Alliant Energy Corp Q4 FY2024 Earnings Call

Alliant Energy Corp (LNT)

Earnings Call FY2024 Q4 Call date: 2025-02-21 Concluded

Call artefacts

Transcript

Speaker-labelled transcript of the call.

Read transcript
8-K earnings release

Item 2.02 release filed around the call (2025-02-21).

View 8-K filing
10-K filing

The annual report covering this quarter (filed 2025-02-21).

View 10-K filing
Audio

Call audio is not captured yet.

Slides

A slide deck is not captured yet.

Transcript

Auto-generated speakers
Operator

Thank you for holding, and welcome to Alliant Energy's Year End 2024 Earnings Conference Call. Note that at this time, all lines are in a listen-only mode. I would now like to turn the call over to your host, Susan Gille, Investor Relations Manager at Alliant Energy. Please go ahead. Good morning. I would like to thank all of you on the call and webcast for joining us today.

Susan Gille Head of Investor Relations

We appreciate your participation. With me here today are Lisa Barton, President and CEO, and Robert Durian, Executive Vice President and CFO. Following prepared remarks by Lisa and Robert, we will have time to take questions from the investment community. We issued a news release last night announcing Alliant Energy's year-end and fourth-quarter financial results and affirmed our 2025 earnings guidance range. This release, as well as an earnings presentation, will be referenced during today's call and are available on the Investor webpage of our website at www.alliantenergy.com. Before we begin, I need to remind you the remarks we make on this call and our answers to your questions include forward-looking statements. These forward-looking statements are subject to risks that could cause actual results to be materially different. Those risks include, among others, matters discussed in Alliant Energy's news release last night and in our filings with the Securities and Exchange Commission. We disclaim any obligation to update these forward-looking statements. In addition, this presentation contains references to ongoing earnings per share, which is a non-GAAP financial measure. References to ongoing earnings exclude material charges or income that are not normally associated with ongoing operations. The reconciliation between ongoing and GAAP measures is provided in the earnings release which is available on our website. Non-GAAP adjustments include an asset valuation charge related to IPL's Lansing generating station of $0.17 per share recorded in the second quarter of 2024, restructuring and voluntary employee separation charges of $0.08 per share recorded in the fourth quarter of 2024, an asset retirement obligation charge for steam assets at IPL of $0.06 per share recorded in the second quarter of 2024, and an adjustment of deferred tax assets due to Iowa tax reform of $0.04 per share recorded in the fourth quarter of 2024, and in 2023. At this point, I will turn the call over to Lisa.

Thank you, Sue. Good morning, everyone, and thank you for joining us. 2024 marked another year of solid financial and operational performance during which we made considerable progress on our key strategic priorities. As we review our strong operational and financial performance for 2024, we'll look ahead to 2025, providing updates on our progress towards achieving key strategic objectives that enhance our ability to support our customers, communities, and importantly drive shareholder growth now and for generations to come. Reflecting on 2024, I'm extremely proud of the progress we made and the strong foundation we built, one that positions us well to drive sustainable growth and deliver meaningful value. Our ongoing 2024 EPS growth aligns with our long-term target of 5% to 7%. We increased our dividend with 2024 marking the 21st straight year of dividend increases. We successfully commissioned 1.5 gigawatts of solar energy investments, adding to our 1.8 gigawatt wind generation fleet, reinforcing our leadership in regulated owned renewables. Our approved electric rate review construct in Iowa stabilizes electric base rates for customers through the end of the decade and allows us to grow in tandem with our economic development success rate. This positions the company to earn its authorized return on equity through the retention of new tax credits, energy margins, and capacity revenues. While we invest in energy resources to support growing energy demand, this provides a framework to support economic development through an individual customer rate construct enabling the company to capture meaningful economic development growth to benefit our communities. By putting our newly IUC approved construct into action, we reached a significant milestone in our economic development efforts, securing commitments with signed agreements of up to 1.9 gigawatts of data center load at our Big Cedar site in Cedar Rapids. Our individual customer rate or ICR construct in Iowa and Wisconsin are key tools for economic development and community growth. We recently filed an ICR contract for one of two Iowa data centers, and we look forward to the IUC's review of this contract. We expect the second ICR contract to be filed in the first quarter. As we have highlighted in previous calls, we are committed to ensuring all ICRs benefit existing customers, new customers, and our shareholders, which will be demonstrated in these confidential filings. Our team continues to advance our purpose-driven strategy and is taking measures today to enable the achievement of our financial and operational objectives over the long term. We operate in two states that have enacted legislation to fast track and support economic development, creating new opportunities for growth and investment. To complement legislation adopted last year to support mega projects, Iowa Governor Kim Reynolds recently introduced legislation to continue providing tools to accelerate economic development in the state. Key provisions of the bill include non-contested integrated resource plan filings with the IUC and the requirement to file non-contested IRPs at least every five years. Lowering the threshold for advanced rate making to 40 megawatts and expanding eligibility requirements for advanced rate making to encourage all-of-the-above energy solutions and technologies in Iowa. In Wisconsin, the legislature enacted a sales and use tax exemption for data centers. This legislation is designed to increase investments and growth in the sector. With that in mind, I'm excited to announce we have an agreement in principle with a data center customer that has purchased land in Beaver Dam, Wisconsin. As noted in previous calls, we have increased our focus on economic development, and this will continue to be our focus in the months and years ahead. Expanding the competitive advantage of our service territory through our efforts to drive economic development in Iowa and Wisconsin is driving meaningful outcomes, attracting new investments, creating jobs, and supporting investments in the infrastructure needed to support long-term growth in the communities we serve. Tying our economic development wins back to our CapEx plans, as you recall, in November 2024, we refreshed our capital expenditure plan to incorporate energy resource investments to meet the first phase or up to 1.1 gigawatts of our data center growth. At this time, we also indicated that we had an additional 800 megawatts of data center load backed by fully executed land, transmission, and energy supply agreements, where we were awaiting greater clarity on the timing of the load ramp. We now have that clarity. Given our confidence in our Wisconsin Beaver Dam location, we expect to add this new data center demand to our updated resource supply plan, capital expenditure plan, and financing plan, which will be provided as part of our Q1 2025 earnings release. As noted in Slide 5, we are taking a responsible approach to meeting these needs using a combination of existing capacity, new generation, demand response, and capacity purchases. This allows us to accelerate our ability to meet the load while building length in our CapEx plan well into the future. Our economic development efforts, including the addition of new data center loads, are projected to increase energy sales. This increase in sales will help distribute fixed costs across a larger customer base, contributing to more stable and manageable rates for our customers. We recognize speed to market is critical for meeting the needs of growing and new customers, whether they are large load industries or local expansions. Our reliable, balanced portfolio of existing resources combined with our inventory of MISO queue positions to connect new energy resources, short-term market purchases, and our track record of successful execution gives us confidence in our ability to capture these opportunities. Now let me briefly touch on the investment growth opportunities associated with our 16% interest in American Transmission Company. MISO transmission investments present a strategic opportunity for us to enhance regional grid stability. Earlier this year, MISO announced capital investments for tranche 2.1. ATC expects to be assigned approximately $2 billion of tranche 2.1 with an additional opportunity through the right of first refusal or competitive bid process of up to $1.8 billion. We do not expect a material impact to our earnings related to tranche 2.1 until post-2030. At Alliant Energy, we are committed to strengthening the energy grid by reducing outages, improving recovery times, and expanding capacity with a balanced mix of cost-effective and proven technologies. At the same time, we continue investments in future innovations to meet growing demand while maintaining affordability for our customers. Looking back on my first year as CEO, I'm proud of our team's relentless dedication and execution of our purpose-driven strategy. Their dedication not only strengthens our service to customers and communities but also fuels sustainable long-term value creation for our shareholders. As we celebrate National Engineers Week, I'm proud to recognize the exceptional contributions of our engineers whose innovation and expertise continue to propel our industry forward. Equally important, I extend my deepest gratitude to our dedicated generation team, line crews, and extended team for their unwavering commitment to delivering reliable energy to our customers. Your hard work and dedication are the backbone of our operational success and the driving force behind our continued progress. I will now turn the call over to Robert to provide our financial results, financing plans, and an update on regulatory matters.

Thank you, Lisa. Good morning, everyone. Yesterday, we announced 2024 ongoing earnings of $3.04 per share compared to ongoing earnings of $2.82 per share in 2023. These ongoing earnings contributed to a compounded annual earnings growth rate in excess of 6% over the last ten years. The year-over-year ongoing earnings change was primarily due to higher revenue requirements from capital investments. This positive driver was partially offset by higher depreciation, financing expense, and lower AFUDC associated with our customer-focused capital expenditure programs. The remaining year-over-year earnings drivers largely relate to the negative impacts of milder temperatures on electric and gas sales and our team's successful efforts to offset a significant portion of the negative 2024 temperature impacts with actions taken to capture higher tax benefits and lower O&M expenses. We are extremely proud that our 2024 O&M expenses, excluding non-GAAP adjustments, were approximately $30 million less than in 2023. The result of our employees' efforts to manage our business to deliver long-term financial consistency. We also completed restructuring activities in the fourth quarter of 2024, which resulted in a 5% reduction in our workforce for individuals who chose a voluntary employee separation package, which will provide sustainable cost savings in the future. The winter temperatures in 2024 were some of the warmest on record in our service territory and across the U.S. These temperature impacts on electric and gas margins decreased Alliant Energy's earnings by approximately $0.15 per share in 2024. In comparison, temperatures decreased Alliant Energy's earnings by $0.06 per share in 2023. Excluding impacts of mild temperatures, the margins from our electric sales were close to plan, with higher than expected sales to residential and commercial customers due to greater than forecasted meter growth partially offset by lower sales to our lower margin IPL industrial customer, primarily due to less demand from customers who operate their own generation. In 2024, we continued our steadfast focus on keeping bills cost-effective for the customers we have the privilege to serve. On a revenue per kilowatt hour basis, average retail electric rates only increased by approximately 2% and 1% for IPL and WPL, respectively. Both changes were below the U.S. rate of inflation in 2024. And our average retail natural gas rates on a cost-protected therm sold declined by approximately 10% when compared to 2023. These results were achieved despite both utilities implementing base rate increases in 2024. We were also successful with many initiatives in 2024 to help create value for our customers in the future. We were awarded $80 million of grants to lower capital costs for customer-focused investments. We secured $3 billion of conditional commitments for loan guarantees from the U.S. Department of Energy's loan programs office, and if finalized, those loans would help us cost-effectively finance future clean energy generation and storage for both Iowa and Wisconsin customers. We initiated safe harbor activities with the intention of preserving the qualification of tax credits for future energy storage and renewable projects, and as Lisa mentioned, we are utilizing our individual customer rate construct in both states, which allows us to capture growth from economic development activities occurring within our territories, which will in turn absorb a portion of fixed costs and help reduce costs for all customers. Our teams also had success with improving cash flows last year. 2024 cash flows from operations increased by approximately $300 million or 35% when compared to 2023. This substantial increase was primarily the result of the successful monetization of tax credits generated in 2024, improved recoveries of infrastructure investments with new base rates in both Iowa and Wisconsin, and successful efforts by our employees to reduce the working capital requirements of our core utility business. I'm also pleased to report that our investing cash flows in 2024 align with our projected CapEx managers set at the beginning of the year. Due to our proactive procurement activities and our continued track record of successful execution of our key construction projects. Moving to 2025, we are affirming our 2025 earnings guidance range of $3.15 to $3.25 per share. And we have based our long-term 5% to 7% earnings growth rate target off our 2024 ongoing earnings of $3.04. Our efforts to support customer value by making smart investments and controlling operating costs all while receiving constructive regulatory outcomes will support our ability to consistently deliver solid financial results. Turning to 2025 financing. Our current 2025 financing plans are included on Slide 8. We anticipate updating our 2025 to 2028 financing plans in conjunction with our next capital expenditure update, which we expect to share on next quarter's earnings call. Finally, I'll highlight our regulatory initiatives in progress, as well as those regulatory filings we plan to initiate later this year. We have four active dockets in progress before the Public Service Commission of Wisconsin, which involve requests for certificates of authority for customer-focused investments. These dockets relate to investments, which will enhance the reliability and resiliency of the Riverside natural gas generator facility, refurbish the Ford Wind and Bentry wind farms, extend production tax credits from the facilities for the benefit of our customers, and enable a new long-duration energy storage project called Energy Dome, which would be sited next to WPL's Columbia Energy Center. The expected timing of decisions from the Public Service Commission of Wisconsin on these dockets is provided on Slide 9. We also have two active filings in progress before the Iowa Utilities Commission, seeking approval for an individual customer rate for one of the new data centers in Cedar Rapids, Iowa, and an approximate 100-megawatt Cedar River natural gas generator station which would be located on the existing site of the Prairie Creek generating station. Finally, for our planned regular regulatory filings this year, we anticipate filing a Wisconsin retail electric and gas rate review for test years 2026 and 2027 at the end of this quarter, and in conjunction with our updated capital expenditure plan, we also expect to make regulatory filings later this year in both Iowa and Wisconsin for additional renewables and dispatchable resources to enhance reliability, further diversify our energy resources, and meet growing customer energy needs. Thank you for your continued support and look forward to speaking with many of you in the coming months. At this time, I'll turn the call back over to Lisa to provide closing remarks.

Thank you, Robert. I'd like to close by focusing on what you can expect from the Alliant Energy team. We are actively looking to expand our competitive advantage by driving sustainable growth and long-term value. Our tenets driving affordability and delivering value. Advancing growth at scale through economic development. Adapting regulatory and advocating for legislative constructs to support growth and win-win outcomes. Responsibly powering growth by growing at the pace of our customers and using capacity length, new resources, load response, and capacity purchases. I'm extremely proud of the foundation we've established in 2024. We are well-positioned to drive sustainable growth and create meaningful shareholder value. Thank you for your continued support. At this time, I will turn the call back over to the operator to facilitate the question and answer session.

Operator

Thank you, Ms. Barton. At this time, the company will open the call up for questions from members of the investment community. On your phone, you will hear a prompt that your hand has been raised. Should you wish to decline from the polling process, please press star followed by two. Please go ahead and press star one now if you have any questions. First, we will hear from Shahriar Pourreza at Guggenheim Partners. Please go ahead.

Speaker 4

Hi. Good morning.

Hey, Shahriar. How are you?

Speaker 4

Good. How are you doing?

Great. Thanks.

Speaker 4

Excellent. So, Lisa, the new data center — we got a new data center in Wisconsin. The CapEx update is coming next quarter. Can we just get a little bit more color on where you could see yourself within that five to seven percent, especially as we look out towards the end of the plan? Are we near the top end? Is this something you'll communicate on in the Q1 CapEx revision update? Just a little bit more sense there.

Q1 will have a much better line of sight, Shahriar, with respect to where we'll be. What you will see in that will be the 1.9 gigawatts associated with phase one and phase two of the Cedar Rapids build-out as well as the new Wisconsin facility. So let me be clear: we'll provide the updated capital plan and financing assumptions in Q1.

Speaker 4

Okay. Got it. Got it. And then just on the CapEx update, Lisa, will we see normal distributions being pushed out, or do you think it's purely additive to the 10% CAGR?

One of the things right now we're looking at is just what are the needs of our customers and communities, and we are leaning in a little bit more on the generation side right now, and a little less so on the distribution.

Speaker 4

Okay. That is perfect. And then just one last one if I may. There's obviously a lot of focus around the Wisconsin opportunity. Maybe if we can come back to Iowa for a sec. Any updated color on a potential phase two at Big Cedar and/or Prairie View? Just any timing of that announcement. Thanks.

So what we have based and reflected there right now: we had 1.1 gigawatts as phase one, another 800 megawatts being phase two, totaling the 1.9 that you see there. And that's with two different data center customers. One, you probably saw the announcement, is QTS. The other one is not wanting us to release their name at this point in time. We just want to always make sure that we're abiding by the wishes of our customers.

Speaker 4

Got it. Makes sense. Congrats on the execution. Appreciate it. See you soon.

Thank you. Bye-bye.

Operator

Next question will be from Nicholas Campanella at Barclays. Please go ahead.

Speaker 5

Hey, everyone. Good morning. Thanks for all the updates. I just wanted to ask when we think about financing this incremental CapEx that's going to be coming across the plan, if we were to add a dollar of CapEx, what's the associated equity need with that going forward? And maybe you can update us on where your FFO to debt is trending. Thanks.

Yeah, Nick. This is Robert. So as we think about where we stand right now with our balance sheet, we feel like we've got a really strong balance sheet and improving cash flows. But as you think about the capital expenditure refresh that we plan on sharing with the first quarter call, think about roughly 45% to 50% of any new capital additions are expected to be financed through equity and the remaining through what I would characterize as debt issuances. Specifically on your cash flow question, as I shared with my prepared remarks, we made some pretty significant progress with improving our cash flows in 2024. We saw about a 35% increase or about $300 million of cash flow from operations relative to what we saw in 2023. That was largely because of the monetization of tax credits, the improvements that we saw as a result of the base rate increases that we implemented to recover infrastructure, but probably one of the things I'm more proud of is the fact that we're doing a really good job with optimizing our working capital. We're looking forward to continuing that trend here into 2025 and actually seeing, if anything, an upside when it comes to additional tax credit monetization as we continue to build out more renewables and storage and generate more tax credits that are available for sale.

Speaker 5

That's great. And then just with the Wisconsin opportunities still in focus and you're going to be filing this Wisconsin rate review soon, maybe you can talk about what's different in this case versus prior cases.

I wouldn't say it's much different. I would characterize the key drivers for this rate review are predominantly related to rate base additions since the last case. Think about all of the solar that we completed over the last couple of years, as well as new battery storage projects—all of that has been approved by the Public Service Commission of Wisconsin. We also have some advanced gas path projects, intended to improve the capacity and efficiency of our Nina and Sheboygan natural gas facilities that have been approved by the PSCW. So a large portion of what we'll be seeking for recovery is just rate-based additions, partially offset by some of the fuel cost savings from those projects as well as some of the tax benefits. As far as key issues, you'll see the typical questions about return on equity and capital structure; we feel like we're well-positioned to have a good case in front of the commission in a couple of months.

Speaker 5

Alright. Great. We're looking forward to first quarter, and have a great weekend.

Operator

Next question will be from Julien Dumoulin-Smith at Jefferies. Please go ahead.

Julien Dumoulin-Smith Analyst — Jefferies

Thank you, operator, and thank you, team. Appreciate it. Appreciate the time. And congratulations again. Very nicely done here with you.

Thank you.

Julien Dumoulin-Smith Analyst — Jefferies

Maybe just to follow up on a few things here. One item that stands out is the backdrop of renewables execution and reliance on tax credits through the plan. Specifically, how do you think about safe harboring and to what extent you and your partners have ensured access to the tax credits and any other avenues to ensure that the plan is intact, including wind projects?

Great question, Julien. I'm extremely proud of the team's activities in the fourth quarter and here into the first quarter of 2025 to position us well to safe harbor a significant majority of the renewables and battery storage in our current plan. We've taken actions to put down payments on certain projects and initiated construction activities for others. We feel well-positioned with safe harboring for the substantial majority of the projects that are planned for the next four years, related to renewables, including wind and solar as well as battery storage that we have in our plan right now.

Julien Dumoulin-Smith Analyst — Jefferies

Right. And that includes ongoing permitting activities you're comfortable with?

Yes. We don't have any concerns currently with permitting. We don't tend to put our wind projects on public lands, so we don't face that kind of risk. We've also been proactive in getting ahead on MISO positions and other items to navigate what can be a choppy period for these activities.

And just to highlight, Julien, we've gone through safe harboring before, so we're very experienced with this. We're feeling comfortable about how we've positioned ourselves for the future.

Julien Dumoulin-Smith Analyst — Jefferies

I would expect nothing less, Lisa. Thank you. Just with respect to the data set opportunity quickly, can you elaborate a little more on the opportunities piece in the slides? The slide shows something like 2.1 gigawatts delineated—can you talk a bit about the timeline to get up to that full upside opportunity bucket, given many seem to be coming online around 2028?

Think of it this way: the upside 'light blue' opportunities are companies where we're having active discussions. That's why you'll see a balanced approach in our resource planning: some new generation, extensions and conversions like Edgewater, evaluating Columbia, and using an all-of-the-above approach. We want to be as competitive as possible so that when data centers come knocking, Alliant is the first place they'll go. We'll have a lot more information for you in Q1—everything will be revealed in Q1.

Julien Dumoulin-Smith Analyst — Jefferies

Including the upside opportunities. Excellent. Thank you.

Operator

Thank you. Next question will be from Andrew Weisel at Scotiabank. Please go ahead.

Andrew Weisel Analyst — Scotiabank

Hi. Good morning, everybody. Just to clarify, first question: is Big Cedar essentially fully booked at this point?

It is.

Andrew Weisel Analyst — Scotiabank

Okay. Great. And then do you have a new customer at Beaver Dam, and with the additional sites, how confident do you feel that you'll be able to serve a strong number of potential data center customers over time?

We want to position ourselves to attract as much economic development for our communities as possible, and that's why we've made some of the decisions that we've made. Our economic development team is acutely focused on figuring out how to attract these customers and to make sure that it's a win for new customers, existing customers, and shareholders. While some growth is tied to the land that we have, it's not necessary; it has been a great accelerator for these opportunities. These types of customers are really looking for transmission capacity and sufficient generation available to meet their needs. We have a very flexible resource planning process that allows us to be adaptive compared to a number of our peers.

Andrew Weisel Analyst — Scotiabank

Okay. Great. It ties in neatly to my next question about the proposed legislation in Iowa about integrated resource planning. How do you think about that in terms of flexibility or lack thereof? On one hand it helps with long-term generation planning; on the other hand you need to be very flexible to work with fast-moving hyperscalers and data centers. How do you think about that?

I think it's relatively neutral. We can file a plan at any time. What the legislation is intended to do is to avoid people going beyond five years. To adapt to the needs of our customers and communities, we'd file more often. In the last resource plan exercise we had low, medium, and high cases, which allowed considerable flexibility in determining needed resources. Quite frankly, if we wanted to go in tomorrow, we can go in tomorrow and file another resource plan. We feel that it's very supportive of what we need to advance economic development.

Andrew Weisel Analyst — Scotiabank

Okay. Great. One correction to what I said earlier: we do have a little bit of room still at Big Cedar. My apologies.

Oh, okay. Great. More options is always a good thing.

Andrew Weisel Analyst — Scotiabank

One last one: advanced rate making has been a moving target in the past. Can you talk about the proposed legislation and how it might clarify things going forward—what's in that proposal and how you think it might play out?

That's a great question, Andrew. Historically, we've used advanced rate making principles largely for renewable expansion and some larger natural gas facilities. Recent legislation expanded it to include battery storage and nuclear. The current proposal takes an all-of-the-above approach and lowers the megawatt threshold to 40 megawatts, so we see this as an opportunity to use many different resources to meet demand from new customers. It gives us flexibility and demonstrates the willingness of Iowa to drive economic development. We're looking forward to seeing it progress through the legislative process and hope to utilize it in the near future.

Andrew Weisel Analyst — Scotiabank

Flexibility seems to be a theme. Thank you very much, guys. Appreciate the help.

Operator

Next, we will hear from Paul Fremont at Ladenburg. Go ahead.

Paul Fremont Analyst — Ladenburg

Hi. Congratulations on a good quarter. Would you potentially look to put into place a similar regulatory structure as what you have in Iowa with confidential contracts, especially for large data centers?

Wisconsin and Iowa have very different constructs. In Iowa, filings might be every four years, which can make it challenging to grow at the pace of customers. In Wisconsin, rate reviews are every two years with a forward-looking construct, so there are no plans to change to Iowa's model.

Paul Fremont Analyst — Ladenburg

Can you discuss the flexible rate structure mentioned in the presentation, particularly the individual customer rate? What changes are being discussed in Iowa to help attract large energy user customers?

The individual customer rate construct came from the settlement we worked through last year. It allows us to customize contracts for the needs of a particular customer and submit them confidentially to the IUC for approval. The commission has to act within ninety days or it's otherwise approved.

Paul Fremont Analyst — Ladenburg

But with the proposed legislation in Iowa, how would that change the individual customer rate construct and make it more flexible to attract customers?

If you look at the proposed legislation, think of it as a further expansion. There are parameters in the current individual customer rate order; this would expand it further, giving us even more flexibility to offer those types of rates to more customers beyond the data centers we're currently pursuing under the existing individual customer rate.

Paul Fremont Analyst — Ladenburg

And in terms of the additional generation you're looking to add, should we think of all of that as being renewable, or will some of it be gas?

Some of it will be gas. It's an all-of-the-above approach.

Operator

Next question will be from Ashok Khan at Berenberg. Please go ahead.

Speaker 9

Thank you. My questions have been answered. I appreciate it.

Operator

Miss Gille, there are no further questions at this time.

Susan Gille Head of Investor Relations

With no more questions, this concludes our call. A replay will be available on our investor website. We thank you for your continued support of Alliant Energy and feel free to contact me with any follow-up questions.

Operator

Thank you. Ladies and gentlemen, this does indeed conclude your conference call for today. Once again, thank you for attending. And at this time, we ask that you please disconnect your lines. Enjoy the rest of your day.