Acme Solar Holdings Limited (ACMESOLAR) Q3 2026 Earnings Call Transcript

Concluded Jan 30, 2026 Audio replay Verified speakers
Jan 30, 2026 1:12:10 120 turns
Period
FY2026 Q3
Runtime
1:12:10
Sources
2 artifacts
Revenue 4.97B INR +42.3% YoY
Diluted EPS 1.87 INR/shares -10.5% YoY
Net income 1.14B INR +1.5% YoY

Transcript & audio

Verified speakers 1:12:10 Audio
Operator

Ladies and gentlemen, good day and welcome to ACME Solar Holdings Limited Q3 FY26 Earnings Conference Call hosted by Muthilal Oswal Financial Services Limited. As a reminder, all participant lines will be in the listen-only mode and there will be an opportunity for you to ask questions after the presentation concludes. Should you need assistance during this conference call? Please signal an operator by pressing star then zero on a touch-tone phone. Please note that this conference is being recorded. I now hand the conference over to Mr. Abhishek Nigam from Motila Loswal Financial Services Ltd. Thank you and over to you sir.

Abhishek Nigam Representative

Yeah. Thanks, everyone. Good morning, everyone, and thank you so much for joining in. And on behalf of the company, we have with us today Mr. Manoj Kumar Upadhyay, Chairman and Managing Director, Mr. Nikhil Thingra, CEO, Mr. Rajat Kumar Singh, Group CFO, Mr. Ankit Verma, Head of Corporal Finance, and Mr. Arim Chopra, Head of Finance and Accounts. And now, without any further delay, I'll hand it over to the management for opening comments. Over to you, sir.

Good morning, everyone. Thank you all for joining us today. I am Rajat Kumar Singh, Group CFO of the company. I am joined by our founder and chairman, Mr. Manoj Kumar Upadhyay, Mr. Nikhil Ringla, our CEO, Mr. Ankit Balma, Head of Corporate Finance, and Mr. Arun Chopra, Head of Finance and Accounts. It is my pleasure to share the highlights of our Q3 performance. So, I would like to start with sector highlights and their implications on us. India continues to maintain strong momentum in capacity addition, with 30 GW of solar and 4.5 GW of wind addition in 9-month ending FY26, taking cumulative renewable energy capacity to 258 GW. Further, power demand rebounded sharply in December 25, with energy demand at 138 billion units, a 7% year-on-year increase. Followed by subdued power demand during April to November 25, when energy demand was flat on account of early monsoon. We expect the demand revival to continue going forward, resulting in increased PPS signing. Further, China has announced withdrawal of VAT export revets for solar products and failed withdrawal of VAT export on batteries from April 26. While this represents a policy shift, the impact will ultimately be governed by supply-demand dynamics, which we expect to remain favorable for buyers. Against this backdrop, for our FY27 plan contracted capacity of 1.5 gigawatt, we have already procured 1.7 gigawatt peak-up modules. And a large amount of BSS within the budgeted cost covering about 50% of module requirement and entire BSS requirement, which doesn't have any impact of planned VAT reduction in China. On the orders procured, there is a saving of more than 10% in the overall capex from the budgeted cost. We are pleased to inform we have signed order for additional 5 gigawatt hour of BSS within the budgeted cost. So, marginal cost for procurement done post-batch announcement done in China for both modules and battery is well within the budgeted cost. Therefore, we don't foresee any impact on budgeted cost of Chinese announcement. On curtailment, there are two kinds of curtailment. Transmission linked and grid stability related. We would like to assure you there is no impact on revenue from grid stability based curtailment on ISDS side as it's completely protected by GNA regulations. There is only transmission infrastructure related curtailment due to in-process transmission links which is temporary. This doesn't impact any long-term GNA holders as once granted there is no impact. of such curtailments. For us, we faced one-time curtailment loss of about 17.5 crores in our 300 MW CUR project due to operations under temporary GNA during the quarter. Excluding this, curtailment across the remaining portfolio was negligible, less than 1 crore, reflecting Thank you. of annualized revenue due to fattlement. Importantly, now with commissioning of Narela Khetri line with effect from 14 December 2025, You didn't keep cute. Thank you. Thank you. Additional 2 gigawatt hour of hour in the Q1 of FY27. Towards this, 1150 MWh of BSS has already been delivered at three sites and is at advanced stages of commissioning. With respect to our under-construction capacity, we have committed total capex of 8200 crores, which includes capex incurred of about INR 2550 crores and purchase order aggregating to about This activity is available for all under-construction projects, including unsigned PPAs. Thank you. Thank you. Thank you. 250 MW FDRE NSPC PPA has been signed yesterday at a tariff of Rs.4.33 per unit and is allocated under the green shoe option. Thank you. Are under construction portfolio. The tariff discovered demonstrates the competitiveness of renewable over thermal power generation at competitive price. With this addition, our total portfolio stands at 7770 MW, including 16.0 GWh of B. Now, coming to our financial performance, our total revenue for the quarter stands at Rs.617 score, a 54% increase year-on-year driven by capacity addition and higher CUF, EBITDA margin of 91.5% in Q3FY26, Operating leverage and optimize operational efficiency. In terms of balance sheet strength, our net operational debt to EBITDA stands at 4.2 times, net debt to net worth stands at 2.2 times, net debt to net worth stands at 2.2 times. Coming to our debt optimization efforts, through successful refinancing efforts and credit rating upgrades across parent and subsidiary levels, we have reduced the weighted average cost of our debt of our operational portfolio to 8.45% per annum, down by over 100 fixed basis points from December 24. Also, the weighted average cost of debt for entire outstanding debt covering operational and under-construction projects. 5 gigawatt operational. And balance is A category, underscoring the continued strengthening of our credit profile. Now at last, coming to operational metrics for the call. Thank you. Now, at last, I would like to briefly outline our strategic priorities till FY27. As part of our capacity build-up plan, we intend to execute approximately 1.5 gigawatts of contracted renewable capacity in FY27 and more than 10 gigawatt hour of BSS commissioning by calendar year 2027. In terms of execution readiness for FY27, Ed has been secured for almost entire capacity. Land acquisition has been completed for majority of the projects. Connectivity is fully secured. And majority of modules and BSS capacities have been ordered and have started delivering at sites and getting commissioned in phases. This level of preparedness gives us strong visibility on timely execution and disciplined capacity addition. As a strategy, We are tracking DHS installment of 10 gigawatt of our FDRE projects by calendar year of 2027 to unlock value early. By deploying batteries at existing operational sites, we are optimizing the use of available transmission infrastructure, saving transmission capex of about 20 lakhs per megawatt, and avoiding execution and right-of-way challenges. This approach is expected to enable early cash flow generation while ensuring seamless integration of BESs with the respective FDRE projects upon full commissioning, where they will continue to operate under long-term PPS for 25 years. PPS signing continue to remain a key focus area with near-term visibility of approximately 770 MW. This includes invitation received for signing of 130 MW REMCL PPS. Thank you. 1.5 gigawatt of secured and applied connectivity inventory available for a Coming live in phases. Thank you very much.

Operator

We will now begin with the question and answer session. Anyone who wishes to ask a question may press star and 1 on the touch-down telephone. If you wish to remove yourself from the question queue, you may press star and 2. Participants are requested to use answers while asking a question. Ladies and gentlemen, we will wait for a moment while the question queue assembles. The first question comes from the line of Aniket Mithil from SBI Mutual Fund. Please go ahead.

Aniket Mithil Analyst — SBI Mutual Funds

Yes. In your opening remarks, you mentioned that there has been some increase in the marginal cost of procuring modules. If you could just quantify that in the current environment, what is the cost? Of procuring modules now, and accordingly, what would be the capital cost for us to set up a solar project?

Right, right, Aniket. So, like we mentioned, there is a withdrawal of the rebate, which is different for modules and which is different for battery. So, basically, what we are seeing is there is a marginal increase in the prices of sales because right now for our projects, we need to only procure sales from there. Rest of the BOS is all from India. So, there is only impact on the sales to the extent of, you can say, on overall module cost, it's not more than one rupee. Basically, the impact of this change is only one rupee, if you look at the landed cost of modules for us, because there is a China procurement, there is a FTA procurement. So, suppliers are able to supply from either of these, and we look at the overall landed cost to us, which is not more than one rupee, and from our budget, it is, let's say, less than by one, one and a half rupees, even after this increase.

Now, the other thing is important to share here. 50% we have already procured, which was where this one rupee was not counted for or it was not there. So, technically, 30 to 40% of our additional capacity, this one rupee will be applicable.

The other thing is, in terms of the impact, usually we have seen in the past, this kind of impact happens at the transition phase of the procurement. What we also do is, we procured quite a lot of modules before March. That is, we expedited our orders, and we have lined up deliveries for quite a lot of modules prior to March. And of course, there will be a disruption, and there is a Chinese New Year coming up in February. So usually we see that these kind of disruptions are caused to increase prices of Chinese products. Which basically even out as we go in supply and demand, because ultimately this is all driven by their regulations. There is no change in their supply-demand dynamics. So this is temporary, because there is, of course, a glut there, and we don't see this impact of even one rupee lasting for more than a couple of months.

Aniket Mithil Analyst — SBI Mutual Funds

Okay. Just to understand from an overall capital cost perspective, what would be the...

So, it was, let's say, around 3.3, it would have gone to 3.35? Yeah.

Aniket Mithil Analyst — SBI Mutual Funds

This is on a DC basis?

Yeah, on a DC basis, yeah.

Aniket Mithil Analyst — SBI Mutual Funds

Okay, and this includes soft costs?

Every cost, all the costs.

Aniket Mithil Analyst — SBI Mutual Funds

And sorry, just to clarify again, this is for a non-tracker system.

Yeah, yeah, we don't do no trackers.

Aniket Mithil Analyst — SBI Mutual Funds

Just, you know, one more question was, you know, our VIN project has delayed quite a bit, and while you've been commissioning, it's taking us some time to commission. Could you just highlight on that, you know, when do we expect this project to get completed and the reasons for delay?

Sure, sure. So, wind project is expected to be completed in February, early part of February. So, the reason for delay was there was a sand mining sort of sand mining ban in Gujarat, which was there, due to which you could not take the sand from the neighboring areas, which impacted this in the last phase, in the last couple of months. But of course, we have overcame that kind of issue, and we have been able to build it within the timelines. Basically, in terms of pathways and the rains, of course, where there were extended rains last year, which again impacted the timeline. Because we have basically seen that the pathways construction is almost like a right-of-way construction in wind, which is like building a transmission line in solar. So it takes time. And, of course, we got extension also because of these reasons. And we are building within those timelines.

Aniket Mithil Analyst — SBI Mutual Funds

Okay, got that. I'll join in the queue for phone-offs. Thank you.

Operator

Thank you. Thank you. The next question comes from the line of Mohit Kumar from ICICI Securities. Please go ahead.

Mohit Kumar Analyst — ICICI Securities

Yes, good morning, and thanks for the opportunity. My first question is on the tool team I got you signed yesterday. H250MW is part of the NHPC where you assign the green shoe capacity, and can I expect this entire capacity to be commissioned in the F28? And the related question is, have you given a discount on the initial numbers? I think the rate was 4.56, right? It's not wrong, yeah.

So, just to answer your three questions, the first two are yes. The green shoe is part of the original capacity allotted, and, of course, it is expected to be commissioned in FY28, definitely. And, of course, on the tariff discount, yeah, there is a discount because there is an impact on the ISTS charges. The charges, it could be there for DISCOMs because of the delay in PPS signing, so there is some discount there, which is to factor in those charges which the DISCOM may face.

Mohit Kumar Analyst — ICICI Securities

Have we got the DISCOM approval or DISCOM PSA signed for this? Yeah, yeah, yeah.

The process is that the PSA gets signed between NHPC and DISCOM, and then the PPA gets signed between the NHPC and us, so both of these activities have been completed. The only thing pending is the regulatory approval from Punjab Regulator and also similar thing from the CRC. But the PPA has been signed with NHPC, and the PSA has been signed between Punjab and NHPC.

Mohit Kumar Analyst — ICICI Securities

Can you please help us with the COD for 680 MW and 190 MW FDRE projects?

Right. So, in terms of the 190 MW projects, we are targeting FY27 for the project. And for the NHBC projects, it is FY28. And these are in sync with the substation timelines at both these projects.

Mohit Kumar Analyst — ICICI Securities

First question, sir, how do you see the impact of the new DSM regulation, which are going to kick in from April 26, and our preparedness as an industry?

Yes, yes. So there is a lot of deliberations happening on this DSM regulations at all the industry forums, at the power ministry, at the renewable ministry, and it is a matter of high discussion, and all the top decision makers are apprised of the difficulty which the wind projects primarily may face more than solar. And, of course, the thing is you can overcome this. Of course, it is coming in phases. As you know, it is coming in phases until 2030. The thing is, with batteries coming up, the overall instability caused by the renewable power will reduce. So, there is a lot of emphasis on installing batteries on the existing plants. So, that is, the power ministry and MNRE are together working on resolving this issue. There are a couple of solutions being floated around. One is that making it prospective and not retrospective. The other solution is being contemplated is to install batteries at the existing plants to take care of the unpredictability of the radiations and these wind flow. So, and of course, allowing that excess battery to be sold in Merchant to compensate the developer. So, different solutions are being worked out for wind and solar, and also looking at the prospective implementation. So, this is something being happened. In terms of solar, it has a much lesser impact as compared to wind. And the other thing is it is not impacting on the battery-based projects because they don't have such problems.

So, it is also very important to note that most of our projects in Rajasthan, they are all being fitted with the battery. So, technically, in all those projects, there will be hardly any impact because the battery will be able to take care of that.

Operator

The next question comes from the line of Akash Mehta from Canary HSBC Live. Please go ahead.

Abhishek Nigam Representative

Yeah. Hi, sir. Thank you for taking my question. First, just wanted to check in terms of the battery, in terms of your capacity addition of 2 gigawatt hour that has happened. How much, I mean, in terms of profit, if you look at the run rate is about 2,000, 2,100 crores, right, in terms of operating profit. So, how much this could kind of, the battery projects could kind of have in profit if you just help us understand in terms of one gigawatt hour if you sell it in merchant in terms of next couple of quarters.

So, a 1 gigawatt hour of battery results in around 170 crores of EBITDA if operated for 12 months, and this is assuming a 5 rupee arbitrage between buy and sell price. So, that's the broad math.

Abhishek Nigam Representative

Okay, I think that's quite helpful. And if you, I mean, next, I mean, going into fiscal 207, you mentioned 1.5 gigawatt will be added, right?

I mean, for admin A. In terms of battery, yeah, in FY27, we plan to install around 4 GWh, and CY27, 10 GWh.

Abhishek Nigam Representative

No, in terms of total capacity addition, I mean, in terms of the

overall plans, yeah, so So, FY27, 1.5 gigawatts of contracted capacity we will install. And battery addition is, let's say, 4 gigawatt hour in FY27, which is, of course, in some cases part of the project, in some cases merchant, and around 6 gigawatt hour more in the rest of the CY27.

Speaker 3

So, 1.5 gigawatt of capacity, which is scheduled for

commissioning in FY27, will require roughly battery capacity of roughly 3.3 gigawatt hour. And over and above, anyway, this will get installed and be integrated to FDI projects. And over and above, roughly 1.5 to 2 gigawatt will further get installed.

So these are 1.5 gigawatt mostly FDRE. So they technically will be 3.5 gigawatt of solar, some 400-500 megawatt of wind, and 3.5 gigawatt hour of battery.

Abhishek Nigam Representative

Okay, I think that's fair. So, this will come in one quarter, or this is more of first half or second half? I mean, if we just help us with that.

Yeah, basically, see, this is the connectivity timelines for each substation. So, yeah, it is coming actually in very – there is some capacity which is coming up in the first round Q2 of FY27. So, starting from Q2, these will all come up.

Abhishek Nigam Representative

Okay.

Of course, battery installation will happen from this quarter only, but in terms of the full project commissioning, FDRE commissioning, that will start from Q2.

Abhishek Nigam Representative

Okay. And lastly, on the industry level, have you seen any pickup in terms of the PPA signing? I mean, there are existing around 40 million of PPA that's there in the system. But, I mean, what's your view and how much time it will take for the market to kind of absorb this?

So, see, everybody is trying to make an effort to streamline the takeoff. And, of course, as the power demand has gone up, so, of course, there are a couple of elections also coming up. So, we will see that there will be a takeoff in terms of the PP at the industry level. A couple of reasons for that. One is that the bids are now coming with the demand-centric bids, and there is a lot of reduction in the new bids which are coming, which is, of course, increasing the demand for the existing PPAs. The other thing with existing PPS is they are to be done with Chinese sales, and, of course, the cost which a developer is able to offer is a competitive, and also the ISTS waiver, because the connectivity is tagged up with these projects are coming up early, like 26, 27, 28. Every state wants to take benefit of the ISTS waiver charges, because it's a very tangible number. So, there is an incentive inbuilt in these bits for the projects to take up. And, of course, now with streamlining of RIAs, which is being contemplated, wherein no competing bid for an existing bid will come up, which will further increase the takeoff. Because what happens is one RIA comes up with a bid which is undercutted by another bid, which is unlikely to happen in the future. So that is why we will take off. As far as we are concerned, we have a near-term visibility of, we have signed PPAs, as mentioned in our presentation, and we have near-term visibility of 770 megawatts. We have signed around 450 megawatts this quarter. So, as you can see, we are an example of that these PPAs are happening, and, of course, it will happen. What happens is states are trying to aggregate large procurements. They are doing it in phases because quite a bit of pipeline is there, like you rightly mentioned, for TKW. So everybody is picking and choosing in terms of what they want to buy. Most of the states have peak power requirements, so they are trying and fit their peak power requirements along with the available pipeline. So we think that there will be a good takeoff in the next one or two quarters because there has been quite some time where people have deliberated each state, and there are large states, you know, five, seven states, which are likely to buy.

Abhishek Nigam Representative

I think that answers my question. Thanks a lot, and all the very best.

Operator

Thank you. Thank you. The next question comes from the line of Apoorva Bahadur from IIFL Capital. Please go ahead.

Apoorva Bahadur Analyst — IIFL Capital

Hi, sir. Thank you for taking that question. I had a query around the battery commissioning. When should we expect the first best to be commissioned? And secondly, will it be modular, as in, like solar modules, can we keep on adding those containers and probably start operating them parallelly, or do we have to require for a site to reach a critical site before commissioning it?

Thank you, Purva, for the query. So, basically, it is modular. We have already taken CA approval for around far more than 580 MWh of battery commissioning. So, we are doing it parallel execution at three sides. So, you will see that each of these sites, there are one gigawatt hour plus of installation at two sites, and one site is around, you can say, closer to a gigawatt hour. So, at each of these sites, we will take them to the four gigawatt hour, which we spoke about in the next, you can say, six to nine months, starting from this month, February, starting from February. So, it is modular. The only thing which you need to do is just call, we need to take up the CA approval, which we can do in phases. There is a seven-day prior notice which you need to give for the approval. It is completely modular. What you need to have is basically the transmission infrastructure to enable the supply of power, which we have at all phases. So, the long lead item which is required, which is the transmission connectivity, which we have at all sites. So, the rest of all is modular. The battery, the BCS, the electrical infrastructure, that is all modular.

So, we are starting with the 500 megawatt hour, as Nikhil mentioned. So, every, I mean, at three sites, the capacity is around 100 to 150 megawatt to start with, and we will keep on adding more and more batteries as they are coming on the site. And in this process, we have to just inform CEA to come and visit at every time when we add.

Just to add on this, we have 1.2 gigawatt hour lying at our site, out of which we have taken approval for only 600 megawatt hour. So, you will see that we will take more and more because it is all modular, and, of course, it is helpful for the grid. So, and we have got approvals also, the connectivity approvals, but, of course, since we are doing the charging at large scale, it will be done in phases.

Apoorva Bahadur Analyst — IIFL Capital

And sir, we will be charging these using the merchant power.

Yes, yes. For time being, until our time our FDRE plants come up, we will be charging using merchant power, you are right, during solar hours.

Apoorva Bahadur Analyst — IIFL Capital

Thank you. Also quite commendable. I think we managed well on the curtailment side. Industry has been suffering. Would be curious to know about this revenue recovery on CTU curtailment. Who will pay? Is there a key structure that the DISCOMPs need to pay even if it's a great stability-related curtailment? Or is there any other mechanisms? Secondly, are we receiving those payments or are we sitting in our receivables?

So, we are receiving those payments. How it works is, this is part of the ancillary regulations of the transmission guidelines. What it means is that for the stability of the grid, they can do a transdown. Basically, what it means is that for the grid stability, if the CA or NRLDC chooses to adjust your power, the state can't adjust its schedule. The state has to get the same amount of units it was supposed to get. And it has to pay, because it has got those units, it has to pay for it. So there is, we, and we don't have to adjust our schedule. We are also paid as per our schedule. They didn't end up, and both sides are, therefore, supplying, and they are taking, and our bill does not get adjusted, because this is done purely to adjust the grid stability. So, there is a very clear regulation. Nobody even, the state doesn't know that we were being cut trade also, because this is completely done at the central grid level, and the state has no involvement in this whole trans-down scheme.

Apoorva Bahadur Analyst — IIFL Capital

And, sir, where we are connected to the state grid, how has been the situation on curtailment?

So, state-grade, of course, we are trying to get the similar regulation done in their transmission rules because generally what happens at the state level, the transmission and GENCO both are owned by the state government. So, there is a common officer or the regulator who is taking care of that. So there is actually a very minor curtailment which happens in the state, which we have mentioned that it was around less than one crore on the state-level portfolio. So there also the regulator is sympathetic to this cause because now states also have significant solar assets which are also impacted, and they are trying to put up a lot of batteries at state level, as you know, with the VGF, which is coming up at the state level. So, we see this, again, as a temporary problem because states have aggressively picked up the batteries, so there will be less inability they will have to adjust their grid. So, there is an impact in Rajasthan, but which is very minor, and, of course, we are trying to solve it regulatory, and states are themselves trying to solve it through batteries.

Apoorva Bahadur Analyst — IIFL Capital

Okay, okay, fair enough. So, last question from my side, and this pertains to the other entity, promoter entity, which houses the green hydrogen business. I understand that we have won a couple of sticky options. Any update on that, as in how should we expect a build out over there? And secondly, will there be any sort of arrangement between ACME Solar and ACME Clean Tech of sale of power, and how would that work?

Great. So, see, we have won the auction, and, of course, there is that GAAPA, which is going to get signed. So, it is, of course, not yet signed, and there will be in a quarter or so, it may get signed. So, they will make their own arrangement regarding power, in terms of the power. So, there is no requirement from our side to supply that power. Of course, they will be buying through various mechanisms, including procurement from RIAs, including their own Capex, and maybe from CNI, because it will involve some bit of connectivity sharing. So that's the broad. We have not yet evaluated in detail whether it makes sense for us to supply or not. So we will be able to tell you once we make that analysis. So right now, there is no plan to supply to them for that power. Because there are certain regulations which we also need to see, they will need to see in terms of the EOUs, in terms of the NFE. So it is evolving space because there are a lot of regulations which are enabling the green hydrogen today in terms of transmission waiver, in terms of these export-oriented units. So I think that regulatory framework is still getting frozen. So they have not yet. Of course, there is a lot of connectivity available with them. So they can do their own power also. So there is no decision as of now whether we will be supplying or not because we have our own KPEX plan. We have our own sort of demand coming up from the utilities. So there is no decision that we are going to supply to that company.

Apoorva Bahadur Analyst — IIFL Capital

Understood, sir. Thank you very much.

Operator

Thank you. A request to all participants. Please just take your questions to two participants. For more questions, please return the queue. The next question comes from the line of Dhruv Muchal from HDFC AMC. Please go ahead.

Dhruv Muchal Analyst — HDFC AMC

Yes, sir. Thank you so much. I had a structural question on the curtailment thing. I'll understand how it happens in all those. So, the point is... Assuming that India keeps adding about 25-30 gigahertz and probably even more annually, and your demand grows by about 12-15 gigahertz on an incremental basis, there is an excess of solar supply every time. Probably batteries will address it to some degree, but then there could be timing issues, the cost issues, and multiple issues. So it seems this curtailment thing... Unless I'm wrong, this curtailment thing could be a bit structural. So, just wanted to understand, is it fair to assume a 5 or probably 10% impact on revenue because of curtailment for future projects, or you already build that in any forecast in terms of how your IRRs are going to get built up, or the whole understanding itself is wrong?

See, Drup, you are right on the numbers in terms of structural, but how it works is the regulation. Basically, it's a regulated sector, right? So you are right in terms of the supply-demand maths. And of course, there will be an impact of battery, which you rightly said it will be adjusted. But the thing is, there is a difference between curtailment and payment. So, in terms of our revenue, because of the regulations, there is no impact because this was made keeping in mind the must-run status of renewables, keeping in mind that the revenue need to be paid because nobody is at fault here in terms of the developers. So, there will be no revenue impact, of course, on the net, and the states also, and the buyer will get whatever units they are getting because it's at the central grid. It is not a one-to-one correlation between the supplier and demand. If it was a one-to-one correlation and we were not on the national grid, let's say for the CNI thing, which is the buyer is curtailing us, that is not the case. It is a grid stability thing. So even despite this supply demand, there will be no impact on the revenues.

Now, the other thing I think you should know, Dhru, that the government is adding, the government and the state, central government and the state, both are adding large amount of the battery. And these batteries, what they are doing is, as you rightly said, 12 gigawatt. Even if you add 25 gigawatt of solar, if you add... Enough battery, technically it is 6-7 gigawatt of round-the-clock power. So what most of the states are doing, they started with 2 hours of battery, now 4 hours of battery, now they are talking of 8 hours, 10 hours of battery, as the battery prices have come down. So you'll see that more or less they get optimized. And the government is also thinking this by giving them this VGF. So from the central government, instead of building additional transmission capacity, they found out that giving this VGF for the battery, what will happen is it will also create additional capacity from existing grid.

In terms of the two facts, the Power Grid is also building the ancillary batteries on a large scale. They have come up with a tender for in South, they are building their battery. Power Grid also has a plan to put batteries, and NEP has a 300 gigawatt hour plan by 2030 for the batteries. So, of course, everybody is aware of this issue, but as far as our payment is concerned, that is not at risk.

Dhruv Muchal Analyst — HDFC AMC

Sure. No, sir, just extending, sorry to just extend this a bit. I understand the batteries will happen in this, but the only risk that we see, at least from a few years' perspective, is that the bids that we have seen in batteries are extremely, probably... For the external guide teams, some of the players have bid extremely low, and given how the battery prices have changed, some of these bids might not actually convert to physical assets, and that realization will happen over a period of time, and the states will then rebuild, and all those things will happen. So this creates a timing gap, probably, I don't know, two years, three years, or probably it can be lower. So during the timing gap, can this be a thing? I understand you are assured because of your payment, and there is a difference between dispatch and your payment, but if the quantum keeps on increasing, do you have a pushback from the system that this is too much now, we can't handle this? So just trying to understand how the system works.

No, of course, of course. It's a very valid problem. See, there is a lot of discussion going on about converting the existing solar into battery and freeing up the existing connectivity, which is there at ISTS. So, there are various solutions for reducing the peak supply of solar power because, you know, we have around 52 gigawatts of CTU-connected renewable today. And this 52 gigawatt of solar and wind, out of which wind is only 10 gigawatts, it can be converted into peak power in the existing construct of the PPAs. So there are some low-hanging fruits in terms of solving this problem, which everybody is mindful of. So there is, and in terms of the bids, there is a large capacity coming up from credible developers in terms of the FDRE, in terms of the peak power. If you even adjust the state-level bids, which are there, and that is mostly at HTU. The state-level bids where you are seeing excessive competition, they are mostly at STU, and they are not at CTU. We are talking mostly about CTU here, right, because our playing field is CTU. So, there you have not seen those kind of bids and those kind of irrational competition because that has happened at the state level where there is a VGF. And so, you should separate the two, the credibility of the developers doing the CTU projects, the power grid, which is highly credible, and the developers which are doing not standalone batteries, but a battery comes solar, which you require extensive connectivity, extensive land purchase. So, the issues you are seeing is mostly on the STU level bids at the stage. Government is mindful of the CTO level issue, which they are trying to solve.

Dhruv Muchal Analyst — HDFC AMC

One quick question is, on slide 7, you mentioned about connectivity inventory for upcoming bids. So this is over and above the LOA bids you have, right? I mean, for the future bids that you will be bringing, this is for connectivity for that. Yeah, yeah.

Operator

Thank you so much, and all the best. Thank you. The next question comes from the line of Nikhil Abhyankar from UTI AMC. Please go ahead.

Nikhil Abhyankar Analyst — UTI AMC

So, a couple of questions. First, related to the best system. So, what are we exactly targeting? Will we look to cater to both the morning and the evening peaks? Will we be able to do any terms more than one through the system?

Yeah, yeah, we can do that both. It depends on because what we are trying to get is we are trying to get arbitrage of the cheap power versus the peak power. So, if the morning arbitrage, for example, in the morning time, solar time, we charge the battery, we will be able to do it in the evening. Even the night time, especially between 12 o'clock to 2 o'clock, if again the power cost goes down, we can charge it and do it in the morning. So, we are flexible. Our batteries, actually, they are designed to work for two cycles.

Nikhil Abhyankar Analyst — UTI AMC

And this guidance of 170-odd was based on one turn or more than one turn?

Yes, it is based on one. If you do two, it will be double.

Nikhil Abhyankar Analyst — UTI AMC

So, just a continuation to that, will there be early commission for BES system impact or are there for which the BES is being procured? I mean, the life of BES system is considered to be around 11-12 odd years. So, early replacement will it impact the… The project is done?

No, it is not. In fact, today's modern batteries, they are actually designed for 18 to 20 years. And in fact, they are designed for 1.6 cycles a day. 1.6 cycles a day means someday two cycles, someday one cycle. In our business model, normally, we have kept 12 to 13 years of replacement of the batteries. So technically, we are not affected for one year, one and a half years of this operation.

And in terms of the battery replacement, when we talk it is a cell replacement only. The associated infrastructure does not need to be replaced. And secondly, when we are realizing revenue early, we are making a good IRR on that particular KPEX. So that will also add up to the utilization because this is good bidda for the KPEX done.

Nikhil Abhyankar Analyst — UTI AMC

And just on the under construction portfolio, can you just give us a timeline in terms of budget capacity which we expect to be cash consumption in, say, next to over two years, 27 and 28, and the related cappus as well?

So, yeah, like we said, 1.5 gigawatts is likely to happen by FY27, right? And in addition to that, around 2 gigawatt hour of battery, which is, of course, these are the bestest part of it. So, 1.5 gigawatt by FY27 and 1.1 gigawatt by FY28. So, let's say we have around 2.6 gigawatt of signed BPAs, right? Because let us track the signed PPAs, because as and when PPA gets signed, we can upgrade this thing. So let's simplify things. So FY27, 1.5 gigawatt. FY28, 1.1 gigawatt. So here comes the CAPEX. CAPEX is around 12,000 crores for this FY27 till capacity. And you can say around 10,000 crores for the 1.1 in FY28.

Nikhil Abhyankar Analyst — UTI AMC

And this includes the best cost as well?

This includes the best cost as well, yes.

Nikhil Abhyankar Analyst — UTI AMC

And, sir, on the unsigned TPA projects portfolio, do you expect any movement or, I mean, not really?

No, no, we do expect a movement. We have tried our best to accommodate the status also in the presentation. We have said that in the near term, 770 megawatts of additional PPA finding in addition to what we have done of 450 megawatts. So we expect those to move for reasons we mentioned earlier during the call in terms of the attractiveness of because of the ISTS waiver, which is currently going on, the timeliness of land purchase and every availability which the supply side has. So we expect the movement and also because of the less bids which are coming off a similar sort of construct. So we expect these PPS to move and large states to buy.

Nikhil Abhyankar Analyst — UTI AMC

And just a final question, of the current under construction portfolio, can you give us how much DCR modules will they require in the next few years?

We don't need any DCR.

Nikhil Abhyankar Analyst — UTI AMC

Okay, got it. Thank you, Anurag.

Operator

Thank you. The next question comes from the line of Yogesh Patil from Dalat Capital. Please go ahead.

Yogesh Patil Analyst — Dolat Capital

Thanks, sir. I have a couple of questions. Sir, questions related to, again, connectivity. Till date, we have 6.1 gigahertz and the capacity is under flow A. If you could give us how much of this capacity is having a GNA at once and a temporary GNA at once at this stage. And correct me if I'm wrong, correct understanding that all of our PPA sign capacity has a full GNA access.

Yes, yes. Basically, you get a in-principle approval, then you get a final approval. That is at the, you can say, pre-buildout stage, right? So, we have got the connectivity approval for the whole capacity where PPA is signed. And this GNA, whether it is a short-term or a long-term, is operationalized when the system is built, right? So, when your system is fully built, you get a long-term GNA, and in terms of, let's say, if there is any element which is not complete, you can get a short-term GNA, and you can supply power. So, this connectivity agreement operationalization is signed when it is built out. So, right now, we have connectivity, full connectivity allotted for the PPA signed and unsigned, both, like we said, and we have excess inventory of around 7 gigawatts of additional connectivity. This GNA, of course, we have dates for each and every substation within the timelines we are targeting, and that is why we have given the current schedule of those transmission lines, we have scheduled the CODs. And also in terms of a regulatory point that if there is a delay due to any element of the transmission line, there is an automatic extension given in the PPAs for that sort of delay, which compensates. And we also track. We also track on a monthly basis, basically the actual site visits to that CTO substation, where are they in terms of the actual progress of that transmission link. And, of course, if there is a delay at their end, we adjust our capex to save on the IDC. So in our existing ongoing projects, we are fully tracking that, and we have synced up our transmission, our commissioning dates as per that.

Yogesh Patil Analyst — Dolat Capital

Yeah, so the second question, I need a small understanding on procurement of the equipment for the project. At the time of entering into the contract with the equipment supplier from India or China, do you sign this contract generally in case of Indian rupee terms or US dollar terms?

So with all the Indian suppliers, and it includes the Chinese suppliers who are based in India, like the turbine suppliers, the transformer suppliers, the inverter suppliers, there are actually quite a lot of Chinese suppliers who have manufacturing or assembly in India. So they are all done in rupees. I can give you examples of a lot of these suppliers who are Chinese but based in India, so they are all rupee. Most of that is rupee. The only bit which is done in dollars is the batteries. Batteries and sell by the module supplier, not by us. So the only thing which is done is the batteries. And in some cases, we have tried and bought, you can say, GIS, which is again bought out from India, again from a Chinese supplier, but they are billing it from India. So only batteries is in dollars, rest is all in rupee.

Yogesh Patil Analyst — Dolat Capital

Okay, and the last one, do you sign the fixed price contract with the equipment supplier or a flexible price contract? I mean, if the solar module raw material prices goes up, goes down, who takes the losses or the profits of this contract?

So, we have realized over a period of time that signing these flexible contracts have not much value because sometimes because of the regulatory changes or any change, these prices are difficult to hold. Even if you take a, you can say, a CPBG or any sort of regulatory mechanism, it is difficult for anybody to service. So we always sign a fixed price contract with no linkages, and these are all short-term contracts wherein the supply starts from, let's say, maximum couple of months, including the shipping time. So, and we try and sign with the large suppliers who have such kind of monthly capacities such that they are able to service a large volume within a month of production. So, we don't sign flexible contracts.

Yogesh Patil Analyst — Dolat Capital

Thanks. Thanks a lot. All the best.

Operator

Thank you. The next question comes from the line of Saurabh Aria from Oakden Capital. Please go ahead.

Saurabh Aria Analyst — Oakden Capital

Yeah. Hi, sir. Congrats on good set of numbers. Couple of clarification. The first one is this green shoe, which we have won with NHPC. So, just want to understand, this was not part of the last year's presentation. I mean, this is the last quarter presentation. Is it like a new one should consider?

Right. Right, Saurabh. You're right. It was not part of our presentation because, see, green shoe is something which happens later than the original allotment. Our PPA, as you know, got signed for the original allotment quite a long while back. So we had no clarity on the signing of this PPA till the time the regulator, the NHPC told us that they are seeing the demand for this power, considering the connectivity we have, considering the availability of supplying power we have. And then very short term, we were able to get this signed. And this happened between the last quarter and this quarter. So that is why we are updating because till the time we don't take green shoe projects until they fructify because that is something which is tentative. So that is the reason they were not part of our last presentation.

Saurabh Aria Analyst — Oakden Capital

You are already building this project, and it had a scheduled timeline of June 27th. So, would this be accommodated at same place in terms of connectivity, land, and everything? So, how can the planning be so quick within a span of 12 months for something which is just one?

We have got connectivity for even 7 gigawatts post this, post the allotted this thing. So, you know, we have, we are not treating the under construction projects and the PPA science projects as far as the land and transmission line are concerned because they are long lead items. And connectivity, of course, without connectivity, you can't hope to be in business even bidding. We have, let's say, long lead items also like a power transformer ordered because we are very confident that these things will happen. If this PPA does not get signed, the other PPA can get signed. So when we plan a project, we plan a particular set of sites which we keep on developing. Of course, we don't order batteries, we don't order modules, and we don't take any financing. Till then, we push through our equity. And this is not certain. These are all sites which are developed. When we are telling you that 770 megawatt of PPA will also get signed, right? So for those sites also, we have the land and transmission line. See, because of this transmission waiver thing, you need to do that. If you don't do that, you will not get a customer for your PPA because the customer wants the power before the June 27 or before June 28 because these are the timelines. Post-June 28, everybody is equal, right, because there is no differentiation in terms of the transmission waiver, and it reduces the attractiveness of the CTU-connected projects. So it is important to do that, and we have been doing that.

Saurabh Aria Analyst — Oakden Capital

Sure. And if you could, you know, break up this 770 megawatt, which is further PPA signing you are expecting, is it, does it pertain to old projects or new projects?

So, yeah, this 770 megawatt is a mix of old and new projects. And, of course, like I said just before this, it's a function of the preparedness. When a state is looking at the, of course, he looks at his own requirement in terms of peak power. So all these have a peak power element, and also they have a high peak power element. Basically, they look at the mix of how much peak power are you able to supply, how much wind power also sometimes. They have peculiar requirements depending on each state to state, depending on their power profile. So it's a mix of old and new projects, and of course, it's based on their requirement, and also the timelines in which we are able to supply and the readiness. Because, see, a lot of states have procured power which are not coming on time because of the connectivity delays, because of the land delays. So, they are really trying to see whether you can deliver that power within the timeline because everybody is very conscious about these timelines now. So, this is a mix of old and new. We have not disclosed the exact thing because we will like to disclose once the PPA gets signed. But, of course, they are in advanced stages of regulatory approvals.

Saurabh Aria Analyst — Oakden Capital

Fair enough. Thank you very much, sir. All the best. Thank you.

Operator

Thank you. The next question comes from the line of Pradeem Nishaudhary from JM Financial Group. Please go ahead.

Speaker 3

Yeah, hi. Thank you for the opportunity, sir. Just one question regarding the project cost, like in your PPT as well and in your opening remarks, you spoke about the equipment currently being ordered within the budgeted cost. So what really do we mean, like, by this budgeted cost, like, what sort of target IRRs or the budgeted project IRRs are we assuming that would help us get more sense of the kind of prices we are bidding for, right?

Sure, sure, sure. So, we take care of high-team returns. That is the threshold we have that we don't bid for anything lower than 16% return. I think we mentioned that in the past also. So, high-team returns is our threshold. And when we look at, for us, let's say a 1.5% movement is a very significant movement in IRR. So, when we say there is no impact, it is less than that usually. And in terms of the capex, so like we said, we have changed our strategy. This is, let's say, preponing the batteries to utilize that capex. We are able to order batteries at a short time because we have connectivities which are operational and which can take batteries. See, nobody will be able to keep batteries for more than six months because they degrade. And because there is a capex involved, there is an interest during construction, so only a developer who can make them operational will be able to get those batteries. So that is why these returns are not impacted, because we are able to get those batteries, because, you know, there is so much capacity established in the world, primarily China. So there are very few guys who are able to take deliveries, let's say, in March, April, May. That is how the world works in terms of what actually can you take. There may be somebody who is willing to give them an order for next year, but they will not put a price for that guy.

Speaker 3

Alright, but, like, my concern relates more to the fact that the project said the tariffs have already been decided, and I'm assuming the batteries or the solar modules are ordered towards the end of the project CAPEX, right? So, there, how are we really protecting ourselves? Even there, we have a budget, and especially for the ones where 50% of the remaining, like you said, that 50% we've already ordered, and for the remaining 50%, it's still yet to be ordered. So, what are plans for the remaining 50%?

Right, right. So, why do we say that we are with the budget? Because, see, the policy change, there is a policy change in China, right? So, post that policy change in April, we have April delivery, which is happening at a price which is, you can say, much less than the budgeted cost, which is a high-team return. So, that is why we are saying that we are within budgeted cost because the marginal delivery we are taking in April, this is the April price with post-regulations, is also well within the range. And 50%, of course, we have procured where we are installing them, that is well within the range also. So, on that basis, we are saying that we are well within the budgeted cost.

Speaker 3

Understood. And on the PTAs, I believe now around 800 megawatts to 1000 megawatts is what we don't have near-term visibility, right? Like where we are yet to sign the PTAs and there's no near-term visibility. So what sort of timelines are we looking there? And especially when you say that we have a near-term visibility for, say, around 750 megawatts. So, by near-term, you're meaning the next three, six months. Is that what we're able to assume? And what about the remaining ones? Again, the reason, if you can just repeat the reason you gave for us expecting... Acceleration and TTA signings. I know you answered to one of the previous participants, but I didn't really understand it. So if you can just repeat the reason as well.

No problem, no problem. Completely understand your query. So, in terms of the beyond 770 megawatts, right, there is a very, when we say near term, we basically say that when there is a buyer approval. Basically, the first thing you need in a PPA discussion is the buyer approval, whether they are okay to take that offering or not. So, we have buyer approval for this much capacity. We don't have written buyer approval for the rest of it. That is why we did not say near-term number, but there is a very good chance of those PPAs also getting signed in the next quarter only, right, which is around 700 megawatts more other than 770 megawatts. And why did we not put it? Because there is no written buyer approval we have, right? And there are differences in how each state procure power. Somebody takes a prior regulator approval. Somebody takes a post-signing approval. So there are various stages in a PPA implementation. The PPA gets signed. Somebody takes a prior approval, which is good for us because it includes definitiveness. Somebody takes a post-facto approval, that is also fine. We have to go along with it. So, that 750 megawatts more of FDRE hybrid PPA, that is, again, at a very advanced stage. And there, and also there is a timeline difference between each state. So we have not put it because we only want to put it where we have a buyer consent, but there is a 700 megawatt more of PPA, which is under advanced discussion, but I don't have a written thing to write. So that is why we did not write it.

Speaker 3

Understood. And the reason you were saying that overall in the industry, we are expecting the PPA finance to accelerate, could you just repeat that again?

Yes, yes. So the reason primarily is that these set of players who have won these bids, right, of course they are serious players and they have made, because they have made significant investments on getting connectivities, on offering earnest money deposits, performance bank guarantees, and they have got huge fixed costs in terms of teams. So most of the players who have won these bids, 42 giga lot of bids, are quite serious about building those projects in 2026, 2027, and 2028. And this is the period which gets you an ISTS waiver as a buyer. Basically, you're aware that ISTS waiver is expiring on the central grid in 26 phases. So the states find it, and states which don't have a good renewable at their own state, they don't have flexibility to build state-connected projects because they are expensive, because the sunlight is not there. So, those... States, particularly, will be very keen to buy these CTU-connected projects, which have a transmission waiver element built in. And who can supply to them? Nobody where the bid happens today will be able to supply with the ISTS waiver in hand, right? Because the bid cycle itself is very long. They take 90 days to do an auction, and then there is a LOA. And there is, of course, the element of buying the Chinese sales or Indian sales also, which make the price slightly costlier. And, of course, it will take time. So, because of the preparedness of the supply side, And also on the demand side, this ISTS waiver expiring, these two are making an attractive win-win proposition. The only hitch which was coming was there are concurrent offerings of similar kind outstanding from various bidding agencies, which is making the choice difficult for these buyers. So that is the reason the PPAs were taking time because it was actually done, let's say, on a standalone basis by all four agencies, which created a sort of... of supply of these PPAs, which leads to delay. So as people choose what they want to buy, and the suppliers also customize their offerings and choose what they want to sell, how it will be attractive to the buyer. I think it will clear. And of course, the power demand in last year also plays on people's mind that how do I see the power demand coming up. So some of these, and of course, there are elections every year we have some election which also delay these things. And there is a cycle itself which takes time. So we are expecting these things to happen because of the preparedness and also because of the regulatory ISTS waiver thing.

Speaker 3

And usually the size, yes, we will, how much on a per, like in terms of the tariff, can it cost additional ones for the projects commissioning post-28?

So, see, there is, there is, each state has a different sort of charges depending on how much their transmission infrastructure is utilized currently. Let's say if there is no rebate, it could go to up to 1 rupee, more than 1 rupee, if there is no rebate.

For solar, actually, this will be a different view. So, for example, if it is only solar, it may go up to 1 rupee is 30, 1 rupee is 40 paisa. If it is solar plus battery, it can come down to 80 paisa. If it is FDRE, it can further come down to 30, 40 paisa. That's why you will see more and more power is round-the-clock power or FDRE to reduce the impact of the FDRE. What is the impact of ISTS waiver in future?

It's very substantial. For each state we have seen, it is very substantial because NHBC and SECI and all these agencies are very mindful that can you give it before 27, 28, and it is very important. We have not seen a state who does not care about it.

Speaker 3

All right. And my last question is regarding the under construction projects. So are we, like, of course, our execution has been brilliant, but on the grid construction, are the grids also corresponding, are they coming up on time or are we expecting certain delays over the next couple of years of projects that we've planned to launch? Commission.

See, there was a, it's a very, very hotly reviewed project thing at all levels. So, in terms of the planning of these transmission projects, there are a lot of changes which have happened over the last few years. They have given a, let's say, earlier they used to plan it in 18 months. Now they are giving a 24 to 30 month period to these transmission period. They are planning it early. They are coming up. So, this gives a lot of time for these guys to come up on the committed time and not getting extended. So, of course, what we are seeing is we have kept a buffer of a quarter delay in all our planning. So, and of course, this can happen because depending on what are they upgrading, right? In some cases, they are building a transmission line. In some cases, there is no transmission line. So, if there is a transmission line, there could be, let's say, a one quarter delay because of ROW issues and other things. But if there is a local installation of, you can say, infrastructure, electrical infrastructure only, then the delay is very much unlikely because these are a local execution. But by and large, we track the various cycles of these transmission infrastructure. And we don't see a delay in where there is no transmission line, but where a transmission line, a three-month delay can be there, and we keep on monitoring our CAPEX as per that. If we foresee that it could extend, we defer that CAPEX, and also we can take the strategy of – we have already done that, right? To hedge that risk, we had called batteries at the operational substations. We have broken the plant into two, right? The batteries at the operational substations where there is no risk at all, and then the modules at those plants where the new infrastructure is coming up. So you can take multiple ways to solve this problem because this is beyond our hands.

Speaker 3

All right. Thank you, and all the best.

Operator

Thank you. Thank you. Ladies and gentlemen, due to time constraint, that was the last question for the day. I now hand the conference over to the management for closing comments. Thank you, and over to you, sir.

I would like to thank you. Thanks to all of you that... You had a very, very important question you asked us, and I hope my team must have given you the input. If there is any further input, we will be very happy to provide. We can assure you that we are working on the technology, we are working on the execution, we are working with the government on the policy advocacy, and we are also working on the regulatory framework. So as a company, we believe we are not only just doing execution, we are also creating a... Policy framework for the entire industry, and we are also doing something on the technology side. I think I must have shared with you in my last presentation that we are already testing peroskite technology, and we believe that that will be very useful in the coming years. So we have already started. That will give the industry as well as ECMI as input to see whether the technology moves from the current silicon-based to peroskite-based. We are also doing robotic installation. That is one of the challenges in this industry. If you want to increase from 1 gigawatt or 2 gigawatt per year to 5 gigawatt per year, one of the biggest challenges in the industry was how to install 5 gigawatt, 6 gigawatt of modules manually. So this year, we are doing automation of that. We have created a very special team, only focusing on the future technology, which can help us to install without the manpower. So we are doing that automation and implementing robotics. That's the second thing we are doing. Third thing, we have applied for the patent on the two, three areas. That is also one of the significant improvements by our R&A team, where we will be working on the optimization of the battery, renewable wind. So the beacon provides almost like a base load power. Base load power, similar like nuclear or similar like this one, and much cheaper than thermal or nuclear. So those are the areas ACME always known to work on, and I can assure you will be continuously working and taking it forward.

Operator

On behalf of ACME, Solar Holdings, and Mutilalo Solar Financial Services Limited, that concludes this conference. Thank you for joining us, and you will now disconnect online.