August 18, 2026 1st Quarter of FY2026 Financial Results Conference Call Q&A Summary Date and Time: Friday, August 7, 2026, 15:00-16:07 (Web meeting) Speakers: Naoki Okada, Director, President and CEO Kazuhito Iijima, Director, CFO ◆ YoY Changes in Q1 Results and Details of the Forecast Revision Q1.

Operating profit in the Telecommunication Systems business increased significantly year on year. Could you provide a breakdown of optical components, optical cables, and other products?

A1.

In the Telecommunication Systems business, net sales increased significantly from JPY 143.8 billion in Q1 of FY2025 to JPY 264.4 billion in Q1 of FY2026, while operating profit increased from JPY 34.0 billion to JPY 98.0 billion. The majority of the increase in net sales was attributable to optical components, which were also highly profitable due to short lead-time responses. In addition, profitability improved more than the increase in net sales, supported by growth in engineering business for data center in the U.S. and an improved product mix for optical fiber cables.

Q2.

What changed after the announcement of the forecast revision dated June 18? The 1st half forecast has also been revised upward substantially. What happened during this period? Could you quantify, as much as possible, the breakdown of the factors behind the 1st half and full-year forecast revisions, including volume increases in optical components due to data center project orders, the impact of hydrogen, price increases and improved product mix?

A2.

The upward revision to the 1st half forecast was mainly since orders for a large optical component project expanded beyond our initial forecast. For the full-year forecast, we revised the forecast by incorporating a large project into the second half as well, whereas they had previously been factored in only for the 1st half. Quantifying the factors behind the 1st half and full-year forecast revisions is difficult as of today, but we will consider providing such information in the future based on your request. The impact of hydrogen has eased considerably, and its impact is much smaller than that of the large order for optical components.

◆ Large Optical Component Project Q3.

Could you explain the background to the large optical component order that was the main factor behind the latest forecast revision? Was this order received suddenly, or were they strategically targeted? Also, are they expected to continue into FY2027 and beyond, or will additional orders be difficult due to capacity constraints?

A3.

The latest forecast revision was mainly attributable to the sudden receipt of new large optical

1 / 5

component order outside the U.S. We believe this order was secured because we were able to respond to urgent customer demand with short lead times. We expect the project to continue at least through FY2026. In the forecast revision dated June 18, the project was incorporated only for the 1st half, but this time it has also been incorporated into the 2nd half. However, the possibility of continued orders or further order expansion for similar projects depends on customer investment plans and the occurrence of such projects, so it is difficult to provide a clear outlook at this point. Demand outside the U.S. is also increasing, and we intend to continue actively pursuing such opportunities. On the other hand, at present, there are no new large projects for which orders are certain in the 2nd half. Q4.

Data center projects are generally planned carefully in advance, and sudden orders do not seem to occur very often. Do you have any understanding of the circumstances behind this order?

A4.

As this relates to customer information, we are unable to provide details.

Q5.

Could you explain the content of optical components, the production structure, including in-house and outsourced production as well as domestic and overseas production, and how you respond to short lead-time and large-volume order? Do you strategically hold inventory, or do you produce in response to orders? Also, how should we understand this in light of the fact that there did not appear to be a significant inventory build-up at the end of FY2025?

A5.

Optical components are connectivity and cabling-related products used within data centers, including pre-connectorized cables, patch cords, cabinets, patch panels, splice cassettes, and similar products. Production is not conducted in Japan; rather, we utilize production sites around the world. We refrain from commenting on inventory strategy or specific approaches to handling individual projects, as these relate to our business strategy. However, we are responding to customer requirements by utilizing our global production and supply structure.

Q6.

You previously stated that, while optical fibers and optical cables capacity remain constrained, you would like to make optical components and similar products a third pillar of earnings. Since when have you been targeting this opportunity?

A6.

Since new plants for optical fibers and optical cables take time to start up, we have been focusing since last year on expanding sales of optical components, which use relatively smaller amounts of optical fibers, as one measure to address this issue. In addition, by allocating limited optical fibers to higher value-added products, average selling prices have also increased.

◆ Regional Trends Q7.

Looking at net sales by region, Asia recorded a large increase after the U.S. Does “outside the U.S.” for the large optical component project refer to Asia? If so, is it an Asia-related project for an existing U.S. hyperscale customer, or are you beginning to capture local data center projects in Asia, including China?

A7.

We would like to refrain from commenting on specific customer names, regions, or similar details,

2 / 5

as these constitute confidential sales information. We would ask you to make your own assessment based on the significant increase in net sales in Asia. Another factor contributing to high profitability is that projects for Asia are not affected by U.S. tariffs. ◆ Prices, Price Increases and Product Mix Q8.

To what extent have prices increased year on year for each product? Could you provide a rough breakdown of the “price increases and improved product mix +JPY 23.4 billion” shown on page 7 of the presentation material for 1Q of FY2026? Are you also raising prices for the same products?

A8.

We are making progress on price revisions for the same products, including those associated with short lead-time responses. At the same time, the product mix is improving as we allocate optical fiber to high value-added products in areas where we have strengths, such as ultra-high-fibercount cables and Air Blown WTC™. Therefore, it is difficult to clearly separate the effect of price increases from the effect of an improved product mix. As one example of a price revision for the same product, certain customers accepted a price increase of approximately 25%.

◆ Optical Fiber Procurement and Supply Environment Q9.

Regarding external procurement of optical fiber, some market participants believe that the supplydemand environment may improve globally as demand for drone applications settles down. Have you seen any change in procurement conditions? Also, from a medium- to long-term growth perspective, is it correct to understand that top-line growth from FY2027 onward will depend on the volume of external procurement?

A9.

Since we do not handle optical fiber for drone applications, we do not have information on supplydemand trends for that application. On the other hand, global optical fiber prices remain on an upward trend, and demand is strong not only from data centers but also from telecommunications carriers. Therefore, at present, we do not feel that supply-demand tightness has eased. From a medium- to long-term perspective, we expect demand to continue expanding steadily. If we can increase external procurement volumes before the new plant starts up, we believe this will contribute to top-line growth. Accordingly, external procurement can be both an upside factor and a risk factor. Although we will continue working to improve productivity and yields at existing facilities, we expect to remain dependent to a certain extent on external procurement until the new plant is completed.

◆ Production Capacity, New Plants and Optical Connector Capacity Expansion Q10.

Are there any updates on capacity expansion plans for optical connectors and optical fiber cables? Also, could you update us on the progress of the new U.S. plant? In addition, is it correct to understand that optical components capacity still has room, even taking into account the large project order received FY2026?

A10.

We continue to expand optical connectors capacity appropriately and in a timely manner, as before. The new optical fiber plant in Sakura began operations last year and is currently operating

3 / 5

at a level close to full capacity. We continue working to improve productivity and yields. Regarding the new U.S. plant, we are currently in the process of selecting a location. In June 2026, we established Fujikura Optical Cable Systems LLC as a preparatory company for construction. Optical components, like optical connectors, do not require large-scale investments and have short lead times for start-up, so we intend to invest flexibly in response to demand trends. ◆ Sources of Competitiveness and Profitability, and Review of the Mid-Term Plan Q11.

What are the sources of competitiveness and excess profitability in optical components and engineering business for data center? If the advantage is only short lead-time response, it may be difficult to maintain superiority. Can know-how such as shortening construction periods be maintained going forward? In addition, in the Mid-Term Plan, you separated upstream operations, where capacity expansion takes time due to constraints, from downstream operations, where capacity can be expanded flexibly, and presented a growth scenario for downstream operations. In light of the large project order received this time, has there been any change in the thinking behind the Mid-Term Plan?

A11.

Our strengths lie in high value-added products such as SWR™/WTC™, flame-retardant cables, and Air Blown WTC™, as well as in our technological capabilities that enable us to continue developing new products. We believe we can maintain this differentiated advantage. Another strength is our ability to provide optical fiber cables, optical connectors, fusion splicers, and engineering business for data center as an integrated solution. In particular, providing engineering business together with products creates significant value for customers by shortening construction periods. Short lead-time response is also becoming one of our strengths, as customers are increasingly prioritizing delivery schedules over prices amid tight procurement conditions. At this point, we are not considering a review of the Mid-Term Plan. Since this project is projectbased and some aspects of the future remain uncertain, we would like to take a little more time before discussing medium- to long-term future plans. In the short term, we will seek top-line growth in optical components, engineering business for data center, and other areas that are less constrained by optical fiber production capacity, while supplementing capacity shortages through external procurement, including preforms and optical fibers, and in this case cords and cables. Over the medium to long term, we will also focus on increasing optical fiber production capacity through the new plant. This new plant is not merely a repeat investment to increase capacity; rather, it aims to achieve high productivity through innovative manufacturing technologies. We are targeting a cost-competitive structure that will allow us to compete sufficiently even if the supply-demand environment eases and price competition intensifies in the future.

◆ Equity-Method Investment Income Q12.

Is the increase in share of profit of equity-method investments due to the strong performance of US Conec?

4 / 5

A12.

As you suggest, demand for ferrules remains strong, and the performance of US Conec, share of profit of equity-method investments, remains solid. This has led to an increase in equity-method investment income and is also one factor behind the forecast revision.

5 / 5