Enviro Infra Engineers Limited (EIEL) Q1 2027 Earnings Call Transcript

Concluded Aug 12, 2026 Audio replay
Aug 12, 2026 1:10:41 124 turns
Period
FY2027 Q1
Runtime
1:10:41
Sources
2 artifacts
Revenue 3.59B INR +49.1% YoY
Diluted EPS 2.27 INR/shares -5% YoY
Net income 398.27M INR -4.9% YoY

Transcript & audio

1:10:41 Audio
Operator

Ladies and gentlemen, good day and welcome to the Enviro Infra Engineers Limited, Q1-FI27-ORIX Conference Call. Before we begin the conference, a brief disclaimer. This conference call may contain forward-looking statements about the company which are based on relief, opinions, and expectations of the company as on the date of the call. These statements are not the guarantees of future performance and may involve risks and uncertainties that are difficult to predict. As a reminder, all participant lines will be in the listen only, and there will be an opportunity for you to ask questions at the end of today's presentation. Should you need assistance during this conference call, please signal an operator by pressing star, then zero on your touchstone phone. Please note that this conference is being recorded. I would now like to hand the conference over to Mr. Manish Jain, Managing Director of Enviro Infra-Engineers Limited. Thank you, and over to you, sir.

Manish Jain Other

Thank you, Manu. Good morning, everyone. I would like to welcome you all to our Q1FI27 earnings call. On call today with me is our investor relation team from AdSectors. We have shared our earnings presentation and press release, and I hope you have had the opportunity to go through it. On behalf of the entire team, I am pleased to share our operational and strategic progress for the first quarter of FY27. Q1 FY27 continue to reflect the transformation that EnviroInfra engineers has been building over the past year. As we strengthen our core position in water and wastewater infrastructure while expanding our presence across renewable energy and better energy storage systems and wind DPC segment. Our water and wastewater treatment business along with our operations and maintenance portfolio remain the foundation of our execution during the quarter. At the same time, our renewable energy platform continue to gain momentum with increasing capabilities across solar, wind, and battery storage. Our focus remains firmly on disciplined execution across all our businesses. In water and wastewater, we continue to strengthen our technical capabilities, expand our geographical presence, And pursue larger and more complex projects in a renewable energy and best we are focused on building a scalable platform supported by our capabilities across solar wind and energy storage. We believe the convergence of water infrastructure, renewable energy and energy storage presents a meaningful long term opportunity for Enviroinfo engineers. As an engineering and technology-driven infrastructure company, we are focused on leveraging technology, engineering capabilities, and execution expertise to address evolving infrastructure requirements. Our priority is to convert these opportunities into sustainable growth while maintaining execution discipline, healthy margins, and prudent capital allocation. Now, turning to our order book and execution pipeline, our total order book stands at approximately 6,721 crore, providing strong revenue availability for the coming periods. The order book comprises to be 3,694 crore in water and wastewater treatment segment and 3,027 crore across renewable energy and best. Within the water and wastewater segment, we have 2696 crore of execution orders and around 998 crore O&M orders, while in the renewable portfolio, we have execution orders worth Rs.1948 crore, while ITP and O&M comprises projects worth 1079 crores. This Divertified Order Book provides us with a strong execution pipeline and allows us to participate across multiple segments of environmental infrastructure and clean energy value chain. During the quarter, we have secured a new EPC and O&M contract worth 113 crore from Sardar's Rover Naranda Nigam Limited in Gujarat. Further extending our water infrastructure portfolio. To our step-down subsidiary, which is Suyo Gurja Limited, we have secured a renewable energy contract worth 207.5 crore for land aggregation and balance of plant works for a hybrid wind and solar project. This further strengthens our capabilities in the renewable energy value chain. And provides additional execution opportunities through the Suyuk load platform. During the quarter, we also secured two hybrid NUT model projects in Varanasi, Uttar Pradesh, under Namami Gange program with a combined value of Rs. 256.9 crore. These include a 60 MLD serious treatment plant at Lota valued at Rs. 130 crore and a 45 MLD serious treatment plant at DDO Nagar valued at 126.8 crore. Both projects have a 18-month construction period followed by a 15-year O&M period. With these additions, our hemp portfolio has now increased to 5 projects, further extending our long-term revenue visibility and the quality of our order book. On the execution and business outlook side, Our focus remains on converting the strong order book into revenue through discipline project execution. Our water and wastewater business continues to remain the core of our operations with execution spread across multiple states and project categories including WWTPs, WSSPs, and ZLD projects. The core water and wastewater treatment segment contributes Good morning, everyone. Approximately 255 crore representing 71% of the consolidated revenue, underscoring its significance to the overall business. At the same time, our renewable energy flow platform is also gaining meaningful scale. During Q1 FY27, renewable segment revenue contributed approximately 104 crore, which is around 29% of the consolidated revenue. Reflecting the increasing contribution of this business to overall operation as mentioned, our renewable capabilities now span, solar, wind, and dust with both EPC and IPP opportunities. We believe the combination of these capabilities provide us with a broader platform to participate in India's ongoing transition towards cleaner and more flexible energy infrastructure. Going forward, our priority remains to maintain execution momentum across existing order book, pursue quality opportunities, and ensure discipline, bidding, and capital allocation. On the financial performance side, for Q1 FY27, revenue from operations is true at 359.2 crore. Registring a growth of 49% Y-on-Y, driven by a continued execution across our order book. EBITDA is stood at 75.7 crore, registering a 17.87 Y-on-Y growth. EBITDA margin is stood at 21.07%, compared with 26.65% in Q1 FY26, and 18.7% in Q4 FY26. The movement in EBITDA margin reflects the current project and execution mix along with the impact of input cost. Profit after test stood at Rs 45.2 crore, registering a 6.47% Y on Y growth, while pack margin stood at 12.38%. Broadly stable, sequentially compared with 12.37% in Q4 FY26. Overall, the quarter reflects strong revenue growth, continued execution momentum, and an increasing contribution from our renewable energy platform. Looking ahead, GC and YRO evolving into an integrated engineering services specialist across various industry verticals, wherein we can leverage our technological and project expertise on a wide range of projects. We remain confident in our ability to execute the existing order book and continue to build a quality pipeline of opportunities across water infrastructure, renewable energy, and best. Our focus for the remainder of FY27 will remain on strong execution, working capital discipline, maintaining healthy margins, and creating sustainable long-term value for our stakeholders. With that, I would like to open the floor for questions.

Operator

Thank you very much, sir. We will now begin the question and answer session. Anyone who wishes to ask a question may press star and 1 on their touchstone telephone.

Saurabh Bhagath Analyst — Individual Investor

If you wish to remove yourself from the question queue, you may press star and 2.

Operator

Participants are requested to use handsets while asking a question.

Saurabh Bhagath Analyst — Individual Investor

Ladies and gentlemen, we will wait for a moment while the question queue assembles.

Aswin Patil Analyst — Intelligent Prosperity Solutions

We have our first question from the line of Raman KV from Frequent Investments.

Naman Jain Analyst — Centrum Broking

Please go ahead.

Operator

Hello, sir. Can you hear Raman?

Manish Jain Other

Yes, you are audible.

Raman K V Analyst — Frequent Investments

Yes, sir. My first question is with respect to the margin side. Our gross margin was lying significantly well. Can you explain what was the main reason between the decline of gross margin?

Manish Jain Other

If you would have seen our earning guidance for current financial year, since the start of this war, the input cost, it has gone for an increase. So there is a slight reduction in our guidance in the EBITDA margins. Earlier, we used to give margin guidance in the range of 22 to 24%. For the current financial year, we have lowered our guidance a bit in the range of 21 to 22 %. The results reflect that the guidance which we have given is in line with the actuals. Our EBITDA margins right now are 21% at the standalone level, and we are happy to confirm that our EBITDA margins have remained at the same level of 21%, even at the console level, where it is getting consolidated with the business of renewables. So, that says that the margin, EBITDA margin, which we expected somewhere in the range of 19 to 20% with the blend of renewables, so we have been in a position to achieve margin slightly better than what was the expectation earlier from our side.

Raman K V Analyst — Frequent Investments

Understood sir. So, basically the decline in margin is primarily because of raw material and not because of the excess competition.

Manish Jain Other

Ah, no. It is because of the increase in the raw material cost, it is one. It is a blend of renewables, second. And third, a lot of development work which was going on in the last financial year, we were increasing our team size since we were getting new projects with a very healthy order book that we do have in for the water and wastewater treatment sector itself as well in in our company. Our employee costs, if you will see, it has gone to an extent of somewhere around 7% in Q1. Which earlier used to be in the range of around 3 to 3.5%. So we expect a prudent level of somewhere around 5 to 5% of the employee cost when we will move ahead in the financial year. And then the finance cost as well, which right now reflects at around 4%, but at a blended level during this entire financial year, when the top line is expected to be in the range of 2000 crore. So we can expect this financial cost to be also to be in the range of 3 to 3.5%. So with this, definitely our margins, fat margins, which are right now looks at 12.5%. So a delta of somewhere around 1.5 to 2% is always visible. So that says the movement in the company is in the right earnest and we are going good.

Raman K V Analyst — Frequent Investments

Understood, sir. My second question is with respect to the order book, you gave a rough split between the water and waste, water EPC business as well as the renewable EPC business. I just want to understand what will be your timeline to execute these projects, and on the OEM side, for how long are we supposed to do on an average, are we supposed to provide OEM to the end user?

Manish Jain Other

First of all, with respect to the execution order book that we do have in our hands, so 2,700 crore is the order book which is available in the water and wastewater treatment segment. The timeline of execution here is 18 to 24 months. So practically, if I say this entire order book of 2,700 crore is to be executed over in a period of next two years. Coming to the renewable side, this total order book of 2000 crore, it is to be executed over a period of 12 to 18 months time. Now coming to operation and maintenance, when we talk about the water and wastewater treatment segment, all the turnkey projects, whether it is EPC, whether it is HEM, all are blended with an operation and maintenance. So this order book do come along with the execution order book at the start itself.

Raman K V Analyst — Frequent Investments

Which spans a period of 5 to 15 years.

Manish Jain Other

So, at an average level of 10 years, we can say roughly around 100 crore can be the top line from the operation and maintenance. The operation and maintenance in itself gives a better EBITDA margin, but the quantum or the value of this operation and maintenance in comparison to execution, that will remain to be in the range of 3 to 5%. Regarding the O&M order book for our renewable segment, it spans out either from the EPC, which is for a period of 5 to 12 years, and then the IPP projects where the IPP income will come over a period of 25 years. So this is how the entire order book will move.

Raman K V Analyst — Frequent Investments

Understood sir.

Operator

I will join back in the EQ. Thank you sir. Thanks a lot. Thank you. We have a next question from the line of Vidisha from C.R. Kothari Answers. Please go ahead.

Vidisha Analyst — CR Kothari

Hello, sir. So, can you quantify the impact of the raw material cost increase that led to the margin decline versus what you said, the project mix? And also, if you can give a split between the segments, the EBITDA margins for solar, wind, and water increasing.

Manish Jain Other

First of all, if I talk about the, this profitability in the different segment, water and wastewater treatment segment, we expect EBITDA margin somewhere in the range of 21 to 22%. And in the renewable segment, which spans over solar, wind and gas, the EBITDA margins shall be in the range of 15 to 18%. So at a blended level, we can expect the EBITDA margins to be somewhere in the range of 19 to 20%. There can be a different split in the wastewater and water segment as well, which is paying over EPC, M, and then the type of water or EPC of serious treatment plants or EPC of common efferent treatment plants. So, this is the blend or the product mix across that quarter, which will drive the right EBITDA margin. So, at a blended level, we can say around 20% is the EBITDA level, which we can achieve in the entire financial year.

Operator

Sorry to interrupt you, Wadi. Your voice is speaking.

Vidisha Analyst — CR Kothari

Hello, my voice.

Operator

No, it's still breaking. Can you please move to a better reception area?

Vidisha Analyst — CR Kothari

Is it better now?

Operator

Yes.

Vidisha Analyst — CR Kothari

So, in the new order that we run, is there an increase in raw material cost, part 2?

Manish Jain Other

The raw material price impact is somewhere in the range of 1 to 2% of the overall top line of the company. So this is what we have accounted for in terms of our guidance of EBITDA margin, which we have lowered to an extent 21 to 22% right now in place of 22 to 24%, which were predominantly available in the previous years.

Vidisha Analyst — CR Kothari

Okay, so the cost will be borne by the company in the new orders as well.

Manish Jain Other

There is a price variation clause in the tender as well, which is linked to WPI and CPI index. There is some price which gets covered with this price variation and some part which we are required to absorb. There was one point of time when we were seeing the war has just ended and things will settle down and then definitely the margin again could have been, it could have improved. But we will have to just wait for it. Some of the price in peace definitely we may have to absorb in our EPC price itself.

Vidisha Analyst — CR Kothari

And just lastly, what was the contribution of wind revenue from wind segment? And in renewables, can you give us split ONM and EPC?

Manish Jain Other

Yeah. Wind segment in Q1 has contributed 80 crore out of 359 crores. And the revenue, this order book is basically 2000 crore execution order book in renewables. And around 1000 crore O&M and IPP revenues order book in the renewables segment.

Vidisha Analyst — CR Kothari

That's it for mine. Thank you, Naldemir.

Operator

Thank you. Thank you. We have our next question from the line of Sudeep Anand from Systematics. Please go ahead.

Sudeep Anand Analyst — Systematics

Yeah, good morning, sir, and congratulations for a good set of numbers. Just a few questions. One, sir, we have seen that our overall profitability got impacted because of the higher interest cost. So, I know this is largely because of the IPP, but what could be the peak date we are looking at based on the current order book that we have to execute?

Manish Jain Other

Good morning, Sudeepji. Basically, profitability has got impacted because of one is, as I explained, it is the cost impact since the prices have gone for an increase. There is a blend with renewables, but fortunately, at least for this quarter, there is no downside, which we see from the renewable order book, which we have executed in the current quarter. So the total revenue mix, the profitability, as we will go further in this financial year. Oh, the revenue right now is somewhere around 20% as we see in the guidance in the first three quarters, it remains to be somewhere in the range of 20, 20, 20. And the last quarter accounts for around 40% of the overall revenues in the financial year. So as we will move ahead, the The cost, the indirect cost which is employee cost or finance cost which will get reduced as a percentage of sales. So, the profitability is expected to improve slightly.

Aswin Patil Analyst — Intelligent Prosperity Solutions

Right. Okay.

Sudeep Anand Analyst — Systematics

And So, can you just give some more color on the bidding pipeline in both the water segment and the renewable, and what could be the exit, FI27 exit order books that you are looking at?

Manish Jain Other

Presently, the projects for which the bids are already submitted and for which the evaluation is going on, it is somewhere in the range of 3000 crore. Apart from this, there is a robust pipeline, which is available in form of bidding. So we are looking for projects somewhere in the range of 6,000 to 7,000 odd crores for which bids have already been invited and we will be submitting our bids. So this way the order book pipeline in the water and wastewater treatment segment remains to be very bullish. In the renewable segment, since the order book is already at a very decent level for the current financial and we see the next financial year as well. So we are not going big at all in the renewable segment. Rather, our focus will be first to go for execution. In solar, wind, BES, all-sea segments, and then we can look forward to a further increase in the order book. Nevertheless, we expect some good orders in the wind EPC segment, wherein we are looking for some good projects of around 600 to 800 crores further getting accumulated in the company.

Sudeep Anand Analyst — Systematics

Okay. Thank you. Thank you so much, sir. Thank you. And all the best. Thank you.

Operator

A reminder to all participants, if you wish to ask any questions, you may press star and 1. Anyone who wishes to ask a question may press star and 1 on their touch-tone telephone. Next question is from the line of Nanan Jainishra from Centrum Broking. Please go ahead.

Naman Jain Analyst — Centrum Broking

Yeah, thanks for the opportunity. Sir, what is in terms of balance sheet, what is the status of disable or unbilled revenue as I present?

Manish Jain Other

I will say the position is not improved right now. The position is still, I will say it's bloated, but we are hoping since the funds are already allocated, even in the last quarter, we had confirmed the movement of funds should be there, but it remains slow. It remains low. The working capital cycle still remains loaded. I don't have the exact numbers or I cannot see the numbers which are there. But it is there. But by September when we will come out with our cash flow position, I am quite sure that we'll be sitting at a healthy cash flow level. Still, what I will say is the cash flow position in the company that is stable. We are able to meet all our liabilities well in time, there is no slippage at all with respect to any of our liabilities. There is a slight slowdown in the cash flow receiving from the government clients, but we do hope the cash flow cycle will improve.

Naman Jain Analyst — Centrum Broking

Okay, so with respect to the CEO, Gurja, The second tranche investment for the beginning 25%, so when do you expect it will complete and what is the target revenue for this year and what is what kind of pipeline you are looking in terms of order book?

Manish Jain Other

The total acquisition which we did in Suyo Burja limited, the total acquisition value was 311 crores. The first range of 111 crore has already been paid. The second range of 100 crore will be paid after FY27 sometime July. So it will be based on the KPIs which we have seized in terms of the revenue, the bottom line, and the order book which will be available. So there can be a slight increase or decrease in the amount of payments that will be paid at that point of time. It will be paid through a mix of internal accruals and some debt which we will take as the acquisition funding. At least at present, 80 crore is what Suyog has done in the first quarter. Our expectation is in the range of 400 to 450 crore what we will do as revenue from Suyog Urja Limited. In terms of order pipeline, the present order pipeline in Suyog Urja in Wend APC is somewhere in the range of 800 crore and we do expect another 500 to 600 crore projects. Which will come in when DTC segments for this financial year.

Naman Jain Analyst — Centrum Broking

And margin in this segment is close to 14-15%?

Manish Jain Other

If I talk about EBITDA margin, these are in the range of 15-16% at pet level I will say it is 12% plus which we can do.

Naman Jain Analyst — Centrum Broking

Okay, okay. So, I mean, this year FY27, we will consider it in terms of profitability about 51% more and the 75% impact in terms of profitability will come in FY28, right? When we complete the second term subject to achieving the revenue target of FY26 or order book target. That is the right?

Manish Jain Other

FY28, after FY28, it will be third branch. So, there were three branches, first branch already pitched, second branch after FOI 27, third branch after FOI 28.

Naman Jain Analyst — Centrum Broking

So, keyword number we are on track to achieve whatever target we have set. Yeah, yeah, yeah, we are well on target in this. Okay. Okay. That is all for me sir.

Operator

Thank you. Thank you. A reminder to all participants, if you wish to ask any questions, you may press star and 1. Next question is from the line of Aswin Patil from Intelligent Prosperity Solutions.

Aswin Patil Analyst — Intelligent Prosperity Solutions

Please go ahead. Thank you for the opportunity.

Sudeep Anand Analyst — Systematics

I want to ask you, sir, looking ahead to F.28, do you see any possibility of margin moving to a structural higher level from the current 20 to 20% range?

Manish Jain Other

There is always a possibility of improvement but when we give any of the guidance, it is based on a surety level that the minimum margins which will be achieved. So at a blended level where we talk about water and wastewater segment and then the renewable segment as well. So we look forward to EBITDA margin in the range of 19 to 20%. Then these are the EBITDA margins I have already explained. In the water and wastewater treatment segments, we expect it to be in the range of 21-22 and in the renewable segments 15-18%.

Aswin Patil Analyst — Intelligent Prosperity Solutions

Okay, okay.

Manish Jain Other

Thank you.

Operator

Thanks, Manila. How much? Thank you. We have our next question from the line of Ankur Shah, an individual investor. Please go ahead.

Ankur Shah Analyst — Individual Investor

Hi, I hope I'm audible. So I have a quick question for you as an individual investor. Last year, there was a massive delta between what the management committed and what was achieved. I think we gave over about 7% year on year target. How confident are we this year in terms of execution and achieving the top line guidance of what you've been providing? And my other question is that are we chasing growth at the cost of margins? Or is it the genuine case where you mentioned the raw materials and the employee costs have gone up, which has significantly impacted your bottom line? And I just want some clarity over there.

Manish Jain Other

Let me explain how the last year had panned out. At the start of the last year, we were going ahead with an order book in hand, which was approximately 1200 crores. So if I would have given any guidance based on that number, 50 to 60% conversion, the total revenue guidance could have been in the range of around 600 crores. However, a lot of projects were there for which the bids were submitted and we were expecting the results. The result started coming, but the order book accumulation, the process remained a bit slow. So, during the entire financial year, we expected the order book which swell and then the revenue from the respective order book that will also increase. However, that was not the case and that didn't come through. Our total revenue guidance, now if I say as a percentage of the starting order book, it is more than 95%. So, that means I will say company has not done bad at all. Now, in terms of the EBITDA margins, our guidance has never been higher than 22 to 24%. We are one of the companies where we are in a position to maintain that level of EBITDA margins, expecting margins even more than that. At least I have not never given that level of guidance. And what we could foresee is that the margin could increase as a as a measure of efficiency levels that we never rule out or as a measure of the product mix. Now, coming to the current financial year, based on the best pipeline, which was available with us, we are sitting on a very, very healthy order book, at least at present. Our water and waste water treatment order book in itself is more than 2700 crores. And then the renewable segment guidance. When we look forward to the achievement of the top line and the bottom line, there is an investment of 75 crores which we have done in the renewable segment. And if we see the profitability which will be coming out of it and we understand the ROE levels, ROE levels if you see our guidance of around 700 crore and if we are able to achieve a profitability from the renewable in the range of around 60 to 70 odd crores, you can just imagine the type of ROE that we can get from that segment. Now coming to water and wastewater again, basically at this healthy order book, we have maintained a conservative conversion rate of 50% and we are expecting 1300 crore to be our top line. So we look forward to maintaining our guidance. There has been a slight increase in the input cost, the development which happened in the last year. If you could just see to our presentation at the time when we had gone public, our total team size was around 900, which has now increased to 2300. It is just because we were getting the order and we wanted our team to be there so that we can execute the project as we are doing very efficiently and in a time bound manner. So, that means, at one point of time, our costing has increased slightly in terms of the employee cost. We do understand when we will go ahead and we will complete this financial year, as a percentage, definitely, these costs will come down. It will reflect on the improved profitability. However, our guidance will remain in the range what we are projecting and we do hope that this year the guidance is based on the availability available order book and we will be able to maintain the guidance.

Ankur Shah Analyst — Individual Investor

Thank you, sir. Best wishes.

Operator

Thanks a lot. Thank you. A reminder to all participants, if you wish to ask any questions, you may press star and 1. Anyone who wishes to ask a question may press star and 1 on the touchstone telephone. We have our next question from the line of Manish from Keynote Capital. Please go ahead.

Manish Analyst — Keynote Capital

Hi, sir. I just have two questions. One question is on JJM. So, what are the receivables we have from JJM mission and any update on JJM 2.0? And the second question is on our cash flow. So, are we going to be a cash flow CFO positive in H1 balance sheet?

Manish Jain Other

First of all, talking about the JGM, as we have already mentioned in our all previous interactions, JGM constitutes very, very small percentage in our order book or the receivable segment right now. There was only one portion of the order book which we took in MP and then we continued our execution. At present, that trial and commissioning part is going on for which 15 to 20 odd crores is what we bill and then the payments get released. If we talk about the JGM side as a whole, as we understand JGM and JGM 2.0 right now, these are now streamlined and the funds are releasing. Fortunately for us, we were working in MP and the funds didn't get stalled even in the last financial year and we were moving smoothly under JGM projects as well. So, the total component of JJM either as unbuilt receivables or as order book to my understanding will not be more than 150, 160 odd crore in our total balance sheet. Coming to see this operational cash flows, operational cash flow definitely looks to be On our positive side, even in the last two financial years, if we take into account the service concessionary receivable, which is a part which is receivable over a period of 15 years, and it is taken up in the operational cash flow activities itself, and it goes negative by somewhere around 85 crores. But even as, as per the audits, what we do, we do expect that cash flow, operational cash flows should turn positive. We do hope, but we cannot give any guarantees on this. We are hoping a lot of funds which are going to be released shortly based on that OCF should turn positive.

Manish Analyst — Keynote Capital

Okay, and we stick to our guidance of EBITDA margins and FAT margins that was given in last quarter. So, that is around 21% or 21 to 22% in EBITDA and FAT was somewhat around 13.5 to 14% for this year. So, do we stick to that guidance?

Manish Jain Other

This guidance is for the revenues from water and wastewater treatment segment. So, on a standalone basis, these will maintain our guidance. At a blended level, the EBITDA margins could be in the range of 19% to 20% with profitability in the range of somewhere around 13% to 14%.

Manish Analyst — Keynote Capital

Alright, that's it, Pumat. Thank you.

Operator

Thank you. A reminder to all participants, if you wish to ask any questions, you may press star and wad. We have our next question from the line of Raman from Sequent Investments. Please go ahead.

Raman K V Analyst — Frequent Investments

Hello, sir. Can you hear me?

Naman Jain Analyst — Centrum Broking

Yes, you are on again.

Raman K V Analyst — Frequent Investments

So, my question is with respect to wastewater treatment ham project. We have around 400 crores of order. On an EPC basis, you said the order execution in wastewater segment lies between 18 to 24 months. So can you specify how much time will it take for our HAMP project to be executed? One is that. And second, on the water supply project, we have a very small order book from that side, 100 crores. So, will that be executed in this year or I just want to understand the execution cycle for this water supply project. Is it like a quarterly basis execution cycle or is it like a, again, one or two years execution cycle for this?

Manish Jain Other

Uh, first of all, uh, with respect to the HEM projects, uh, in case of a HEM project, there is a process, uh, paired to defining or declaring the effective date. Effective date, uh, specify the start of physical execution of the project. Prior to which there are certain condition precedent which are required to be fulfilled on all parts. All part means it is concessionaire. In our case, the funding agency is NMCG and the department with whom we are executing this project is UP Jalnegan. So all are required to have their condition precedent satisfied. The general timeline once a project is awarded. It is five and a half months. One and a half months for the creation of SPV and then another four months for completing the design and drawing and in that particular time to achieve the financial closure. After that, the execution period ranges between 18 to 24 months as the projects have been awarded to us across these 500 projects. So, the timeline will move like this and once after the construction completion, there is a 3-month timeline for the stabilization of plant and to achieve COD. COD is the commercial operation start date by which we achieve the performance guarantee. Based on which that plant has designed and once the COD is achieved, the 15-year operation and maintenance is start during which the operation and maintenance payments along with the annuity along with interest that is released on a quarterly basis. Now coming to the water treatment order book under JGM, which is somewhere around 100 crore in our book. We expect that this entire, it's a small portion of this 1200 crore order book, which we were executing. And we are expecting that this particular order book will be completed within this financial year. And once this gets completed, the operation and maintenance of 10 years that will commence. There are total five projects. The five projects will get commissioned one by one. Out of which, first of the project is where we do expect that by October, the commissioning will be recorded and the operation and maintenance will commence. So this is how this water site, this order book will move further.

Operator

Thank you, sir. A reminder to all participants, if you wish to ask any question, you may press star and one. We have our next question from the line of Sheetal Shah, an individual investor. Please go ahead.

Sheetal Shah Analyst — Individual Investor

Am I audible, sir?

Operator

Yes, audible.

Sheetal Shah Analyst — Individual Investor

Very good afternoon, sir. If I remember correctly, sir, in the last con call, you had guided for a revenue of consolidated revenue of 2000 crore in FY27. And a net profit of around 260 to 270 crore in FI 27. Am I right, sir?

Manish Jain Other

100% right.

Sheetal Shah Analyst — Individual Investor

So, sir, as per our history of execution, sir, Q1 constitutes around 21% of our total turnover. So, if we follow this, our turnover should be in the range of around 420 or 25 crore, sir. But this quarter we delivered around 360 crore. So my question is, sir, what was the reason of this lower than expected execution? And do you still speak to your guidance of around 2,000 crore turnover in FI 27, sir? Yes, you can continue, sir.

Manish Jain Other

She said, first of all, as our guidance, when we say 20% should be the top line, there is a delta of 1 to 2% on either side, which is possible. So if I say, if we have achieved 360 crore as the top line during this quarter, then we are well on target. Let me tell you the reason for this. There we do have some best projects from NTPC which is a 3930 megawatt hour project that this procurement of the materials for against this particular order that will commence in Q3. So there will be a significant jump Q3 and onwards when the top line will, it is likely to swell. So we are well on target of achieving this 2000 crore. We don't find any slippages. Wherever we have given our guidance, whether it is renewable, a combination of that solar, IPP, or BES IPP, BES EPC. So, we are well on target. We are in a position to achieve that top line of 2000, and we stick to our guidance of 260 to 270 crore fat levels.

Sheetal Shah Analyst — Individual Investor

Very nice to hear from you, sir. Sir, my second question is regarding the order intake, sir. Can you please tell how much order you have bidded in this quarter, sir? And what is your strike rate, sir? Or I may even say, how much order info you expect in FI27, remaining part of FI27?

Manish Jain Other

First of all, our present bid pipeline for which the evaluations are already undergoing, these are somewhere in the range of 3000 crores, another 6 to 7000 crore projects are available for which bidding is going to happen in a short time, which are already invited and the bids are being submitted. The strike rate of company in the last financial year has been in the range of somewhere around 20%. So, we can expect an order book, an order inflow of somewhere around 2,500 crore to be there in the current financial year. This was our guidance as well. And now if I say out of this 2500 crore 256 crore is what we have got in the current financial year till now. There are two hemp projects at Varanasi, totaling 256 crores. So, we do expect that 2250 crores that we expect to get in the current financial year. We are well on target, and we look forward to achieving this guidance again.

Sheetal Shah Analyst — Individual Investor

Okay, very nice to hear from you, sir. And my, sir, other question is, sir, regarding receivable, you highlighted that there is no problem, but your receivables, working days are bloated, if I heard properly, sir. So, do you think by September it will be cleared, sir, or there will be no bad debts or anything you foresee?

Manish Jain Other

First of all, there will be a prudent working capital cycle. So we want ourselves to get shifted to the prudent working capital cycle. We are definitely hoping that the funds will flow from the government side and the working capital cycle will get eased out. This is one part. Second part is with respect to the cash flows which are available with the company. Even at present, even with the bloated working capital cycle, the company is having a significant unencumbered funds available. So that way we are comfortable, we are completing our projects, we are making the payments well on time. So there is no hindrance or any slowdown anywhere. In the history of the company, there have never been any bad debts, and we continue to maintain debt levels in future.

Sheetal Shah Analyst — Individual Investor

Okay, sir. And last question from my side.

Operator

Sorry to interrupt you, Ashit. May I please request to be rejoined with you?

Sheetal Shah Analyst — Individual Investor

Only one question, sir. If I pause, only last question.

Operator

Okay.

Sheetal Shah Analyst — Individual Investor

Thank you very much, sir. Last year, we had a problem in execution as we could not get the order in time. So, we were not able to meet our target. This year, we have order in hand. So, I just want to reiterate, sir, do you foresee any other headwinds which may not allow us to achieve this target? Do you foresee any headwinds, sir?

Manish Jain Other

In case of an EPC company, The top line is a derivative of the order book available order book. So we were going a bit aggressive and we look forward to that the order book would increase significantly in the initial months and then we will be in a position to execute against that order book, which is not the normal industrial norm. However, if you look into the revenue in comparison to the order book available at the start of the financial year, then the conversion rate is in the range of around 90-95%. So, that never says there is any slowdown at all with respect to the execution. Execution has always been the key forte of the company and their entire controls are available. We don't foresee any slippages. Current financial year, the order book is already available. We are well on it. So, we can keep on moving and even if no new order comes, then this top line of 2000 crore is what we can easily achieve from the current order book available with us.

Sheetal Shah Analyst — Individual Investor

Very nice of you, sir. On behalf of all our small shareholders, I wish you all the best to achieve your target this time, sir. Thank you very much, sir.

Operator

Thanks a lot. Thank you. Ladies and gentlemen, in order to ensure that the management is able to address questions from all participants in the conference, please limit your questions to two per participant. Should you have a follow-up question, we request you to rejoin the queue. I repeat, please restrict yourself to only two questions per participant. Next question is from the line of Vidisha from CR Kothari Answers. Please go ahead.

Vidisha Analyst — CR Kothari

Hello. Any revenue guidance for this year?

Manish Jain Other

The revenue guidance is 2,000 crore for this financial year.

Vidisha Analyst — CR Kothari

Thank you.

Aswin Patil Analyst — Intelligent Prosperity Solutions

Thank you.

Operator

We have our next question from the line of Saurabh Bhagath, an individual investor. Please go ahead.

Saurabh Bhagath Analyst — Individual Investor

Why do my question have been answered in the previous one?

Operator

Thank you. We have our next question from the line of Saurabh Bhagath, an individual investor. Please go ahead.

Saurabh Bhagath Analyst — Individual Investor

Hi, this is Saurabh Bhagath. Basically, Thank you very much. I have invested in this company since last two years. Last time, actually, we used to get the orders in the same year, and we tried to execute some of the orders in the same year, so that actually the revenue visibility was there. Now, this 2,000 crore revenue guidance, we already have the orders in hand. What is the best strategy we can have over the month that, okay, we can execute much more or get the revenue of around, let's say, $2,500 or $3,000? What do we need to do? Because previously, we used to do it, let's say, we get the order this year, and we try to execute and get some portion in the revenue side. Is it like, is it the same case or the story got changed? Now we are so conservative in guiding our revenue because last year we missed it? Or still we can assume like North Star's guidance like 2,500 or 3,000 crore revenue this year itself? Even like we used to do it in two years back or one year back.

Manish Jain Other

Aroji, then whenever we give any of the guidance, so we do expect that we will meet at least this threshold level. So for this financial year, that threshold level is 2000 crore based on the availability of orders that we had at the start of the financial year. Out of the 2700 crore order pipeline with the execution period of two years, so 50% is the conversion which can be expected out of that order book. So 1300 crore, 1350 crore is what we do expect on a straight line basis. What happens is whenever we move on for the execution of the projects, there are certain projects which are just on the verge of start. There are some projects which are in a growth phase. There are some projects which are under execution. So there are different stages of the project wherein we cannot predict how the project can move. So as a ratio since the size of the company at one point of time, we used to be 500 or 700 odd crores. So that movement seemed to be quite fast. But now at a blended level, when we say, so blended level, first we look forward to the guidance, which we give. So that guidance should meet. And then we would like to outdo that guidance as well. You rightly said what we can do to increase our top line to 2500 crore or 2700 crore. I just explained during the last financial year, though our top line was slattish, a lot of development work was going on in the company. It was in terms of team building. It was in terms of getting the new orders from the water and wastewater treatment segment. We were integrating into renewables. We acquired some assets of solar. We bidded for this best project and we won projects from NTPC, best EPC projects. Then we acquired this IPP project, then we acquired solar, this wind ETC company, which is Suyo Burja. So a lot of development has happened in the last financial year, the results of which will accrue in the current financial year. 2000 crore is the guidance which we understand we will achieve at any cost. We look forward to out doing that number as well, but as a guidance, I will maintain that level at 2,000 crores right now.

Saurabh Bhagath Analyst — Individual Investor

Second question is like a decennation plant and the export opportunity overseas opportunity. Are you going looking at these two opportunities? Because your competitors are going in those two opportunities.

Manish Jain Other

In the previous concourse, if you would have heard, we were maintaining that we will go for the geographical expansions, we will go for the higher value projects, higher capacity projects, then we confirmed we will wait for some of the CBG projects or biogas to electricity projects which we were executing as a part of our STP projects. And then ZLD. So, now if I talk about basically geographical expansion, now we are available in 17 states. ZLD, yes, last year we got one of the ZLD projects which we are executing in Maharashtra for a textile area, Ichal Karanji, Lakshmi and Parvati near Kolapur. Our projects of biogas to electricity and CBG projects, two projects have been completed and commissioned. Now we have entered into one CBG project from the agricultural waste, which we are doing as a part of developing a cattle feed shelter, cattle shelter in Ampi. Here we have got a vast land of around 275 acres, where we will be developing the cattle shelter, their feedstock will be there, agricultural residue in form of napier grass will be there, and we will develop a solar farm as well. So this is how we have integrated ourselves over the period. Going forward, we have already submitted bids overseas. We are waiting for the outcomes and we are again looking forward to some diesel projects as well. So if we see by the end of this financial year, the overseas project and the desalination project should also be there in the company's role.

Operator

Thank you. We have our next question from the line of Daksha Malhotra from Adhrib Global. Please go ahead.

Daksha Malhotra Analyst — Adhrib Global

Yeah, good afternoon, sir. How are you?

Manish Jain Other

Good afternoon. Good. How are you, Daksha?

Daksha Malhotra Analyst — Adhrib Global

Very well, G. Thank you. It says F526 was a tough year for EPCE and no doubt, you know, we'll have to appreciate why we were not getting. Enough tenders and orders in the water waste water, we did quite well in diversifying our business and getting into the renewables and different parts of renewables decently well. Now, sir, just two principal questions. One is on the water, wastewater, how is the pull? The projects that we are bidding for, especially the government project, Amrut and all, we are not getting payments on time. But how is the pull? Is the EPC, you know, the project condition improving? From where it was, or is it still a little slow from the government departments as far as the new ordering as well as payments are concerned? And on the, you know, on the same question, in the next, you know, two, three years, we have opened up our... Thank you. And naturally to do it, we have expanded our team, added employee cost and all that also. So just with a two, three year horizon, sir, if you can shed some light on how things are looking and what are your beyond F by 27 targets, maybe 28, 29, 30. Yeah, that would be helpful.

Manish Jain Other

First of all, outlook with respect to water and wastewater treatment segment. I would say there is a lot of traction which is happening in this particular segment itself in terms of projects coming under Amrutu or the projects from Namami Gangay and the projects from state government tying up for loans from World Bank or ADB or Zika. So there is a lot of traction and as I confirm almost around 7000 worth of crore of projects are available where we do have our keen interest and we are bidding for these projects. The order the bidding pipeline may be much larger than that. I am talking about the bid pipeline where we do have our interest. So that's...

Daksha Malhotra Analyst — Adhrib Global

Sorry sir, this 7000 crore is purely water?

Manish Jain Other

Not, when you say water, basically it is, I am not predominantly available in the water segment, rather I will say wastewater, so it will be sea waste treatment plants or common effluent treatment plants along with infra. It is all, I am not talking about renewables right now.

Daksha Malhotra Analyst — Adhrib Global

Okay, okay. So, this 7000, the pipeline is wastewater, not renewable, not empty jobs. Yeah, yeah, yeah. Right.

Manish Jain Other

So, that says we can have a very healthy order book going forward as well, and a lot of work is happening in this segment. Now, going further, since diversification remains one of the key factors if we have to maintain the level of growth, so the diversification in the water and wastewater treatment sector, how we did it, it was through the geographical expansion first in India. Now, we are looking forward to the opportunities in the overseas market as well. Then the next segment which we entered into was G-Cell. There is a lot of opportunity which is coming up in India in terms of reuse of water from the Seavis treatment plants. That will be one of the biggest opportunities which will get opened up. So ZLD, then this reuse of water and some desalination projects where we do have our keen interest and we are looking forward to building some of the projects with some joint ventures. This is how the diversification in the water segment will continue and we will move forward. Now coming to the renewables, again the diversification that is the need of the hour, that is why we entered into renewables, we invested a small chunk of fund into that renewable. Within first year, we have built it up to a sizable company. Now this the acquisition of Wend ETC company which we did it has integrated us across the entire chain of renewable which is solar, Wend and then Bess. So once this execution till this point of level the order book which is available with us that completes. We can move forward as a developer as well. We can look forward to the hybrid opportunities in this segment. So, that opportunity and the availability of opportunities, that will be very, very high, at least for Enviro. And that is how we look forward to, we'll keep on growing. TVG was also one of the segments, basically, which is getting derived from the wastewater treatment segment itself. So, we are also concentrating on it because it can create a good value chain. So, this is how we are trying to integrate across different segments.

Daksha Malhotra Analyst — Adhrib Global

Right. So, sir, combining all these three, just... Sorry to interrupt you, Daksha.

Operator

May we please request you to rejoin the queue?

Daksha Malhotra Analyst — Adhrib Global

No, this was a part of the original question. I think this is continuing that part, no? Just two, three years. Where do we see ourselves combining these three? What is the envision in the next two, three years? Where do we see the, you know, top-line trajectory, margin trajectory? Just... Thank you. How do we see the picture painting, you know?

Manish Jain Other

We look forward to a continuous growth of somewhere around 25-30%. It should be their minimum at which the company should keep on growing and with maintaining the healthy margin levels. I think our EBITDA margins and PET margins, even with the renewables entry, have been at a very decent level, and we expect and we will continue to foresee that our margins remain good. We are not inclined to go for the projects where the margin profile goes low, and that will be our key area where we will see that the margin profile should get maintained.

Operator

Thank you. Daksha, we request you to thank you for any further queries. We have our next question from the liner. Raman from Sequel Investments, please go ahead.

Raman K V Analyst — Frequent Investments

Hello. Thank you for allowing me to ask a follow-up. Again, on the hybrid HAM project with respect to wastewater treatment, I just want to understand that you mentioned that you will float a SPV and then it will be exhibited over the next five months post the SPV. So, you also mentioned in the opening remark that you want to focus more on HAM projects going forward. So, can you also give a bid pipeline with respect to only HAM projects where you are bidding?

Manish Jain Other

At least at present, we have submitted our bid for two more HEM projects. We are expecting some HEM projects which will be available for bidding in next three to four months time since the DTRs are just on the move. So at least at present, we do have two projects for which the bid evaluations are underway.

Raman K V Analyst — Frequent Investments

And this 400 crores of project is, is this a one project or is it like a multiple project?

Manish Jain Other

Uh, there are total of five projects, uh, under him, uh, which we have got one project is completed. Second project is just on the verge of completion, which is at Mathur. Third project is at Saharanpur, uh, for which three milestones have been completed out of it and it is moving ahead of time. These two projects are new ones and for which the work shall come in sometime in the month of October and November, at least at present as we expect.

Aswin Patil Analyst — Intelligent Prosperity Solutions

Understood, sir. Thank you.

Operator

Thank you. Ladies and gentlemen, due to time questions, that would be the last question of the day, and I now hand the concepts over to Mr. Manish Jain, Managing Director, for closing comments. Over to you, sir.

Manish Jain Other

Thank you for your continued trust and interest in environmental engineers. We remain focused on disciplined execution, sending our poor water and wastewater business. And scaling our renewable energy and best platforms. With a healthy order book and expanding capabilities, we remain committed to delivering sustainable growth and creating long-term value for our stakeholders. Thank you once again for joining us today. Thank you.

Operator

Thank you. On behalf of Enviro Infra Engineers Limited, that concludes the conference. Thank you for joining us and you may now disconnect your lines.