Good afternoon and welcome to Applied Digital's Fiscal First Quarter 2027 Conference Call. My name is Pascal Behrman and I will be your operator today. Before this call, Applied Digital issued its financial results for the Fiscal First Quarter ended August 31, 2026 in a press release, a copy of which has been furnished in a report on Form 8K filed with the Securities and Exchange Commission, or SEC, and will be available in the Investor Relations section of the company's website. Joining us on today's call are Applied Digital's Chairman and CEO, Wes Cummins, and CFO, Saidal Mamand. Following their remarks, we will open the call for discussions. Before we begin, Matt Glover from Gateway Group will make a brief introductory statement. Mr. Glover, you may begin.
Thank you, Pascal. Hello, everyone, and welcome to Applied Digital's fiscal first quarter 2027 conference call. Before management begins, we would like to remind everyone that some statements we're making today may be considered forward-looking statements under securities laws and involve a number of risks and uncertainties. As a result, we caution you that there are a number of factors, many of which are beyond our control, which could cause actual results and events to differ materially from those described in the forward-looking statements. For more detailed risks and uncertainties and assumptions relating to our forward-looking statements, please see the disclosures and earnings release and public filings made with the SEC. We disclaim any obligation or undertaking to update forward-looking statements to reflect circumstances or events that occur after the date the forward-looking statements are made, except as required by law. We also discussed non-GAAP financial metrics and encourage you to read our disclosures and the reconciliation tables to the applicable GAAP measures and earnings released carefully as you consider these metrics. We refer you to our filings at the SEC for detailed disclosures and descriptions of our business, as well as uncertainties and other variable circumstances, including but not limited to risks and uncertainties identified under the captioned Risk Factors in our annual report on Form 10-K and our quarterly reports on Form 10-Q. You may access Applied Digital's SE filings for free by visiting the SEC website at www.sec.gov. But I'd also like to remind everyone that the call is being recorded and made available for replay via a link in the Investor Relations section of Applied Digital's website. I'll turn the call over to Applied Digital's Chairman and CEO, Wes Cummins. Wes.
Thanks, Matt, and good afternoon, everyone. Thank you for joining our Fiscal First Quarter 2027 Earnings Conference Call. as we begin fiscal 2027 i'd like to provide an update on our vision our strategy and most importantly our execution today we have approximately 36 billion in contracted revenue across five campuses three states and two very different geographic regions of the country our focus is on converting our contracted portfolio into sustainable profitable growth while continuing to selectively pursue new opportunities across our expansive land and power portfolios during the past year success was primarily measured by aggressively growing our portfolio of campuses and our total contracted value associated with those campuses over the near to medium term we expect to continue expanding our existing campuses and selectively adding new locations with a strong focus on execution and bringing contracted capacity online for our customers over the next 12 months we expect to place over 600 megawatts into service versus the 250 megawatts over the past 12 months let me turn to our vision and strategy which remains unchanged our goal is to become the category leader in design build deployment and operation of our purpose-built ai factories achieving that requires us to balance several things well selecting the right customers matching those customers with a funding strategy that optimizes our financial returns and executing consistently on our builds we believe we are well positioned to do all three. We have a proprietary and proven data center design that has gained acceptance by the leading top-tier hyperscalers. We have a well-honed supply chain, deep energy partnerships, and a demonstrated ability to deliver on our lease commitments. Importantly, our data center design is different from many of our competitors. Some competitors' facilities are designed primarily around the typical five- to six-year lifecycle of a GPU. We've taken a different approach and are building for the long term with 30-plus year horizons. We believe our AI factories are designed to be substantially more adaptable as compute architectures, network configurations, and electrical and mechanical requirements evolve over time. Our design and our investment strategy are based on a set of core principles intended to extend the useful life of our AI factories and campuses well beyond any single generation of compute architecture that matters because we believe the customers signing long-term leases with us expect these facilities to continue serving their needs well beyond the initial lease term as a result we believe our design and build strategy together with our franchise model are highly differentiated and will generate outsized returns for our stockholders over the long term our primary focus remains straightforward build large sustainable ai factory campuses and sign durable high quality long-term contracts we target taker pay contracts of at least 15 years with proven tier one investment grade hyperscalers that are leaders in the ai industry and are well positioned to convert their investment into sustainable and profitable growth we view our customers ability to convert their ai investments into durable and sustainable earnings as an important metric as we make decisions on who we will build for This is a relatively narrow group of customers who represent enormous demand and significant long-term spending potential. These customers have told us that they value our quality of design, the quality of our builds and the strength of our world-class team. In addition to signing new contracts, one of our priorities is to continue to expanding our existing campuses. We also see opportunity to capture premium pricing as demand grows and we realize the economies of scale inherent and large ai campus developments we have continued to make progress on expansion opportunities with our existing customers while also advancing discussions around additional campuses we currently expect approximately 250 megawatts of expansion leases to be executed by calendar year end and materially higher pricing compared to prior leases as we continue to expand our existing campuses and seek to lock in premium pricing we believe these campuses contain significant and underappreciated embedded value. We expect that value to grow over time as we execute against our contract portfolio and focus on delivering outsized long-term returns to our stockholders. I'd like now to turn to our execution in North Dakota, where we are currently building multiple AI factories across three campuses. North Dakota is our largest operating region and remains core to our strategy. We have repeatedly said it's low cost of power, abundant energy resources, low population density, and favorable climate make it one of the most compelling regions in North America for large-scale AI factory development. We expect additional tier one hyperscalers to recognize those advantages over time. It is also the place where we have made the majority of our investments to date, both in the campuses we are building and in the communities with which we have partnered. Power remains the single largest gating factor in our industry and north dakota is one of the few regions where we believe new generation can be added at meaningful scale speaking to that scale we recently took a step a significant step in expanding our power position in north dakota by entering into a long-term power purchase agreement with base electron an independent power producer in which we hold an approximate 10 percent equity stake the agreement covers an approximately 1200 megawatt natural gas facility that base electron is developing in center north dakota adjacent to our polaris forge three campus with deliveries expected to begin in 2030. this is exactly the kind of outcome our model is built to produce while many operators are waiting in interconnection queues for capacity they do not control we are contracting for dedicated generation at the scale of our campuses with an agreement that can follow our tenants and a timeline aligned with our future development needs we believe this dedicated supply substantially strengthens our ability to expand our North Dakota campus on our own timeline rather than the grids and gives us greater visibility into the power resources that will support our future growth in the region. To put the pace of our execution in North Dakota in perspective, we signed our first lease with Core Weave in May of 2025 for our first two buildings at Polaris Forge I, the first of which was then under construction. By the end of calendar year 2025 the first building was fully operational capable of supporting more than 40 000 liquid cooled nvidia gb 300s the second building which broke ground in summer 2025 became operational approximately one year later as of today we have achieved full ready for service or rfs across our first two buildings that are polaris four to one campus with our third building progressing on schedule the operational buildings encompass 10 data halls and are supported by 250 megawatts of critical IT load. This represents 150% increase in delivery capacity. At Ellendale alone, we believe we are substantially ahead of our closest competitors in delivery capacity. And with the expected initial operation of our Harwood North Dakota campus, we anticipate having 300 megawatts of total critical IT online across North Dakota by the end of this calendar year. We believe this level of delivered capacity places us among the leading companies in our category regardless of geography. In the United States beyond North Dakota, we are developing campuses with substantial expansion potential in Louisiana and Alabama. These markets offer compelling characteristics including access to power and strong state and local support for the build-out of national AI capacity. We view the presence of other top-tier hyperscalers developing large-scale AI campuses in these regions as further reinforcing their strategic importance. Our development activity in Louisiana and Alabama continues to progress, and we remain encouraged by the scale of customer demand across the region. We expect revenue contribution from this region of the country to begin in the first half of calendar year 2027. We recently took our first steps outside the United States. While our focus remains firmly on executing our domestic projects, We believe select European markets may provide attractive opportunities to leverage our expertise and extend our platform over time as we continue to build Applied Digital into a category leader. As part of that early look, we signed an agreement for up to one gigawatt of potential power capacity in Finland. We view this as a measured first step. The agreement provides meaningful long-term potential while limiting our initial exposure and protecting downside risk, while our near-term execution priorities remain centered on the United States. Turning to our data center hosting business, our 286 megawatts of capacity for Bitcoin mining across our two North Dakota sites continues to operate efficiently and provide steady, high margin revenue with minimal ongoing capital investment. And now to chrono scale in which we have an approximately 96% ownership stake. NeoClouds continue to represent one of the fastest growing segments in this market. NVIDIA expects NeoClouds to exit this year with 8 gigawatts of installed capacity up from 3 gigawatts at the end of 2025. During the quarter, Chronoscale announced plans with Microsoft for a 50-megawatt AI compute deployment in North America featuring NVIDIA GB300 NVL72 systems. This deployment is expected to significantly expand Chronoscale's existing business with a Tier 1 investment-grade customer and represents another important step in scaling the platform. with recent new contracts chronoscale is on track to reach 1 billion of arr in 2027 and momentum for additional contracts continues to build with that i'll turn the call over to our cfo said all moment for a detailed review of the financials at all thank you west and good afternoon everybody this quarter we completed the financing of our first campus earlier this year we had only one remaining tranche of debt to place for the final 150 megawatt building at Polaris Forge 1.
In June, as we discussed on our last call, we closed that tranche, a $1.59 billion offering of 7% senior secured notes due 2031 issued at par. With the proceeds of the offering, we have funded construction of the third HPC building at Polaris Forge 1 and have repaid the $300 million bridge facility we put in place in may with that the full 400 megawatts of the core weave campus of polaris forge one and the 200 megawatts of contracted capacity polaris forge two are now fully funded the pricing of that deal is worth pointing out our first polaris forge one related notes placed last year carry a nine and a quarter coupon this tranche placed priced at seven percent we believe the pricing reflects the credit enhancements we secured of core weave earlier this year and growing investor confidence in our platform. We are earning that confidence by executing and delivering our buildings on track and on budget and we expect the first building at Polaris Sports 2 to similarly be on track and on budget. This success supports market confidence in our ability to execute. It drives us to reach our previously stated goal to keep bringing our cost of capital down first at the project level and over time by refinancing operating buildings into lower cost markets such as ABS. We also added flexibility at the corporate level. In June, we upsized a revolving credit facility to $430 million of commitments, with an additional $120 million accordion remaining available. Looking ahead, the next campuses we need to finance are Polaris Forge 3, Delta Forge 1, and Delta Forge 2. All of these are leased to the same Tier 1 investment-grade hyperscaler under 15-year take-or-pay leases. We believe this fact changes the financing conversations with potential creditors. Recall, Tier 1 investment-grade tenants open access to a deeper pool of capital, which we believe supports more attractive terms. We are following the same framework, preferred equity from Macquarie Asset Management, followed by project-level debt, which allows applied digital shareholders to attain a majority ownership stake in each site. We are already in active discussions with leading lending institutions, and given the credit quality of this customer, we have a high level of confidence in our ability to fund these campuses at favorable rates and terms. Now let's turn to the quarter. As a reminder, CoronaScale is included in our GAAP consolidated results, but is excluded from our non-GAAP financial measures. We reported total revenue of $341.9 million, up 322% from $80.9 million in the prior year quarter. Our HBC hosting business generated $262.6 million of revenue, consisting of $65.8 million of base rent, $183.5 million of tenant fit-out services, and $13.3 million of tenant recoveries. Our data center hosting segment, which operates our two Bitcoin hosting sites, generated $37.8 million in revenue in line with the prior year quarter. We continue to be very pleased with this business, which generated $13.3 million of operating profit in a single quarter, on approximately $111.9 million of segment assets. Segment operating profit this quarter more than doubled from $6 million in the prior quarter, driven by a favorable power pricing. KronaScale's revenue was $41.5 million this quarter, including approximately $23 million of GPU hardware sales. Services and other cost of revenues was $245.7 million, primarily consisting of $176.1 million in tenant fit-out services performed within our HPC hosting business, $22.4 million associated with KronaScale's GPU hardware sales, $19.8 million in energy costs, and $17.6 million in depreciation and amortization. Data Center rental and other cost of revenues was $43.9 million, primarily due to $22.4 million in depreciation and amortization expense on our operational AI factories at our Polaris Forge One campus, $13.3 million in expenses which are reimbursable as tenant recoveries, and $7.8 million in personnel and other operating costs supporting our facilities. SG&A was $114.7 million this quarter. This was primarily due to $65.4 million in stock-based comp, $16 million of professional services mainly related to transactions, $15.6 million of personnel expenses, and $4.8 million of lease expenses. One item worth calling out in the quarter. Our stock-based compensation expense included $41.3 million tied to one-time performance stock units. We also recorded $67.5 million of a non-cash loss from the change in fair value of our Babcock and Wilcox warrants and the common stock investment. Both are marked to market every quarter as B&W stock price changes. Net loss from continuing operational operations attributable to common stockholders was $221 million or $0.76 per share. Adjusted net loss was $4.1 million or one cent for a diluted share. Adjusted EBITDA was $64.4 million, up from $500,000 in the prior year quarter. Net operating income, or NOI, which is exclusive to our HPC hosting business, was $58.8 million, representing an 89% margin. From a balance sheet perspective, we believe we remain well positioned. We ended the quarter with approximately $2.9 billion in cash and cash equivalents, plus $0.7 billion of restricted cash and against approximately $6.4 billion of debt. Note, more than 80% of that principle does not come due until fiscal 2031 or later. Stockholders' equity is approximately $1.6 billion. Our goal remains to maintain one of the strongest balance sheets in the industry through the majority of the construction phase and will execute as such. With that, I'll turn the call back over to Wes for closing remarks.
Thank you, Setol. before we open the call for questions i want to close on something that comes up in nearly every investor conversation we have today the growing scrutiny around data center development across the country we are seeing more local moratoriums tighter zoning requirements longer permitting timelines and greater community resistance in certain markets some may view this as a risk to our industry we see it differently we believe it actually increases the strategic value of our campuses that are already powered, operating, and supported by their communities. We think the reason is straightforward. At our campuses, once they're established, we believe much of the hardest work has already been done. The land is controlled, power and interconnection are in place, permits have been secured, fiber, workforce, and local supply chains have been established, and perhaps most importantly to us, the community knows who we are and sees how we operate this is why we think expanding at existing campuses is materially different than starting from scratch in a new market we are already seeing this dynamic across our portfolio customers tell us they want additional capacity in places where they have confidence it can actually be delivered as new data center development becomes more difficult than certain markets we believe the scarcity value of established powered and community supported campuses increases we think that dynamic creates meaningful barriers to entry and can support stronger economics on expansions and renewals and over the long term higher terminal values for our assets put simply our view is that every new restriction elsewhere makes what we already own harder to replicate and more valuable this is also important when we think about the long-term value of these assets our leases have 15 year based terms but the land power interconnection community support behind these campuses have the capacity to last far longer than any single lease when a base term ends then we see that that a tenant with ten thousand tens of thousands of gpus deployed in a powered liquid cool campus faces a simple choice renew with us or try finding comparable power and approval somewhere else in a market where new sites are becoming increasingly difficult to approve we believe that makes renewals more likely support stronger renewal pricing and allows our tenants to continue refreshing their technology within the same facility for decades. This is why we believe in the durability of our leases and that the terminal value of these campuses is meaningfully higher than a traditional real estate model would have sold. We also believe that the value should continue to grow as new supply becomes harder to build. And local leaders have told us the reason our communities want us to expand is because we have worked hard to earn their trust our approach has always been simple do it the right way in north dakota mdu's customers have saved about 45 million dollars since our ellendale project began because we use excess grid capacity and help spread fixed costs across more load in harwood we paid for over 100 million dollars of substation and grid upgrades ourselves which benefit the entire community and our model already meets the ratepayer protection pledge that governor armstrong joined alongside 21 other governors local leaders have also shared with us that the positive economic impact on these communities has been significant and it's drawing national attention including coverage on fox business news and the all in podcast ellendale is a great example since we began our partnership with the community local tax revenue has expanded roughly tenfold from approximately 400 000 a year to nearly $4 million. These tax dollars are helping fund schools, infrastructure, and emergency services. Construction workers on our sites earn six-figure incomes on average, and many of those dollars stay in the local economy. We were honored that Mid-America Economic Development Council recently named Polaris Forge One its Project of the Year, recognizing the campus for its economic impact, community investment, partnerships, and technological innovation. That award belongs as much to the Ellendale community as it does to us, and we are incredibly grateful to everyone who continues to make Polaris Forge 1 possible. We also invest directly in our local communities. Through Applied Digital Cares, we recently committed $350,000 across five organizations in Oliver County, home to Polaris Forge 3. That includes funding the new sheriff's deputy, a new life pack for the county ambulance repairs to two fire trucks, computers so every student in grades 7 through 12 at Center Stanton has device and repairs to the community center and pool and center as governor armstrong put it north dakota wins when companies like applied digital choose to be more than an employer we don't just build in communities we build with them and that is why we are what they are welcome welcoming us back to grow and why we believe each of our campuses have significant embedded value that will continue to build over time in closing we believe we're in the right place at the right time and doing this the right way more than ever we're in control of our own destiny across the full stack we own the land we design we build and operate the ai factories through chronoscale we reach all the way to gpu compute and through partners like base electron we have visibility into the power that feeds it all if demand continues on its current path we and we continue to execute and deliver for our customers and our communities as we've been doing we believe we have the ability to grow our operating portfolio to three and a half to four gigawatts by the end of calendar year 2030. With that operator, we're happy to open the call for questions.
Operator
We will now begin the question and answer session. Please limit yourself to one question and one follow-up. If you would like to ask a question, please press star one to raise your hand. To withdraw your question, press star one again. We ask that you pick up your handset when asking a question to allow for optimum sound quality. If you are muted locally, please remember to unmute your device. Please stand by while we compile the Q&A roster. Your first question is from the line of Mike Grendel with Northland Securities. Mike, your line is open. Please go ahead.
Hey guys, thank you. You know, applied clearly as a first mover advantage in North Dakota, Can you talk a little bit about the perception of North Dakota as a market and the receptivity you're seeing from hyperscalers?
Sure, Mike. Thanks for the question. So what we're seeing in North Dakota, obviously we have, you know, three customers there ourselves already. We're aware of a self-build project, roughly one gigawatt self-build project from one of the tier one hyperscalers in the state as well. and we've been speaking that that is outside of the ones that we already have in the state and we're having multiple conversations with other of the tier one hyperscalers for additional capacity in the state of north dakota so the the answer is is i think um all of them will eventually be there and that's a state that has one of the most attractive things about the state beyond the power and the climate and you know the population density is they have a framework for how data centers are treated in the state and so everyone knows exactly what to expect as you go through a process in that state and as long as you do the development the right way uh it's a it's an extraordinarily attractive state to be in and i think it's just going to become more so uh over over the, you know, the remainder of this year of 27 and 28.
And then, you know, maybe for Seidol, you know, the bond market has been challenging to say the least. Can you talk about current options you're seeing for investment grade hyperscaler, you know, debt funding?
Yeah, thanks for the question, Mike. And it's a great question. As you can recall, we completed the Polaris Forge 2 and the Polaris Forge 1 financing, which you could argue are not the same credit quality, great tech customers, they execute great, great tenants to have. So when you think about the go forward with Polaris Forge 3 and Delta Forge 1 and 2, given that it is in high investment grade hyperscaler, there's multiple options beyond the high yield bond market, which we have liked and we've been an issuer in with the past projects. So for instance, the project finance market is well open for high investment grade offtakes, as well as there's some new innovations within the investment-grade bond market. So what we have seen, there's flexibility amongst various products that we can tap. Obviously, we weigh those and find a mix that works for our profile. But what we are focused on in a rate environment that can move around 50 to 100 basis points, one, we don't underwrite leases where a 100 basis point move would impact our economics really. But then two, we focus then on terms where we can refinance in a year or two years with minimal penalties. So once that construction risk, which generally there's anywhere from 25 to 100 basis points of construction risk premium on a debt instrument, once we go past the construction phase, we have the flexibility to lower our costs relatively quick into a more permanent financing. That is our focus. We're nimble. And it's a great thing having, you know, a high investment grade hyperscaler with multiple options to run at.
That's good to hear. Hey, thanks, guys.
Operator
Your next question comes from the line of Nick Giles with B. Riley Securities. Nick, your line is open. Please go ahead.
Yeah, thanks, operator. Hi, guys. Congrats on the recent execution. I just wanted to ask about this Finland announcement. I think in the release you highlighted limited initial exposure and I was just hoping you could expand on that point. What kind of options are embedded in the current agreement and how you kind of see you know the commercial side of that of that site progressing? Thanks.
Sure, Nick. Thanks. So that for the site we we purchased the site and then we have the option so the initial power of that site comes in 2028 and then additional power which is typical of almost any site that's going to scale to a gigawatt there's there's break points where they'll get approvals for you know additional power ads there's pretty good line of sight to that but then there would be additional payments at that point but there's an off-ramp for us uh prior to those additional payments so it's a pretty minimal amount for us to have this kind of exposure in a market that we we think has become pretty attractive uh as far as the european market goes and and we've you know we've spent the last i don't know 12 months looking into that market and we've looked at probably 30 to 40 different sites and we we landed on this one we think it's a good site and it's kind of coincided nicely to a point where our our existing and the other potential customers that we talked to have started asking more in the last you know four months about european capacity so those things kind of go pretty well together but it gives us a lot of optionality to the upside with pretty minimal financial risk got it no thanks for that Wes and um maybe just switching gears in your
prepared remarks I think you really highlighted the longevity of these data center campuses today and I I heard it as kind of a changing tone or maybe highlighting that more so uh than you have in the past so I was just wondering if there's you know what were the genesis of those comments I mean obviously GPU refresh cycles continue to be part of the discussion here but um yeah anything that you'd highlight from that perspective i'd appreciate sure nick so it's a couple of things we've we've talked you know for since we started the design that we use today right we we i call it our fourth generation data center design with this design we made it extraordinarily flexible with all of the learnings we had um gathered through the processes we went through with all
of the hyperscalers so one it's flexible enough to work for any of the hyperscalers but two we made it flexible to future proof it as much as possible and some of that comes into how we do the electrical some of it in the cooling a big part of it is uh the amount of space that we put inside the data hall so that uh you know the trend is for higher power densities and that's the foreseeable future but if it goes to much lower power densities we have the space inside of the facility to accommodate that as well so we just built maximum flexibility we've talked about this for a few years now. But what I'm seeing in the market is a lot of things happening that are just hyper-focused on how quickly something can come online and doing close to unnatural acts, I would say, to just put capacity online as quickly as possible. And while I'm not saying that's a good or a bad business strategy, I just want to differentiate from what we're doing, which is a much more longer term view of how we build the data centers so that they're very long-term assets you can never fully you know know what the future brings but that's the view that we have with the company that's how we designed them that's how we design them from a redundancy from both a power and cooling perspective because we could build a slightly cheaper product we do have to make sure that we can operate this product for at least 15 years on our current leases within the slas but we want to operate them longer than that but it's just really more insight into kind of the thought process and the longer term thinking behind our data center design and build and the
Operator
operations versus some of the other things that we're seeing just overall going on in the market makes sense uh appreciate the update guys your next question is from the line of derek whitfield with texas capital derek your line is now open please go ahead good afternoon and congrats on your continued commercial and execution progress.
Thanks. Wes, I wanted to start with the 1.3 gigawatts of U.S. capacity that you're currently marketing. During the last call, you noted your experience in a healthy market at present and would expect base rates to improve on a risk-adjusted basis. How would you characterize what you're seeing in the market today since really the last call?
Seemingly, everything that's happening from a regulatory moratorium perspective is playing your benefit but would just love your perspective and color on that sure so from a demand perspective in the market uh we're seeing no no i wouldn't say big change either way i mean it feels like we're at max i've thought of that for you know kind of the last two years and it continues to notch up but but demand remains extremely robust uh for you know right now so people are still pushing for things they can get in 2027 uh really almost everything in 27 should be fairly contracted at this point uh we start moving into 28 and 29 we have stuff that's contracted into into 28 um but we're seeing a lot of demand for that as well and and really it's these locations like we keep pointing to north dakota but louisiana is a great market for us as well and so so is alabama uh we've had a great experience there with the community and the the certainty of being able to continue to get the permits of existing power that we have in campus uh the supply chain for us to continue to execute uh i would just you know reiterate those comments about we we fully expect to you know do some lease expansion and new campuses at materially higher rates versus what you know we signed our last contracts for uh in the in the first half of of 2026. very good and then for my follow-up i wanted to come back to spend one while i realized you're early in the process with the emerging european ai market i wanted to ask to give a feel on how build cost might compare versus the us as you think about the labor building and equipment supply yeah so we've actually went through that exercise and and the build cost is very we expect it to be very similar uh on a dollars basis um versus euro and so and by that i mean you know if we converted the euros back it would be roughly the same uh dollars what i would expect there is a more elongated delivery timeline uh in europe just kind of how it works versus what we do here in the us but the goal is to replicate you know the same thing from the supply chain and design and build perspective uh in the markets when we enter europe versus here but we've done that work in it and expect a a very similar cost perfect great update guys thanks your next question comes from the line of rob brown with lake street capital markets rob your line is now open please go ahead good afternoon congratulations on all the progress Just to follow up a little bit more on North Dakota and the ability to expand there and
Rob Brown
Analyst — Lake Street Capital Markets
how base electron fits into that, given your BPA. How does that sort of start to enable the expansion there, and what years are most affected Sure.
So we start to think about 2030, Rob, primarily on base electrons. So base electrons building the 1.2 gigawatts in center expect base electron to build. the significant amount of capacity on the the eastern side of the state as well will help campus expansion over in the hardwood campus and then potentially in the middle part of the state around jamestown so there's a there's a new wbi pipeline that wbi is owned by mdu that they approved and are moving forward with that pipeline it's been in the works for years um and so we will be an off taker of gas at center and you know at hardwood for certain and possibly in Jamestown but the way we have worked that with with the gas pipeline is to have you know almost unlimited capacity for expansion and center it's going to be the closest location to the beginning of the pipeline and then these pipelines you know typically taper the further they go out so to have really big expansion capability at center this will all be front of the meter grid connected, but also expanded different locations across the state. From an equipment perspective, you know, we're looking at procured equipment that's roughly 2.4 to 2.5 gigawatts of generation capacity there already, but we expect it to go significantly larger given the demand that we're seeing in the future there in North Dakota. Great.
Rob Brown
Analyst — Lake Street Capital Markets
Thank you. I just want to follow up on the supply chain work you've done. You've executed very well on plan. How have you mitigated any supply chain constraints or what do you think in terms of supply chain?
Sure. I mean, supply chain, I think, is tight across the industry and you have some components more so than others. the biggest what we've talked about this before from a supply chain perspective the biggest thing we did was was almost two years ago lock in key components in the supply chain with certain of our suppliers and in some of those instances we actually purchased full factory capacity output from certain factories for I believe a four-year time frame to make sure that we had those key components locked in so that's been a big help to us we're pushing to upsize uh upside that amount that we can take because we think as we go out into 27 and 28 and 29 uh we're going to need more supply chain to continue to build to the the demands that we're seeing in the marketplace but that that was the key piece for us is putting those relationships those key relationships in place quite some time ago to make sure that we're locked into our places in the supply chain for key components thank you your next question is from the line of george sutton with craig hallam george your line is now open please go ahead thank you wes you used the term selective when you were talking about the future build i want to make sure i understand the term selective you're referring to i think you're referring to the quality of folks that you'll work with versus uh the amount of capacity that you'll ultimately be able to build is that a that a fair conclusion yeah that's right george uh is the you know the company today is in a different place versus what it was a year ago and uh we we have a limited amount of capacity to build and so we're we're being more selective with the customers that will build for it and and that you're right on the on the credit quality aspect of that.
So relative to the 250 megawatts of expansions, you basically define them as likely coming at premium pricing. Can you just give us a sense of how you're defining premium pricing? How broad is that statement versus just the base rent? What might else be involved?
Well, what we're pushing for on that, George, we're not to get into too much detail but we've talked about this before which is um potentially longer duration and higher uh significantly higher lease rates um don't want to to pin that but you you know you can think of definitely north of of 15 plus increases on the lease rate but also could include uh longer duration on the on the leases that's that's how we're defining that all right perfect Great.
Thanks, guys. Thanks, George.
Operator
Your next question comes from the line of Darren Aftahi with Lucid Capital Markets. Darren, your line is open. Please go ahead.
Thanks, guys, for taking a question. Congrats on the progress. Just on Finland, I said a couple of points of clarification I wanted to get answered. So is there any way, Wes, you can elaborate on how much power initially is going to be at the site? Second point, what kind of community or governmental risk is there in that region, either kind of near term or longer term? And then lastly, was the site sort of procured on an absolute basis or was this sort of procured with a specific customer or customer to you in mind?
So we view the location that we found in Finland, you know, it felt a lot like the communities that we build in in North Dakota. So there's a really positive receptivity from a local level on the community level. The country as a whole has been fairly receptive to data center. so we we really focused on that for our you know to make this decision on the site plus you know the land availability the the fiber this this site happens to be about 30 kilometers from a self-build of one of the large hyperscalers and then as far as the staging of the of the power the first 100 megawatts is available in 2028 and then it continues to ramp up through 2031 to the to the full gigawatt.
Operator
Your next question comes from the line of John Todaro with Needham and Company. John, your line is open. Please go ahead.
Hey, thanks for taking my question. Congrats. As we look after the four gigawatts or so by year-end 2030, I guess just what steps do you need to take to ensure you kind of get there? How much is reliant on base electron? And then And also in Europe, too, it seems like some of that's going to come a little bit later, 2031, as you said. So is there other sites in Europe that you need to get to as well?
Yeah, so thanks, John. And I'll just clarify. I saw here we went right to the four gigawatts. It was three and a half to four gigawatts that we talked about by the end of 2030. So that's really, from a power perspective, we have power in the power pipeline. Some of that includes the additional capacity from base electron that comes on in 2030. But from a power perspective, we believe we have that in the pipeline. This was really an exercise around how much more can we ramp up our build and delivery? And if you kind of work through the math for us internally, if you want to get to the high end of that number, To get to the high end of that number, that really has us delivering about one gigawatt per year in 29 and 30, right? So that kind of if you take a bridge to the end of calendar year 28, getting to around two gigawatts, we as a company think that that's kind of the level we can ramp our construction and delivery up to. So it's really those two things combined, but much more so on the ability and capacity to do construction and deliver for customers.
Okay, understood. That's helpful. And then a follow-up just on chronoscale, designed to 50 megawatts. Obviously, it seems like it could start ramping quite a bit from here. Just wondering, kind of as we look out a few years, could we almost expect chronoscale to be at 400 megawatts or so in applied sites, It's almost like what CoreWeed did or, you know, less so. Yeah, just curious about ChronoScale, the potential customer down the line.
Yeah, so thanks for that question. That's a great question. So when we look at that right now, and you've seen, you know, over the coming month or so, the strategy we're using to secure data center capacity for ChronoScale is outside of the large-scale applied digital sites. those sites we contract to what we have said which is uh tier one and you know investment grade hyperscalers the ability to secure other capacity with we have found a nice strategy for securing uh more near-term grid capacity that isn't at that that that scale at a single location but at multiple locations but i i think you could see you know chrono scale moving up to multiple hundreds of megawatts uh in capacity online outside or applied digital data center uh builds it with you know over 27 and 28 um but but i i want to bifurcate this where it is two separate strategies where you know by digital strategies it remains the same build for high quality tenants at large scale and then uh we're we're using our knowledge base to help chrono scale secure capacity um at you know sites that are more like you see the the first microsoft site of 50 megawatts that are kind of 50 to 100 megawatt sites that have been passed over uh because they don't scale to to the the most the gigawatt side or the multi-hundred megawatt But there's a lot of those around the country that are grid tied that we think we can help them bring online over the next, you know, two or three years, a significant amount, actually, in 2027. So that's really, I appreciate you letting me make that clarification around the strategy. Yeah, sounds great. Thank you, Wes. Appreciate it. Thanks, John.
Operator
Your next question comes from the line of Michael Donovan with Compass Point. Michael, your line is open. Please go ahead.
Hi guys, thanks for taking my question. Is it fair to seeing your existing McQuarrie relationship would extend to Finland?
So, McQuarrie has been- I couldn't have asked for better- McQuarrie, McQuarrie. McQuarrie, I thought you said McQuarrie. I was going to talk about the partnership there. McQuarrie is North America. That partnership is in North America.
I'm not saying we couldn't have something similar, but the current agreement we have is just north america appreciate that ed and if you had a big interesting accordion i'll not stop you there but uh good no that's all that's what i have for that excellent and then to follow up on nick's question as inference becomes a larger share of customer workloads are you seeing changes in the mix of gpus cpu storage requirements and if so are any of those changes contributing to the premium lease rates that you mentioned or expecting?
So I'll tell you where we're seeing a change. So we're seeing a change over the past 18 months on the tenant fit out or the technical fit out TFO. And what we're seeing in, because we execute that in almost actually every lease that we have, we execute that. The TFO is becoming much more flexible, is what I would say. So if you roll back a year ago, or especially 18 months ago, the TFO, we would know exactly what was going into our data center based on the TFO, and now we can't really tell, and the TFO has become a larger dollar amount for our customers, but I think they're building in a significant amount of flexibility inside the facilities to be able to accommodate whatever workloads they want to deploy. And that, you know, between, we'd always talk to like GPU, TPU, but I think it's also in the amount of CPU mix, the storage, all of those pieces, network topology. But that's really where we're seeing that.
Appreciate that. And then one more fun day. You mentioned economies of scale for your current builds. Are there any circumstances where you would consider smaller modular build-outs?
I think that's a great place for ChronoScale. Now, just to clarify on that, are you talking about like the containerized solutions that people are talking about for, you know, edge compute or just like a, you know, a 20, 50, 100 megawatt containerized solution? Yeah, more in line with 20, 50. not so much a containerized one but or like smaller we're looking at those that's a that's a one of the ways we're um securing uh data center capacity at chrono scale is those types of of modular builds on a smaller scale appreciate that and congrats on the execution thank you this concludes our q a i will now turn the call back to wes cummings for closing remarks thanks everyone for joining our call and we'll look forward to speaking to you again in january