6-K

SSR MINING INC. (SSRM)

6-K 2021-12-29 For: 2021-12-24
View Original
Added on April 10, 2026

UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

FORM 6-K

REPORT OFFOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR15d-16

UNDER THE SECURITIES EXCHANGE ACT OF 1934

For December 24, 2021

Commission File Number: 001-35455

SSR MINING INC.

(Translation of registrant’s name into English)

#800 - 7001 E. BelleviewAve.

Denver, Colorado

USA 80237

#800 – 1055 Dunsmuir Street

PO Box 49088, Bentall Postal Station

Vancouver, British Columbia

Canada V7X 1G4

(Addressof principal executive offices)

Indicate by check mark whether the registrant files or will file annual reports under cover Form 20-F or Form 40-F.

☐  Form 20-F                ☒  Form 40-F

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1):  ☐

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7):  ☐

DOCUMENTS FILED AS PART OF THIS FORM 6-K

See the Exhibit Index hereto.

SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

SSR Mining Inc.
(Registrant)
Date: December 24, 2021 By: Signed: “Michael J. Sparks”
Michael J. Sparks
Title: Executive Vice President and Chief Legal & Administrative Officer

****

SUBMITTED HEREWITH

Exhibits
99.1 News release dated December 24, 2021

Exhibit 99.1

News Release

December 24, 2021

SSR MINING ANNOUNCES COMMISSIONING AND RAMP-UP OF THE ÇÖPLER FLOTATION CIRCUIT


Çöpler Remains Well On Track For 2021Production & Cost Guidance

DENVER

  • SSR Mining Inc. (NASDAQ/TSX: SSRM; ASX: SSR) (“SSR Mining”) is pleased to announce the commencement of commissioning and ramp-up activities at Çöpler’s sulfide plant flotation circuit following the receipt of all required permits and approvals. A key component of the 2020 Çöpler District Master Plan (“CDMP20”), the Çöpler flotation circuit was completed on time and on budget in the third quarter of 2021. The flotation circuit utilizes latent capacity in the sulfide plant, and its commissioning is anticipated to increase the gold and sulfide sulfur grades processed through the autoclaves, reduce reagent use, and increase total sulfide plant throughput and gold production.

About SSR Mining

SSR Mining Inc. is a leading, free cash flow focused intermediate gold company with four producing assets located in the USA, Turkey, Canada, and Argentina, combined with a global pipeline of high-quality development and exploration assets in the USA, Turkey, Mexico, Peru, and Canada. In 2020, the four operating assets produced approximately 711,000 gold-equivalent ounces. SSR Mining is listed under the ticker symbol SSRM on the NASDAQ and the TSX, and SSR on the ASX.

SSR Mining Contacts

F. Edward Farid, Executive Vice President, Chief Corporate Development Officer

Alex Hunchak, Director, Corporate Development and Investor Relations

SSR Mining Inc.

E-Mail: invest@ssrmining.com

Phone: +1 (416) 306-5789

To receive SSR Mining's news releasesby e-mail, please register using the SSR Mining website at**www.ssrmining.com.

SOURCE: SSR Mining Inc.

| 1 |

| --- |

CautionaryNote Regarding Forward-Looking Information

Except forstatements of historical fact relating to the Company, certain statements contained in this press release constitute forward-looking information,future oriented financial information, or financial outlooks (collectively “forward-looking information”) within the meaningof Canadian securities laws. Forward-looking information may be contained in this document and the Company’s other public filings.Forward-looking information relates to statements concerning the Company’s outlook and anticipated events or results and, in somecases, can be identified by terminology such as “may”, “will”, “could”, “should”, “expect”,“plan”, “anticipate”, “believe”, “intend”, “estimate”, “projects”,“predict”, “potential”, “continue” or other similar expressions concerning matters that are not historicalfacts.

Forward-lookinginformation in this press release is based on certain key expectations and assumptions made by the Company. Although the Company believesthat the expectations and assumptions on which such forward-looking information is based are reasonable, undue reliance should not beplaced on the forward-looking information because the Company can give no assurance that they will prove to be correct. Forward-lookinginformation in this press release include statements concerning, among other things: forecasts; outlook; production costs and performanceof the Company’s processing facilities. Forward-looking information is only a prediction based on the Company’s current expectationsand the Company’s projections about future events. Actual results may vary from such forward-looking information for a variety ofreasons including, but not limited to, risks and uncertainties disclosed in the Company’s filings on the Company’s websiteat www.ssrmining.com, on SEDAR at www.sedar.com, on EDGAR at www.sec.gov and on the ASX at www.asx.com.au and other unforeseen eventsor circumstances. Other than as required by law, the Company does not intend, and undertake no obligation to update any forward-lookinginformation to reflect, among other things, new information or future events.