Standard Lithium Ltd Earnings Call Transcript, Nov 16, 2026
Standard Lithium Ltd. (SLI)
Standard Lithium expects FID by the end of the first quarter of 2027 after completing LG Energy Solution and Trafigura offtakes, and is targeting over $1.2 billion in senior secured project debt for SWA, with construction beginning shortly thereafter. AI summary
Earnings Call Transcript - SLI 2026-11-16
Operator
Ladies and gentlemen, thank you for standing by. Welcome to Standard Lithium's third quarter 2026 conference call. All lines have been placed on mute to prevent any background noise. After the speaker's remarks, there will be a brief question and answer session. If you would like to ask a question, please press star one to raise your hand. To withdraw your question, press star one again. It is now my pleasure to turn today's call over to Daniel Rosen, VP of Investor Relations and Strategy for Standard Lithium. Please go ahead.
Daniel Rosen, Head of Investor Relations
Thank you, and welcome, everyone. I am joined today by David Park, our CEO and Director, Andy Robinson, President, COO, and Director, Salah Gamoudi, Chief Financial Officer, and Mike Barman, Chief Development Officer. Before we begin, I would like to start with a reminder that some of the statements made during our call today, including any related to company performance, expectations, and timing of projects, may constitute forward-looking statements. Please note the cautionary language about forward-looking statements contained in our press release, which also applies to this call. I will now turn the call over to David.
David Park, CEO
Thanks, Dan, and thank you to everyone for joining us today. To begin the year, we laid out the four primary deliverables required to be completed before taking FID at our SWA project, executing key construction contracts, completing a federal environmental review under the National Environmental Policy Act, or NEPA, finalizing our customer offtake agreements, and securing project financing. After completing the first two of these objectives in the second quarter, we were able to conclude the customer offtake process in the third quarter while making significant progress in advancing project financing, now the key remaining work stream prior to reaching FID. These are substantial achievements that are the culmination of years of work by our team and our partners. We secured long-term commercial agreements with one of the world's leading battery producers in LG Energy Solutions, as well as one of the largest global commodity traders in Trafigura. This has been one of the most important and time-intensive work streams, and we now have the volume commitments needed to support finalizing the project debt financing. We continue to advance the project financing process and have been working closely with the export credit agencies, each of which remains focused on supporting the strategic SWA project. Their comprehensive due diligence review is now substantially complete without any material concerns being raised, and we're now targeting over $1.2 billion in total senior secured project debt. Exceeding initial expectations of up to $1.1 billion. The ECA-led financing process has taken longer than initially anticipated. However, we've not lost sight of the tremendous opportunity to put a highly attractive financing package in place that will fund a substantial portion of the project's capital requirements. It's been worth the effort, and it's important to take the time necessary to structure it optimally to ensure success for all parties. Based on the latest financing timeline, we expect to take FID by the end of the first quarter of 2027, with construction beginning shortly thereafter on a two- to three-year timeline. Finally, in the third quarter, we released a preliminary economic assessment for the Franklin Project in East Texas, our first of several planned projects, highlighting the strength of one of the biggest and highest quality lithium brine resources in North America. It has the potential to produce up to 70,000 tons of battery-quality lithium carbonate annually and is a key part of our plans to build a world-class portfolio of lithium projects. I'll now turn the call over to Andy.
Andy Robinson, COO
Thanks, David. Completing the commercial offtakes last quarter was a substantial achievement for the SWA project. In August, we signed our second binding take-or-pay agreement, this one with LG Energy Solution, one of the world's leading lithium-ion battery producers and the largest outside of China. The project will supply LGES with 8,000 tons per year of battery quality lithium carbonate over a 10-year period following the start of commercial production. Pricing and other key commercial terms are subject to confidentiality but have been structured to support the project financing. Then, in September, we amended our binding agreement with Trafigura, one of the largest global commodity to traders, who provides valuable access to multiple industry supply chains that rely on lithium chemicals, along with a broad suite of customers. Similar to LGES, the original agreement was for 8,000 tons per year, battery-quality lithium carbonate on a take-or-pay basis over a 10-year period. Under the amendment, a joint venture with Equinor now has the option, at its own election, to supply up to an additional 4,000 tonnes battery-quality lithium carbonate in each year of the agreement. Combined with the initial commitment, the maximum possible volumes to be delivered to Trafigura on a take-or-pay basis has increased to 12,000 tonnes per year. The amendment also provides valuable production flexibility because the additional volume is deliverable solely at our election, and we retain the ability to allocate that volume to other strategic customers in the future if a superior commercial or strategic opportunity emerges. The financing-driven target for the SWA project was to secure binding customer offtake agreements for roughly 80% or 18,000 tonnes of the 22,500 tonnes of annual nameplate lithium carbonate capacity in its initial phase. Between our two customers, total commitments have now reached 16,000 tonnes of battery-quality lithium carbonate per year, with the additional 4,000 tonnes that can be sold at our discretion to either Trafigura or another party. The total of 20,000 tonnes of contracted volumes exceeds our financing thresholds. These agreements give us long-term commitments from two globally leading counterparties, and our expanding partnerships are a testament to the high quality of the SWA project and the importance of our role in developing a scalable and competitive domestic lithium supply chain. Most importantly, with the customer offtake process now complete, we have moved to finalizing and closing the SWA project financing as quickly as possible before taking FID and moving into construction. In the meantime, we've continued to make meaningful progress with our EPCM, Wood, who's overseeing the upstream wellfield, and our EPCC, SMB, supported by Hatch, who are responsible for the central processing facility. They've been operating under a limited notice to proceed for the last six months, focusing on key activities to de-risk the SWR project and optimize the construction schedule. This includes detailed engineering, identifying long lead time items with vendors, completing relevant construction permitting, building the team, and engaging with the community. They're expected to transition to the full and finalized EPCC and EPCM contracts once the JV takes a positive FID. We'll also be completing some important pre-FID works in the coming weeks, including tree clearing in key locations, so that we're able to support the planned construction schedule. Standard Lithium also achieved an important technical milestone with one of its collaboration partners, Nano One. Nano One used lithium carbonate from our southwest Arkansas pilot plant to produce lithium ion phosphate cathode material and battery cells in North America. That result helps to further validate that SWA projects process flow sheet and the suitability of our material in downstream battery applications. It also speaks to our commitment to technological innovation and support for the development of a domestic, fully integrated energy storage supply chain. Separately, in September, we announced a preliminary economic assessment for the Franklin Project in East Texas before filing the underlying report the following month. The PDA contemplates annual production capacity of up to 70,000 tons of battery-quality lithium carbonate and is highlighted by attractive economics, including an unleavered pre-tax net present value of $5.9 billion on a 100% ownership basis, assuming an 8% discount rate, an internal rate of return of 26%, and a three-year payback period. Along with average annual lithium cash operating cost of roughly $4,200 per tonne and a capital intensity of just under $50,000 per tonne. Additionally, it includes an upgrade and an upsized mineral resource from the maiden resource estimate that was published last year, with some of the highest lithium and brine concentrations reported in North America. The new indicated resource is 1.77 million tonnes lithium carbonate equivalent, or LCE, at an average lithium concentration of 562 milligrams per litre, while the upgraded inferred resource is 2.13 million tonnes LCE at an average concentration of 572 milligrams per litre. The PEA also considers this scenario based on the co-located bromine facility of 50,000 tonnes per year alongside the lithium operation. Standard Lithium and Equinor plan to further evaluate potential commercial opportunities for both bromine and potash, given the significant scale and quality of the resources, as well as the designation of potash as a U.S. critical mineral in 2025. The Franklin PEA demonstrates the strength of one of the largest and highest quality lithium brine resources in North America. These latest results establish a strong foundation to advance the Franklin Project as the first of our large-scale projects planned within a much broader East Texas position and underscore the scale and national importance of our resource footprint. It supports our longer-term goal of producing more than 100,000 tons of lithium chemicals annually in Texas across multiple phases and projects, and will continue to fill in our leasehold and advanced resource definition across that position. The joint venture has just commenced additional drilling activity in the project area and will be advancing technical de-risking of the project with the goal of moving the Franklin project to a preliminary feasibility study. I'll now turn the call over to Salah to discuss our financial results and the SWA project financing in more detail.
Salah Gamoudi, CFO
Thank you, Andy. For the third quarter ended September 30, 2026, we reported a net loss of $36.7 million compared with a net loss of $6.1 million in the same quarter last year. The main driver of the higher loss was a $41 million loss on the financial assets associated with contingent FID payments from Equinor due to fair value remeasurements. Partially offsetting this loss was the recording of a deferred income tax benefit of $10.9 million for the court. Under our agreement with Equinor, a $40 million contingent payment to standard lithium was tied to achieving FID at the SWA project by January 1, 2027. Based on our latest estimate of being in a position to take FID and the resultant change in target date, we no longer expect to reach FID by that contractual deadline. We therefore reduce the carrying value of the contingent payment to zero, resulting in a $31.4 million fair value remeasurement loss in the quarter. It is important to emphasize that this adjustment solely reflects the expected timing of FID relative to the payment deadline, and in no way it reflects any change in our assessment of the overall likelihood of achieving FID or a change in our view of the underlying fundamentals or prospects of the project. In fact, our confidence in being able to take FID at SWA has improved, given that we've now secured all required off-date contracts in support of our project finance process. Continue to advance limited notice to proceed activities with our EPC contractors, are past most stages of diligence with our ECA project financiers, and continue toward securing final terms and preparing definitive documentation in that effort. The remaining $9.6 million fair value remeasurement loss for the quarter relates to a separate $30 million contingent payment under our agreement with Equinor that is tied to taking FID at the Franklin Project, Or any of our other assets in East Texas by January 1st, 2029. With the delay at and current focus on taking the SWA project to FID and beginning construction, And the resultant extension of SWA project completion timelines, we expect that our attention, capital allocation, and focus on execution at SWA will lower the probability of achieving FID at our first project in East Texas by the contractual deadline for our contingent FID payment. This resulted in a re-measurement of the financial asset down to $10.6 million. This change does not reflect a reduction in our view of the probability or likelihood of achieving an FID in East Texas. To the contrary, with the recent issuance of our PEA for the Franklin Project demonstrating immense resource production and value creation potential, we are more confident in our ability to develop our East Texas leasehold positions than before. Turning to operating costs, G&A held fairly flat during the third quarter of 2026, compared to the same quarter in the prior year at $3.1 million. Higher personnel costs were offset by lower consulting and professional fees as we brought some functions in-house as we continued to mature the business. Demonstration plant costs were $1.0 million, down from $1.1 million during the same quarter in the prior year. As more of the work was focused on and allocated to SmackOver Lithium project development. Our share of the SmackOver Lithium joint venture's loss was $1.8 million compared to a $0.9 million loss in last year's quarter. Driven primarily by increased development, commercial, and operating activity at the JV partnership level for SWA as we move closer to FID. And at East Texas, as we continue to both expand our leasehold position and advance our understanding of the resource. Interest income increased by $1 million year-over-year to $1.2 million, reflecting higher average cash balances. Foreign exchange impact was immaterial this quarter following a July 1, 2026 change in Standard Lithium's accounting policy. Changing from a functional currency in Canadian dollars to U.S. dollars at our parent company level. This change was affected as currently and for the foreseeable future, the majority of our capital raised and spent has been and will be in U.S. dollars. We ended the quarter with a strong cash balance of $118.1 million and $114.4 million in working capital. Standard lithium has no term or revolving debt obligations outstanding. For the quarter, we contributed $19.3 million to SMAC over lithium, with $11 million going to Southwest Arkansas and $8.3 million going to East Texas. Through the first nine months of the year, this was $46.5 million to SMAC over lithium, or $26.1 million and $20.4 million to SWA and East Texas, respectively. These contributions supported advancing key required milestones ahead of taking FID at SWA, including entering into our EPC contracts, off-take agreements, continuing to advance the ECA financing process, and limited notice to proceed activities by our EPC contractors, including early-stage engineering and other work that will help de-risk our construction and commissioning timelines. However, we aren't a one-project company. And we've continued to increase our leasehold position, understanding of the resource, and de-risking of our projects in East Texas, including preparing the PEA for the Franklin Project.
Salah Gamoudi, CFO
We raised approximately $300,000 in gross proceeds under our existing at-the-market equity program during the third quarter, bringing
Salah Gamoudi, CFO
the year-to-date total to $22.4 million. This was a significant pullback in activity, particularly in more recent months, in light of the weaker equity market environment. We will continue to be disciplined and prudent in our potential usage of this program. Turning to SWA project financing, we continue to work closely with our selected ECAs, including the Export-Import Bank of the United States, Export Development Canada, and Export Finance Norway, among others. Key diligence work streams have mostly been concluded as we move towards reaching final terms and definitive documentation. Our SWA project is shovel-ready, and concluding on the ECA process is one of the final steps in enabling us to pick up that shovel and start digging. We are now targeting over $1.2 billion in total senior secured project debt, exceeding our initial expectations of up to $1.1 billion. The company is actively working to finalize all additional lender funding requirements, including a cost-overrun facility, other reserve accounts, and contingencies. This will ultimately inform the final SWA project capital funding requirements. Incremental capital requirements beyond the senior secured project debt are expected to be financed by our $225 million grant from the Department of Energy. of which we expect approximately $200 million will be remaining when we take FID, as we have been collecting on the grant as a cost share during this past year, as well as respective funding contributions from Standard Lithium and Equinol. The equity contribution required by Standard Lithium will be supported in part by the proceeds from our equity raised last year, as well as additional funding sources. We continue to believe the scale, structure, and terms of the debt we are pursuing via the ECAs and a strong syndicate of commercial banks are extremely attractive for the SWA project and weighed against numerous alternatives that were evaluated. We believe the financing opportunity fully justifies the meaningful time and effort required to complete it, which we expect to demonstrate in due course. Under the current financing timetable, we expect to reach FID by the end of the first quarter of 2027 and to begin construction shortly thereafter. With that, I'll turn it back over to David.
David Park, CEO
Thanks, Salah. We said last quarter that we expected to complete the customer offtake process and publish the Franklin PEA in the third quarter. We delivered both. These are very important and achievements that have been many months in the making. At SWA, the commercial agreements with LG Energy Solution and Trafigura give us clear visibility to finalize the project financing and provide greater confidence and validation as we prepare to move quickly from development into construction. And at Franklin, we now have a foundational asset in East Texas on which to build upon while strengthening our first mover advantage in the smackover formation. This progress reflects years of technical, engineering, and commercial work by our team and our partners. Our focus, alongside Equinor, is on securing financing, completing the work needed for FID, and being ready to move promptly into construction once that decision is taken. We are committed to keeping you updated as that work progresses. Before we open the call for questions, I'd like to welcome Ralph Alexander, who joined our board as an independent director in October. Ralph brings more than four decades of leadership across energy, chemicals, power, and infrastructure, and we look forward to leveraging his highly valuable and relevant expertise. Thank you again for joining us today. Operator, I'll turn it back to you for questions.
Operator
We will now begin the question and answer session. If you would like to ask a question, please press star 1 to raise your hand. To withdraw your question, press star 1 again. We ask that you pick up your handset when asking a question to allow for optimum sound quality. If you are muted locally, please remember to unmute your device. Please stand by while we compile the Q&A roster. Your first question comes from the line of Katie LeChapelle from Canaccord, Gnuity. Your line is now open. Please go ahead.
Katie Lechapelle, Analyst — Canaccord Genuity
Hi, y'all. Thanks for taking my question. Last week, we saw Lithium America's increase in capital costs at Sacker Pass for 30%. The key drivers that they noted were labor rates in the United States, impacting a number of projects as well as inflation and tariffs. So the question is, how comfortable are you guys feeling around the last published capital cost number that you put out on phase one, and is there a plan to update it prior to FID next year? Thanks.
David Park, CEO
Yeah, thanks, Katie. We are continuously assessing the situation and tracking our peers. We do not expect cost pressure of that order of magnitude on our project. I think you'll note a different nature of operations and a different contracting strategy. You'll remember that our cost estimate of approximately $1.5 billion was grounded in a DFS and a feed that was 18 months of work in the making. And then in the first quarter of last year, sorry, the first half of last year, we contracted with our EPC contractors who validated those numbers. And in our contracts that we let, we built in tariffs and escalation into those contracts. Additionally, we picked a contractor who is supplying their own craft labor, which is different than the situation you cite. And then the nature of our construction is modular and doesn't require the large, complex logistics and staffing required to deliver on site. I believe our peak construction at site peaks out at approximately 600 people, not the many thousands of people you'll see in some of the other operations that are cited. In addition, our contracting structure has built-in incentives for our contractors to deliver on time and on budget, so we feel comfortable that the guidance we've provided to date is the best guidance at this point in time. However, we will be updating in the first quarter around FID, providing further guidance.
Katie Lechapelle, Analyst — Canaccord Genuity
Okay, awesome. A similar question on the operating costs. Are you seeing areas of potential cost pressure on different inputs or reagents? Or perhaps on the flip side, are you seeing areas for optimization?
David Park, CEO
Yeah, no, we're not seeing cost pressure that gives us concern on the operating side. For, you know, the last six years of operating the demonstration facility, the team has been very focused on Developing a process and a flow sheet that minimized the use of reagents and kept reagent costs to a minimum for fear of potential reagent and escalating costs. So both reagents, power, labor, you know, all of those, I think we feel comfortable with the estimates we have on our operating costs.
Katie Lechapelle, Analyst — Canaccord Genuity
Got it. Thank you, guys. It's very helpful. I'll turn it back.
Operator
Your next question comes from the line of Max Yarrow with BMO Capital Markets. Your line is now open. Please go ahead.
Max Yarrow, Analyst — BMO Capital Markets
Hey, guys. Thanks for taking my question. And just following up on the last one, if you're still comfortable with the $1.5 billion CapEx estimate, could you provide a little bit more color on thinking between needing the $1.2 billion of debt? Is that to fund reserve accounts, a change in how you're thinking of the debt equity mix? Anything you can provide is helpful. Thanks.
David Park, CEO
Sure.
David Park, CEO
Salad, do you want to give a breakdown on that?
Salah Gamoudi, CFO
Sure. No, happy to. So we do have the $1.5 billion base CapEx, which is grounded in our feed study in DFS. When you look at the potential targeted senior secured debt of $1.2 billion, plus the $200 million grant, plus the split between us and Equinor for the remaining equity need being $45,55, $55 to us, that, you know, on its face would seem to be a fairly light load. However, what we need to make sure folks are aware of is that as part of the senior secured financing process, there are additional contingencies to that $1.5 billion base CapEx, additional reserves, debt service reserve accounts. There is cost overrun facilities. There are minimum working capital balances. There are additional needs that can increase your total capital requirement beyond base CapEx figures. So while we don't think that we're going to see. Well, as David mentioned, an order of magnitude of CapEx increases some other projects around the world that have been in construction or approaching construction. There are additional capital requirements which we'll need to solve for, and as of right now, we are working with the export credit agencies to define exactly what those figures are, and they are still subject to negotiation, which we hope to wrap up here, as we've mentioned by Q1.
Max Yarrow, Analyst — BMO Capital Markets
Thanks a lot. That's helpful, Cutler. I'll turn it back over.
Operator
Your next question comes from the line of Joseph Rigor with Roth Capital Partners. Your line is now open. Please go ahead.
Joseph Rigor, Analyst — ROTH Capital Partners
Hey, David, team. Thanks for taking the questions. Just following a bit on the financing side and that the market has made around these contingent payments. Just for clarity, because the verbiage was a little hard to follow, do you guys still have contingent payments you expect to receive, and did you lose any as a result of this delay, because I know you took the accounting adjustment, but is there still an opportunity to get Equinor to make these payments, or is this the deadline passes, you don't get the payment?
David Park, CEO
Yeah, I'll take that one, Joe. Thanks for the question. With respect to the milestone payment for Southwest Arkansas, that payment will be lost in its entirety if we do not meet a year-end FID. And what we're saying at this point in time is we're now targeting first quarter FID, so I think the best assumption is that we will not get that $40 million payment from Equinor.
Joseph Rigor, Analyst — ROTH Capital Partners
And then, given that, was that part of the reason you went from 1.1 to 1.2 on the debt, or was, is there now an equity need that's not covered? You know, how should we think about, you know, the impact of losing that payment?
David Park, CEO
I think you should. Well, first, those are really two different issues. You know, at one point in time, we believed with the export credit agencies, we would be able to source up to $1.1 billion, and now we believe we have the potential to source over $1.2 billion. So, that's more a reflection of the ECAs doing their technical diligence, commercial diligence, and financial diligence and telling us, you know, how much debt they believe the project can support. So, that is a different issue than the $40 million issue. Thank you. That said, if we were to have been able to collect that $40 million issue, that would be $40 million less equity that standard lithium would need to contribute into the project. I don't know, Salah, if you would like to say that differently? Would you like to add to it or say it differently?
Salah Gamoudi, CFO
No, I think you couched it correctly, David. I mean, it is a one-for-one increase in the equity that we will need to come up with. In order to take FID at Southwest Arkansas for our portion of the capital contribution for our 55%. We were going to receive the $40 million before. Now that our base case targets a Q1 27 FID, that'll be past the date on which we can collect that $40 million. So $40 million will have to come from somewhere. That can come from a variety of sources, namely our balance sheet, which has a significant cash position as of this disclosure, but also any sort of incremental capital. That we raise as part of this process. There is a second FID payment, so not to get too into the weeds, but just to make clear, there is an East Texas FID payment for $30 million, which would be effective if we take FID on our first East Texas project by 1-1-29. We still, on a probability weighted basis and on a discounted basis, have reflected that in our balance sheet and still have some expectation that we may be able to collect on that payment for East Texas.
Joseph Rigor, Analyst — ROTH Capital Partners
Okay. All right. Thanks for the added color there, so it made it easier. All right, guys, I'll turn it over.
Operator
Your next question comes from Daniel Magder with RJ. Your line is now open. Please go ahead.
Daniel Magder, Analyst — RJ
Good afternoon, everyone. Understanding your shovel ready here under the limited notice to proceed, how quickly can you move from development to construction post FID?
David Park, CEO
Yeah, thanks, Dan. Good question. We have, the team is continuing to work, as you said, under limited notice to proceed. We believe that we, you know, with that, we're advancing engineering. We're advancing, well, our contractors are advancing their dialogue with vendors. So we should be, you know, assuming a first quarter FID, we should be, you know, beginning construction and, you know, very active in the second quarter. So we plan to hit the ground running at this point in time.
Daniel Magder, Analyst — RJ
Got it. And I guess just shifting focus here, but post the release of the Franklin PEA, have your thoughts around sequencing shifted, I guess, related to SWAT 2 and Franklin?
David Park, CEO
Yeah, I'd say it's premature to give a definitive answer at this point in time. Clearly, the Franklin project is a very attractive project and a high priority for us longer term. Right now, Priority One is getting Southwest Arkansas Phase One to FID and begin construction. In parallel with that activity, we'll continue our exploration program in East Texas, and hopefully sometime next year, make a decision with respect to brownfield funding of, you know, whether we advance brownfield Southwest Arkansas or Franklin Project next. But right now, priority one is Southwest Arkansas, phase one.
Operator
Understood. I'll back the line. Thanks. Your next question comes from the line of Eric Boies with Evercore. Your line is now open. Please go ahead.
Eric Boies, Analyst — Evercore
Good afternoon and thanks. Two for me. I think that the $1.5 billion budget, the original one, included a 12% contingency. I realize the precise numbers are still being finalized, but given the inflationary environment, does it make sense that we should expect, you know, a larger 15 to 20% contingency on top of, you know, remarked prices?
David Park, CEO
Yeah, I think it is fair to say that that number did include contingency. When Salah is quoting cost overrun facilities, other contingencies, and other reserve accounts, these are contingencies over and above that number that the export credit agencies would like us to put in place. I don't know, Salah, if you'd like to say anything more than that.
Salah Gamoudi, CFO
Now, what I would say there, Eric, is that these are still terms that are matters and subjects of negotiation, so we can't give you a precise set of figures as to what the contingency percentages are, how we're viewing that. The DFS comes up with an estimate at a point in time based on a very, very detailed engineering analysis and statistical analysis that supports it, but there are other risks that the ECAs need to round out above and beyond that and get comfort with, and so, you know, as a result, would we expect there to be increased contingencies over and above what is in a definitive feasibility study? Yes, that is very typical and is within, you know, market trends and practices that we've seen on other projects. Do we, you know, expect that? The CapEx figure, the base CapEx figure, including contingency, will increase in order of magnitude as what we've seen in some other recent developments in some lithium projects. At this time, we don't expect that.
Eric Boies, Analyst — Evercore
Got it. Okay, thanks. And then second would just be, what kind of minimum Franklin spending preserves progress there, the PFS, in 2027? Thanks.
David Park, CEO
So, Laura, why don't you take that one?
Salah Gamoudi, CFO
Sure. So I would say that, you know, we haven't put out specific guidance on that, Eric, but, you know, as juxtaposed to the capital requirements at SWA, it'll be much, much smaller. You know, I think that historically, we've spent for our portion of the CapEx that has gone into East Texas, you know, in the 20 to 40 million range per year, I would expect that that would be maybe even on the lower end, And the level of spend that we would expect to conduct in East Texas in order to keep advancing those projects. But as we've mentioned, and as I'll say again, reiterating what David said earlier, our focus is taking FID at Southwest Arkansas, contributing capital to Southwest Arkansas, and getting to production at Southwest Arkansas. That is the number one goal of this company at this point in time. We are not a one project company. We'll continue to develop others, but... Southwest Arkansas is number one in our primary focus.
Eric Boies, Analyst — Evercore
Great, thank you.
Operator
Your next and final question comes from the line of Noel Parks with Tuhi Brothers Investment Research. Your line is now open. Please go ahead.
Noel Parks, Analyst — Tuohy Brothers Investment Research
Great, thanks. So I guess as I heard your discussion of the deadline for the payment from Equinar, I guess I'm just surprised that there wasn't some openness to renegotiation on that condition, given that the offtake was in place, and I imagine that sort of the Norway ECA's participation probably maybe wouldn't have happened or wouldn't have been in the mix if Equinor had not been the partner. So, does... Did this signal some sort of chilling of the standard Equinor relationship that they weren't willing to extend sort of some flexibility on the payment condition?
David Park, CEO
Yeah, no, great question. First, I'll say our relationship with Equinor remains very strong. We work day in, day out with them. Their team is salt and peppered in the joint venture team, so we work alongside them on a regular basis. We also have an ongoing dialogue with their leadership. They are very excited about the Southwest Arkansas Project and working diligently alongside us to try and get. It to a positive FID by the end of the 1st quarter. So strategically, this is something they want to see get done and they want to see get done as quickly as possible. Frankly, this is an item that was a negotiated term when the joint venture was put in place. There was a deadline with an incentive. We missed it, and it was not their doing that we missed it, and we are where we're at on it, but it is not a sign of their commitment to the project, and we continue to work very well together.
Noel Parks, Analyst — Tuohy Brothers Investment Research
Okay, thanks. And one thing I was interested in is, could you talk a bit more about how the option with Trafigura works on your option for the additional 4,000 TPA of offtake at standards options?
David Park, CEO
Sure. Mike, would you like to provide some color on that one?
Mike Barman, Other
Sure, no problem. So the traffic euro option is an option in any year during the term of the contract to have traffic euro take up to an additional 4,000 tons for the following year. So the benefit of that option is that it really gives us a lot of flexibility. In terms of how we how we utilize it, how we look for other areas or opportunities for strategic or financial financially beneficial alternative offtake effectively with the traffic with the traffic your option as a backstop. So for example, we were we were really quite Intent on getting long-term offtake, as you saw with the two contracts that we have for 10 years. 10 years is an exceptionally long-term for most customers, and therefore, we can now look at, for example, a broadened scope of offtake where we can get a five-year contract and then use the traffic year option as the backstop for the remaining five years to meet the obligations of the lenders. So the traffic euro option was very beneficial for our process. It allows us maximum flexibility going forward, while also meeting the obligations of the lenders in terms of a volume commitment.
Noel Parks, Analyst — Tuohy Brothers Investment Research
Great. And I just wondered if you have any thoughts on lithium macro at this point, since there is the… I forget the baseline price. That's $22,400. That's assumed in the East Texas PEA. And now at the moment, we have prices sort of below that. And so I just wonder if you had any thoughts on just where pricing stands right now.
David Park, CEO
Sure. Great question. We continue to feel that, you know, that pricing in the long-term pricing in the range of that 20,000 to 25,000 a ton is the right range to be using. We see long-term demand growth. That requires new builds to come online and incentive pricing for those new builds to come online. So, you know, based off our dialogue with our end customers, as well as with others who would like to buy our product, as well as frequent dialogue with leading industry consultants, we continue to think that something in and around $22,000 is the right long-term price forecast.
Operator
Great.
Noel Parks, Analyst — Tuohy Brothers Investment Research
Thanks a lot.
Operator
There are no further questions at this time. This concludes today's call. Thank you for attending. You may now disconnect.