countries are not aligned with achieving the Paris Agreement, only one of the three strategic scenarios assumes a temperature increase of well below 2°C. The three scenarios include differing assumptions on carbon pricing and result in differing commodity price forecasts. Our central case commodity price forecasts represent a blend of the three scenarios. As a consequence, our central case is not aligned with the goals of the Paris Agreement. These central case commodity price forecasts are used pervasively in our financial processes including impairment testing, estimating remaining economic life, and discounting closure and rehabilitation provisions. We have disclosed sensitivity information based on cash flows flexed for the carbon and commodity price forecasts generated by the one scenario that we believe is consistent with achieving the goals of the Paris Agreement. These sensitivities indicate that, in relation to impairment testing for example, higher recoverable amounts would have been determined had we applied commodity price forecasts aligned with the Paris Agreement. In addition to commodity price forecasts, given the significant investment we are making to abate our carbon emissions, we have also considered the potential for asset obsolescence, with a particular focus on our investments in the Pilbara, but no material changes to accounting estimates have been necessary. The closure date and cost of closure is also sensitive to climate assumptions, but no material changes have been made in the year specific to climate change. Our Approach to Climate Change 2021 | riotinto.com30
Emissions and energy data GHG emissions summary – equity basis Equity greenhouse gas emissions – million tonnes carbon dioxide equivalent (Mt CO2e) 2021 2020 2019 2018 2010 Total Scope 1&2 GHG emissions 31.1 31.5 31.5 34.0 44.53 Scope 1 emissions 22.7 22.8 23.1 24.7 Scope 2 emissions 8.4 8.7 8.3 9.3 2018 GHG emissions target baseline (adjusted for acquisitions & divestments) 32.5 Scope 3 emissions1 553.5 570 – – Operational greenhouse gas emissions intensity (tCO2e / t Cu-eq)(equity)2 6.4 6.2 6.1 6.2 2021 equity greenhouse gas emissions by product group & source (Mt CO2e) Electricity4 Anodes & Reductants Process Heat Mobile Diesel Other 2021 Total emissions (Mt CO2e) Aluminium 10.4 5.2 4.9 0.3 1.1 21.9 Aluminium (Pacific) 8.1 1.7 0.2 0.0 0.2 10.2 Aluminium (Atlantic) 0.6 3.5 0.5 0.0 0.6 5.2 Bauxite & Alumina 1.6 0.0 4.3 0.3 0.3 6.5 Minerals 1.4 1.2 0.5 0.3 0.1 3.4 Iron Ore 0.8 0.0 0.1 2.1 0.0 3.0 Copper 1.3 0.0 0.2 0.8 0.0 2.2 Other (includes Shipping and corporate functions) 0.1 0.0 0.0 0.5 0.0 0.6 Total 14.0 6.4 5.6 4.0 1.1 31.1 2021 equity greenhouse gas emissions by location (Mt CO2e) Scope 1 emissions (Mt CO2e) Scope 2 emissions (Mt CO2e) Total emissions (Mt CO2e) Australia 12.8 6.0 18.8 Canada 6.0 0.0 6.0 South Africa 0.3 1.1 1.4 USA 1.0 0.0 1.0 Other: Rest of Africa 0.2 0.0 0.2 Other: Europe 0.4 0.0 0.4 Other: Asia, New Zealand, Central America, South America 2.0 1.3 3.3 Total 22.7 8.4 31.1 Restatement of 2018 emissions baseline and progress towards our 2030 targets 31.5 31.0 32.0 32.5 33.0 A djusted 20 18 B aseline (in 20 20) RTA A djusted 20 18 B aseline (in 20 21) RTC RTIO RTM O ther 20 20 RTA RTC RTIO RTM O ther 20 21 32.6 32.5 0.28 0.77 0.31 0.23 0.03 31.5 0.10 0.46 0.03 0.07 0.01 31.1 1. 2020 Scope 3 emissions have been re-estimated using the 2021 methodology (using the 2020 methdology our Scope 3 emissions were reported as 519.4Mt CO2e) 2. Historical information for copper equivalent intensity has been restated in line with our 2021 review of commodity pricing to allow comparability over time 3. Our estimated 2010 equity emissions total of 44.5Mt CO2e includes emissions of 9.5Mt CO2e from assets that were divested between 2010 and 2018. 4. Electricity includes imported power and own generation; process heat includes diesel consumption from stationary sources such as pumps; mobile diesel sources are haul trucks, locomotives and other mining fleet. Note: The sum of the categories may be slightly different to the Rio Tinto total due to rounding. 31Our Approach to Climate Change 2021 | riotinto.com
Carbon intensity curves of global commodity producers by sector Pac.Al Atl.Al RT Pac Al 0 5 10 15 20 tC O 2/ t A l Global production Industry average 0% 25% 50% 75% 100% Aluminium Iron Ore IOC RT Pilbara kg C O 2/d ry t of ir on o re Global production Industry average 0% 25% 50% 75% 100% 0 50 100 150 200 RT 1.5 2.5 1.0 0.5 2.0 0 t C O 2/ t A l 2O 3 Global production Industry average 0% 25% 50% 75% 100% Alumina Copper RT With full KUC RECs + Escondida repowering 0 5 10 15 tC O 2/tC uE q Global production Industry average 0% 25% 50% 75% 100% Source: CRU, Wood Mackenzie, Rio Tinto analysis, 2020 data Scope 1 and 2 emissions – 100% managed basis Total managed greenhouse gas emissions (Mt CO2e) 2021 2020 2019 2018 2017 2010 Scope 1 Emissions 16.9 17.1 17.2 18.0 20.0 27.2 Scope 2 Emissions 9.3 9.5 9.7 11.0 11.0 17.0 Total Emissions 26.1 26.6 26.9 29.0 31.0 44.2 Total managed GHG emissions equal the sum of Scope 1 emissions and Scope 2 emissions minus the Scope 1 emissions resulting from the supply of electricity and steam to third parties. 2021 sources of electricity used (managed operations) 4% 1% 71% 1%8% 15% Hydro Diesel Coal Natural gas Other renewables Others Emissions and energy data continued Our Approach to Climate Change 2021 | riotinto.com32
Scope 3 emissions summary Total equity Scope 3 greenhouse gas emissions (million tCO2e) 2021 2020 Scope 3 - Upstream 27.5 242 Scope 3 - Downstream 526 5462 Total 553.5 570 Sources of Scope 3 equity emissions1 2021 2020 Upstream emissions 1 Purchased goods and services 16.3 14.32 2 Capital goods 1.9 1.42 3 Fuel and energy related activities 2.9 2.8 4 Upstream transportation and distribution 5.9 5.1 5 Waste generated in operations 0.1 0 6&7 Business travel & employee commuting 0.4 0.14 8 Upstream leased assets Not applicable3 Not applicable Downstream emissions 9 Downstream transportation and distribution 2.7 3.0 10 Processing of sold products Iron Ore 364.6 376.4 Bauxite & alumina 144.5 1522 Titanium dioxide feedstock 4.9 5.8 Copper concentrate 0.5 0.6 Salt 7.2 6.0 Other5 1.6 2.0 11 Use of sold products 0 0 12 End of life treatment of sold products Not material Not material 13 Downstream leased assets Not applicable3 Not applicable 14 Franchises Not applicable3 Not applicable 15 Investments Not applicable4 Not applicable Total 553.5 570 1. To identify and calculate Scope 3 emission sources across our operations, we have used the World Resources Institute (WRI) and World Business Council for Sustainable Development (WBCSD), Greenhouse Gas (GHG) Protocol: A Corporate Accounting and Reporting Standard (Revised Edition) (2015), GHG Protocol Corporate Value Chain (Scope 3) Accounting and Reporting Standard (2013) and the Technical Guidance for Calculating Scope 3 Emissions (version 1.0) (available at https://ghgprotocol.org/). 2. Approximate equivalent 2020 figures for purchased goods & services, and capital goods emissions from spend data, bauxite & alumina processing have been re-estimated using the 2021 methodology and provided to allow comparability over time. 3. Not applicable since Rio Tinto does not lease significant upstream and downstream assets or have franchised operations. 4. This category is for reporting emissions from company investments not already reported in Scope 1 and 2. Rio Tinto reports using the equity share approach, so all Scope 1 and 2 emissions from managed and non-managed investments are included in Scope 1 and 2 reporting and Scope 3 emissions within other applicable categories of Scope 3 reporting. 5. Other processing of sold products included an estimate for salt in 2020, in 2021 salt has been reported separated with new methodology The bauxite and alumina processing of sold products 2021 equivalent is calculated using 2021 methodology and 2018 CRU factors (as were used in 2020 reporting). 2018 CRU data is higher in average emissions). Where there have been changes in reporting methodology, the 2020 data has been provided for context in an equivalent way using the same vintage of emission factors that were selected for use in the 2020 report. Purchased goods and services Capital goods Fuel and energy related activities Upstream transportation and distribution Business travel, employee commuting & waste Downstream transportation and distribution Processing of titanium dioxide feedstock Processing of copper concentrate Processing of other sold products Processing of salt 144.5 Processing of bauxite and alumina 364.6 Processing of iron ore 44.4 16.3 1.9 5.9 0.5 2.7 4.9 0.5 1.6 7.2 2.9 33Our Approach to Climate Change 2021 | riotinto.com
©2022 KPMG, an Australian partnership and a member firm of the KPMG global organisation of independent member firms affiliated with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited by a scheme approved under Professional Standards Legislation Independent Limited Assurance Report of KPMG (KPMG Australia) to the Directors of Rio Tinto plc and Rio Tinto Limited 2 Scope 1 and 2 GHG Target Information Rio Tinto’s Scope 1 and 2 GHG Target Information includes: the processes described to set the Scope 1 and 2 GHG Emissions Targets (the “Scope 1 and 2 GHG Targets”); the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement; and the description of the targets and roadmap to deliver the Scope 1 and 2 GHG Targets, as described in: Part 1 disclosures over the basis for target alignment with efforts to limit warming to 1.5°C and the goals of the Paris Agreement contained within “Reducing the carbon footprint of our operations”; Part 2 “1. Scope 1 and 2 emissions targets and roadmap” and the target and roadmap disclosures contained within “Implementing our Climate Action Plan: Scope 1 and 2 targets and roadmap”, in the Rio Tinto Climate Change Report 2021. Our assurance does not extend to information in respect of earlier periods or to any other information included in the Rio Tinto Climate Change Report 2021 the year ended 31 December 2021. Reporting Criteria The Reporting Criteria used for the reporting of the Scope 1 and 2 GHG Target Information are: the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement, as described in Part 1 of the Rio Tinto Climate Change Report 2021; the Climate Action 100+ Net Zero Company Benchmark framework disclosures relevant to Scope 1 and Scope 2 emissions targets; the Recommendations of the Task Force on Climate-related Financial Disclosures (June 2017) Guidance over Metrics and Targets relevant to Scope 1 and 2 GHG emissions; and the additional disclosures as described and presented within the sections of the Rio Tinto Climate Change Report 2021 highlighted above. Basis for Conclusion We conducted our work in accordance with International Standard on Assurance Engagements ISAE 3000 (Revised) Assurance Engagements other than Audits and Reviews of Historical Financial Information and in respect of greenhouse gas emissions, International Standard on Assurance Engagements ISAE 3410 Assurance Engagements on Greenhouse Gas Statements issued by the International Auditing and Assurance Standards Board (Standards). In gathering evidence for our conclusions, our assurance procedures comprised: enquiries with relevant Rio Tinto personnel to understand and evaluate the design and implementation of the key systems, processes and internal controls relevant to the Scope 1 and 2 GHG Target Information; reviewing the Scope 1 and 2 GHG Target Information and comparing it with relevant documentation including existing external disclosures and internal climate-related management position papers, policies and procedure documents; testing the targets and disclosed information to source documentation on a sample basis; identifying and testing key assumptions supporting calculations and/or significant related claims; assessing whether the processes, targets and plans are consistent with the Reporting Criteria; and reviewing the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 to ensure it is consistent with our overall knowledge of Rio Tinto. CONCLUSION Based on the evidence we have obtained from the procedures performed, we are not aware of any material misstatements in the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 for the year ended 31 December 2021, which has been prepared by Rio Tinto plc and Rio Tinto Limited (together Rio Tinto) in accordance with the Reporting Criteria. ©2022 KPMG, an Australian partnership and a member firm of the KPMG global organisation of independent member firms affiliated with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited by a scheme approved under Professional Standards Legislation Independ nt Limited Assurance Report of KPMG (KPMG Australia) to the Directors of Rio Tinto plc and Rio Tinto Limited 2 Scope 1 and 2 GHG Target Information Rio Tinto’s Scope 1 and 2 GHG Target Informa ion inclu es: the proc sses described to set the Scope 1 and 2 GHG Emissions Targets (the “Scope 1 and 2 GHG Targets”); the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement; and the description of the targets and roadmap to deliver the Scope 1 and 2 GHG Targets, as described in: Part 1 disclosur s over the basi for target alignme t with efforts t limit w rming to 1.5°C and the goals of the Paris Agreement contained within “Reducing the carbon footprint of our operations”; Part 2 “1. Scope 1 and 2 emissions targets and roadmap” and the target and roadmap disclosures contained within “Implementing our Climate Action Plan: Scope 1 d 2 targets and roadmap”, in the Rio Tinto Climate Change Report 2021. Our assurance does ot extend to information i re pect of earlier periods or to any other infor ation included in the Rio Tinto Climate Change Report 2021 the year ended 31 December 2021. Reporting Criteria The Reporting Criteria used for the reporting of the Scope 1 and 2 GHG Target Information are: the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement, as described in Part 1 of the Rio Tinto Climate Change Report 2021; the Climate Action 100+ Net Zero Company Benchmark framework disclosures relevant to Scope 1 and Scope 2 emissions targets; the Recommendations of the Task Force on Climate-related Financial Disclosures (June 2017) Guidance over Metrics and Targets relevant to Scope 1 and 2 GHG emissions; and the additional disclosures as described and presented within the sections of the Rio Tinto Climate Change Report 2021 highlighted above. Basis for Conclusion We conducted our work in accordance with International Standard on Assurance Engagements ISAE 3000 (Revised) Assurance Engagements other than Audits and Reviews of Historical Financial Information and in respect of greenhouse gas emissions, International Standard on Assurance Engagements ISAE 3410 Assurance Engagements on Greenhouse Gas Statements issued by the International Au iting and Assurance Standards Board (Standards). In gathering evidence for our conclusions, our assurance procedures comprised: enquiries with relevant Rio Tinto personnel to understand and evaluate the design and implementation of the key systems, processes and internal controls relevant to the Scope 1 and 2 GHG Target Information; reviewing the Scope 1 and 2 GHG Target Information and comparing it with relevant documentation including existing external disclosures and internal climate-related management position papers, policies and procedure documents; testing the targets and disclosed information to source documentation on a sample basis; identifying and testing key assumptions supporting calculations and/or significant related claims; assessing whether the processes, targets and plans are consistent with the Reporting Criteria; and reviewing the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 to ensure it is consistent with our overall knowledge of Rio Tinto. CONCLUSION Based on the evidence we have obtained from the procedures performed, we are not aware of any material misstatements in the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 for the year ended 31 December 2021, which has been prepared by Rio Tinto plc and Rio Tinto Limited (together Rio Tinto) in accordance with the Reporting Criteria. ©2022 KPMG, an Au tralian partnership and a member firm of the KPMG global organisation of independent me ber firms affiliat d with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited by a scheme approved under Professional Standards Legislation Independent Limited Assurance Report of KPMG (KPMG Australia) to the Directors of Rio Tinto plc and Rio Tinto Limited 2 Scope 1 and 2 GHG Target Information Rio Tinto’s Scope 1 and 2 GHG Target Information includes: the processes described to set the Scope 1 and 2 GHG Emissions Targets (the “Scope 1 and 2 GHG Targets”); the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement; and the description of the targets and roadmap to deliver the Scope 1 and 2 GHG Targets, as described in: Part 1 disclosures over the b sis for target alignment with efforts to limit warming to 1.5°C and the goals of the Paris Agreement contained within “Reducing the carbon footprint of our operations”; Part 2 “1. Scope 1 and 2 emissions targets and roadmap” and the target and roadmap disclosures contained within “Implementing our Climate Action Plan: Scope 1 and 2 targets and roadmap”, in the Rio Tinto Climate Change Report 2021. Our assurance does not extend to information in respect of earlier periods or to any other information included in the Rio Tinto Climate Change Report 2021 the year ended 31 December 2021. Reporting Criteria The Reporting Criteria used for the reporting of the Scope 1 and 2 GHG Target Information are: the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement, as described in Part 1 of the Rio Tint Climate Cha ge Rep rt 2021; the Climate Action 100+ Net Zero Company Benchmark framework disclosures relevant to Scope 1 and Scope 2 emissions targets; the Recommendations of the Task Force on Climate-related Financial Disclosures (June 2017) Guidance over Metrics and Targets relevant to Scope 1 and 2 GHG emissions; and the additional disclosures as described and presented within the sections of the Rio Tinto Climate Change Report 2021 highlighted above. Basis for Conclusion We conducted our work in accordance with International Standard on Assurance Engagements ISAE 3000 (Revised) Assurance Engagements other than Audits and Reviews of Historical Financial Information and in respect of greenhouse gas emissions, International Standard on Assurance Engagements ISAE 3410 Assurance Engag m nts on Greenhouse Gas Statements issued by the International Auditing and Assurance Standards Board (Standards). In gathering evidence for our conclusions, our assurance procedures comprised: e quiries with relevant Rio Tinto personnel to understand and evaluate the design and implementation of the key systems, processes and internal controls relevant to the Scope 1 and 2 GHG Target Information; reviewing the Scope 1 and 2 GHG Target Information and comparing it with relevant documentation including existing external disclosures and internal climate-related management position papers, policies and procedure documents; testing the targets and disclosed information to source documentation on a sample basis; identifying and testing key assumptions supporting calculations and/or significant related claims; assessing whether the processes, targets and plans are consistent with the Reporting Criteria; and reviewing the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 to ensure it is consistent with our overall knowledge of Rio Tinto. CONCLUSION Based on the evidence we have obtained from the procedures performed, we are not aware of any material misstatements in the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 for the year ended 31 December 2021, which has been prepared by Rio Tinto plc and Rio Tinto Limited (together Rio Tinto) in accordance with the Reporting Criteria. Our Approach to Climate Change 2021 | riotinto.com34
©2022 KPMG, an Australian partnership and a member firm of the KPMG global organisation of independent member firms affiliated with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited by a scheme approved under Professional Standards Legislation Independent Limited Assurance Report of KPMG (KPMG Australia) to the Directors of Rio Tinto plc and Rio Tinto Limited 3 In accordance with the Standards we have: used our professional judgement to plan and perform the engagement to obtain limited assurance that we are not aware of any material misstatements in the GHG Target Information, whether due to fraud or error; considered relevant internal controls when designing our assurance procedures, however we do not express a conclusion on their effectiveness; and ensured that the engagement team possess the appropriate knowledge, skills and professional competencies. We believe that the evidence obtained is sufficient and appropriate to provide a basis for our limited assurance opinion. How the Standard Defines Limited Assurance and Material Misstatement The procedures performed in a limited assurance engagement vary in nature and timing from, and are less in extent than for a reasonable assurance engagement. Consequently, the level of assurance obtained in a limited assurance engagement is substantially lower than the assurance that would have been obtained had a reasonable assurance engagement been performed. Misstatements, including omissions, are considered material if, individually or in the aggregate, they could reasonably be expected to influence relevant decisions of the Directors of Rio Tinto. Use of this Assurance Report This report has been prepared for the Directors of Rio Tinto for the purpose of providing an assurance conclusion on the Scope 1 and 2 GHG Target Information and may not be suitable for another purpose. We disclaim any assumption of responsibility for any reliance on this report, to any person other than the Directors of Rio Tinto, or for any other purpose than that for which it was prepared. Management’s responsibility Management are responsible for: determining that the Reporting Criteria is appropriate to meet their needs; preparing and presenting the Scope 1 and 2 GHG Target Information in accordance with the Reporting Criteria; establishing internal controls that enable the preparation and presentation of the Scope 1 and 2 GHG Target Information that is free from material misstatement, whether due to fraud or error; ensuring the basis of preparation in accordance with which the Scope 1 and 2 GHG Target Information has been determined and compiled is clearly and unambiguously set out in the Rio Tinto Climate Change Report 2021; and telling us of any known and/or contentious issues relating to the Scope 1 and 2 GHG Target Information. Our Responsibility Our responsibility is to perform a limited assurance engagement in relation to the Scope 1 and 2 GHG Target Information for the year ended 31 December 2021, and to issue an assurance report that includes our conclusion. Our Independence and Quality Control We have complied with our independence and other relevant ethical requirements of the Code of Ethics for Professional Accountants (including Independence Standards) issued by the IFAC Ethical Standards Board, and complied with the applicable requirements of International Standard on Quality Control 1 to maintain a comprehensive system of quality control. [signature] KPMG 23 February 2022 [signature] Adrian King Partner Melbourne, Australia ©2022 KPMG, an Australian partnership and a member firm of the KPMG global organisation of independent member firms affiliated with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited by a scheme approved under Professional Standards Legislation Independ nt Limited Assurance Report of KPMG (KPMG Australia) to the Directors of Rio Tinto plc and Rio Tinto Limited 2 Scope 1 and 2 GHG Target Information Rio Tinto’s Scope 1 and 2 GHG Target Information includes: the processes described to set the Scope 1 and 2 GHG Emissions Targets (the “Scope 1 and 2 GHG Targets”); the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement; and the description of the targets and roadmap to deliver the Scope 1 and 2 GHG Targets, as de cribed in: Part 1 disclosures over the basis for target alignment with efforts to limit warming to 1.5°C and the goals of the Paris Agreement contained within “Reducing the carbon footprint of our operations”; Part 2 “1. Scope 1 and 2 emissions targets and roadmap” and the target and roadmap disclosures contained within “Implementing our Climate Action Plan: Scope 1 and 2 targets and roadmap”, in the Rio Tinto Climate Change Report 2021. Our assurance does not extend to information in respect of earlier p riods or to any other i formation included in the Rio Tinto Climate Change Report 2021 the year ended 31 December 2021. Reporting Criteria The Reporting Criteria used for the reporting of the Scope 1 and 2 GHG Target Information are: the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement, as described in Part 1 of the Rio Tinto Climate Change Report 2021; the Climate Action 100+ Net Zero Company Benchmark framework disclosures relevant to Scope 1 and Scope 2 emissions targets; the Recommendations of the Task Force on Climate-related Financial Disclosures (June 2017) Guidance over Metrics and Targets relevant to Scope 1 and 2 GHG emissions; and the additional disclosures as described and presented within the sections of the Rio Tinto Climate Change Report 2021 highlighted above. Basis for Conclusion We conducted our work in accordance with International Standard on Assurance Engagements ISAE 3000 (Revised) Assurance Engagements other than Audits and Reviews of Historical Financial Information and in respect of greenhouse gas emissions, International Standard on Assurance Engagements ISAE 3410 Assurance Engagements on Greenhouse G s Statement issued by the International Au iting nd Assurance Standards Board (Standards). In gathering evidence for our conclusions, our assurance procedures comprised: enquiries with relevant Rio Tinto personnel to understand and evaluate the design and implementation of the key systems, processes and internal controls relevant to the Scope 1 and 2 GHG Target Information; reviewing the Scope 1 and 2 GHG Target Information and comparing it with relevant documentation including existing external disclosures and internal climate-related management position papers, policies and procedure documents; testing the targets and disclosed information to source documentation on a sample basis; identifying and testing key assumptions supporting calculations and/or significant related claims; assessing whether the processes, targets and plans are consistent with the Reporting Criteria; and reviewing the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 to ensure it is consistent with our overall knowledge of Rio Tinto. CONCLUSION Bas d on the evidence we have obtain d from the procedures performed, w are n t aware of any material misstatements in the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 for the year ended 31 December 2021, which has been prepared by Rio Tinto plc and Rio Tinto Limited (together Rio Tinto) in accordance with the Reporting Criteria. ©2022 KPMG, an Au tralian partnership and a member firm of the KPMG global organisation of independent me ber firms affiliat d with KPMG International Limited, a private English company limited by guarantee. All rights reserved. The KPMG name and logo are trademarks used under license by the independent member firms of the KPMG global organisation. Liability limited by a scheme approved under Professional Standards Legislation Independent Limited Assurance Report of KPMG (KPMG Australia) to the Directors of Rio Tinto plc and Rio Tinto Limited 2 Scope 1 and 2 GHG Target Information Rio Tinto’s Scope 1 and 2 GHG Target Information includes: the processes described to set the Scope 1 and 2 GHG Emissions Targets (the “Scope 1 and 2 GHG Targets”); the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement; and the description of the targets and roadmap to deliver the Scope 1 and 2 GHG Targets, as described in: Part 1 disclosures over the b sis for target alignment with efforts to limit warming to 1.5°C and the goals of the Paris Agreement contained within “Reducing the carbon footprint of our operations”; Part 2 “1. Scope 1 and 2 emissions targets and roadmap” and the target and roadmap disclosures contained within “Implementing our Climate Action Plan: Scope 1 and 2 targets and roadmap”, in the Rio Tinto Climate Change Report 2021. Our assurance does not extend to information in respect of earlier periods or to any other information included in the Rio Tinto Climate Change Report 2021 the ye r ended 31 December 2021. Reporting Criteria The Reporting Criteria used for the reporting of the Scope 1 and 2 GHG Target Information are: the alignment of the Scope 1 and 2 GHG Targets with efforts to limit warming to 1.5°C and the goals of the Paris Agreement, as described in Part 1 of the Rio Tint Climate Cha ge Rep rt 2021; the Climate Action 100+ Net Zero Company Benchmark framework disclosures relevant to Scope 1 and Scope 2 emissions targets; the Recommendations of the Task Force on Climate-related Financial Disclosures (June 2017) Guidance over Metrics and Targets relevant to Scope 1 and 2 GHG emissions; and the additional disclosures as described and presented within the sections of the Rio Tinto Climate Change Report 2021 highlighted above. Basis for Conclusion We conducted our work in accordance with International Standard on Assurance Engagements ISAE 3000 (Revised) Assurance Engagements other than Audits and Reviews of Historical Financial Information and in respect of greenhouse gas emissions, International Standard on Assurance Engagements ISAE 3410 Assurance Engag m nts on Greenhouse Gas Statements issued by the International Auditing and Assurance Standards Board (Standards). In gathering evidence for our conclusions, our assurance procedures comprised: e quiries with relevant Rio Tinto personnel to understand and evaluate the design and implementation of the key systems, processes and internal controls relevant to the Scope 1 and 2 GHG Target Information; reviewing the Scope 1 and 2 GHG Target Information and comparing it with relevant documentation including existing external disclosures and internal climate-related management position papers, policies and procedure documents; testing the targets and disclosed information to source documentation on a sample basis; identifying and testing key assumptions supporting calculations and/or significant related claims; assessing whether the processes, targets and plans are consistent with the Reporting Criteria; and reviewing the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 to ensure it is consistent with our overall knowledge of Rio Tinto. CONCLUSION Based on the evidence we have obtaine from the procedures performed, we are not aware of any material misstatements in the Scope 1 and 2 GHG Target Information presented in the Rio Tinto Climate Change Report 2021 for the year ended 31 December 2021, which has been prepared by Rio Tinto plc and Rio Tinto Limited (together Rio Tinto) in accordance with the Reporting Criteria. 35Our Approach to Climate Change 2021 | riotinto.com
This report includes “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical facts included in this report, including, without limitation, those regarding Rio Tinto’s financial position, business strategy, plans and objectives of management for future operations (including development plans and objectives relating to Rio Tinto’s products, production forecasts and reserve and resource positions), are forward-looking statements. The words “intend”, “aim”, ”ambition”, “project”, “anticipate”, “estimate”, “plan”, “believes”, “expects”, “may”, “should”, “will”, “target”, “set to” or similar expressions, commonly identify such forward-looking statements. Such forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rio Tinto, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Such forward-looking statements are based on numerous assumptions regarding Rio Tinto’s present and future business strategies and the environment in which Rio Tinto will operate in the future. Among the important factors that could cause Rio Tinto’s actual results, performance or achievements to differ materially from those in the forward-looking statements are levels of actual production during any period, levels of demand and market prices, the ability to produce and transport products profitably, the impact of foreign currency exchange rates on market prices and operating costs, operational problems, political uncertainty and economic conditions in relevant areas of the world, the actions of competitors, activities by governmental authorities such as changes in taxation or regulation and such other risk factors identified in Rio Tinto’s most recent Annual Report and Accounts in Australia and the United Kingdom and the most recent Annual Report on Form 20-F filed with the United States Securities and Exchange Commission (the “SEC”) or Form 6-Ks furnished to, or filed with, the SEC. Forward-looking statements should, therefore, be construed in light of such risk factors and undue reliance should not be placed on forward-looking statements. These forward-looking statements speak only as of the date of this report. Rio Tinto expressly disclaims any obligation or undertaking (except as required by applicable law, the UK Listing Rules, the Disclosure Guidance and Transparency Rules of the Financial Conduct Authority and the Listing Rules of the Australian Securities Exchange) to release publicly any updates or revisions to any forward-looking statement contained herein to reflect any change in Rio Tinto’s expectations with regard thereto or any change in events, conditions or circumstances on which any such statement is based. Nothing in this report should be interpreted to mean that future earnings per share of Rio Tinto plc or Rio Tinto Limited will necessarily match or exceed its historical published earnings per share. Forward-looking statements Our Approach to Climate Change 2021 | riotinto.com36
Printed by Park Communications on FSC® certified paper. Park works to the EMAS standard and its Environmental Management System is certified to ISO 14001. This publication has been manufactured using 100% offshore wind electricity sourced from UK wind. 100% of the inks used are HP Indigo ElectroInk which complies with RoHS legislation and meets the chemical requirements of the Nordic Ecolabel (Nordic Swan) for printing companies, 95% of press chemicals are recycled for further use and, on average 99% of any waste associated with this production will be recycled and the remaining 1% used to generate energy. This document is printed on Evolution Digital Uncoated 100% paper containing 100% recycled fibre. The FSC® label on this product ensures responsible use of the world's forest resources. Designed and produced by Black Sun riotinto.com
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom Rio Tinto Limited Level 7, 360 Collins Street Melbourne VIC 3000 Australia
Notification of dividend / distribution Notification of dividend / distribution 1 / 6 Announcement Summary Entity name RIO TINTO LIMITED Security on which the Distribution will be paid RIO - ORDINARY FULLY PAID Announcement Type New announcement Date of this announcement 23/2/2022 Distribution Amount AUD 6.62840000 Ex Date 10/3/2022 Record Date 11/3/2022 Payment Date 21/4/2022 DRP election date Tuesday March 29, 2022 17:00:00 Additional Information The 2021 final dividend of AUD 5.7704 per share is fully franked at the applicable corporate rate of 30%. The special dividend of AUD 0.8580 per share is fully franked at the applicable corporate rate of 30%. Refer to below for full details of the announcement EXHIBIT 99.8
Notification of dividend / distribution Notification of dividend / distribution 2 / 6 Announcement Details Part 1 - Entity and announcement details 1.1 Name of +Entity RIO TINTO LIMITED 1.2 Registered Number Type ABN Registration Number 96004458404 1.3 ASX issuer code RIO 1.4 The announcement is 1.5 Date of this announcement 23/2/2022 1.6 ASX +Security Code RIO ASX +Security Description ORDINARY FULLY PAID Part 2A - All dividends/distributions basic details 2A.1 Type of dividend/distribution 2A.2 The Dividend/distribution: relates to a period of six months 2A.3 The dividend/distribution relates to the financial reporting or payment period ending ended/ending (date) 31/12/2021 2A.4 +Record Date 11/3/2022 Special Ordinary New announcement
Notification of dividend / distribution Notification of dividend / distribution 3 / 6 2A.5 Ex Date 10/3/2022 2A.6 Payment Date 21/4/2022 2A.7 Are any of the below approvals required for the dividend/distribution before business day 0 of the timetable? Security holder approval Court approval Lodgement of court order with +ASIC ACCC approval FIRB approval Another approval/condition external to the entity required before business day 0 of the timetable for the dividend/distribution. 2A.8 Currency in which the dividend/distribution is made ("primary currency") AUD - Australian Dollar 2A.9 Total dividend/distribution payment amount per +security (in primary currency) for all dividends/distributions notified in this form AUD 6.62840000 2A.10 Does the entity have arrangements relating to the currency in which the dividend/distribution is paid to securityholders that it wishes to disclose to the market? 2A.11 Does the entity have a securities plan for dividends/distributions on this +security? 2A.11a If the +entity has a DRP, is the DRP applicable to this dividend/distribution? 2A.11a(i) DRP Status in respect of this dividend/distribution Full DRP 2A.12 Does the +entity have tax component information apart from franking? Part 2B - Currency Information 2B.1 Does the entity default to payment in certain currencies dependent upon certain attributes such as the banking instruction or registered address of the +securityholder? (For example NZD to residents of New Zealand and/or USD to residents of the U.S.A.). 2B.2 Please provide a description of your currency arrangements All dividends will be paid by direct credit. Where a securityholder has nominated an Australian or United Kingdom financial institution account for receipt of payments, payment will be made by direct credit in AUD or GBP as Yes No Yes We have a Dividend/Distribution Reinvestment Plan (DRP) Yes No
Notification of dividend / distribution Notification of dividend / distribution 4 / 6 applicable. Payments in GBP will be converted from AUD at the exchange rate applicable 5 business days prior to the dividend payment date and released to the ASX the following day. Computershare Investor Services Pty Ltd, Rio Tinto Limited's share registry offers a currency election facility (Global Wire Facility) in a range of currencies. Securityholders may elect to receive their dividend in a currency of their choice via the Global Wire Facility. Terms and conditions of the Global Wire Facility can be accessed at: auwww.investorcentre.com/ 2B.2a Other currency/currencies in which the dividend/distribution will be paid: Currency Payment currency equivalent amount per security GBP - Pound Sterling GBP 2B.2b Please provide the exchange rates used for non-primary currency payments 2B.2c If payment currency equivalent and exchange rates not known, date for information to be released 13/4/2022 Estimated or Actual? 2B.3 Can the securityholder choose to receive a currency different to the currency they would receive under the default arrangements? Part 3A - Ordinary dividend/distribution 3A.1 Is the ordinary dividend/distribution estimated at this time? 3A.1a Ordinary dividend/distribution estimated amount per +security AUD 3A.1b Ordinary Dividend/distribution amount per security AUD 5.77040000 3A.2 Is the ordinary dividend/distribution franked? 3A.2a Is the ordinary dividend/distribution fully franked? 3A.3 Percentage of ordinary dividend/distribution that is franked 100.0000 % 3A.3a Applicable corporate tax rate for franking credit (%) 30.0000 % 3A.4 Ordinary dividend/distribution franked amount per +security AUD 5.77040000 3A.5 Percentage amount of dividend which is unfranked 0.0000 % 3A.6 Ordinary dividend/distribution unfranked amount per +security excluding conduit foreign income amount AUD 0.00000000 YesYes No No Actual
Notification of dividend / distribution Notification of dividend / distribution 5 / 6 3A.7 Ordinary dividend/distribution conduit foreign income amount per security AUD 0.00000000 Part 3B - Special dividend/distribution 3B.1 Is the special dividend/distribution estimated at this time? 3B.1a Special dividend/distribution estimated amount per +security AUD 3B.1b Special dividend/distribution amount per +security AUD 0.85800000 3B.2 Is special dividend/distribution franked? 3B.2a Is the special dividend/distribution fully franked? 3B.3 Percentage of special dividend/distribution that is franked 100.0000 % 3B.3a Applicable corporate tax rate for franking credit (%) 30.0000 % 3B.4 Special dividend/distribution franked amount per +security AUD 0.85800000 3B.5 Percentage of special dividend/distribution that is unfranked 0.0000 % 3B.6 Special dividend/distribution unfranked amount per +security excluding conduit foreign income amount AUD 0.00000000 3B.7 Special dividend/distribution conduit foreign income amount per +security AUD 0.00000000 Part 4A - +Dividend reinvestment plan (DRP) 4A.1 What is the default option if +security holders do not indicate whether they want to participate in the DRP? 4A.2 Last date and time for lodgement of election notices to share registry under DRP Tuesday March 29, 2022 17:00:00 4A.3 DRP discount rate 0.0000 % 4A.4 Period of calculation of reinvestment price Start Date End Date 4A.5 DRP price calculation methodology Shares will be purchased on-market on or as soon as practicable after the dividend payment date. It may be necessary to carry out several market transactions to acquire the number of shares required and the DRP price will be the average of the deal prices of those transactions. DRP price will be announced to the market. Do not participate in DRP (i.e. cash payment) YesYes No
Notification of dividend / distribution Notification of dividend / distribution 6 / 6 4A.6 DRP Price (including any discount): AUD 4A.7 DRP +securities +issue date 4A.8 Will DRP +securities be a new issue? 4A.9 Is there a minimum dollar amount or number of +securities required for DRP participation? 4A.10 Is there a maximum dollar amount or number of +securities required for DRP participation? 4A.11 Are there any other conditions applying to DRP participation? 4A.12 Link to a copy of the DRP plan rules under Rio Tinto Limited tab.https://www.riotinto.com/invest/shareholder-information/dividends 4A.13 Further information about the DRP Part 5 - Further information 5.1 Please provide any further information applicable to this dividend/distribution 5.2 Additional information for inclusion in the Announcement Summary The 2021 final dividend of AUD 5.7704 per share is fully franked at the applicable corporate rate of 30%. The special dividend of AUD 0.8580 per share is fully franked at the applicable corporate rate of 30%. No No No No
EXHIBIT 99.9
Notice to ASX

23 February 2022
Changes to Ore Reserves and Mineral Resources
Rio Tinto today announced to the Australian Securities Exchange (ASX) changes to the following estimates of Ore Reserves and Mineral Resources compared to those published in the 2020 Rio Tinto Annual Report:
•Mineral Resources at Rio Tinto's Winu project in Western Australia;
•Ore Reserves and Mineral Resources at Rio Tinto Aluminium (RTA) Pacific Operations at Weipa; and
•Ore Reserves and Mineral Resources at Rio Tinto's Jadar project in Serbia.
The updated estimates will be included in Rio Tinto's 2021 Annual Report which will be released to the market on 24 February 2022. Today's announcements to the ASX were made in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code) and the ASX Listing Rules. Mineral Resources are reported in addition to Ore Reserves. Mineral Resources and Ore Reserves are quoted on a 100 per cent basis.
Rio Tinto's Mineral Resources and Ore Reserves as at 31 December 2021, and Rio Tinto's interests, will be set out in full in its 2021 Annual Report.
Copies of each of the full releases to the ASX are available on Rio Tinto's website at Resources & reserves (riotinto.com).
Winu Mineral Resources
The updated estimates of Mineral Resources at Winu are supported by a substantial increase in drilling information acquired since the release of the initial Inferred Mineral Resource dated 28 July 2020, and on the advancement of mining and processing studies. These estimates comprise an Indicated Mineral Resource of 249 Mt at 0.45% copper, 0.33 g/t gold and 2.72 g/t silver, and an Inferred Mineral Resource of 358 Mt at 0.37% copper, 0.28 g/t gold and 1.95 g/t silver, giving a total Mineral Resource of 608 Mt at 0.40% copper, 0.30 g/t gold and 2.26 g/t silver, or 0.49% copper equivalent, at 0.2% copper equivalent cut-off. This represents a 21% increase in tonnage, a 16% increase in copper grade, a 12% increase in gold grade, a 40% increase in contained copper metal and a 35% increase in contained gold metal.
Rio Tinto further reports that:
•contained copper metal in the total Mineral Resource has increased 40%; and
•the Winu deposit is still open in several directions with drilling programs in 2022 continuing to target extensions.
A proportion of the total Resource meets the requirements for Indicated Mineral Resources and an Indicated Mineral Resource is reported for the first time.
Since the initial public release of Mineral Resources, drilling targeting Winu mineralisation has continued, resulting in an 83% increase in reverse circulation drilled metres, a 93% increase in diamond drill metres, for an overall increase of 88% drill metres.
The deposit remains open at depth as well as to the north, south and east and the project team continues to explore the deposit margins. While exploration activity has been somewhat constrained by site clearances at surface, the presence of copper, gold and silver mineralisation of a similar geological style and setting at the margins indicates that the Winu deposit is not, at this time, limited by geology. Further work is required to confirm and increase understanding of extensions to the orebody.
In 2021 the project transitioned from Rio Tinto Exploration to Rio Tinto Copper where it will be advanced through the next phase of delivery. Recent technical and commercial reviews, independent of the study team, were positive and the project continues to enjoy support from the Rio Tinto Board which has approved additional expenditure to progress early works at Winu and further prepare the project for a final investment decision.
The Winu project team continues to work with local Nyangumarta and Martu Traditional Owners and regulators to progress the agreements and approvals required for any future development.
Supporting information for the update to the Winu Mineral Resource estimate is set out in the release to the ASX dated 23 February 2022 "Rio Tinto reports first Indicated Mineral Resource and 40% increase in contained copper at Winu project".
Weipa Ore Reserves and Mineral Resources
RTA Pacific Operations has written back bauxite ore from Ore Reserves to Mineral Resources due to a routine review of price assumptions over the life of the mine.
RTA Pacific Operations Ore Reserve estimate, for the Amrun deposit, has decreased by 218 Mt, from 1,044 Mt to 826 Mt. The reduction in Ore Reserve estimate is associated with a routine review of price assumptions over the life of the mine, and updated orebody knowledge. There has been no material change to the economic cut-off methodology or process. There has been no material change to the other reserve modifying factors, including governmental, tenure, environmental, cultural heritage, social, community or operational.
RTA Pacific Operations Mineral Resources exclusive of Ore Reserves, for the Amrun deposit, has increased by 172 Mt, from 678 Mt to 850 Mt. The increase was mainly due to changes in the forecast pricing assumptions used in the reserving process. Those blocks removed from the 2021 Ore Reserve that are physically located above the remaining economic blocks have also been removed from the Mineral Resource.
RTA Pacific Operations Mineral Resources exclusive of Ore Reserves, for the East Weipa and Andoom deposits, has increased by 28Mt, from 35Mt to 63Mt. The increase was mainly due to changes in the forecast pricing assumptions used in the reserving process. Those blocks removed from the 2021 Ore Reserve that are physically located above the remaining economic blocks have also been removed from the Mineral Resource.
Supporting information for the update to the Weipa Ore Reserve and Mineral Resource estimates is set out in the release to the ASX dated 23 February 2022 "Changes to Rio Tinto Aluminium (RTA) Pacific Operations Ore Reserve and Mineral Resource Estimates for Weipa".
Jadar Ore Reserves and Mineral Resources
As a result of the Government of Serbia in January 2022 cancelling the Spatial Plan and revoking all related permits, Rio Tinto has decided to no longer report an Ore Reserve for the Jadar lithium-borates project in western Serbia. Accordingly, the Mineral Resources estimate has been updated to incorporate previously declared Ore Reserves, as well as additional drilling data. This data was collected up to the end of 2021 and prior to the Government cancelling the Spatial Plan, and has resulted in an updated geological model, and reclassification of significant tonnage from Inferred to Indicated Mineral Resource category. This change has been made to reflect the current status of the project.
Rio Tinto remains committed to exploring all options and is reviewing the legal basis of the decision by Government of Serbia and future implications for our activities and our people in Serbia.
The Mineral Resources comprise 85.4 Mt of Indicated Resources at 1.76% Li2O and 16.1% B2O3 with an additional 58.1 Mt of Inferred Resources at 1.87% Li2O and 12.0% B2O3.
Rio Tinto committed $2.4 billion of funding to the Jadar lithium-borates project, in July 2021, subject to receiving all relevant approvals, permits and licenses and ongoing engagement with local communities, the Government of Serbia and civil society.
The proposed project consisted of an underground mine, sustainable industrial processing and waste facilities as well as associated infrastructure. Production estimates included approximately 58 kt of battery grade lithium carbonate, as well as 160 kt of boric acid (B2O3 units) and 255 kt of sodium sulfate as by-products per year.
Supporting information for the update to the Jadar Ore Reserve and Mineral Resource estimates is set out in the release to the ASX dated 23 February 2022 "Rio Tinto updates Ore Reserves and Mineral Resources at Jadar".
Important notices
Winu Mineral Resources
The Winu Mineral Resource estimates referred to in this release were set out in the release to the ASX dated 23 February 2022 "Rio Tinto reports first Indicated Mineral Resource and 40% increase in contained copper at Winu project" (Winu release). The Competent Person responsible for the information in the Winu release that relates to Mineral Resources is Mr James Pocoe, who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM).
Copper equivalents have been calculated using the formula CuEq = ((Cu%*Cu price 1% per tonne *Cu_recovery) + (Au ppm*Au price per g/t*Au_recovery) + (Ag ppm*Ag price per g/t*Ag_recovery)) / (Cu price 1 % per tonne). Metal prices applied were provided by Rio Tinto Economics and generated based on industry capacity analysis, global commodity consumption and economic growth trends. Details of recoveries are shown on an average basis for material types in the Winu release. It is the company's opinion that all the elements included in the metal equivalent calculation have a reasonable potential to be recovered and sold.
RTA Ore Reserve and Mineral Resources
The Ore Reserve and Mineral Resource estimates for RTA Pacific Operations referred to in this release were set out in the release to the ASX dated 23 February 2022 "Changes to Rio Tinto Aluminium (RTA) Pacific Operations Ore Reserve and Mineral Resource Estimates for Weipa" (RTA release). The Competent Person responsible for the information in the RTA release that relates to Ore Reserves is Mr William Saba who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). The Competent Person responsible for the information in the RTA release that relates to Mineral Resources is Mr Angus C. McIntyre, who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM).
Jadar Ore Reserves Mineral Resources
The Mineral Resource estimates for Jadar referred to in this release were set out in the release to the ASX dated 23 February 2022 "Rio Tinto updates Ore Reserves and Mineral Resources at Jadar" (Jadar release). The Competent Person responsible for the information in the Jadar release that relates to Ore Reserves is Mr Allan Earl who is a Fellow of the Australasian Institute of Mining and Metallurgy (MAusIMM). Mr Earl's assessment is supported from a metallurgical perspective by Mr Gary Davis who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM) The Competent Persons responsible for the information in the Jadar release that relates to Mineral Resources are Mr Mark Sweeney who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM) and Mr Jorge Garcia, who is Member of the European Federation of Geologists (EFG).
No new information
Rio Tinto confirms that it is not aware of any new information or data that materially affects the information included in the Winu release, the RTA release or the Jadar release (together, the ASX releases), that all material assumptions and technical parameters underpinning the estimates in the ASX releases and the production target in the Jadar release continue to apply and have not materially changed, and that the form and context in which the Competent Persons' findings are presented have not been materially modified.
| Contacts | Please direct all enquiries to media.enquiries@riotinto.com | ||||
Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 | Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Amar Jambaa M +61 472 865 948 | ||||
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 | Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 | ||||
riotinto.com
Notice to ASX 23 February 2022 Rio Tinto updates Ore Reserves and Mineral Resources at Jadar As a result of the Government of Serbia in January 2022 cancelling the Spatial Plan and revoking all related permits, Rio Tinto has decided to no longer report an Ore Reserve for the Jadar lithium-borates project in western Serbia. Accordingly, the Mineral Resources estimate has been updated to incorporate previously declared Ore Reserves, as well as additional drilling data. This data was collected up to the end of 2021 and prior to the Government cancelling the Spatial Plan, and has resulted in an updated geological model, and reclassification of significant tonnage from Inferred to Indicated Mineral Resource category. This change has been made to reflect the current status of the project. Rio Tinto remains committed to exploring all options and is reviewing the legal basis of the decision by Government of Serbia and future implications for our activities and our people in Serbia. The Mineral Resources comprise 85.4 Mt of Indicated Resources at 1.76% Li2O and 16.1% B2O3 with an additional 58.1 Mt of Inferred Resources at 1.87% Li2O and 12.0% B2O3 The changes in Mineral Resources and Ore Reserves are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code) and the ASX Listing Rules. Supporting information relating to the changes is set out in this release and its appendix. Mineral Resources are quoted in this release on a 100 percent basis. These changes will be reflected in Rio Tinto’s 2021 Annual Report, which will be released to the market on 24 February 2022, and which will set out in full Rio Tinto’s Mineral Resources and Ore Reserves position as of 31 December 2021, and Rio Tinto’s interests. Rio Tinto committed $2.4 billion of funding to the Jadar lithium-borates project, in July 2021, subject to receiving all relevant approvals, permits and licenses and ongoing engagement with local communities, the Government of Serbia and civil society. The proposed project consisted of an underground mine, sustainable industrial processing and waste facilities as well as associated infrastructure. Production estimates included approximately 58 kt of battery grade lithium carbonate, as well as 160 kt of boric acid (B2O3 units) and 255 kt of sodium sulfate as by-products per year1. 1 These production targets are underpinned as to 54% by Indicated Mineral Resources and as to 46% by Inferred Mineral Resources. The relevant estimates of Mineral Resources are as set out in this report and have been prepared by Competent Persons in accordance with the requirements of the JORC Code. There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the production target itself will be realised. EXHIBIT 99.10 /LSE
2 Jadar Ore Reserves and Mineral Resources update A full tabulation of the Jadar Ore Reserve and Mineral Resource is provided in Table A and Table B. Table A Jadar Mineral Resources as at 31 December 2021 Classification Tonnes (Mt) Li2O (%) B2O3 (%) Previous Current Previous Current Previous Current Measured - - - - - - Indicated 55.2 85.4 1.68 1.76 17.9 16.1 Inferred 84.1 58.1 1.84 1.87 12.6 12.0 Total 139.2 143.5 1.78 1.80 14.7 14.4 Table B Jadar Ore Reserves as at 31 December 2021 Classification Tonnes (Mt) Li2O (%) B2O3 (%) Previous Current Previous Current Previous Current Proved - - - - Probable 16.6 - 1.81 - 13.4 - Total 16.6 - 1.81 - 13.4 - Figure 1 Jadar Project location map
3 Summary of information to support Mineral Resource reporting Mineral Resources are supported by the information set out in the appendix to this release and located at Resources & reserves (riotinto.com) in accordance with the Table 1 checklist in the JORC Code. The following summary information is provided in accordance with rule 5.8 of the ASX Listing Rules. Geology and geological interpretation The deposit occupies a continuous area approximately 3.0 km west-east by 2.5 km north-south at depths from 100 m to 720 m below surface. Mineralisation is present in three broad zones containing stratiform lenses of variable thickness hosted in a much thicker gently dipping sequence mainly composed of fine-grained sediments crossed by faults. Economic grades in the Lower Jadarite Zone (LJZ) occur from depths of approximately 300 m in the south, dipping at about 10 degrees to the north where they exceed 720 m in depth. From a stratigraphic point of view, it is observed that sedimentation in the basin is associated with a low energy environment for large periods with widespread distribution of stratigraphic units in the basin. There were periodical influxes of coarser clastics that are interpreted to be sourced mainly from the slopes of the basin to the north and northwest. Contribution from the west-southwest seems to be important during certain periods of basin fill. Jadarite, LiNaSiB3O7(OH), is a mineral unique to the Jadar deposit that was previously unknown to science. Its composition was determined by the Natural History Museum in London and was accepted in 2006 as a new mineral in the literature by the International Mineralogical Association (IMA) Commission on New Minerals, Nomenclature and Classification Faculty of Earth & Life Sciences Vrije Universiteit Amsterdam De Boelelaan 1085, 1081 HV Amsterdam, Netherlands. The new mineral was named after the Jadar River. Jadarite consists of rounded micro-crystalline grains, nodules or concretions. On a larger scale the jadarite occurs in stratigraphic lenses that appear as bands of higher and lower lithium and borate grades in core. At the scale of the project area, jadarite mineralisation can vary from 1 to 2 m to over 50 m in thickness. The mechanism for nucleation of the jadarite particles remains problematic, but it is hypothesised that individual jadarite grains grew either at the water-sediment interface, or within the soft sediments. As the jadarite crystal grew it pushed aside other fine-grained minerals, to the extent that these formed a coating to act as a barrier to prevent the particle from coalescing with adjacent particles. Consequently, in high-grade bands the rounded character may be deformed as the particles changed shape to account for the limited space, forming a mosaic texture. Based on drill hole core observations, there appears to be a range of jadarite crystal textures, sizes and shapes. This proposed mode of deposition of jadarite rich sediments has resulted in the harder jadarite crystals hosted within a matrix of softer sediments ranging from fine mud to marls, carbonate rich sediments, clays and siltstones. Drilling techniques; sampling and sub-sampling techniques; and sample analysis method Geological exploration of the Jadar deposit has been completed using HQ3 and NQ3 angled diamond drill (DD) holes. Total drilling within the Jadar deposit includes 518 diamond drill holes having drilled a total of 204.7 km. Core recovery in Jadar deposit is generally excellent, with an overall recovery of 98.8%. In addition to the drilling undertaken, a 3D seismic program has been completed over the deposit that has increased confidence in the geological model and location and orientation of the modelled higher grade mineralisation. Logging and sampling of core is undertaken at the core facility. In the earlier holes mineralised and unmineralized core as sampled and assayed. In the later holes only core intervals containing visible jadarite or borate mineralization were sampled after better understanding of the lithium and boron grade distribution. The HQ3 core is sampled by quarter-core, generally 1 m length quarter core is processed, with the remainder being retained for later submission as duplicates, re-assay etc. Sampling from NQ3 intervals is half core. All cores are cut by diamond saw. Both lithium and boron are assayed as elemental percentages, but for processing and estimation are converted to oxide percentages of Li2O and B2O3 by multiplying with factors 2.153 and 3.22, respectively. For a smaller group of samples, a broad suite of elements was analysed by analytical method is a Na2O2 fusion
4 followed by ICP-AES, with major oxides determined by XRF including possible hazardous or radioactive elements such as As, Hg, Pb, Tl, Th and U, with no elevated grade values observed that would be considered hazardous. Estimation methodology The geological and resource modelling for Jadar was generated using the Micromine geological modelling software. The LJZ grade model consists of 13 domains, global estimation parameters were used in unfolded space for grade estimation in the mineralised LJZ domains and transformed back to real space for resource reporting. The Isatis geostatistical software package was used for geostatistical input to the grade estimation process including statistical analysis, variography, kriging neighbourhood analysis, and block model validation and global change of support studies. Grade estimation was undertaken in Micromine using Ordinary Kriging (OK) for all economic variables, dry bulk density and other variables using a parent block size of 20 mN x 20 mE x 2 mRL, with sub-celling down to 5 mN x 5 mE x 1 mRL. Cut-off grades and modifying factors The grade model used for reporting Jadar Mineral Resources is based on LJZ grade domains defined using a US$300/t contained (Li2O and B2O3) cut-off grade (COG), with the lithium oxide and borate dollar values based on 2020 internal pricing forecast and projected operating costs. The US$300/t COG represents a natural break in the grade distribution between the modelled and reported higher grade jadarite mineralisation and lower grade background material. As jadarite is a new mineral to the mining industry, it was important to demonstrate that the ore can be processed economically. Significant processing studies have been undertaken and it has been demonstrated from pilot plant studies that the jadarite can be processed economically with high recoveries. Thus, the JORC requirement for “reasonable prospects for eventual economic extraction” can be reasonably justified. Criteria used for classification The Jadar Mineral Resource category determination is based on a number of factors including, confidence in the resource data, drill hole density in the LJZ - with Indicated Mineral Resources having drill hole spacing less than 150 m, geological continuity and confidence in the structural model and grade continuity based on the semivariogram and sectional interpretations. Currently only the LJZ has been classified as Mineral Resource based on completed studies.
5 Competent Persons’ Statement The information in this report that relates to Mineral Resources is based on information compiled under the supervision of Mr Mark Sweeney, member of the Australasian Institute of Mining and Metallurgy (MAusIMM), and Mr Jorge Garcia, who is Member of the European Federation of Geologists (EFG). Both have sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which they are undertaking to qualify as Competent Persons as defined in the 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Both Mr Sweeney and Mr Garcia are full-time employees of Rio Tinto and each of them consents to the inclusion of Jadar Mineral Resources in the Report based on the information compiled under his supervision in the form and context in which it appears. The information in this report that relates to Ore Reserves is based on information compiled under the supervision of Mr Allan Earl who is a Fellow of the Australasian Institute of Mining and Metallurgy (MAusIMM) and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Earl’s assessment is supported from a metallurgical perspective by Mr Gary Davis who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM) and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Earl is full-time employee of Snowden Mining Industry Consultants Pty Ltd working as a consultant to Rio Tinto while Mr Davis is a full time Rio Tinto employee, and each of them consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.
6 Contacts Please direct all enquiries to media.enquiries@riotinto.com Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948 Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary. riotinto.com
Appendix 7 Jadar JORC Table 1 The following table provides a summary of important assessment and reporting criteria used at Jadar for the reporting of Mineral Resources and Ore Reserves in accordance with the Table 1 checklist in The Australasian Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code, 2012 Edition). Criteria in each section apply to all preceding and succeeding sections. Section 1: Sampling Techniques and Data Criteria Commentary Sampling techniques • All samples for assaying and density determination are taken from predominant PQ3 (some HQ3 and rarely NQ3) vertical or occasionally inclined core drilling. • Sample representativity is ensured by drilling on a pseudo-grid that is generally evenly spaced at an average of 100 m, but with closer spacing at certain locations so that geostatistical measures are informed. Most holes are drilled through the entire jadarite-bearing sequence into visibly low grade material below the Lower Jadarite Zone. Drill core size is considerably larger than grain size, and orientation approximately perpendicular to the bedding ensures that each sample is representative of the beds through which it passes. Drilling techniques • From 2004, a total of 609 drill holes (216,595.6 m) were drilled for resource, geotechnical, hydrogeological, sterilisation, bulk sampling and shallow geotechnical drilling programs. • All resource data for the Project comes from diamond drilling. As of the end of 2021, the project database contains 518 cored diamond drill holes (204,782.6 m). Of the 518 cored drill holes, 319 of them were sampled and assayed (53,676 samples) for an aggregated length of 76,240.9 meters to support the current resource estimation process. Samples from all assayed holes are included for the BM6.0 resource model. • Approximately 53% of all diamond drilling from 2004 to 2014 was conducted with HQ3 diameter using standard triple-tube wireline drilling. From 2015, resource drilling (predominantly for a metallurgical recovery bulk sample) was undertaken using PQ3 diameter, representing roughly 45% of the total meters cored for the project. The balance corresponds to NQ3 drilling for early holes at depth. • Additional samples for metallurgy test work were obtained from a 43 hole dedicated PQ3 drilling campaign in 2018, and from PQ intercepts from other holes drilled with that diameter in the deposit. These holes were used for resource estimation. • Additional bulk sample drilling for pilot plant metallurgical test-work was completed via 1 large-diameter (368 mm) core hole. This hole was not used for resource estimation. • A number (91) of open rotary bit holes (86-244 mm) were also drilled as a part of hydrogeological drilling program (installed: piezometers, wells, shallow wells, etc.) for ground water monitoring. These were not included for resource estimation. • Due to the nature of the rock and characteristics of drilling, the use of core orientation during drilling was impractical. Instead, downhole ABI surveys were conducted for more than 70% of the cored diamond holes drilled in the deposit to obtain real orientation data for geological features.
8 Drill sample recovery • All core is usually un-broken with excellent overall recovery (averaging around 98%). Core loss is mostly recorded in the near surface (up to 30-35 m) in alluvium, well above the mineralised horizons, vugs or cavities are rarely seen. Some ‘disking’ occurs, usually because of low adhesion of one bed to another and the occurrence of fine- grained phyllosilicates – i.e. clays - on bedding faces, though this does not materially affect recovery. • Core recovery within jadarite mineralisation is generally excellent (averaging 99.2%) and no relationship between reduced recovery and mineralization has been observed. Sample bias due to preferential loss/gain of fine/coarse material in jadarite mineralization is considered very unlikely. Jadarite particles adhere to their matrix during drilling and are cut through at core edges. Neither the particles nor the matrix are lost preferentially. An exception occurs in the NaBo (Sodium Borates) zone, where occasional bands of a higher-solubility borate mineral is ‘necked’ down, but calculations indicate that the consequent bias is negligible (loss of pure borax is estimated to bias positively the assay results by +0.06%). • When lower core recovery is obtained, this is usually due to structural fracturing, producing brecciated core. Holes with <85% recovery in total or <95% recovery in mineralisation are re-drilled. • HQ core in 0.6 m-long core boxes was taken to the core shed where recovery per meter is estimated and recorded by the logging geologist. For the PQ holes, 1 m long PVC core boxes were used, with the same logging procedure applied. • Large diameter (86-244 mm) drilling uses a rotary bit to obtain samples of large chippings, with acceptable recovery calculated on a 1 m long sample weight/estimated weight base but these are only used for metallurgical test-work and are not used for Mineral Resource estimation. Recovery Histogram (518 holes) Logging • All core is photographed both dry and wet, and fully logged by geologists for geotechnical features, lithology, stratigraphy, visible mineralization and other characteristics (grain size, texture, colour, etc.). • Logging is completed in the core shed, directly using dedicated laptops, with logging templates that will only accept pre-defined codes or values within numeric ranges. From 2016 the use of an acQuire off-line logging module (synchronised with main database) was implemented for lithology, mineralogy and geotechnical logging. • Logging is currently peer reviewed and regularly supervised by a senior Project Geologist. During 2015 and 2016, a separate core re-logging program covered the main mineralized section for 87 holes drilled in previous years. The validated dataset was used to develop discrete lithological geodomains to support resource estimation, mining, hydrogeology, geotechnical and metallurgical studies, and the methodology has been adopted for subsequent drilling campaigns. • Down hole logging was performed using a variety of probes for deviation surveys,
9 calliper and temperature. This included geophysical logging to record the orientation of bedding, structures, and for other geotechnical measurements (ABI, N-Gamma, porosity, Density, MagSus, etc.). Sub-sampling techniques and sample preparation • Core sampling is completed at the core shed after logging, based on sampling criteria determined by the Jadar Project Sampling Procedure. • In early holes, all cored length was sampled with longer sampling intervals used in un- mineralized lengths. In 2010 a review of results for un-mineralised intervals demonstrated that these were of very low grade (near analytical method detection limit) and not of economic interest. From that moment (from hole JDR_38) sampling has been based on core intervals containing visible jadarite or borate mineralisation, extended for a further 4 samples above and below observed mineralisation. • HQ3 is sampled by quarter-core, generally 1 m length quarter core is processed, with the remainder being retained for later submission as duplicates, re-assay etc. Sampling from NQ3 intervals is half core. All cores are cut by diamond saw. • Sampling for the PQ3 holes drilled in 2015 was carried out using a diamond core side- cut (6-7 mm) with the remaining core sent to the pilot plant for processing test-work. From that moment onwards all PQ3 core has been quarter sampled, which is roughly equivalent in sample mass per meter to half HQ core. PQ3 sample lengths were selected based on lithological and mineralisation boundaries. • Up to 2011 drill hole samples were prepared in an external preparation laboratory in Belgrade. From 2011 to 2015, sample were prepared at Jadar core shed facilities, from where sealed pulp batches were sent to the ALS Laboratory for assaying. Due to the limited capacity of the on-site preparation facility, samples from PQ holes have been prepared at ALS Bor Laboratory from 2016 onwards. • Samples as received at the lab are weighed, immersed in water for volumetric measurement and then dried at temperature just under 60º C, for a minimum of 24 hours. The low temperature precludes thermal decomposition or dehydration of borate minerals present in the ore, so no crystal water losses occur during drying. • After drying, samples are weighed again to determine dry bulk density, and then the entire sample is crushed to -1.4 mm in two stages (first stage to –2 mm by jaw crusher and in second stage to -1.4 mm by rotary crusher, both stages >85% passing). • The crushed sample is subsampled in a rotary splitter to obtain 200-300 g, pulverized to -75 µm (>85 % passing) and then riffle split to produce 100-150 g pulp for assaying. The unused rifle split pulp is stored in the sample archive. • The sampling procedure is considered appropriate to the type of mineralisation. Drill quarter-core size is considerably larger than grain size (except where mineralisation occurs in the form of veins) and orientated approximately perpendicular to the bedding. Use of a rotary splitter when the coarse sample size is near the jadarite grain size should ensure no bias introduced in splitting. The final pulp size is much smaller than the grains, which will break by brittle fracturing to ensure full homogenization so that the pulp is representative. Quality of assay data and laboratory tests • A general quality assurance/quality control (QAQC) involving duplicate samples in every stage (core duplicates, crush, pulp and laboratory stage duplicates) is implemented. All results are assessed via cross plots and statistics for precision and accuracy. • The following QAQC controls are inserted in each batch of pulps: − 1st and every 40th are blanks, − Every 20th is a field duplicate, from a 2nd quarter-core from a sample in the same batch, − Every 20th is a coarse duplicate – prepared from a second split of the rotary splitter, − Pulp duplicates are produced by ALS and reported at a frequency of 1 in 20 of the pulps they receive. − Matrix-matched customised standards are inserted in pairs (one high grade & one low grade) every 20th • From mid-2015 the QAQC procedure was modified to include a full set of cascaded duplicates from core to pulp, where every 20th primary sample was twinned by a core
10 duplicate and each of these duplicated at crush and pulp stages, resulting in 8 individual pulps for assaying. • The standard suite of assays includes Li2O, B2O3, SiO2, Fe2O3, CaO, MgO, Na2O, K2O, MnO and SrO. Additional assays as, C_GAS05, S_IRO7, C_CO3 and S_SO3_NONLECO, Cl and F were conducted on selected samples for processing design purposes. • Early samples (until 2012) were assayed at the SGS-Lakefield laboratory in Ontario, Canada, where samples for lithium and boron were prepared by KOH fusion and then assayed by ICP-AES. In 2012, the decision was made to switch laboratory for improved turnaround times and to use a broadly adopted fusion package comparable across laboratories. A round robin test involving six laboratories was conducted, and since then all lithium and boron samples have been assayed by ALS in Vancouver, and more recently in their facilities in Ireland. The analytical method is a Na2O2 fusion followed by ICP-AES, with major oxides determined by XRF. Verification of sampling and assaying • High and low grade intersections are visibly identified and verified by Rio Sava geologists. • Sample details are recorded directly into templates in laptops. All data transfer is electronic following an agreed protocol and procedure (sampling data entry procedure, assays data verification and data storage into a database procedure). • Lithium and boron assays are verified against visual mineral estimates and cross checked against core where discrepancies are noted. • The QAQC review and approval workflow is embedded in the acQuire workspace, with individual approval required for each batch before data is released for use. The review and approval is conducted by a designated senior geologist. • Project QAQC reviews are conducted regularly on a campaign basis, and for data supporting resource estimates. • Elemental concentrations for Lithium and Boron are reported by the laboratory. A chemical conversion factor is applied directly after import of the assays to the database to derive the Li2O and B2O3 concentrations, which are incorporated to the database for subsequent uses in modelling. There is no further adjustment to assays. • There are no twinned holes in the project area. Location of data points • All surveyed coordinates are within Serbian Gauss Kruger projection system, using the Hermannskogel datum, Zone 6 (MGI_Zone_6). • Drill hole collars surveying after drilling is conducted by an external licensed surveying company, Geomax. The equipment used is a total station instrument SOKKIA-SET610 with stated accuracies of 2 mm ± 2 mm/km. All coordinates are received in Gauss Kruger Zone 6 with no coordinate transformation applied. • Down holes surveys, including deviation, are carried out by an external company, Fugro, with data delivered in electronic format and imported to acquire. Deviation data is exported at 25 m intervals for use in geological and resource modelling. • All down hole survey azimuths (deviation and ABI) are oriented to Magnetic North. Magnetic declination corrections are provided by the Serbian Magnetic Institute. Local monthly average correction factors extracted from that dataset and used for the calculation of True North Geodetic azimuths. • A total of 21 early holes which were assayed do not have downhole survey measurements. The 21 un-surveyed holes were collared vertically, and after investigation of deviations in surveyed holes it is considered that locational inaccuracy for un-surveyed holes is within acceptable error, and suitable for use in resource modelling. • In addition, 14 of the 21 un-surveyed early holes are barren (or very low grade mineralisation) thus do not influence the mineralised project area. Data spacing and distribution • Drill spacing is on a pseudo-grid that is generally evenly spaced at an average of 100 m. Drill hole spacing ranges from 25 m around the geostatistical-cross area, moving up to over 200 m in the peripheral areas. Drill spacing is sufficient to establish geological and grade continuity, and to support the current Mineral Resource classifications.
11 Drill hole location map Drill hole spacing histogram (319 holes) Orientation of data in relation to geological structure • The majority of resource drill holes are vertical resulting in the drilling intersecting the sub-horizontal mineralisation at right angles. • Geological structures such as faulting range from sub-vertical to bedding parallel. Vertical drilling is unlikely to regularly intersect these structures and will statistically misrepresent sub-vertical fractures. As a result the lateral extent of faulting is uncertain. • Since 2012, 66 inclined holes were drilled to intercept interpreted steep fault structures. These faults displace the ore in the vertical direction and are important for mining studies. • In 2015, a 3D seismic survey, covering 10.5 km2 was undertaken to improve understanding of the structural model. An additional six inclined drill holes were drilled to confirm the new structural interpretation. Sample security • All sampling (cutting, tagging and packing into PVC bags) is conducted within the core shed by technicians based on sample lists, prepared and supervised by a geologist.
12 • Pre 2011 drill hole samples were prepared in an external preparation laboratory in Belgrade. From 2011 to 2015, samples were prepared at the Jadar core shed facilities, from where batches were sealed and sent to the ALS Laboratory for assaying. Due to the limited capacity of the on-site preparation facility, samples from PQ holes have been prepared at ALS Bor Laboratory from 2016 onwards, with ALS coordinating the shipment to the analytical laboratory either in Vancouver or Ireland. • Chain of custody was followed insuring that only dedicated personal from the Jadar team and assaying laboratory had access to the samples at all stages of the sampling process. • There was no analytical laboratory visits or audits. Jadar team members randomly visit the ALS–Bor prep-laboratory when samples are prepared externally. • After assaying, the remaining pulp material is returned and stored in the Jadar Project warehouse, along with an archive of pulp duplicates, allowing for re-assays if required. Audits or reviews • An independent review and resource estimation was undertaken by AMEC in January 2009, which was presented as a fully compliant NI 43-101 report. • Rio Tinto conducted two internal resource estimation reviews in December 2012 and November 2013. • A Rio Tinto Exploration senior geologist and Jadar Project Competent Person conducted four internal QAQC reviews at specific dates coincident with the end of large drilling campaigns, the last one in April 2020 and including all assays and drilling data incorporated to the resource model supporting this release. • Jadar Project has had three external audits completed in the past eight years: − An audit in October 2011 conducted by SRK (Rio Tinto Corporate Assurance QAQC Internal Audit Report - Dec. 2011) − An audit in September 2016 conducted by SRK (Rio Tinto Group Internal Audit Resources and Reserves Internal Audit Report – Oct. 2016) − An audit conducted in December 2018 by AMC (Rio Tinto Group Internal Resource and Reserve (R&R) Internal Audit Report – Dec. 2018 ) • Audits concluded that the fundamental data collection techniques are appropriate and overall internal audit rating is “Satisfactory” or “Good”.
13 Section 2: Reporting of Exploration Results Criteria Commentary Mineral tenement and land tenure status • Rio Sava Exploration d.o.o., a fully owned subsidiary of Rio Tinto Energy and Minerals Product Group, is the legal owner of the Jadar Project. • The Exploration License got to the end of its life cycle in February 2020. Subsequently, Rio Tinto applied for a “Retention License” under Serbian regulations, with the new permit covering an area of 61.5km2 approved by the Government. According to the legal framework in Serbia, the retention permit became void once the company obtained approval for its Elaborate on Resources and Reserves and submitted the supporting documentation and application for the mining license on 6th January 2021. In January 2022, the Government of Serbia cancelled the Spatial Plan for the Jadar Project and required all related permits to be revoked. We remain committed to exploring all options and are reviewing the legal basis of the decision and the implications for our activities and people in Serbia. Exploration done by other parties • The Jadar deposit was discovered by Serbian and American geologists working for Rio Tinto in 2004, with no pre-existing exploration for lithium and boron in the area. • Since its discovery, exclusively Rio Tinto without involvement of third party exploration companies has conducted activities at the Jadar Project. • After the discovery of Jadar, a handful of junior companies have been exploring around and outside Rio Tinto licenses, without significant results to date. Geology • The Jadar deposit, discovered in 2004 in Western Serbia, is a concentration of lithium and boron in a mineral new to science named jadarite, LiNaSiB3O7(OH). The deposit is located in a valley with flat-lying farmland covering a surface area of 3.0 km by 2.5 km. Known lithium and borate mineralisation lies at depths from 100 m to 720 m below surface. • The mineralisation is hosted in a lacustrine sedimentary sequence of Miocene age dominated by calcareous claystones, siltstones, sandstones and clastic rocks (about 400 m to 500 m thick). The sequence dips to the north at between 0 and 25 degrees or more, but typically between 5 and 10 degrees, and it includes several thin tuff beds that provide valuable marker horizons for stratigraphic correlation. Miocene sediments lay unconformable on a basement of Cretaceous age. General lithological column
14 • The deposit includes three types of mineralisation occurring as stratiform lenses of variable thickness, and hosted in a gently dipping sequence of mainly fine-grained sediments that is dissected by faults: - Jadarite LiNaSiB3O7(OH) mineralisation, new to science and so far unique to this deposit; occurs within a stratiform sedimentary lacustrine sequence with sub- horizontal beds of jadarite as rounded grains, nodules, or concretions generally in the range 1 mm to 10 mm in a siltstone / mudstone matrix. Jadarite is mainly concentrated in three gently dipping tabular zones known as the Upper, Middle and Lower Jadarite Zones (UJZ, MJZ and LJZ), - Sodium borates (NaBo), mainly in the form of Ezcurrite - Na4B10O17.·7H2O, but also as Kernite - Na2B4O7.4H2O, and Borax - Na2B4O7·10H2O, occurs as lenses that are interbedded with jadarite-bearing siltstones and mudstones, present mainly enclosed or adjacent to the LJZ with a more restricted areal distribution, - Gypsum occurs as layers of gypsiferous sandstone mixed with carbonate and crosscut by fibrous selenite gypsum veinlets; it is concentrated in the upper part of the sequence in the transition from lacustrine to brackish conditions (sub economic). Drill hole information • Not applicable as no Exploration Results being reported. Data aggregation methods • Not applicable as no Exploration Results being reported. Relationship between mineralisation widths and intercept lengths • Drill holes are regularly surveyed for deviation, and real in situ bedding orientation obtained from downhole ABI (acoustic borehole imaging) geophysical surveys. • Based on drilling techniques and sub horizontal stratigraphy, the mineralisation intercepts approximate true thickness. Diagrams Exploratory License map
15 Jadar basin geological map (based on SFRY General Geological Map 1:100,000) Deposit geological map and cross sections 3,7 and 8
16 Balanced reporting • Not applicable. There are no specifically released exploration results for Jadar deposit. Other substantive exploration data • In addition to drilling, ground magnetic, 2D test seismic line and full 3D seismic surveys have been completed since 2004 to identify faults, possible dykes, and alluvial limits. • During the early exploration stage (pre-2007), geophysical surveys were conducted over a wider area including gravity, magneto-telluric and magnetic techniques, providing initial information about Jadar basin basement depth.
17 • Early in 2015 a 2D Seismic test line (2.2 km) was carried out across the central part of deposit to determine ground response and optimum seismic layout parameters and energy source for a later 3D seismic survey. • In the summer of 2015 a 3D seismic survey, within an area of approx. 10.5 km2 (covering planned decline area, central part of deposit as well as jadarite intercept on the north (JDR_122), was carried out. First results of 3D seismic data processing and interpretation provided additional information enhancing confidence in the continuity of the stratigraphic unit’s, subsurface structures and identification of the main faults position and orientation. • Calgary based consultant Earth Signal Processing (ESP) reprocessed 3D seismic data in June 2017 to enhance resolution for the lacustrine section, resulting in a much crispier and continuous image. This reprocessed and depth migrated 3D Seismic cube provided by ESP was used for subsequent structural interpretation updates. Further work • The deposit is clearly defined through drilling. Limited potential remains for resource extension of the Lower Jadarite Zone to the north, but this is unlikely to have a significant impact on the overall resource tonnage.
18 Section 3: Estimation and Reporting of Mineral Resources Criteria Commentary Database integrity • All drill hole data are securely stored in the Jadar Project AcQuire database that is located in the Belgrade office server. The server is backed up daily. • All data transfer to the AcQuire database is in digital form and has been verified and validated by the database geologist and exploration geologists. Additional automated validation checks have also been incorporated into the AcQuire logging modules. As a result, the likelihood of transcription or keying errors in the final resource database is low. Site visits • The Jadar Competent Persons have visited the Jadar Project regularly in previous years. The latest site visit being December 2019, with earlier quarterly visits in 2019. The site visits typically included the Belgrade office, and the drilling operations, core facility and sample prep lab facilities on site. Due to the COVID-19 pandemic regular Project site visits were cancelled in 2020 and 2021. Geological interpretation • The lithostratigraphic model is well understood, and is considered to be robust: o Detailed logging from drilling with variable data density supports the lithostratigraphic interpretation. The lithostratigraphy from the Lower Jadarite Zone to surface has been logged and modelled as 2D wireframe surfaces and 3D volumes. o Volcanoclastic material in the form of tuffs, tuffaceous sandstones and pyroclastic fragments provide useful marker horizons for grade modelling and resource estimation. • The structural model at Jadar is complex but is at a stage of development that is appropriate for an ongoing Feasibility Study and associated mining studies: o The main basin scale structural faults displacing the mineralised domains during and post deposition have been identified. Major faulting appears to be a combination of plastic deformation and fault displacement based on seismic interpretations and drill core orientation angles. o Minor faulting (<10 m) at the scale of mining is less well understood; many of these faults are not yet in the current structural model. These structures are largely below the vertical resolution of the 3D seismic survey and their presence is noted from the structural logs and stratigraphic correlations. • The jadarite and borate mineralisation has been modelled in three separate horizons: o Lower Jadarite Zone (LJZ) - thickness: 1m – 50 m o Middle Jadarite Zone (MJZ) - thickness: 1m – 20 m o Upper Jadarite Zone (UJZ) - thickness: 1m – 15 m o Only LJZ has been classified as Mineral Resource based on completed metallurgical and mining studies. Additional processing test work for the MJZ will be required to improve resource confidence. • The horizontal and vertical spatial distribution of the tabular jadarite and sodium-borates (NaBo) is well understood based on current drilling and has resulted in robust 3D wireframes for the Jadarite and Borate lithodomains volumes constraining the high grade lithium and borate mineralisation. • The 3D mineralised wireframes used to constrain grade estimation have been modelled using the current 3D wireframe geodomain (lithological) model and constrained laterally using a US$300/tonne cut-off grade (COG). The dollar COG is based on a US dollar value calculated using Rio Tinto price curves for lithium carbonate and boric acid. • The genesis of the jadarite and borate mineralisation is conceptual at this stage: o Jadarite and borate beds are thought to have formed at or near the water–sediment interphase in the sediments from hydrothermal fluids entering the basin. o The jadarite and borate mineralisation has similarities to other deep water borate environments (i.e. Furnace Creek Fm. in US). • Jadarite bearing sediments are affected by sedimentary processes during deposition, including dewatering, sliding, slumping and extensional/compressional fractures associated with these events. Mineralisation is affected by normal and reverse fractures post lithification with limited remobilisation of jadarite and other borate minerals.
19 • Significant mineralogical changes in the vertical are controlled by the geochemical evolution of the basin and mineralising events over time, and by the basin scale graben faulting that constrains the jadarite and NaBo mineralisation. Dimensions • Jadarite mineralisation is found in a continuous area of approximately 3 km wewst-east by 2.5 km north-south, and at depths from about 100 m to 720 m below surface. The Jadar deposit is sub-divided in three major zones known as the Upper Jadarite (UJZ), Middle Jadarite (MJZ) and Lower Jadarite Zone (LJZ), of which the LJZ is the carries the highest value and is most laterally continuous and homogeneous in grade and thickness. As such, it is the basis for the economic study of the project at this stage and contributes to all reported Mineral Resources. • Jadarite mineralisation in the LJZ consists of rounded micro-crystalline grains, nodules or concretions. On a larger scale the jadarite occurs in stratigraphic lenses that appear as bands of higher and lower lithium and borate grades in core. At the scale of the project area, jadarite mineralisation can vary from 1 to 2 m to over 50 m in thickness. Estimation and modelling techniques • The estimation process was completed using the Micromine geological modelling software package and Snowden’s Supervisor geostatistical software package. The “unfolding” option in Micromine was used to account for the undulating jadarite and borate mineralisation, and to preserve grade variations in the vertical direction. • Mineralised domains and background mineralisation were estimated in 3D space using ordinary kriging with up to four estimation passes to account for the highly variable nature of the drilling density that ranges from 25 m to over 150 m in plan view. • A parent block size of 20 mN x 20 mE x 2 mRL was used for grade estimation, with sub- celling down to 5 mN x 5 mE x 1 mRL used in the block model. Current block size was selected taking into account drill hole spacing, and geometric constraints with modelling of the LJZ mineralisation. When evaluating the parent block size, consideration was also given to integrating the hydrogeological and geotechnical models with the resource model for mine planning purposes. • Data was composited to 2 m, the same interval as the parent block thickness in the vertical direction. The 2 m composites were selected from the 1 m raw assay data to remove unwanted variability in the vertical direction. Larger composite intervals were not evaluated, as they would exceed the vertical dimensions of the parent block in the block model. • Statistical and variography studies were undertaken using the Supervisor geostatistical software package and confirmed that the geostatistical approach to grade estimation was appropriate. No grade cutting was required for either jadarite or borate grades. • Grade estimates were constrained laterally within a boundary polygon that contains the majority of drill holes from the resource database. Grade estimates were not extrapolated outside of this polygon. Grade estimation parameters were optimized using Kriging Neighbourhood Analysis (KNA) studies, taking into account data density, kriging variance, and minimum and maximum numbers of samples. • Block model validation included visual inspection of block grades against composites, composite statistics versus block grades by domain, and swath plots. Check estimates (inverse distance squared – ID2) were undertaken on the economic variables Li2O and B2O3 only. Approximately 24 sensitivity resource estimate models were generated to support the preferred resource estimate, with sensitivity models confirming the centrality of the preferred Mineral Resource estimate. There are no production statistics for reconciliation. Moisture • All density, tonnages and grades are estimated on a dry basis (drying for 30 hours at just under 60º C). Cut-off parameters • The CoG of US$300/t for Mineral Resources has been applied to include only material with prospects for economic extraction from the available mineralised inventory. Sharp hanging wall and footwall grade boundaries preclude the addition of significant tonnes, unless the COG was significantly reduced. • Rio Tinto applies a common process to the generation of commodity prices across the group. This involves generation of long-term price curves based on current sales contracts, industry capacity analysis, global commodity consumption and economic growth trends. In this process, a price curve rather than a single price point is used to develop estimates of mine returns over the life of the project. The detail of this process and of the price point curves is commercially sensitive and is not disclosed.
20 Mining factors or assumptions • Underground mining layouts utilize a variety of underground panel and stope designs for the Jadar Project. A prerequisite for underground mining is that surface subsidence is minimised. As such, stabilised stope fill mining options are being developed. • No assumptions were made regarding modelling of selective mining units at this stage given the proposed variable mining methods and stope sizes. • No minimum ore thicknesses were assumed in the modelling of the jadarite mineralisation to allow mine layout trade-off studies. • In the central area of the LJZ, mineralised thickness varies between 3 m and 50 m, with an average ore thickness of around 15 m. The assessment of internal dilution is dependent on the mining cut-off grade and will be evaluated during the economic assessment of the ore material for underground mining. Metallurgical factors or assumptions • The pilot plant test-work on bulk samples from LJZ has been successful in achieving the separation of jadarite particles from the fine-grained matrix, then dissolution in acid and refining to produce market-quality lithium carbonate and boric acid products. • There is a viable route to process economically the jadarite and borate ore, confirmed by the latest pilot processing tests, including costs and recoveries. Environmental factors or assumptions • Work on the communities, social performance, environment and permitting aspects of the Jadar Project is undergoing review. Previously, the Government of Serbia had adopted a Spatial Plan for a Special Purpose Area (SPSPA), which covers the project area and acts as a zoning definition to support the industrial nature of the mine and processing facility. These approvals are the basis for scope and content of the Serbian Environmental Impact Assessment. Numerous environmental studies have been completed or commenced that support the Environmental Impact Assessment, the Environmental Design Criteria, disposal of process residue storage and waste dumps and the future operations of the mine. In January 2022, the Government of Serbia cancelled the Spatial Plan for the Jadar Project and required all related permits to be revoked. We remain committed to exploring all options and are reviewing the legal basis of the decision and the implications for our activities and people in Serbia. Bulk density • Dry Bulk Density (DBD) measurements are determined by the water displacement method on uncoated core. • The drill hole core condition is generally good, with high percentage core recoveries. Observed voids in the core are rare, as a result, core density is considered to be a reliable estimator of dry bulk in-situ density. • Dry bulk density measurements have been validated by external laboratory test work. • Total of 16,821 dry bulk density estimates are in the resource database. • Density values have been estimated into the block model using the inverse distance estimation method. Below is the location of DBD data for the LJZ.
21 Classification • The Jadar resource model for the LJZ has been classified as an Indicated and Inferred Mineral Resource. • The Jadar Mineral Resource category determination is based on a number of factors: o Drill hole density in the LJZ, with Indicated Mineral Resources having drill hole spacing less than 150 m. o Slope of Regression geostatistical parameter for individual block confidence to support drill hole spacing for resource classification. o Geological continuity and confidence in the structural model supported by detailed lithological modelling work. o Grade continuity based on the semivariogram and sectional interpretations, that indicates a high degree of continuity of grade within the LJZ. • The Competent Person is satisfied that the stated Mineral Resource classification accurately reflects the interpreted geological and structural controls, and confidence in the grade estimates. Audits or reviews • The Jadar Project has had three external audits completed in the past eight years: o An audit in October 2011 conducted by SRK (Rio Tinto Corporate Assurance QAQC Internal Audit Report - Dec. 2011) o An audit in September 2016 conducted by SRK (Rio Tinto Group Internal Audit Resources and Reserves Internal Audit Report – Oct. 2016) o An audit conducted in December 2018 by AMC (Rio Tinto Group Internal Resource and Reserve (R&R) Internal Audit Report – Dec. 2018 ) • The 2016 Audit covered two main components: o Data collection component (all field, core-shed and office activities related to the so-called “Core to Model” procedures C2M); o Resource estimation component (resource estimation block model BM 4.1). • The 2016 Audit concluded that the fundamental data collection and resource estimation techniques are appropriate and overall internal audit rating is ‘Satisfactory’. No technical findings related to the resource estimation process were identified. Two low rated findings were identified relating to procedural issues, these have now been addressed. • The 2018 Audit overall internal audit for the Jadar R&R estimation processes into the PFS is rated ‘Good’. No adverse ‘Findings’ were identified during the audit. Discussion of relative accuracy/ confidence • There is a high level of confidence in the reported global estimates of the tonnes and grades for the Jadar Mineral Resources due to observed grade and geological continuity of the jadarite and borate mineralisation. • Inferred Mineral Resource estimates are generally based on drill hole spacing greater than 100 m, and block grades should be considered as smoothed given the relatively small block
22 size of 20 mN x 20 mE x 2 mRL. • Due to uncertainties in the structural model there may be structural disturbance at the scale of mining that have not been identified in the current structural model. The 3D seismic interpretation and orientated core data are being used assist in resolving these issues and improve confidence in the structural model. • Grade estimation has been improved by the use of 3D wireframe domains to constrain the grade estimates. Wireframes are based on a US$300 COG, further work is required to determine the most suitable economic COG for the project once mining and processing cost estimates are further developed in the current FS. • Accuracy and confidence of Mineral Resource estimation estimate has been accepted by appropriate for the level of classification by the Competent Person.
Notice to ASX 23 February 2022 1 Changes to Rio Tinto Aluminium (RTA) Pacific Operations Ore Reserve and Mineral Resource Estimates for Weipa Rio Tinto’s 2021 Annual Report which will be released to the market on 24 February 2022 will include changes in estimates of Ore Reserves and Mineral Resources at RTA Pacific Operations for Weipa, compared to those published in the 2020 Rio Tinto Annual Report. The Ore Reserve and Mineral Resource estimates are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code) and the ASX Listing Rules. Ore Reserves and Minerals Resources are quoted on a 100 per cent basis (100% Rio Tinto share). Mineral Resources are reported in addition to Ore Reserves. Rio Tinto’s 2021 Annual Report will set out in full Rio Tinto’s Mineral Resources and Ore Reserves position as of 31 December 2021, and Rio Tinto’s interests. RTA Pacific Operations Ore Reserve estimate, for the Amrun deposit, has decreased by 218Mt, from 1,044Mt to 826Mt. The reduction in Ore Reserve estimate is associated with a routine review of price assumptions over the life of the mine, and updated orebody knowledge. There has been no material change to the economic cut-off methodology or process. There has been no material change to the other reserve modifying factors, including governmental, tenure, environmental, cultural heritage, social, community or operational. RTA Pacific Operations Mineral Resources exclusive of Ore Reserves, for the Amrun deposit, has increased by 172Mt, from 678Mt to 850Mt. The increase was mainly due to changes in the forecast pricing assumptions used in the reserving process. Those blocks removed from the 2021 Ore Reserve that are physically located above the remaining economic blocks have also been removed from the Mineral Resource. RTA Pacific Operations Mineral Resources exclusive of Ore Reserves, for the East Weipa and Andoom deposits, has increased by 28Mt, from 35Mt to 63Mt. The increase was mainly due to changes in the forecast pricing assumptions used in the reserving process. Those blocks removed from the 2021 Ore Reserve that are physically located above the remaining economic blocks have also been removed from the Mineral Resource. Supporting information surrounding the 2021 update to the Ore Reserve and Mineral Resource estimates has been provided on the following pages. EXHIBIT 99.11 /LSE
2 Table A RTA Pacific Operations Mineral Resources as at 31 December 2021 Table B RTA Pacific Operations Ore Reserves as at 31 December 2021 Mineral resources Tonnage Grade Tonnage Grade Tonnage Grade Tonnage Grade Tonnage Grade Tonnage Grade Bauxite Mt % Al2O3 % SiO2 Mt % Al2O3 % SiO2 Mt % Al2O3 % SiO2 Mt % Al2O3 % SiO2 Mt % Al2O3 % SiO2 % Mt % Al2O3 % SiO2 Rio Tinto Aluminium (Australia)(b) - Amrun(c) O/P 100 49.5 11.6 488 50.2 11.8 589 50.1 11.7 262 51.7 12.1 850 50.6 11.8 100.0 678 50.3 11.9 - East Weipa and Andoom(c) O/P 63 49.5 8.4 - - - 63 49.5 8.4 - - - 63 49.5 8.4 100.0 35 51.1 8.3 - Gove O/P 28 49.0 6.8 5.0 49.0 6.6 33 49.0 6.8 0.6 49.1 6.8 34 49.0 6.8 100.0 34 48.7 6.8 - North of Weipa O/P - - - - - - - - - 1,330 52.0 11.6 1,330 52.0 11.6 100.0 1,330 52.0 11.6 Total (Australia) 191 49.4 9.9 494 50.2 11.7 684 50.0 11.2 1,592 51.9 11.6 2,276 51.3 11.5 2,077 51.3 11.6 (a) Likely mining method: O/P = open pit/surface; U/G = underground. (b) Rio Tinto Aluminium bauxite Resources are stated as dry product tonnes and total alumina and silica grades. (c) Amrun and East Weipa and Andoom Resource tonnes increased following conversion of Reserves to Resources based on updated economic assumptions. A JORC Table 1 in support of this change will be released to the market contemporaneously with the release of this Annual Report and can be viewed at riotinto.com/invest/financial-news-performance/resources-and-reserves. Total mineral resources Rio Tinto Interest Total mineral resources as at 31 December 2021 as at 31 December 2021 as at 31 December 2021 as at 31 December 2021 as at 31 December 2021 as at 31 December 2020 Likely mining method(a) Measured resources Indicated resources Total Measured and Inferred resources Ore reserves Rio Tinto share Recoverable Tonnage Grade Tonnage Grade Tonnage Grade mineral Tonnage Grade Bauxite (b) Mt % Al2O3 % SiO2 Mt % Al2O3 % SiO2 Mt % Al2O3 % SiO2 % Mt Mt % Al2O3 % SiO2 Rio Tinto Aluminium (Australia)(c) - Amrun(d) O/P 258 54.2 9.2 568 54.9 9.1 826 54.7 9.1 100.0 826 1,044 54.0 9.1 - East Weipa and Andoom(d) O/P 77 51.7 7.4 1 52.5 9.2 78 51.7 7.4 100.0 78 100 51.4 7.5 - Gove(e) O/P 64 50.6 5.8 0.4 50.0 5.9 64 50.6 5.8 100.0 64 80 50.4 5.6 Total (Australia) 398 53.1 8.3 570 54.9 9.0 968 54.2 8.7 968 1,225 53.5 8.8 (a) Type of mine: O/P = open pit/surface, U/G = underground. (b) Bauxite Reserves are stated as recoverable Reserves of marketable product after accounting for all mining and processing losses. Mill recoveries are therefore not shown. (c) Australian bauxite Reserves are stated as dry tonnes and total alumina and sil ica grade. (e) Gove Reserve tonnes decreased following updated economic assumptions and mining depletion. Type of mine(a) Rio Tinto Interest Proved ore reserves Probable ore reserves Total ore reserves (d) Amrun and East Weipa and Andoom Reserve tonnes decreased following updated economic assumptions, updated orebody knowldege and mining depletion. A JORC Table 1 in support of this change will be released to the market contemporaneously with the release of this Annual Report and can be viewed at riotinto.com/invest/financial-news-performance/resources-and-reserves. Total ore reserves as at 31 December 2021 as at 31 December 2021 as at 31 December 2021 as at 31 December 2020
3
4 Summary of information to support the Mineral Resource reporting The RTA Pacific Operations Mineral Resource estimate is supported by a JORC Table 1 (Sections 1, 2 and 3) document provided in the appendix to this release and located at Resources & reserves (riotinto.com). An increase in RTA Pacific Operations Mineral Resources coincides with the write back of bauxite ore from Ore Reserves to Mineral Resources due to a routine review of price assumptions over the life of the mine. The methodology of determining Mineral Resources has not changed. The bauxite assets have been in operation for more than fifty years and are well understood. Resource work is currently more focussed on asset evaluation rather than exploration, systematically bringing the bauxite classification to higher levels of confidence. The following summary of information for Mineral Resource estimates is provided in accordance with Rule 5.8 of the ASX Listing Rules. Geology and geological interpretation RTA Pacific Operations have two bauxite deposits, one at Gove (NT) and one at Weipa (QLD). The host rocks of the two mine sites have been converted to bauxite via a continuum of weathering. High annual rainfall and a geologically stable environment has provided the perfect ingredients for these world-class bauxite deposits to form over many millions of years. A deep saprolitic zone overlain by a classic mottled zone below the bauxite ore attests to this. The process of bauxitisation involves the conversion of kaolinite to the bauxite minerals gibbsite and boehmite. The principal influence on the process is the composition, supply, and movement of groundwater. The pH of the groundwater is lowered during the process of bauxitisation, and we note that the process is still ongoing as we see a low pH regularly throughout the ground water monitoring bores across the RTA mining leases. To a lesser extent there are organic influences such as vegetation, and possibly burrowing organisms and temperature. Pisolitic textures are dominant, with variable cementation. However, variably cemented coarser nodule horizons are also common. Some deeper bauxite, as well as underlying laterite, contain abundant interconnected solution cavities, which may have been created geochemically and/or biologically (associated with root channels). Modern day root channel structures and infill, in the upper part of the bauxite, are common. Gibbsite is the major ore mineral, with boehmite being of lesser significance. Bauxite occurs on laterally extensive plateaus. The plateaus have been variably dissected by erosion into distinguishable main plateau areas, each with their own characteristics, (outlined further in Table 1). The bauxite orebodies are interpreted as flat-lying horizons with topography dictating the geometry. The orebodies are generally overlain by a thin (<1 m) overburden cover and occasional red soil. Beneath the bauxite ore is often a transition zone defined by angular and lumpy textures and a geochemical signature of higher silica and lower alumina. The transition zone is often underlain by the ironstone, with a distinct change in physical properties, particularly the colour. Drilling techniques; sampling, sub-sampling method and sample analysis method The current drilling method at Weipa utilizes aircore drilling. The typical aircore rig is a Land Cruiser mounted rig with a small enough wheelbase to traverse drill lines cleared with one D-6 dozer blade width. Aircore drilling forces compressed air down a space inside the drill rods to the bit face, where the air is then used to return the sample up the inner tube of the drill rod and out via a cyclone. A three bladed HQ aircore bit is attached to 4-inch rods. The drilling system has been designed to reduce grinding of the sample. Historic drilling utilised auger drilling (until 1991). Drilling at Gove is conducted using a tractor mounted 44 mm diameter vacuum drill rig. Logging is currently conducted on Panasonic Toughpads and data is captured in an offline acQuire logging package at the drill rig. This system allows for data validation to be applied during logging as well as a streamlined method of exporting the data for importing into the main RTA Geology database. Logging is qualitative in nature, i.e., based on lithology. Currently there are ~20 lithologies common to the deposits that get modelled into 4 horizons for the estimation of bauxite resources. All sample intervals (0.25 m) are logged.
5 Logged lithologies are vetted against historical drill holes and assay parameters. Samples for geologic logging and analysis are collected on 0.25 m intervals (~2-3 kg) down hole. Whole samples are collected beneath a cyclone return system, i.e., no sample splitting is conducted, or sub samples taken. Multiscreen sampling is undertaken initially to determine optimum screen size for beneficiation at each deposit. Once determined, samples are then beneficiated at the appropriate screen size (1.7 mm for East Weipa, 0.3 mm for Andoom and 0.6 mm for the Amrun deposits). Bauxite at Gove is direct shipping ore (DSO). Samples are processed and XRF analysed for the major oxides: Al2O3, SiO2, Fe2O3, TiO2 and LOI, as well as minor elements and recovery. Estimation methodology Basic geostatistical analysis is used to help with domaining decisions. Most deposits were modelled as a single laterally extensive domain, apart from Moingum (Hey Point), where two lateral extensive domains have been modelled due to difference in source rocks affecting thickness and grade. Four horizon codes, based on the lithology and assays, are assigned for the modelling and estimation of bauxite resources at Weipa and three at Gove vertically. Interpretation and estimation are currently performed using Datamine’s Studio RM software, with variography undertaken in FSS International Consultants (Australia) GS3M software. The bauxite horizon is flattened to the mid-point of the drill hole intersections at East Weipa and Andoom, while drill hole collars are flattened to constant elevation at Amrun, Norman Creek and Moingum (Hey Point). The wireframes are filled with blocks on an in/out basis; there is no sub-blocking or block proportions used. For the bauxite horizon, major oxides; LOI and Recovery are estimated into parent cells using ordinary kriging. Overburden and red soil are assigned 0% recovery for the estimation of resources. Cemented bauxite grade is estimated as part of the bauxite horizon and assigned a 100% recovery; the proportion of cemented bauxite is estimated as an indicator variable. Major oxide chemistry is also estimated for the overburden, red soil and ironstone horizons, where data is available. Ordinary kriging is used for interpolation, using the variogram models for the bauxite. Block sizes are determined by ½ the drill hole spacing for each deposit. A multiple pass search strategy is used to estimate grades utilising different sized search ellipses that include a specified number of samples and drill holes. The lowest category (Pass 4) is not used in the East Weipa and Andoom areas. Maximum extrapolation distance is slightly less than the maximum search radii due to the requirement to use at least two holes to estimate each block. Cut-off grades and modifying factors RTA Pacific Operations employs a standard approach to identify Mineral Resource volumes with reasonable prospects for eventual economic extraction. Once the Ore Reserves are defined based on applied economic factors in the reserving process, the remaining blocks are evaluated based on grade cut-offs, thickness cut-offs and location (environmental, cultural heritage and infrastructure buffers) for each of the different deposits, and Mineral Resources defined. Criteria used for Mineral Resource classification Classification within the bauxite horizon is based on the search pass used to estimate grades, using increasing search radii and decreasing numbers of samples for each subsequent pass. Passes 1 and 2 are classified as Measured Mineral Resources (120 to 180 m), Pass 3 as Indicated (360 m) and Pass 4 as Inferred.
6 Summary of information to support the Ore Reserve reporting The reduction in Ore reserve estimate is associated with a routine review of price assumptions over the life of the mine, and updated orebody knowledge. There has been no material change to the economic cut-off methodology or process. The Ore Reserve estimate is supported by a JORC Table 1 (Section 4) document provided in the appendix to this release and located at www.riotinto.com/investors/reserves-and-resources. The following summary of information for the Ore Reserve estimate is provided in accordance with Rule 5.9 of the ASX Listing Rules. Economic assumptions and study outcomes The Weipa assets have been operating continuously for several decades, and the Ore Reserve estimates, and life of mine plans are updated annually. This includes the reconciliation of operating parameters and review of input assumptions into the planning processes. The Ore Reserve estimate for Amrun is based on the completed and approved feasibility study and has now been in continuous operation for three years. The Ore Reserve is mined through shallow, open cut techniques developed over several decades of operations. Once the area is tree cleared and the topsoil / overburden removed, the bauxite is hauled to the processing facility for washing and / or sizing. Product bauxite is stockpiled for shipping to both internal and external customers. Several mining areas are active at any one time to enable blending and to mitigate against operational risk. Rio Tinto applies a common process to the generation of commodity price assumptions across the group. This involves generation of long-term price forecasts based on current sales contracts, industry capacity analysis, global commodity consumption and economic growth trends (this includes the bonus / penalty adjustments for quality). Exchange rates are also based on internal Rio Tinto modelling of expected future country exchange rates. Capital and operating cost estimates are sourced from internal Rio Tinto financial modelling and / or project capital estimates. Third party payments are reflective of the current agreements in place. Due to the commercial sensitivity of these assumptions, an explanation of the methodology used to determine these assumptions has been provided, rather than the actual figures. Mining method and assumptions Dilution and mining recovery parameters are applied during the Ore Reserve estimation process, based on reconciliation of past performance and are reviewed annually. As the Ore Reserve is shallow, geotechnical risks are low. Stockpile heights and wet road conditions are managed in accordance with standard operating procedures There has been no material change to other Ore Reserve modifying factors, such as: governmental, tenure, environmental, cultural heritage, social or community. Appropriate agreements and approvals remain in place to enable continued operation of these assets. Processing methods and assumptions Weipa bauxite is beneficiated through established techniques to improve product quality and handleability. This is achieved through the removal of the finer fraction, leaving the coarser material as product. Expected bauxite recovery and quality from the beneficiation process is assessed through laboratory scale test work of samples generated from the resource drilling process.
7 Cut-off grades, estimation methodology and modifying factors The Ore Reserve cut-off is based on an economic parameter, summarised as the margin realised upon sale of the bauxite. The economic cut-off approach considers revenue (bonus/penalty), fixed / operating / capital costs, royalties and other third-party payments. Bauxite that satisfies this economic cut-off, is considered for inclusion in the Ore Reserve. There has been no material change to the economic cut-off methodology or process. Criteria used for Ore Reserve classification Given the high level of confidence in the reserve modifying factors, the majority of Measured Resources were converted to Proved Ore Reserves and all Indicated Resources were converted to Probable Ore Reserves. Inferred Resources were not considered in the estimation of Ore Reserves.
8 Competent Persons’ Statement The information in this report that relates to Mineral Resources is based on information compiled under the supervision of Mr Angus C. McIntyre, who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). Mr McIntyre has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the JORC Code. Mr McIntyre is a full-time employee of Rio Tinto and consents to the inclusion in this report of RTA Pacific Operations Bauxite Mineral Resources based on the information that he has prepared in the form and context in which it appears. The information in this report that relates to Ore Reserves is based on information compiled under the supervision of Mr William Saba who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). Mr Saba has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the JORC Code. Mr Saba is a full-time employee of Rio Tinto and consents to the inclusion in this report of RTA Pacific Operations Bauxite Ore Reserve based on the information that he has prepared in the form and context in which it appears.
9 Contacts Please direct all enquiries to media.enquiries@riotinto.com Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948 Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary. riotinto.com
Appendix 10 Weipa JORC Table 1 The following table provides a summary of important assessment and reporting criteria used at Weipa (as the combination of the Amrun and East Weipa / Andoom deposits) for the reporting of Mineral Resources and Ore Reserves in accordance with the Table 1 checklist in The Australasian Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code, 2012 Edition). Criteria in each section apply to all preceding and succeeding sections. Section 1: Sampling Techniques and Data Criteria Commentary Sampling techniques • Samples for geologic logging and analysis are collected on 0.25 m intervals (~2-3 kg) downhole using aircore drilling methods. • Whole samples are collected beneath a cyclone return system (i.e., no sample splitting is conducted). • Multiscreen sampling is undertaken to determine optimum screen size for beneficiation at each deposit. • Once determined, samples are then beneficiated at the appropriate screen size (1.7 mm for East Weipa, 0.3 mm for Andoom and 0.6 mm for the Amrun deposits). Drilling techniques • The current drilling method utilises aircore drilling. • The typical aircore rig used at Weipa is a Land Cruiser mounted rig with a small enough wheelbase to traverse drill lines cleared with one D-6 dozer blade width. Aircore drilling forces compressed air down a space inside the drill rods to the bit face, where the air is then used to return the sample up the inner tube of the drill rod and out via a cyclone. A three bladed HQ aircore bit is attached to 4-inch rods. The drilling system has been designed to reduce grinding of the sample. • Historic drilling utilised auger drilling (until 1991). Drill sample recovery • No direct recovery measurements of aircore drilling samples are performed. • Whole sample is taken. • Holes are re-drilled if there is excessive sample loss (determined visually). • Sample weights are recorded before and after beneficiation in the laboratory. Logging • Standardised Rio Tinto Aluminium Weipa bauxite logging systems are utilized for drilling. • Logging is currently conducted on Panasonic Toughpads and data is captured in an offline acQuire logging package at the drill rig. This system allows for data validation to be applied during logging as well as a streamlined method of exporting the data for importing into the main RTA Geology database. • Logging is qualitative in nature, i.e., based on lithology. Currently there are ~20 lithologies common to the deposits that get modelled into four horizons for the estimation of bauxite resources. • All sample intervals (0.25 m) are logged. • The holes are generally terminated four samples (1 m) into the floor lithologies as observed by the rig geologist. • Logged lithologies are vetted against historical drill holes and assay parameters. Sub-sampling techniques and sample preparation • No sub-sampling undertaken. • Sample preparation at Weipa is carried out at the purpose-built facility. The facility consists of two Kason washing screens, two drying ovens, a multiple screening facility, and grinding units. Beneficiated, un-beneficiated (crude) and multiscreen drill samples pass through this area prior to their being assayed for the major oxides and loss on ignition (LOI). • Sample preparation at ALS, Brisbane was set up with the same specifications of equipment as Weipa, however, was scalable to install up to six Kasons, larger drying ovens, more grinding capability and room for multi-screens. • The majority of analyses are undertaken at ALS laboratory in Brisbane since 2015, prior to that the majority of the analyses were done at Weipa. Quality of assay data and laboratory tests • Bauxite industry standard XRF analysis of all major elements and a suite of trace elements are undertaken on all samples. • Matrix matched field standards are systematically used. • Laboratory preparation duplicates and assay standards also form part of the QA/QC procedure. • The Weipa Laboratory participates in a “round robin” process managed through the RTA Process Improvement team. This process includes all the RTA and affiliated laboratories and is reviewed on a
11 quarterly basis to ensure that standards are maintained. The Weipa laboratory analysts also carry out internal checks on the assay data. Results not meeting certain criteria or outside a designated range are re-analysed. Standard and duplicate samples are also used by the Mine Geology Department to monitor the performance of the laboratory via standard QA/QC routines. • The ALS, Brisbane laboratory maintains its NATA accreditation through annual inspections and testing as required. RTA visit and audit both the preparation facility and analytical rooms regularly. • Every assay batch returned from the laboratories is checked through acQuire QA/QC objects before being accepted to the database for use in resource estimation. Major oxides, LOI, and KSiO2 are checked routinely against performance of field standards, lab duplicates, and lab standards. • Any results for the standards that lie outside three (3) standard deviations of the mean are classified as failing QA/QC and assays excluded from modelling. • Analysis of the performance of certified standards, field duplicates, blanks and third-party check assaying has indicated an acceptable level of accuracy and precision with no significant bias or contamination. Verification of sampling and assaying • Twin holes were historically used incorrectly. Samples were combined for the two and tested. Results were not comparable for verification purposes. Twin holes are not in use anymore. • Infill drilling programs for resource definition return results in line with the wider spaced drilling. • Data validation occurs throughout the data collection process: during data capture, during importation into the database, following import into the database and during the modelling process (hole name, location checks, RL checks, lithology order checks, missing data, incorrect data). Location of data points • Pre-2016 drill hole peg locations were surveyed to Australian Height Datum (AHD) and the Geocentric Datum of Australia 1994 (GDA94) grid (and converted to local mine grids) by contract surveyors using Differential Global Positioning System (DGPS) survey equipment which was accurate to 10 cm in both horizontal and vertical directions. • Post 2016 surveys utilises GNSS GPS systems. Where survey has not been completed, e.g., Amrun 2018-2019 drilling campaign, LiDAR positioning of drill collar elevations are utilised to assist in the creation of the topographic surface. Data spacing and distribution • All downhole drill sampling is at 0.25 m intervals, and samples are taken of the roof and floor. • No sample compositing is done. Orientation of data in relation to geological structure • Not applicable in lateritic bauxite deposits. All drill holes are vertical, which intersects the horizontal ore body perpendicularly. Sample security • Samples are collected, bagged, ticketed and sealed at the drill sites. Samples are placed in bulk plastic containers, with a capacity of ~ 300 samples, for shipment to the laboratory. All samples are electronically logged into a system for tracking and validation. Samples are placed on a dispatch advise form and verified by the laboratory on arrival. All assay pulps are stored at Weipa or ALS Brisbane in purpose-built sample storage facilities. Audits or reviews • An external Mineral Resource and Ore Reserve audit was completed in 2019 on the Weipa deposit. This audit had an outcome of Satisfactory with one medium and five low rated potential risks to the Mineral Resources and Ore Reserves. Actions were put in place to address all findings. • Numerous internal peer reviews and studies have also been undertaken over the years. These reviews concluded that the fundamental data collection and modelling techniques were appropriate.
12 Section 2: Reporting of Exploration Results Criteria Commentary Mineral tenement and land tenure status • The Weipa Bauxite deposits are located on the western side of the Cape York Peninsula in far north Queensland, Australia. Mining Lease (ML) 7024 and ML 7031 covers the various deposits. ML 7031 was obtained through the acquisition of Alcan in 2007. ML 6024 is a separate lease that is held in order to provide infrastructure access between the north of Embley and south of Embley operations at Weipa. • ML 7024 was granted by the State Government of Queensland under a separate Act of Parliament, “The Commonwealth Aluminium Corporation Pty. Limited Agreement Act 1957”. The effective date of the lease granted under this act is 1/1/1958 and the expiry date is 31/12/2041 with an option to extend to 31/12/2062. Lease extensions past 2062 can be obtained, beyond the initial renewal period, subject to both parties’ right to terminate on two years notice. • ML 7031 was granted by the State Government of Queensland under a separate Act of Parliament “The Alcan Queensland Pty. Limited Agreement Act of 1965”. The effective date of the lease granted under this act is 1/1/1964 and the expiry date is 31/12/2047 with an option to extend to 31/12/2068. Lease extensions past 2068 can be obtained, beyond the initial renewal period, subject to both parties’ right to terminate on two years notice.
13 Exploration done by other parties • Not applicable. Weipa is a mature mining operation with more than 50 years of operational and orebody knowledge. Geology • The rocks of the Cape York Peninsula are divided into two geological units: the sedimentary rocks on the western side of the peninsula and the igneous and metamorphic rocks exposed in the hills on the eastern side of the peninsula (the Coen Inlier). • The Cape York Peninsula bauxites are confined to a dissected laterite plateau, known officially as the Weipa Plateau on the west coast of Cape York Peninsula. The Weipa Plateau is one of three geomorphologic land units that are of particular interest to the geology of the bauxite and kaolin resources. The other two units are the Merluna Plain and the Mapoon Plain. • The Weipa Plateau is a low plateau, usually no more than a few tens of metres above sea level and has been dissected by various river systems resulting in a series of irregularly shaped islands. It is intensely weathered to a depth of 20 m to 30 m with the upper part of the weathered material reconstituted into various nodules as well as some partially cemented rocks. The flatness of the plateau has meant it has been immune to erosion other than by rivers eating away at the sides. Much of the plateau’s volume was removed in solution in the groundwater, which is also responsible for the formation of the bauxite. The sedimentary rocks of the Weipa Plateau fall into two categories: The Rolling Downs Group Sediments; and The Bulimba Formation Sediments (Weipa Beds). • These two groups of sediments are eroded and weathered to form the Weipa bauxites. The different sediments resulted in different types of bauxite formations. • The Bulimba Formation sediments lie on top of the Rolling Downs Group and occupy channels that cut down into them. The Rolling Downs Group were uplifted above sea level and weathered before the Bulimba Formation sediments deposited on them. The river sediments are less homogeneous than the marine ones. Deposition occurred as short erratic events rather than a slow continuous one and a changing sea level resulted in a mixture of sands and clays. The greater variability in the sediments is reflected in greater local variability in grade of the Weipa type bauxites. • Andoom type bauxites are derived from shallow marine sediments that are fine grained, with very little quartz, and this material is generally screened at 0.3 mm. The Weipa type bauxites are derived from river deposited sediments that are coarse grained, with abundant quartz, and this material is therefore screened at 1.7 mm. Drilling at Amrun suggests a more intensely braided river system allowing more mixing between the Bulimba and Rolling Downs formations. This fits with the optimum screen size of the area being between the Andoom and Weipa deposits. Amrun is currently screened at 0.6 mm • The Cape York Peninsula bauxites are thin, tabular deposits that vary from zero to 10 m in thickness and are continuous laterally for many kilometres. The unconsolidated pisolites are generally overlain by 0.5 m topsoil and sit on an ironstone base. • The rocks of the Bulimba Formation and Rolling Downs Group have been converted to bauxite via a continuum of weathering. An annual high rainfall and a geologically stable environment has provided the perfect ingredients for a world-class bauxite deposit to form over many millions of years. A deep saprolitic zone overlain by a classic mottled zone below the bauxite mineralisation attests to this. • The process of bauxitisation involves the conversion of kaolinite to the bauxite minerals gibbsite and boehmite. The principal influence on the process is the composition, supply and movement of groundwater. The pH of the groundwater is lowered during the process of bauxitisation, and we note that the process is still ongoing as we see a low pH regularly throughout the ground water monitoring bores across the RTA mining leases. To a lesser extent there are organic influences such as vegetation, and possibly burrowing organisms and temperature. • The dissolution of both kaolin and quartz controls the distribution of silica grades in the deposits. The combination of kaolin and quartz distributions results in a typical vertical chemical profile that is usually found throughout the deposits and appears to be independent of the bauxite thickness i.e., the same vertical grade trend is found in both thin and thick bauxites. The typical vertical grade profile for silica is high silica at the top of the bauxite, which quickly drops to a much lower silica value that plateaus for the majority of the profile and then rises quickly back to high silica values again right at the base of the bauxite profile. As alumina is left behind by the dissolution of kaolinite, the typical
14 vertical grade profile for alumina is almost the inverse of silica. The relationships between the genetic processes and the resulting grade profiles are displayed in the figure on the next page. Drill hole Information • As this report relates to Mineral Resources and no Exploration Results are being reported, this section is considered not applicable. Resource work is currently more focussed on asset evaluation rather than exploration, systematically bringing the bauxite classification to higher levels of confidence. Data aggregation methods • Not applicable. Weipa is a mature mining operation with more than 50 years of operational and orebody knowledge. Relationship between mineralisation widths and intercept lengths • All drill holes have been drilled perpendicular to the horizontal stratigraphy of the deposit. • All known horizons of the deposits: overburden, red soil, bauxite and ironstone are intersected and sampled during drilling. Drilling continues for 1 m into the ironstone to ensure the transitional boundary between the ore and floor is intersected. Diagrams • Type section for the Weipa deposits. Balanced reporting • Not applicable. Weipa is a mature mining operation with more than 50 years of operational and orebody knowledge. Other substantive exploration data • Not applicable. Weipa is a mature mining operation with more than 50 years of operational and orebody knowledge.
15 Further work • Drilling will continue in the future to further support the five-year and life of mine plans, as well as options for future growth. Section 3: Estimation and Reporting of Mineral Resources Criteria Commentary Database integrity • Data capture is on Panasonic Toughpad digital loggers that have internal validation rules that identify logging errors. • The geological drill hole database (RTA Geology) is managed by the Bauxite Geology Team within Rio Tinto Aluminium. Drilling data is securely stored in a Microsoft SQL Server using an acQuire front end. acQuire is a third-party software product that provides a user-friendly interface to SQL Server and consists of two components: a Relational Data Model (structured storage tables and links) optimised for the storing of exploration and mining data information; and a Software System (objects for data collect/importing/exporting, validation, viewing, modification, etc.) to manage the data and provide end user functionality for the optimum use of exploration and mining data. • The database is located on a virtual server hosted in Rio Tinto’s Azure cloud servers in Sydney. They are backed up daily in accordance with Rio Tinto’s standard back up procedure. • The drill hole database used for Mineral Resource estimation has been internally validated. Methods include checking: acQuire scripts for relational integrity, duplicates, total assay and missing / blank assay values. Domain names. Null and negative grade values. Missing or overlapping intervals. Duplicate data. • Drill hole data was also validated visually by domain and compared to the geological model. Site visits • The Competent Person for the Weipa Mineral Resource visits the site on a regular basis and is involved in all aspects relating to the ore body knowledge. Geological interpretation • The Weipa bauxite geology is not complex in nature and is well understood as a predominantly pisolitic lateritic weathering profile. • Geological modelling of the bauxite horizon is undertaken using drill hole lithological logging and assay data. Logged lithologies are grouped into four horizons for modelling and estimation purposes, these are: Overburden (Soil, Overburden, Sand). Red Soil (Red Soil and Soil Red). Bauxite (Bauxite, Clay Bauxite, Cemented Bauxite, Transition and Clay Transition). Ironstone (Ironstone, Clay ironstone, Transition, Clay Transition and Clay). • For Transition and Clay Transition difficult to log in the field, horizon allocation is based on grade. • Cross-sectional interpretation of the bauxite stratigraphy is conducted. Three-dimensional wireframes of the sectional interpretations are automatically produced and used to generate and inform the block model. • Geological models using the 1970’s data (4 out of 16 models) are not as reliable as those using post 1995 data due to the difference in the quality of drilling and sampling techniques. These areas currently have a downgraded classification and are systematically being replaced with new holes to increase confidence in the Mineral Resource estimation. Dimensions • The Weipa bauxite deposits are laterally very extensive, covering the majority of ML 7024 and ML 7031 (~380k ha). Deposits vary in average thickness from 1.5 m to around 8 m and vary from 0.3 m to 0.6 m below surface cover.
16 Estimation and modelling techniques • Basic geostatistical analysis is used to help with domaining decisions. Most deposits were modelled as a single domain, apart from Moingum (Hey Point) where two domains have been modelled due to differences in bauxite thickness, grades and source rocks. • Interpretation and estimation are performed using Datamine’s Studio RM software, with variography undertaken in FSS International Consultants (Australia) GS3M software. • Four horizon codes, based on the lithology and assays, are assigned for the modelling and estimation of bauxite resources, see the Geological Interpretation section. Each deposit is a single domain laterally, divided into four horizons vertically. • The bauxite horizon is flattened to the mid-point of the drill hole intersections at East Weipa and Andoom, while drill hole collars are flattened to constant elevation at Amrun, Norman Creek and Moingum (Hey Point). The wireframes are filled with blocks on an in/out basis; there is no sub-blocking or block proportions used. • Major oxides, LOI and Recovery for the bauxite horizon are estimated using ordinary kriging into parent cells. • Overburden and red soil are assigned 0% recovery for the estimation of resources. • Cemented bauxite grade is estimated as part of the bauxite horizon and assigned a 100% recovery; the proportion of cemented bauxite is estimated as an indicator variable. • Major oxide chemistry is also estimated for the overburden, red soil and ironstone horizons, where data is available. Ordinary kriging is used for interpolation, using the variogram models from the bauxite domain. • A multiple pass search strategy is used to estimate grades, as shown in the following table. Pass 4 is not used in the East Weipa and Andoom areas. Maximum extrapolation distance is slightly less than the maximum search radii due to the requirement to use at least two holes to estimate each block. Search Radii Samples Pass X (m) Y (m) Z (m) Min Max Per Hole 1 120 120 1.0 12 24 5 2 180 180 1.5 8 24 5 3 360 360 3.0 8 24 5 4 720 720 6.0 8 24 5 • There are no extreme grade values, so no grade cutting is required. • Estimation parameters and search distances are determined from consideration of the drill hole and sample spacing in each deposit, as well as the anisotropy of the variogram models. • The plan extents of the block models extend at least two blocks past the drilling grid. In the vertical direction, four ‘edge’ blocks are created below the base of drilling. • The block size is set at half the drill hole spacing in the horizontal (40 m x 40 m at Andoom and East Weipa; 50 m x 50 m at Amrun) and at the sample spacing in the vertical (i.e., 0.25 m). • The model block size effectively is the selective mining unit (SMU). • Deleterious element silica is assayed using XRF. Kaolinite (reactive silica) is determined using NIR analysis. Quartz is determined by difference. • No specific assumptions are made regarding the correlation of variables during estimation as each element is estimated independently. Some attributes do show strong positive or negative correlation in the drill hole samples, and the similarity in variogram models for different attributes and identical search parameters effectively guarantee that these correlations are preserved in the estimates. • Routine validation of the block model estimation is completed using global model versus sample statistics, swathe plots, grade tonnage curves, volume checks, and visual cross-section comparisons
17 (block estimates against drill hole samples). Filtering by search volume and number of samples can improve comparisons. • The Mineral Resource estimates take appropriate account of previous estimates and mine production. The new models are broadly comparable with previous estimates despite significant changes in methodology. While detailed reconciliation has not been undertaken, the new models appear to reconcile with mine production within tolerable limits, as previous estimates did. Moisture • All Mineral Resource tonnages are reported on a dry basis. • All Mineral Resources are reported as the beneficiated dry product, except for North of Weipa (reported as DSO product). Cut-off parameters • Grade cut-offs are routinely used to determine the potential Mineral Resources of the modelled horizons. Where lithological contacts are transitional, chemical cut-offs based on alumina and silica are used with <15% SiO2 and > 40% Al2O3. These blocks are then reviewed against location (buffer areas), as well as thickness cut-offs ranging from 0.5 m to 1 m for each deposit. • The estimation of Ore reserves utilises an economic parameter, summarised as the margin realised upon sale of the bauxite. The economic parameter is used as a check to validate technical resource assumptions applied in determining available resources. Mining factors or assumptions • Weipa is mined through shallow open cut techniques developed over several decades of operations. After topsoil is removed, front end loaders excavate the bauxite and belly dump trucks transport the bauxite to the beneficiation plant. • As the Weipa orebodies are shallow, geotechnical risks are extremely low. Pre-production drilling is completed in order to provide better definition of the roof and floor contacts for the five-year mine planning process. • Estimates include internal dilutional but no allowance for external dilution or mining recovery. Dilution and mining recovery are applied during the reserving process, not during estimation. • A minimum mining thickness for the bauxite horizon of 0.5 m is used for the final determination of resource figures. Metallurgical factors or assumptions • Weipa bauxite is beneficiated through established techniques to improve product quality and handleability. This is achieved through the removal of the finer fraction and leaves the coarser material as product. • The beneficiation process typically involves wet screening and may include the use of cyclones and classifiers depending on the part of the deposit being beneficiated. • Expected bauxite recovery and quality from the beneficiation process is assessed through laboratory scale test work of samples generated from the resource drilling process. • Bauxite mineralogy has been investigated through numerous studies, primarily using wet chemical techniques, to understand how it will react in the Bayer Process, which is used to extract the alumina at the refineries. • A proprietary mineralogical calculator “MinCalc” is used to estimate bauxite mineralogy and Bayer processing grade for Cape York ore from the routinely collected elemental chemistry and thermogravimetry, as routine wet chemical techniques are prohibitively expensive. MinCalc calibration is orebody specific and is validated and recalibrated during the life of mine operations. Environmental factors or assumptions • East Weipa, Andoom and Amrun have obtained all relevant environmental approvals required to continue operations. • Operation of tailings dams at Weipa (East Weipa and Andoom) and Amrun are covered by relevant government permits. Bulk density • Bulk density is not measured on drill hole samples and is not modelled. • Bulk density has been determined by using the Sand Replacement Method and Nuclear Density Gauge Testing according to Australian standards AS 1289.5.3.1-1993 and AS 1289.5.8.1-1995. • A number of studies have been conducted over the deposits with the most common test pit spacing being 5,000 m. This produced the bulk density utilised in resource tonne calculations. • Default values are also assigned to cemented bauxite, overburden and floor material for each of the different deposits at Weipa, see the table on the next page.
18 Bulk Density Parameters Value (t/m3) Overburden 1.23 Bauxite 1.47 – 1.67* Cemented Bauxite 2.50 Ironstone/Floor 1.42 *Different for each deposit Classification • Drilling is conducted to a 76.2 m x 76.2 m (Andoom and East Weipa) or 50 m x 100 m (at Amrun) spacing for grade control purposes. • To be declared a Measured Resource a deposit must be drilled to a 152.4 m x 152.4 m (Andoom and East Weipa) or 100 m x 200 m (at Amrun) spacing. • Indicated Resources are drilled on a 305 m x 305 m (Andoom and Weipa) or 200 m x 400 m (at Amrun) spacing. • Inferred Resources are drilled on a 914.4 m x 914. 4m (Andoom and East Weipa) or 800 m x 1200 m (at Amrun) spacing and utilize multiscreen drilling. • Classification within the bauxite horizon is based on the search pass used to estimate grades, using increasing search radii and decreasing numbers of samples for each subsequent pass. Passes 1 and 2 are classified as Measured Resources, Pass 3 as Indicated and Pass 4 as Inferred. Search Radii Samples Resource Category Pass X (m) Y (m) Z (m) Min Max Per Hole Measured 1 120 120 1.0 12 24 5 2 180 180 1.5 8 24 5 Indicated 3 360 360 3.0 8 24 5 Inferred 4 720 720 6.0 8 24 5 • Appropriate account has been taken of all relevant factors. • The Competent Person is satisfied that the current Mineral Resource classification reflects the relevant factors for the deposit. Audits or reviews • An external Resource and Reserve audit was completed in 2019 on the Weipa deposit. This audit had an outcome of Satisfactory with one medium and five low rated potential risks to the Mineral Resources and Ore Reserves. Actions were put in place to address all findings. • Numerous internal peer reviews and studies have also been undertaken over the years. These reviews concluded that the estimation techniques were appropriate. Discussion of relative • The relative accuracy and confidence level in the Mineral Resource estimates are considered to be in line with the generally accepted accuracy and confidence of the nominated JORC Mineral Resource categories. This has been determined on a qualitative, rather than quantitative, basis, and is based on the estimator’s experience with a number of deposits at Cape York and similar deposits elsewhere.
19 accuracy/ confidence The main factors that affect the relative accuracy and confidence of the estimates are the drill hole spacing and the local definition of the lithological horizons. • The estimates are local, in the sense that they are localised to model blocks of a size considered appropriate for local grade estimation. The tonnages relevant to technical and economic analysis are those classified as Measured and Indicated Mineral Resources. Section 4: Estimation and Reporting of Ore Reserves Criteria Commentary Mineral Resource estimate for conversion to Ore Reserves • The Ore Reserve estimates are developed from the geological models current as of September 2021, and the Mineralogy model updated in 2020. • Mineral Resources are stated exclusive of Ore Reserves. Site visits • The Ore Reserves Competent Person has been employed by Rio Tinto Aluminium for a significant period and has visited Weipa several times in recent years. Study status • Weipa Operations has been operating continuously for several decades, and the Ore Reserve estimate and life of mine plan are updated annually. This includes the reconciliation of operating parameters and review of input assumptions into the planning processes. • The Ore Reserve estimate for Amrun is based on the completed and approved feasibility study and has now been in continuous operation for three years. This includes the reconciliation of operating parameters and review of input assumptions into the planning processes. Cut-off parameters • The Ore Reserve cut-off is based on an economic parameter, summarised as the margin realised upon sale of the bauxite. The economic cut-off approach considers revenue (bonus/penalty), fixed/operating/capital costs, royalties and other third-party payments. Bauxite that satisfies this economic cut-off, is considered for inclusion in the Ore Reserve. Mining factors or assumptions • The Ore Reserve is mined through shallow, open cut techniques developed over several decades of operations. Once the area is tree cleared and the topsoil/overburden removed, the bauxite is hauled to the beneficiation plant for processing. Several mining areas are active at any one time to enable blending and to mitigate against operational risk. • As the Ore Reserve is shallow, geotechnical risks are low. Stockpile heights and wet road conditions are managed in accordance with standard operating procedures • Dilution and mining recovery parameters are applied during the Ore Reserve estimation process, based on reconciliation of past performance and reviewed annually. • Minimum bauxite mining thickness of 0.9 m is used for Amrun Ore Reserve estimation. • Inferred Mineral Resources are not considered in the estimation of Ore Reserves. Metallurgical factors or assumptions • Weipa bauxite is beneficiated through established techniques to improve product quality and handleability. This is achieved through the removal of the finer fraction, leaving the coarser material as product. The beneficiation process typically involves wet screening and may include the use of cyclones and classifiers depending on the part of the deposit being beneficiated. • Expected bauxite recovery and quality from the beneficiation process is assessed through laboratory scale test work of samples generated from the resource drilling process. • Extractable alumina is calculated through application of a Mineralogy model. Environmental • All relevant environmental approvals have been obtained to continue operations. • An EIS has been completed for Amrun with the relevant governmental approvals having been obtained. • Operation of tailings dams at Weipa (East Weipa, Amrun and Andoom) are covered by relevant government permits. Infrastructure • As East Weipa, Andoom and Amrun are all established sites, all appropriate infrastructure for the existing operation is already developed. This includes water, power, sewage, stores, maintenance
20 workshops, administration buildings and the Weipa township. Any infrastructure expansion required in the future is allowed for in the financial modelling that supports the Ore Reserve. Costs • Operating and sustaining capital costs are sourced from the Weipa Operations financial model. • Future capital costs are based on project study estimates or five-year plan sustaining capital amounts. • Traditional owner and carbon tax assumptions are factored into the financial modelling. • Exchange rates are based on internal Rio Tinto modelling of expected future country exchange rates. Revenue factors • Commodity prices are based on internal Rio Tinto modelling of the future supply and demand balance for bauxite, alumina and aluminium. This includes the bonus and penalty adjustments for quality. • Queensland royalties are included in the financial modelling at 10.0% of the bauxite price. • Exchange rates are based on internal Rio Tinto modelling of expected future country exchange rates. Market assessment • Industry analysis is undertaken to assess the existing and future supply and demand balances in bauxite, alumina and aluminium. This includes assessing likely incentive pricing required to bring on new capacity. • Internal Rio Tinto forecasting revises production guidance on an annual basis. Economic • Operating costs are built up from first principles while capital costs are included based on current estimates. Appropriate escalation is built in where capital costs are to be incurred in the future. • The discount rate to be used in the NPV model is supplied from Rio Tinto corporate and is set based on risk adjusted cost of capital. • Sensitivity analysis is carried out to assess key project drivers and the sensitivity of the project economics to movements in these drivers. Social • Weipa has in place the Weipa Community Co-existence Agreement (WCCCA) with local traditional owners. It also has a Community Relations department that seeks to build relationships with the local communities in and around Weipa. Other • Tenure to exploit the Weipa deposit is granted through two state agreements and is held through two mining leases ML 7024 and ML 7031. • The Queensland Government Comalco (ML 7024) lease expires in 2041 with an option of a 21-year extension, then two years’ notice of termination; the Ely Alcan Queensland Pty. Limited Agreement Act 1965 (ML7031) expires in 2048 with a 21-year right of renewal with a two-year notice period. • An EIS process was completed for the Amrun brown field mining expansion. Both the Queensland and Commonwealth governments have approved the EIS subject to several conditions. Classification • Given the high level of confidence in the reserve modifying factors, most Measured Resources were converted to Proved Ore Reserves and all Indicated Resources were converted to Probable Ore Reserves. • Inferred Mineral Resources are not considered in the estimation of Ore Reserves. • The Competent Person is satisfied that the current classification is reasonable for the Weipa Ore Reserves. • The Competent Person is satisfied that the stated Ore Reserve classification reflects the outcome of technical and economic studies. Audits or reviews • A Mineral Resource and Ore Reserve internal audit was completed in 2019 and in 2015 on the Weipa deposit. These audits concluded that there were medium and low rated potential risks to the Mineral Resources and Ore Reserves. All findings from the recent audit have been actioned for completion by end of 2022. Discussion of relative accuracy/ confidence • Ore Reserve estimates are compared with production data on a half yearly and annual basis at Weipa. This reconciliation shows that for all key parameters, production was within ±5% of the estimates for calendar year 2021.
Notice to ASX 23 February 2022 Rio Tinto reports first Indicated Mineral Resource and 40% increase in contained copper at Winu project Rio Tinto’s 2021 Annual Report which will be released to the market on 24 February 2022 will include changes in estimates of Mineral Resources at Rio Tinto’s 100% owned Winu project in Western Australia, compared to those published in the 2020 Rio Tinto Annual Report. The updated estimates comprise an Indicated Mineral Resource of 249 Mt at 0.55% copper equivalent, and an Inferred Mineral Resource of 358 Mt at 0.46% copper equivalent, giving a total Mineral Resource of 608 Mt at 0.49% copper equivalent, at 0.2% copper equivalent cut-off. Rio Tinto further reports that: • contained copper metal in the total Mineral Resource has increased 40%; and • the Winu deposit is still open in several directions with drilling programs in 2022 continuing to target extensions. The changes in Mineral Resources are reported in accordance with the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, 2012 (JORC Code) and the ASX Listing Rules. Supporting information relating to the changes is set out in this release and its appendix. Mineral Resources are quoted in this release on a 100 per cent basis. The updated Mineral Resource is supported by a substantial increase in drilling information acquired since the release of the initial Inferred Mineral Resource dated 28 July 2020, and on the advancement of mining and processing studies. Rio Tinto’s 2021 Annual Report will set out in full Rio Tinto’s Mineral Resources and Ore Reserves position as at 31 December 2021, and Rio Tinto’s interests. At a 0.2% copper equivalent (CuEq) cut-off the total Mineral Resource is 608 Mt @ 0.40% Cu, 0.30 g/t Au or 0.49% CuEq. This represents a 21% increase in tonnage, a 16% increase in copper grade, a 12% increase in gold grade, a 40% increase in contained copper metal and a 35% increase in contained gold metal. A proportion of the total Resource meets the requirements for Indicated Mineral Resources and an Indicated Mineral Resource is reported for the first time. Since the initial public release of Mineral Resources, drilling targeting Winu mineralisation has continued, resulting in an 83% increase in reverse circulation drilled metres, a 93% increase in diamond drill metres, for an overall increase of 88% drill metres. The deposit remains open at depth as well as to the north, south and east and the project team continues to explore the deposit margins. While exploration activity has been somewhat constrained by site clearances at surface, the presence of copper, gold and silver mineralisation of a similar geological style and setting at the margins indicates that the Winu deposit is not, at this time, limited by geology. Further work is required to confirm and increase understanding of extensions to the orebody. In 2021 the project transitioned from Rio Tinto Exploration to Rio Tinto Copper where it will be advanced through the next phase of delivery. Recent technical and commercial reviews, independent of the study team, were positive and the project continues to enjoy support from the Rio Tinto Board which has approved additional expenditure to progress early works at Winu and further prepare the project for a final investment decision. EXHIBIT 99.12 /LSE
2 The Winu project team continues to work with local Nyangumarta and Martu Traditional Owners and regulators to progress the agreements and approvals required for any future development. Winu Updated Mineral Resource The updated Mineral Resource is presented in Table A at 0.2% CuEq cut-off. At a 0.2% CuEq cut-off the Mineral Resource comprises an Indicated Mineral Resource of 249 Mt @ 0.55% CuEq and an Inferred Mineral Resource of 358 Mt @ 0.46% CuEq. The Mineral Resource is constrained by a notional pit shell supported by preliminary mining studies and economic assessment. (The figures used to calculate Mineral Resources are often more precise than the rounded numbers shown in the tables, hence small differences may result if the calculations are repeated using the tabulated figures). Table A Winu Mineral Resources as at 31 December 2021 at 0.2% CuEq cut-off, within the notional Mineral Resource pit shell CuEq % Cut-off Resource Classification Tonnes (Mt) CuEq (%) Cu (%) Au (g/t) Ag (g/t) >=0.2 Supergene Indicated 26 0.68 0.64 0.52 3.54 Inferred 29 0.51 0.45 0.46 2.12 Supergene Subtotal 55 0.59 0.54 0.49 2.80 Hypogene Indicated 223 0.53 0.43 0.31 2.62 Inferred 330 0.45 0.37 0.27 1.94 Hypogene Subtotal 552 0.49 0.39 0.28 2.21 Total Indicated 249 0.55 0.45 0.33 2.72 Inferred 358 0.46 0.37 0.28 1.95 Grand Total 608 0.49 0.40 0.30 2.26 Included in the Mineral Resource is a higher grade component shown in Table B as a sensitivity. This portion of the Mineral Resource is tabulated at 0.45% CuEq cut-off, constrained by the notional Mineral Resource pit shell.
3 Table B Winu Mineral Resources as at 31 December 2021 at 0.45% CuEq cut-off, within the notional Mineral Resource pit shell CuEq % Cut-off Resource Classification Tonnes (Mt) CuEq (%) Cu (%) Au (g/t) Ag (g/t) >=0.45 Supergene Indicated 15 0.95 0.88 0.72 4.67 Inferred 11 0.83 0.73 0.70 3.49 Supergene Subtotal 27 0.90 0.82 0.71 4.17 Hypogene Indicated 113 0.74 0.60 0.40 3.67 Inferred 129 0.68 0.56 0.34 2.93 Hypogene Subtotal 242 0.71 0.58 0.37 3.27 Total Indicated 128 0.76 0.63 0.44 3.79 Inferred 140 0.69 0.58 0.37 2.97 Grand Total 269 0.73 0.60 0.40 3.36 Table C Comparison of December 31 2021 Mineral Resource to December 31 2020 Mineral Resource 0.2% CuEq Cut-off Tonnes (Mt) Cu (%) Au (g/t) Cu metal (Mt) Au metal (Moz) 2021 608 0.40 0.30 2.5 5.9 2020 503 0.35 0.27 1.8 4.4 % increase 21% 16% 12% 40% 35% 0.45% CuEq Cut-off Tonnes (Mt) Cu (%) Au (g/t) Cu metal (Mt) Au metal (Moz) 2021 269 0.60 0.40 1.6 3.5 2020 188 0.55 0.36 1.0 2.2 % increase 43% 10% 12% 57% 61% Starter pit The total Mineral Resource is inclusive of a higher grade and shallower body of mineralisation that is the subject of detailed geological and geotechnical assessments, mine design and processing studies, supporting a starter pit design. At a 0.45% CuEq cut-off the Mineral Resource inside the starter pit comprises 128 Mt @ 0.76% CuEq Indicated Resources and 25 Mt @ 0.75% CuEq Inferred Resources for a total of 153 Mt @ 0.76% CuEq, as shown in Table D.
4 Table D December 31 2021 Mineral Resource contained within the starter pit CuEq % Cut-off Resource Classification Tonnes (Mt) CuEq (%) Cu (%) Au (g/t) Ag (g/t) >=0.45 Supergene Indicated 15 0.95 0.88 0.72 4.67 Inferred 9 0.86 0.77 0.74 3.74 Supergene Subtotal 25 0.92 0.84 0.73 4.32 Hypogene Indicated 113 0.74 0.60 0.40 3.67 Inferred 15 0.68 0.53 0.41 3.16 Hypogene Subtotal 128 0.73 0.59 0.40 3.61 Total Indicated 128 0.76 0.63 0.44 3.79 Inferred 25 0.75 0.62 0.53 3.38 Grand Total 153 0.76 0.63 0.45 3.72 Figure 1 on page 7 shows the location of the Winu project. Figure 2 on page 8 shows a plan with the location of all Winu drill holes used in the resource evaluation. Figure 3 (page 9) and Figure 4 (page 10) provide representative cross sections through the Winu orebody.
5 Summary of information to support Mineral Resource reporting Mineral Resources are supported by the information set out in the appendix to this release and located at Resources & reserves (riotinto.com) in accordance with the Table 1 checklist in the JORC Code. The following summary information is provided in accordance with rule 5.8 of the ASX Listing Rules. Geology and geological interpretation Winu has been interpreted as a structurally controlled vein hosted Cu-Au-Ag deposit focused on the core of an anticline in Neoproterozoic metasedimentary rocks. There are multiple vein generations and orientations but the veins are interpreted as being predominantly axial planar. Drilling techniques; sampling and sub-sampling techniques; and sample analysis method Drilling has been carried out using a combination of angled diamond (DD) and vertical and angled reverse circulation (RC) drilling methods, with sampling predominantly on a 1 m sample interval but honouring geological boundaries in the diamond drilled core. Assays have been carried out on half core and split RC samples using a combination of sequential leach assays, full acid digest with AES/MS finish and fire assay for gold. RC and DD drilling programmes in 2020 and 2021 focussed on testing and delineating copper and gold mineralisation in the central Winu position with data acquisition for geotechnical, geometallurgical, hydrogeological and waste characterisation studies for a possible starter pit. Resource drilling on the Winu deposit completed since the compilation of the Mineral Resource estimate supporting the December 31 2020 Inferred Resource totalled 242 RC and 131 DD holes for a total increase of 109,366 m. The Mineral Resource estimate supporting the December 31 2021 Mineral Resource statement consists of 528 mostly vertical-near vertical RC holes (124,513 m) and 235 mostly angled DD holes (109,726 m) for a total of 234,238 m, including holes drilled to support geotechnical and geometallurgical studies. Some holes drilled on the licence outside of the area of known mineralisation, such as sterilisation holes on proposed infrastructure footprint, are not used in the Resource estimate. Estimation methodology Grade estimation utilises Ordinary Kriging at panel scale 40 m x 40 m x 5 m with recoverable estimation by Localised Uniform Conditioning based on 10 m x 10 m x 5 m blocks. The objective of the panel scale estimation is to establish a least biased global estimate, taking into account the drill hole spacing. The objective of the Selective Mining Unit (SMU) scale estimation is to predict the likely grade/tonnage distribution to be anticipated at the time of mining. Dry bulk density has been estimated by Ordinary Kriging on 10 m x 10 m x 5 m blocks using approximately 6,000 measurements from drill core. Cut-off grades and modifying factors The lowest cut-off grade reported (0.2% CuEq) is the marginal cut-off grade for the notional pit and the higher grade cutoff (0.45% CuEq) represents a possible economic cut-off. Copper equivalents have been calculated using the formula CuEq = ((Cu%*Cu price 1% per tonne*Cu_recovery) + (Au ppm*Au price per g/t*Au_recovery) + (Ag ppm*Ag price per g/t*Ag_recovery)) / (Cu price 1 % per tonne). Details of recoveries are shown on an average basis for varying cut-offs in the appendix (JORC Table 1). The reasonable prospects for eventual economic extraction test is met on the basis of mining and processing studies that have been developed throughout 2021. These studies indicate conventional open pit mining and processing routes will be appropriate for the exploitation of the Winu deposit.
6 Criteria used for Mineral Resource classification Resource classification is based fundamentally on the level of confidence assigned to interpretations of geology and mineralisation controls, and assessment of fundamental assay and geological data quality. A specific definition of Indicated Mineral Resource is adopted and is described in Table 1. Blocks are assessed on the basis of a quantitative assessment of Cu grade uncertainty using Conditional Simulation, and linked to proposed mining rates and schedule. Inferred Mineral Resources are constrained within a notional Resource pit shell to a maximum depth of 740m with sufficient support provided by preliminary mining, processing and other studies and using Rio Tinto forward-looking price assumptions. Average drill hole spacing is approximately 75 m throughout the deposit within the Resource pit shell with exceptions in several areas. A close-spaced pattern of 14 diamond holes was drilled to test geological and grade continuity at 15 m centres in the east-dipping plane of mineralisation centred on the sulphide breccia units. This set of holes provided sufficient information to support assumptions of short-range grade continuity. Elsewhere, approximately 12 diamond holes were drilled from north to south, or south to north, to test assumptions of the dominant mineralisation trend. Land access restrictions have prevented drilling in a northern section of the deposit; it is intended to complete drilling in this area upon the granting of land clearances. Mineralised material outside of the notional Resource pit shell is not included in the December 31 2021 Mineral Resource statement. However studies are ongoing to determine under what conditions that material may be considered economic. Within the notional resource pit shell a portion of the deposit has been assessed for a starter pit option via detailed geological, mining and processing studies. The starter pit is indicating a mine life of 32 years. The Mineral Resource in the starter pit is classified predominantly Indicated (23 out of 32 planned production years), on the basis of assessments of expected grade variability in the proposed mine sequence at the proposed mining rate of approximately 30 Mtpa total expit material movement.
7 Figure 1 Property location map
8 Figure 2: Drill hole collar location plan for all Winu holes used in the December 31 2021 Mineral Resource evaluation. Cross section line locations are also indicated.
9 Figure 3: Cross section 1 through the Winu orebody showing the geological model and copper assay intercepts.
10 Figure 4: Cross section 2 through the Winu orebody showing the geological model and copper assay intercepts.
11 Competent Person’s Statement The information in this report that relates to Mineral Resources is based on information compiled under the supervision of James Pocoe, who is a Member of the Australasian Institute of Mining and Metallurgy (MAusIMM). James Pocoe has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity to which he is undertaking to qualify as a Competent Person as defined in the JORC Code. James Pocoe is a full-time employee of Rio Tinto and consents to the inclusion in this report of Mineral Resources based on the information that he has prepared in the form and context in which it appears.
12 Contacts Please direct all enquiries to media.enquiries@riotinto.com Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Amar Jambaa M +61 472 865 948 Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary. riotinto.com
Appendix 13 Winu JORC Table 1 The following table provides a summary of important assessment and reporting criteria used at the Winu project for the reporting of Mineral Resources in accordance with the Table 1 checklist in The Australasian Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code, 2012 Edition). Criteria in each section apply to all preceding and succeeding sections. Section 1: Sampling Techniques and Data Criteria Commentary Sampling techniques • Samples used in the Resource estimate were obtained using either reverse circulation (RC) or diamond (DD) drilling. • RC drilling samples were collected from a static cone splitter on a cyclone at 2 m or 1 m intervals depending on drillhole purpose. The samples consisted of 12% of 1 m and 8% of 2 m intervals to produce an average sample weight of 3.6 kg. • Most pre-collars for diamond drill holes were destructively drilled with either tri-cone rock rollers or mud rotary PCD techniques through the unconsolidated Tertiary sands to the top of the consolidated Permian sediments, at which point casing is installed and standard diamond coring techniques are engaged. • Several diamond holes were pre-collared utilising RC rigs. • All diamond core drilling was drilled using 3 m triple tube assemblies. • All drilling has been carried out under Rio Tinto supervision by experienced drilling contractors. • Core was cut using an automated core-cutter and a half core sample was collected on intervals ranging from 0.4 m to 1.3 m length. Drilling techniques • All drilling is from surface. • Drilling is predominantly by reverse circulation with face sampling bit or triple tubed DD core techniques. • DD holes were generally cased to 30 m progressing from PQ3 to HQ3 at 160 m on average; however, exact depths vary from hole to hole. • RC drillholes were cased between 50 m and 70 m. Drill sample recovery • Core recovery was measured and recorded continuously from the start of core drilling to the end of the hole for each drill hole. The end of each run was marked by a core block which provided the depth, the core drilled and the core recovered from block to block. Core sampling was normally every 1 m, however it was modified by the geologist according to mineral/vein/contact. Sampling does not consider drilling recovery except when core loss is greater than 0.4 m. Sampling recovery, independent of drilling recovery, was not detailed in the logging procedure, however it will be included in the next procedure edition. • RC primary and duplicate samples were weighed upon collection at the rig while all RC samples were weighed upon arrival at the ALS Perth sample preparation facility. • Beyond the point down hole that RC samples cannot be recovered dry, a total of two additional 6 m rods are drilled. Drilling of the hole is stopped if these samples are wet. Logging • Detailed descriptions of core were logged qualitatively for lithological composition and texture, structures, veining and alteration. Visual percentage estimates were made for some minerals, including Cu-oxides and Cu-, Fe-, Mo-, Zn-, and Bi-sulphides. • All recovered core was logged in detail. • DD core was oriented using an ACT III RD tool. At the end of each run, the low side of the core was marked by drilling personnel and this was used at the site for marking the whole drill core run with a reference line. Structural and geotechnical measurements were recorded. • All the DD holes were logged before sampling. • The core was photographed both dry and wet inside the core trays. • The logging of the RC chips was done after sieving and washing of the material collected from the cyclone. • All logging information is uploaded into an acQuire database. Sub-sampling techniques and sample preparation • PQ3 (83 mm) and HQ3 (61.1 mm) DD core was sawn into two, and half was collected in a bag and submitted for analysis, the other half was kept in the tray and stored. The DD half core and RC samples were sent to an ALS Limited laboratory, where they were dried and crushed to 70% passing 2 mm and then split using a rotary splitter to produce a 750 g sub-sample. The crushed sub-sample was pulverised with 85% passing 75 µm using a LM2 mill and a 100 g
14 pulp was then subsampled for ICP and 30 to 50 g for fire assay. • A portion of the 2 mm sized material was used for VNIR/SWIR spectral readings, which were sent to aiSIRIS International for interpretation. • Sample sizes are considered appropriate for the style of mineralisation. Quality of assay data and laboratory tests • All samples were submitted to an ALS Limited laboratory in Perth. • 51 elements were analysed using 4-acid digestion followed by ICP-OES/MS measurements, including qualitative Au, Pt and Pd. • 30 g of sample were used for Au analysis by fire assay with AAS finish. • Portable XRF analysis on pulp for Cr, Nb, S, Si, Ta, Ti, Y and Zr was done using a Delta and Vanta Olympus instrument. • Quality control samples consisted of field duplicates (3 per 100), crush duplicates (1 per 55), pulp duplicates (1 per 55), blanks (3 per 100) and certified reference materials (3 per 100). All the results were checked in the acQuire database before being used, and the analysed batches were continuously reviewed to ensure performance within acceptable accuracy and precision limits for the style of mineralisation. Any samples failing this quality control process resulted in re-analysis of the sample batch prior to acceptance into the database. Verification of sampling and assaying • All the sample intervals were visually verified using high quality core photography through Imago, and some selected samples were taken inside the mineralised interval for optical and petrographic microscopy by qualified petrographers. • No adjustment was made to the assay data that are electronically uploaded from the laboratory to the database. • Within the Winu drilling area, a total of 23 sets of twin holes have been drilled and assayed consisting of 6 sets of DD/DD, 14 sets DD/RC and 3 sets RC/RC. Several studies have identified small bias and precision differences between RC and DD where paired data exist. The Competent Person considers the bias to be in an acceptable range. • A systematic analysis of duplicate samples was carried out at each stage of sampling including field, crush and pulp duplicates. The results from the duplicates were within acceptable range for this type of mineralisation and the classification of the resource. The results from blanks did not indicate contamination during the laboratory procedure. Location of data points • Drill hole collar locations were surveyed after drilling utilising a handheld Garmin GPS with an accuracy of 5 m, and on a campaign basis by an independent survey contractor using a Leica Viva GS15 GNSS base and rover system operating in RTK mode to a stated accuracy of +/- 20 mm. • The topography is relatively flat with average elevation of 240 m. • The data for the collars use the Geocentric Datum of Australia (GDA94 zone 51). • Downhole surveys were completed every 10, 25 or 50 m using a Reflex EZ Gyro or Reflex SPRINT-IQ. Some RC drill holes could not be completely surveyed due to downhole blockages. Data spacing and distribution • Combined RC and DD hole spacing after 2021 drilling is approximately 75 m across strike by 75 m along strike (between lines). • A pattern of 14 DD holes at 15 m spacing north-south and east-west was completed in 2020. This close-spaced drilling targeted a representative section of the main mineralised corridor and supports the interpretation of important contacts between supergene and hypogene units and informs the choice of variogram model used in the kriging and recoverable estimation methodology. • Several DD holes drilled throughout the deposit inside the starter pit from north to south, or south to north, test the assumptions of mineralisation trend. • A section in the north of the deposit and partially inside the starter pit is yet to be drilled due to land access restrictions; it is intended to complete drilling in this area in 2022. • The current drilling provides sufficient information to support classification at Indicated Mineral Resource status for a significant portion of the proposed starter pit. All material outside the starter pit and inside a larger pit shell, representing a larger mining option, is classified as Inferred Mineral Resource. • The mineralisation is still open to the north, south, east and at depth and further drilling is planned to explore these zones in 2022. Orientation of data in relation to geological structure • The majority of the drilling is orientated to the west, perpendicular to the dominant structural north-northwest trend associated with the majority of higher grade copper and gold mineralisation. It is recognised that there are multiple mineralisation events and data collection and interpretation to understand the geological structures and controls on mineralisation is ongoing. • DD drilling is mostly oriented east to west at approximately -60 o ; some west to east scissor holes and north-south oriented DD holes have also been drilled.
15 • RC holes are predominantly east to west at -85 o to -75 o dip. Sample security • Samples in calico bags are stored on site in enclosed Bulka-bags and transported via road on trucks from the site to an ALS Limited laboratory in Perth via Port Hedland. • Sample numbers were generated directly from the database. • Each sample was given a barcode at the laboratory and the laboratory reconciled the received sample list with physical samples. Barcode readers were used at the different stages of the analytical process. • The laboratory uses a LIMS system that further ensures the integrity of the results. • All sample pulps are stored in a secure warehouse facility. Audits or reviews • The database containing the Winu data was independently checked by a third party in August 2019 and shown to be accurate. • No independent database reviews were conducted in 2020 or 2021. Section 2: Reporting of Exploration Results Criteria Commentary Mineral tenement and land tenure status • All Rio Tinto Exploration tenements are kept with respect to the legislation in terms of obligations including minimum expenditure. This project is located within Exploration Licence E45/4833, which is 100% owned by Rio Tinto and expires on the 12th of October 2022. Exploration done by other parties • No exploration had been carried out in the Winu area prior to Rio Tinto work in 2016. Geology • The prospect is located on the Anketell Shelf of the Yeneena Basin, a Neoproterozoic sequence of metasedimentary rocks and granitoids that is entirely covered by Phanerozoic sediments (mostly Permian) that range from 50 m to 100 m thick in the Winu area. • The main lithologies intercepted by the current drilling at Winu include metasedimentary rocks (quartzites, metasandstones, and metasiltstones), unmetamorphosed sedimentary cover rocks (conglomerates, gritstones, sandstones and mudstones) and mafic intrusions. Host rocks to copper-gold mineralisation are fine to medium-grained subarkosic metasandstones and biotite-rich metasiltstones. • The mineralisation is predominantly vein and breccia controlled chalcopyrite and chalcocite with associated pyrite, pyrrhotite, molybdenite, scheelite, bismuthinite and wolframite. Several generations of veins and breccias are identified and characterised by different mineralogical assemblages and textures. The main mineralisation event is associated with quartz-K-feldspar-sulphide-dolomite veins with dominantly K-feldspar, muscovite, biotite and/or chlorite wallrock alteration. • Primary sulphide mineralisation is overlain by a supergene blanket containing secondary copper minerals as well as native copper in places. Drillhole Information • A summary of drilling available to support the Winu Mineral Resource and studies is provided below. Not all holes drilled on the licence are used in the Mineral Resource estimate. Holes excluded from the estimate include holes abandoned due to drilling problems and holes drilled to sterilise proposed infrastructure footprint. Drill type Number of holes Total metres RC 528 124,513 DD 235 109,726 Total 763 234,238 Data aggregation methods • Previous public reports on Winu exploration results (“Rio Tinto Exploration Update – copper- gold mineralisation discovered in the Paterson Province in the far east Pilbara region of Western Australia” released to ASX on 27 February 2019; “Rio Tinto Exploration Update – Winu Project”, released to ASX on 6 June 2019; “Rio Tinto Exploration Update – Winu Project”, released to the ASX on 1 August 2019; “Rio Tinto reveals maiden Resource at Winu and new discovery”, released to the ASX on 28 July 2020) have reported intersections in an aggregated form. • No individual drill results are reported in this release. Relationship between mineralisation, • Previous public releases have reported intersections as apparent widths. No individual drill results are reported in this release.
16 widths and intercept lengths Diagrams • Plans are included in the release as below: • Location map (Figure 1), Winu drill hole collar plan (Figure 2), Winu cross section (Figures 3 and 4). Balanced reporting • This is the fifth public release for the Winu deposit. Drilling is ongoing and further updates will be released at an appropriate time. Other substantive exploration data • Specific gravity measurements are taken on 20 cm lengths of solid core every 10 m or 20 m, representing different lithology and mineralised intervals. The measurement used the hydrostatic/gravimetric method (Archimedes Principle of buoyancy). There are approximately 6,000 individual density measurements in the database. • Hyperspectral and high-resolution core imagery is being collected using a CoreScan Hyperspectral Core Imager. Historical Winu core from 2018 and 2019 is imaged as half core. Holes drilled 2020 onwards are whole core imaged prior to sample cutting, where possible. • Magnetic susceptibility was measured for each sample using KT-10 (kappameter) instrument. • Geophysical surveys were carried out over the deposit area including airborne electromagnetics, ground gravity, induced polarisation/resistivity, passive seismic, and downhole density, gamma, conductivity, resistivity, induced polarisation, magnetic susceptibility, and optical and acoustic televiewer. • Geometallurgical characterisation has been conducted on numerous holes since the project commenced and has informed an early understanding of the potential metal recovery. This work continued throughout 2021. • LiDAR imagery was acquired to help in better planning and reporting of the exploration programme. Further work • Rio Tinto will continue to evaluate and interpret the results from the 2021 work programme at Winu. • Drilling is ongoing to define the extents of the mineralisation and to provide increased confidence in a potential initial mining area. • The results presented here indicate the mineralisation is not closed off by the drilling performed to date. • Metallurgical test work is ongoing. • Geotechnical drilling and logging is ongoing. • Installation of water bores and water monitoring points is ongoing. • In addition to the ongoing work at Winu, Rio Tinto has conducted exploration within the broader Paterson Province on its wholly owned licences and joint venture licences during 2021. Section 3: Estimation and Reporting of Mineral Resources Criteria Commentary Database integrity • All drilling data is stored in the Rio Tinto Copper Winu Project acQuire™ drillhole database. • All data previously stored in the Rio Tinto Exploration acQuire™ drillhole database was migrated to the Rio Tinto Copper database in 2021 in a process managed by Rio Tinto IS&T. The migration included all aspects of ore body knowledge data sets and applications. The system is backed up daily to physical and cloud servers. • All newly acquired data is transferred electronically and is checked prior to upload to the database. • In-built validation tools are used in the acQuire™ database and data loggers are used to minimise keystroke errors, flag potential errors and validate against internal library codes. Data that is found to be in error is investigated and corrected where possible. If the data cannot be corrected it is removed from the data set used for resource modelling and estimation. Routine checks of raw assay data against the database have been implemented. • Drillhole collars are visually validated and compared to planned locations. Downhole trends and sectional trends are validated and outliers checked. Statistical analysis of assay results by geology domains are checked for trends and outliers. Ongoing comparison with earlier work is undertaken. • The drillhole database used for the resource estimation has been validated. Methods included checking of QA/QC data, extreme values, zero values, negative values, possible miscoded data based on location within a geology domain and assay value, sample overlaps, and inconsistencies in length of drillhole surveyed, length of drillhole logged and sampled and sample size at laboratory. • The drill core logging data was managed by a computerised system and strict validation steps were followed. • The data are stored in a secured database with restricted access.
17 • Documentation of primary data, data entry procedures, data verification and data storage protocols have all been validated by a third-party audit. Site visits • The Competent Person has worked closely with the Winu site and Perth based project teams throughout 2020 and 2021 and is familiar with drill data acquisition procedures and QA/QC system, geological logging, geological data and its interpretation, and the geological model development. • The Competent Person visited Winu site in December 2021. The site visit allowed the Competent Person to gain familiarity with and confidence in field procedures, in particular those impacting drilling, sampling and logging data acquisition. Geological interpretation • Data supporting the geology interpretation includes drill cores, RC chips, geological logs, borehole geophysical logs, ground and airborne geophysical surveys, core imaging, borehole imaging, and chemical analyses. • The orebody is not yet exposed by mining. • Sequences of cover, supergene zones and hypogene zones are well defined at the scale of the drill grid. Details of geology are discussed in Section 2. • A supergene zone consisting of copper oxides, leached cap and mixed secondary and primary sulphides has been modelled with available data including sequential copper analyses and mineralogy. • Geological differentiation within the hypogene zone is limited to identified sulphide breccia units and proximal quartz-sulphide veins that are associated with most of the copper, gold and silver mineralisation. Several narrow marker units have been identified in the metasediments and a pre- mineral dyke has been identified. • The interpreted genetic model for Winu is that granite intrusions and deformation related to the Paterson Orogeny (approximately 650 million years ago) were the source of the mineralisation, and created the structures into which the veins were emplaced. • Some stratigraphy-parallel veins that crosscut the axial planar fabric have been identified and these appear to be more common on the limbs of the antiform. • Primary mineralisation is remobilised into supergene zones that are discordant to the axial planar fabric. • At deposit scale, copper and gold grade continuity within the broad mineralised central zone of the deposit is well supported by available drilling data. Several breccia units have been identified in the centre of the deposit and, although later, host the highest copper grades. These units are mappable between drill holes along strike. Individual veins are narrower and show less persistence along strike and down dip and cannot be confidently mapped between drill holes. • In the southeast corner of the proposed starter pit and extending into the larger Resource pit shell, gold-dominant (low copper) mineralisation hosted in east-west trending near vertical quartz veins have been intersected in RC and DD drilling. This is a different style of mineralisation to that seen in the main central mineralisation zone and more drilling is required to test grade and extent and to understand the geological controls. Dimensions • Known extents of anomalous copper and gold mineralisation strikes approximately north- northwest to south-southeast with a strike extent of 2,500 m and width of approximately 400 m in the main hypogene mineralisation, and up to 700 m in the supergene mineralisation. Mineralisation occurs below approximately 80 m below surface. Estimation and modelling techniques • Raw RC and DD samples, mostly at 1 m, were length weighted to regular 2 m composites prior to data analysis and estimation. • The supergene zone was divided into several discrete domains on the basis of sequential copper and mineralogy data and the domains are used to constrain grade estimation. • A low-grade copper grade shell was used to limit grade estimation within the hypogene zone. The shell was defined at a low (0.02%) Cu grade and modelled as an Indicator by kriging onto blocks. • In the southeast corner of the deposit, a low-grade Au shell was modelled to constrain estimation of Au and Bi in the hypogene and mixed primary and secondary sulphides zones. The shell was defined at 0.1 ppm Au and modelled as an Indicator by kriging onto blocks. • Exploratory data analysis was conducted to generate domains, evaluate domain boundary conditions, establish variogram models, and define interpolation parameters. • The distribution of copper and gold grades within each domain is typically skewed to the right. A small number of high-grade samples were deemed to be outliers and the values were trimmed back to better-supported grade values prior to use in estimation. The sensitivity of the trimming of outlier values has decreased with the addition of drilling data. No other modifications were made to the composite data used for analysis and estimation. • The raw Cu, Au, Ag and Bi values were transformed to Normal distributions for data analysis and to choose variogram models. The Normal variogram models were back-transformed to raw grade
18 scale prior to use in estimation. • Data analysis, kriging and recoverable resource estimation was completed using Isatis geostatistical software. Final block models are prepared using Vulcan software. • Cu, Au, Ag, and Bi grades were estimated by Ordinary Kriging (OK) onto 40 m x 40 m x 5 m panels followed by Uniform Conditioning (UC) by kriged panel grade and finally a localisation (LUC) onto blocks of 10 m x 10 m x 5 m. • A suite of additional elements and compounds including soluble copper, As, C, S, Na, K, Al, Ca, Fe, Sb, Mg, Si, Mn, Pb, Zn was estimated onto 10 m x 10 m x 5 m blocks by either LUC or directly by OK. • Validation of grade, metal and tonnage estimates is by visualisation along with input data, geological models and previous estimates. • Grade and metal estimates by LUC on 10 m x 10 m x 5 m blocks were compared to 40 m x 40 m x 5 m kriged panel-scale estimates to confirm global unbiasedness, and to global change of support estimates to confirm the distributions are appropriately modelled. Moisture • All tonnages and grades are presented on a dry basis. Cut-off parameters • The cut-off parameters used as the basis of this Mineral Resource are on a copper equivalent basis. A copper equivalent unit is defined as: (((Cu_pct * (Cu price 1%/tonne) * Cu_recovery) + (Au_ppm * Au($/t) * Au_recovery) + (Ag_ppm * Ag ($/t) * Ag_recovery)) / (Cu (price 1%/tonne)) • Average grades for the individual metals included in the metal equivalent calculation are shown in the Mineral Resource tabulations. • Metal prices applied were provided by Rio Tinto Economics and generated based on industry capacity analysis, global commodity consumption and economic growth trends. A single long term price point was used in the definition of ore and waste and in the financial evaluations underpinning the resources statement. • Average recoveries for each of the supergene and hypogene domains were derived from metallurgical test work and detailed mineralogy studies using drill core acquired from purpose- drilled metallurgical and resource drillholes. • Rio Tinto considers that Cu, Au and Ag included in the metal equivalent calculation have a reasonable potential to be recovered and sold. Mining factors or assumptions • Surface mining is the most likely method to be used in the extraction of this orebody. • Mining studies have advanced over the course of 2021 to Prefeasibility level and form the basis of the reasonable prospects of eventual economic extraction test applied to the total Resource (larger pit shell) and the smaller starter pit Metallurgical factors or assumptions • Metallurgical studies have advanced over the course of 2021 to Prefeasibility level. The basis for predictions of metallurgical performance is the ongoing comminution and flotation test work conducted on samples composited from geometallurgical zones from numerous geometallurgical and resource DD holes. • The studies confirm that the mineralisation is amenable to processing through conventional crushing, grinding, and flotation circuits. • The current assumption is that Cu, Au and Ag will be recovered via a flotation circuit with additional Au recovery via a gravity recovery circuit. Environmental factors or assumptions • Detailed closure studies have advanced over the course of 2020/2021 to a conceptual level of study. Bulk density • Dry bulk density field measurements by Archimedes Principle are routinely made on drill core. • Some variability exists between material types in the supergene zone. Dry bulk density values have low variability in the hypogene zone.
19 • Dry bulk density was estimated directly onto 10 m x 10 m x 5 m blocks by Ordinary Kriging. Classification • A starter pit shell centred on the dominant north-south trending Cu-Au-Ag mineralised structures forms the basis of mining studies completed in 2021. Only mineralisation that is considered to have Reasonable Prospects of Eventual Economic Extraction (RPEEE) has been reported as either Indicated or Inferred Mineral Resource in this release. • Inside the starter pit shell a portion of the Mineral Resources is classified Indicated. The adopted definition of Indicated Resources is +/-15% variation in copper metal terms with a 90% confidence interval on an annual basis. • The precision of copper grade estimates has been quantified using a geostatistical simulation and is specific to the mine schedule developed for the starter pit. Classification of the Resource is applied on an annual basis, which means that if the precision of the grade estimates of the set of blocks making up an annual increment meets the criteria for Indicated Resources, all blocks in the annual increment are categorised as Indicated. • Geological controls of gold mineralisation associated with quartz veins in the southeast corner of the starter pit, extending into the larger pit shell, are known at lower confidence. The easterly extent of the starter pit is limited by the bulk processing scheme assumptions (optimised for Cu) and mining in the southeast corner will occur concurrently with other areas. • A mining schedule has been developed for material inside the starter pit. In this schedule, 23 of 32 planned mining years meet the criteria for Indicated. The remainder of material in the starter pit is classified Inferred. • Evaluation of processing flowsheet and rate and mining rate scenarios is ongoing to inform the longer-term strategy for developing the Winu deposit beyond the starter pit. Several cases have been developed demonstrating RPEEE. One particular case is adopted as the basis for reporting Mineral Resources beyond the starter pit. This pit shell encompasses material inside the starter pit. All material outside the starter pit shell and inside the larger Resource pit shell is classified Inferred. In this area, drill hole spacing is wider providing less support for grade continuity than that inside the starter pit. However, drillhole sampling quality, QA/QC including standards, blanks and repeat samples are managed to the same standard as those inside the starter pit. Audits or reviews • A formal external audit of resource estimation methodology and results was conducted in 2020. The audit found that the estimation methodology was fit for purpose; no fatal flaws were identified. • The auditors made several recommendations for further analysis to further support modelling decisions made. This work was conducted prior to the updated Mineral Resource reported here. • Several auditor recommendations in regard to estimation domain definition were adopted in the resource estimation methodology used to generate the estimates reported here. Discussion of relative accuracy/ confidence • The precision of copper grade estimates was determined using a set of geostatistical simulations and relates directly to the planned mining rates inside the proposed starter pit. The uncertainty of copper grade estimates is inherent in the classification scheme described above, specifically +/-15% variation in copper metal terms with a 90% confidence interval on an annual basis. • Confidence in geological boundaries has not been quantified. The Competent Person has taken into consideration the maturity of the geological model in determining that the continuity of geological features associated with copper and gold mineralisation is sufficient to support the classification of the Mineral Resource.
EXHIBIT 99.13
Notice to ASX/LSE

| 28 February 2022 | ||
Shareholdings of persons discharging managerial responsibility (PDMR) / Key Management Personnel (KMP)
As part of its dual listed company structure, Rio Tinto notifies dealings in Rio Tinto plc and Rio Tinto Limited securities by PDMR/KMP to both the Australian Securities Exchange (ASX) and the London Stock Exchange (LSE).
Rio Tinto Performance Share Plan 2013 ("PSP")
The PSP is a performance based share plan which provides participants with a conditional right (known as a Performance Share Award or PSA) to receive Rio Tinto plc or Rio Tinto Limited shares, subject to performance conditions being met.
The PSA granted in 2017 is subject to two performance conditions. Two thirds of the award is subject to Total Shareholder Return (TSR) performance and the remaining third to an Earnings based measure of Relative EBIT Margin. The TSR part of the award vested on 24 February 2022. The remaining third of the PSA granted in 2017 will vest on 31 May 2022 once the relative EBIT margin performance has been established.
On 24 February 2022, the following PDMR/KMP received their vested PSA in the form of shares, of which sufficient were sold to pay applicable withholding tax and other deductions.
| Security | Name of PDMR/KMP | Conditional Award Granted | TSR Vest Portion | No: of Shares Lapsed | No: of Shares Vested* | No: of Shares Sold | Price per Share | No: of Shares Retained | Date of Transaction | ||||||||||||||||||||
Rio Tinto plc shares | Baatar, Bold | 85,174 | 56,782 | 0 | 74,824 | 35,731 | GBP 54.939834 | 39,093 | 24/02/2022 | ||||||||||||||||||||
Rio Tinto plc shares | Barrios, Alfredo | 91,721 | 61,147 | 0 | 80,576 | 37,168 | GBP 54.939834 | 43,408 | 24/02/2022 | ||||||||||||||||||||
Rio Tinto plc shares | Cunningham, Peter | 20,538 | 13,692 | 0 | 18,042 | 8,616 | GBP 54.939834 | 9,426 | 24/02/2022 | ||||||||||||||||||||
Rio Tinto Limited shares | Kaufman, Sinead | 10,989 | 7,326 | 0 | 9,334 | 4,581 | AUD 115.1346 | 4,753 | 24/02/2022 | ||||||||||||||||||||
Rio Tinto Limited shares | Kaufman, Sinead** | 4,848 | 4,848 | 0 | 6,028 | 2,957 | AUD 115.1346 | 3,071 | 24/02/2022 | ||||||||||||||||||||
Rio Tinto Limited shares | Trott, Simon | 8,085 | 5,390 | 0 | 6,867 | 0 | AUD 115.1346 | 6,867 | 24/02/2022 | ||||||||||||||||||||
Rio Tinto Limited shares | Vella, Ivan | 8,149 | 5,432 | 0 | 6,921 | 1,131 | AUD 115.1346 | 5,790 | 24/02/2022 | ||||||||||||||||||||
*The number of shares vested includes additional shares calculated to reflect dividends declared during the vesting period.
**This award was granted in 2018 under the 2018 Equity Incentive Plan.
Management Share Awards (“MSA”) granted under the Rio Tinto 2018 Equity Incentive Plan
The MSA provides participants with a conditional right to receive Rio Tinto plc or Rio Tinto Limited shares, subject to continuous employment.
On 24 February 2022, the following PDMR/KMP received their vested MSA in the form of shares, of which sufficient were sold to pay applicable withholding tax and other deductions. All MSA included in this announcement were granted prior to the PDMR/KMP becoming a member of the Executive Committee.
| Security | Name of PDMR/KMP | Conditional Award Granted | No: of Shares Vested* | No: of Shares Sold | Price per Share | No: of Shares Retained | Date of Transaction | ||||||||||||||||
Rio Tinto plc shares | Cunningham, Peter | 3,244 | 3,913 | 1,869 | GBP 54.939834 | 2,044 | 24/02/2022 | ||||||||||||||||
Rio Tinto Limited shares | Kaufman, Sinead | 3,145 | 3,710 | 1,821 | AUD 115.1346 | 1,889 | 24/02/2022 | ||||||||||||||||
Rio Tinto Limited shares | Vella, Ivan | 2,856 | 3,369 | 616 | AUD 115.1346 | 2,753 | 24/02/2022 | ||||||||||||||||
*The number of shares vested includes additional shares calculated to reflect dividends declared during the vesting period on the original shares granted.
FCA notifications in accordance with the EU Market Abuse Regulation have been issued to the London Stock Exchange contemporaneously with this release.
LEI: 213800YOEO5OQ72G2R82
Classification: 3.1. Information disclosed under article 19 of the Market Abuse Regulation.
Notice to ASX/LSE Page 2 of 3 | ||
| Contacts | Please direct all enquiries to media.enquiries@riotinto.com | ||||
Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 | Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948 | ||||
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 | Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 | ||||
This announcement is authorised for release to the market by Steve Allen, Rio Tinto’s Group Company Secretary.
riotinto.com
Notice to ASX/LSE Page 3 of 3 | ||
EXHIBIT 99.14
Notice to ASX/LSE

28 February 2022
Requisitioned resolution withdrawn
Rio Tinto gives notice, in accordance with ASX Listing Rule 3.17A.2, that the two requisitioned resolutions submitted by Market Forces for consideration at Rio Tinto Limited's 2022 Annual General Meeting in Melbourne, Australia on 5 May 2022 have been withdrawn by Market Forces on behalf of the shareholders who requisitioned those resolutions. These resolutions were originally set out in the notice to the ASX dated 20 April 2021.
The first resolution proposed an amendment to the constitution of Rio Tinto Limited to permit the company's members in general meeting to pass advisory resolutions. The second resolution requested disclosure by the company in relation to its risk threshold to Scope 3 emissions and the measures it will take to reduce this exposure.
Through constructive engagement, and ahead of the non-binding, advisory 'say on climate' resolution to be put to Rio Tinto's annual general meetings, Rio Tinto and Market Forces have worked together to improve the transparency of the intended outcomes of, and risk threshold within, the company's Scope 3 approach.
In reaching an agreement to withdraw the resolution, Rio Tinto recognises shareholder expectations continue to evolve with respect to climate reporting, and welcomes engagement by Market Forces and other shareholders on this issue.
| Contacts | Please direct all enquiries to media.enquiries@riotinto.com | ||||
Media Relations, UK Illtud Harri M +44 7920 503 600 David Outhwaite M +44 7787 597 493 Media Relations, Americas Matthew Klar T +1 514 608 4429 Investor Relations, UK Menno Sanderse M: +44 7825 195 178 David Ovington M +44 7920 010 978 Clare Peever M +44 7788 967 877 | Media Relations, Australia Jonathan Rose M +61 447 028 913 Matt Chambers M +61 433 525 739 Jesse Riseborough M +61 436 653 412 Investor Relations, Australia Natalie Worley M +61 409 210 462 Amar Jambaa M +61 472 865 948 | ||||
Rio Tinto plc 6 St James’s Square London SW1Y 4AD United Kingdom T +44 20 7781 2000 Registered in England No. 719885 | Rio Tinto Limited Level 7, 360 Collins Street Melbourne 3000 Australia T +61 3 9283 3333 Registered in Australia ABN 96 004 458 404 | ||||
riotinto.com