Fervo Energy Company declared commercial operation for the first standardized GeoBlock at Cape Station ahead of its contractual deadline. As of September 30, 2026, binding PPAs totaled 1,054 megawatts and represented approximately $11.9 billion in potential revenue backlog.
FRVO · Fervo Energy Co
You came from your AI assistant. Add Equibles to it and ask about this data directly, free.
Price & Indicators
The closing range uses available history since May 13, 2026; less than a full year is stored.
Up next
Latest documents
Cape Station's first 33-megawatt geoblock declared commercial operations on September 30th, ahead of its contractual deadline, and is generating revenue under its PPA. Fervo signed a 15-year take-or-pay agreement with Google covering approximately 396 megawatts, with commercial operation targeted for mid-2028. Fourth-quarter capital expenditures are expected at $450 to $500 million.
Fervo Energy Company signed a 15-year, 396-megawatt power purchase agreement with Google and declared commercial operation at Cape Station’s GeoBlock 1 on September 30, 2026. Q3 net income was $11.7 million, while operating loss was $43.7 million.
Fervo Energy said Cape Station’s first 33 MW GeoBlock reached commercial operation on September 30, one day before contractual COD, and is generating revenue under its power purchase agreement. Phase I totals approximately 100 MW across three GeoBlocks.
Metrics snapshot
Useful current figures from the complete screener profile.
Quarterly results
AI Brief
Q3 FY26 earnings call · Nov 9, 2026TL;DR. GeoBlock 1 entered commercial operation ahead of its deadline, and the Google 396 MW take-or-pay PPA lifted binding backlog to 1,054 MW. Q3 operating loss reached $43.7 million on higher G&A, and a substation outage expected in early 2027 is a timing factor.
- + GeoBlock 1 was declared in commercial operation ahead of its contractual deadline and is operating in line with expectations. new
- + Binding backlog rose to 1,054 MW and about $11.9 billion of contracted revenue, from 658 MW and $7.2 billion at end of Q2 2026. new
- + A 15-year take-or-pay Google PPA covers 396 MW across eight GeoBlocks, with fixed terms. new
- + Second-half 2026 capital expenditures are now expected at $700.0 million to $750.0 million, below prior expectations, with no change to commercial operation dates. new
- + Updated heat-in-place study supports about 8.4 GW of Cape Station capacity potential, nearly double the prior 4.3 GW. new
- − Q3 operating loss was $43.7 million, with G&A rising to $39.4 million from $27.4 million in Q2 2026. new
- − A one-time substation outage expected in early 2027 is a factor in Cape Station's 2027 timing. new
AI-generated from the earnings call and 8-K · may contain errors · not investment advice
Equibles Research
our published analysis of this companyEquibles Rating
blended score · not investment adviceBlended from price, momentum, positioning, fundamentals & volatility · daily-close · not investment advice. Market backdrop is context, not part of the score.
Guidance & track record
Still-open targets the latest release did not restate under the same label.
Guidance from company 8-Ks · delivered figures from as-reported statements · no analyst estimates involved.
Technicals
trend & momentum for long-term holders SellIllustrative technical + ownership context — a signal mix, not investment advice.
Key metrics
the company's own KPIs, from written earnings releases and filings| Metric | Latest | Period | YoY |
|---|---|---|---|
| Advanced Development | 3 | Q3 2026 | — |
| Capacity in operation | 36 | Q3 2026 | — |
| Capacity under binding power purchase agreements | 1,054 | now (after Google agreement signing) | — |
| Capacity under construction | 466 | Q3 2026 | — |
| Contracted revenue under binding power purchase agreements | $11.9B | now (after Google agreement signing) | — |
| Early Development | 54.7 | Q3 2026 | — |
| Heat-initially-in-place capacity potential at Cape Station | 8.4 | Q3 2026 | — |
| Land portfolio | 670,000 | now | — |
| Ready-to-build capacity | 550 | Q3 2026 | — |
| Subsurface drilling completion for Cape Google 400 | 18% | now | — |
| capacity potential advanced into Advanced Development | 400 | Q2 2026 | — |
| capacity potential advanced into Early Development | 10.5 | Q2 2026 | — |
| capital expenditures | $226.5M | Q2 2026 | — |
| IPO gross proceeds | $2.2B | Q2 2026 | — |
| long-term development target | 1.1 | by 2030 | — |
| Total capital expenditures during the period | 172.8M | Three months ended March 31, 2026 filing | — |
Figures exactly as the company stated them in writing · click a metric with a to chart its history · period links open the stating document · "filing" marks figures stated in the 10-K/10-Q · YoY needs an exactly comparable prior-year period
Versus peers
Utilities - Renewable — same industry group| Company | Mkt cap | YTD | Rev growth Y/Y | P/E | Short % shares |
|---|---|---|---|---|---|
|
FRVO
this stock
Fervo Energy Co
|
$3.36B | — | — | — | 6.6% |
|
BEP
Brookfield Renewable Partners L.P.
|
$20.88B | +13.2% | — | — | 0.3% |
|
AXIAY
AXIA Energia S.A.
|
$19.11B | — | — | — | 0.1% |
|
EDRVY
EDP Renewables S.A.
|
$15.59B | — | — | — | 0.0% |
|
ENLT
Enlight Renewable Energy Ltd.
|
$9.09B | +43.0% | — | — | 0.9% |
Peers by industry group · P/E from as-reported trailing EPS · short % is of shares outstanding
At a glance
key data from every section- Filed
- Nov 10, 2026
- This year
- 14
Fervo Energy Company declared commercial operation for the first standardized GeoBlock at Cape Station ahead of its contractual deadline. As of September 30, 2026, binding PPAs totaled 1,054 megawatts and represented approximately $11.9 billion in potential revenue backlog.